TGI_38BC163404_A03_c0v0_Redacted.pdf

PDF 163 KB Posted

Attached to
USS JOHN FINN (DDG-113) FY26 6J1 CNO BUNDLE #1, Chief of Naval Operation Availability Yokosuka Japan
Solicitation number
N6264926RA009
Issued by

About this file

This document is a WebAIM Short Form Task Group Instruction (TGI) for the USS John Finn (DDG-113), detailing a specific maintenance task to replace peel and stick nonskid deck systems in two magazine areas. The work involves replacing nonskid deck covering in DLS Magazine No. 1 (02-186-2-M) covering 167 square feet and DLS Magazine No. 2 (02-194-1-M) covering 150 square feet, including vertical surfaces up to 6 inches from the deck. The installation must conform to MIL-PRF-24667, Type XI, Composition PS standards.

The task is scheduled to start on 4/20/26 and complete by 6/15/26, with the SRF-JRMC (Southwest Regional Maintenance Center) providing supporting services including crane rigging, utility services (electrical, air, water, steam), and safety and quality assurance inspections. The work will involve painters, carpenters, sheet metal workers, and quality assurance personnel, with all necessary materials to be confirmed through a funding document process.

View the file

Other files

File Type Posted
N6264926RA0090008 SF 30.pdf PDF
RFI Q7A7.rtf RTF text file
Solicitation Amendment N6264926RA0090007 SF 30.pdf PDF
300-23-224.After Hours Hotwork Memo (002).pdf PDF
Solicitation Amendment N6264926RA0090007 SF 30.pdf PDF
Solicitation Amendment N6264926RA0090006 SF 30.pdf PDF
Solicitation Amendment N6264926RA0090004 SF 30.pdf PDF
Solicitation Amendment N6264926RA0090005 SF 30.pdf PDF
RFI Q5A5.rtf RTF text file
RFI Q6A6.rtf RTF text file
Solicitation Amendment N6264926RA0090003 SF 30.pdf PDF
Solicitation Amendment N6264926RA0090002 SF 30.pdf PDF
RFI Q4A4.rtf RTF text file
Solicitation Amendment N6264926RA0090001 SF 30.pdf PDF
RFI Q3A3.rtf RTF text file
RFI Q1A1.rtf RTF text file
RFI Q2A2.rtf RTF text file
Solicitation - N6264926RA009.pdf PDF
TGI_38BC186301_A01_c0v0_Redacted 22JUN.pdf PDF
Attachment (V) Source of Repair Instruction.pdf PDF
TGI_38BC116801A01_c1v1_Redacted.pdf PDF
TGI_38BC125106_A01_c0v0_Redacted.pdf PDF
TGI_38BC163406_A01_c0v0_Redacted.pdf PDF
Attachment (VI) Warranty Tracking Information.pdf PDF
Attachment (III) Request for Information Form.rtf RTF text file
TGI_38BC154101_A01_c0v0_Redacted.pdf PDF
TGI_38BC125105_A01_c0v0_Redacted.pdf PDF
Attachment (IV) GFP_List_V3.xlsx XLSX spreadsheet
Attachment (VII) QASP 26RA009 Bun1.pdf PDF
TGI_38BC112201_A01_c0v0_Redacted.pdf PDF
TGI_38BC112313_A01_c0v0_Redacted.pdf PDF
TGI_38BC186502_A01_c0v0_Redacted.pdf PDF
TGI_38BC112311_A01_c0v0_Redacted.pdf PDF
TGI_38BC112312_A01_c0v0_Redacted.pdf PDF
Attachment (VIII) Contract Data Sheet 26RA009.pdf PDF
Attachment (II) Price Proposal Form N6264926RA009.xlsx XLSX spreadsheet
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

08-AUG-2025 0806

20.15.6.0.9333 (July 2025) ICN: 38BC163404 KeyOp: A03

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: LDS MAG NO. 1 & 2 AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-113 USS JOHN FINN BC1

CU PHASE TITLE: *F/O - REPLACE PEEL AND STICK NONSKID SYSTEM IN 02-186-2-M AND 02-194-1-M

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 3

ES01L026

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

KANO, DAISUKE 231A 3152430098 19-JUL-2025

APPROVED BY: CODE: PHONE: DATE:

KOMATSU, SHUUHEI 231A 3152436786 19-JUL-2025

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

ES01-L026

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

634A1104

1. SCOPE/PURPOSE:

1.1 Title: Peel and Stick Nonskid System in 02-186-2-M and 02-194-1-M; replace

1.2 Location of Work:

1.2.1 DLS Magazine No. One (02-186-2-M)

1.2.2 DLS Magazine No. 2 (02-194-1-M)

1.3 Identification:

1.3.1 Quantity (167 SF), Deck Plating in 02-186-2-M, including vertical surface up to height of 6 inches from deck in and around peel and stick nonskid deck covering area

1.3.2 Quantity (150 SF), Deck Plating in 02-194-1-M, including vertical surface up to height of 6 inches from deck in and around peel and stick nonskid deck covering area

TGI Short Form

08-AUG-2025 0806

20.15.6.0.9333 (July 2025) (Continued) ICN: 38BC163404 KeyOp: A03

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: LDS MAG NO. 1 & 2 AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-113 USS JOHN FINN BC1

CU PHASE TITLE: *F/O - REPLACE PEEL AND STICK NONSKID SYSTEM IN 02-186-2-M AND 02-194-1-M

FOUO Pg 2 of 3

CU PHASE DESCRIPTION (Cont.)

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1.4 Security Classification: None.

1.5 Initial Condition: None.

1.6 Contractor Work start date:

1.7 Contractor Work completion date:

2. PROCEDURE:

2.1 Accomplish the requirements of 009-032 of Ref. No. One, including Table 2, Line(s) 25, for each area listed in 1.3.1 and 1.3.2.

2.1.1 Accomplish the requirements of 009-026 of Ref No. One, including Attachment G, for installation of new peel and stick nonskid deck covering. Application of peel and stick nonskid deck covering must conform to MIL-PRF-24667, Type XI, Composition PS.

2.2 Notes:

2.2.1 Planner: Code 231A D. Kano, 243-0098

2.2.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-6522-9560

2.2.3 JCN ES01-L026 is related to this TGI.

2.3 Government Furnished Material (GFM): None.

2.4 SRF-JRMC will provide the following service work: (TGI No. 38BC163404S02)

2.4.1 [C740] Crane and crane rigging service.

2.4.2 [X99E] Utility service, electrical.

2.4.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

2.4.4 [C106.1] Safety inspection for SRF-JRMC employees.

2.4.5 [C106.2] Gas free inspection for SRF-JRMC employees.

2.4.6 [C133] QA inspection for (G) symbol(s).

4/20/26

6/15/26

08-AUG-2025 0806

20.15.6.0.9333 (July 2025) (Continued) ICN: 38BC163404 KeyOp: A03

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: LDS MAG NO. 1 & 2 AY A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

DDG-113 USS JOHN FINN BC1

CU PHASE TITLE: *F/O - REPLACE PEEL AND STICK NONSKID SYSTEM IN 02-186-2-M AND 02-194-1-M

FOUO Pg 3 of 3

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-26 NAVSEA Standard Items - 1 N 2 LI FY-26 Local Standard Items - ORG N

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

2.1 PNTR , CARP 1, SMTL , QA 22/KE PC

CFM: for all paints, peel and stick nonskid, thinner, and misc such as covering/enclosing materials, and other consumables.

22/MQ CS

Process Funding Document. 10/CT OM

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 38BC163404 KEY OP: A03

File details come from the government source that posted it. Updated .