About this file
This document is a WebAIM Short Form Task Group Instruction (TGI) for the USS John Finn (DDG-113), detailing a specific maintenance task to replace peel and stick nonskid deck systems in two magazine areas. The work involves replacing nonskid deck covering in DLS Magazine No. 1 (02-186-2-M) covering 167 square feet and DLS Magazine No. 2 (02-194-1-M) covering 150 square feet, including vertical surfaces up to 6 inches from the deck. The installation must conform to MIL-PRF-24667, Type XI, Composition PS standards.
The task is scheduled to start on 4/20/26 and complete by 6/15/26, with the SRF-JRMC (Southwest Regional Maintenance Center) providing supporting services including crane rigging, utility services (electrical, air, water, steam), and safety and quality assurance inspections. The work will involve painters, carpenters, sheet metal workers, and quality assurance personnel, with all necessary materials to be confirmed through a funding document process.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
08-AUG-2025 0806
20.15.6.0.9333 (July 2025) ICN: 38BC163404 KeyOp: A03
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: LDS MAG NO. 1 & 2 AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-113 USS JOHN FINN BC1
CU PHASE TITLE: *F/O - REPLACE PEEL AND STICK NONSKID SYSTEM IN 02-186-2-M AND 02-194-1-M
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 3
ES01L026
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
KANO, DAISUKE 231A 3152430098 19-JUL-2025
APPROVED BY: CODE: PHONE: DATE:
KOMATSU, SHUUHEI 231A 3152436786 19-JUL-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
ES01-L026
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
634A1104
1. SCOPE/PURPOSE:
1.1 Title: Peel and Stick Nonskid System in 02-186-2-M and 02-194-1-M; replace
1.2 Location of Work:
1.2.1 DLS Magazine No. One (02-186-2-M)
1.2.2 DLS Magazine No. 2 (02-194-1-M)
1.3 Identification:
1.3.1 Quantity (167 SF), Deck Plating in 02-186-2-M, including vertical surface up to height of 6 inches from deck in and around peel and stick nonskid deck covering area
1.3.2 Quantity (150 SF), Deck Plating in 02-194-1-M, including vertical surface up to height of 6 inches from deck in and around peel and stick nonskid deck covering area
TGI Short Form
08-AUG-2025 0806
20.15.6.0.9333 (July 2025) (Continued) ICN: 38BC163404 KeyOp: A03
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: LDS MAG NO. 1 & 2 AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-113 USS JOHN FINN BC1
CU PHASE TITLE: *F/O - REPLACE PEEL AND STICK NONSKID SYSTEM IN 02-186-2-M AND 02-194-1-M
FOUO Pg 2 of 3
CU PHASE DESCRIPTION (Cont.)
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1.4 Security Classification: None.
1.5 Initial Condition: None.
1.6 Contractor Work start date:
1.7 Contractor Work completion date:
2. PROCEDURE:
2.1 Accomplish the requirements of 009-032 of Ref. No. One, including Table 2, Line(s) 25, for each area listed in 1.3.1 and 1.3.2.
2.1.1 Accomplish the requirements of 009-026 of Ref No. One, including Attachment G, for installation of new peel and stick nonskid deck covering. Application of peel and stick nonskid deck covering must conform to MIL-PRF-24667, Type XI, Composition PS.
2.2 Notes:
2.2.1 Planner: Code 231A D. Kano, 243-0098
2.2.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-6522-9560
2.2.3 JCN ES01-L026 is related to this TGI.
2.3 Government Furnished Material (GFM): None.
2.4 SRF-JRMC will provide the following service work: (TGI No. 38BC163404S02)
2.4.1 [C740] Crane and crane rigging service.
2.4.2 [X99E] Utility service, electrical.
2.4.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
2.4.4 [C106.1] Safety inspection for SRF-JRMC employees.
2.4.5 [C106.2] Gas free inspection for SRF-JRMC employees.
2.4.6 [C133] QA inspection for (G) symbol(s).
4/20/26
6/15/26
08-AUG-2025 0806
20.15.6.0.9333 (July 2025) (Continued) ICN: 38BC163404 KeyOp: A03
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: LDS MAG NO. 1 & 2 AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
DDG-113 USS JOHN FINN BC1
CU PHASE TITLE: *F/O - REPLACE PEEL AND STICK NONSKID SYSTEM IN 02-186-2-M AND 02-194-1-M
FOUO Pg 3 of 3
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - ORG N
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
2.1 PNTR , CARP 1, SMTL , QA 22/KE PC
CFM: for all paints, peel and stick nonskid, thinner, and misc such as covering/enclosing materials, and other consumables.
22/MQ CS
Process Funding Document. 10/CT OM
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 38BC163404 KEY OP: A03