Summary of Technical Special Provisions

This document contains Technical Special Provisions prepared by the City of Pasadena for the Holly Street Bridge Seismic Retrofit and Rehabilitation Project, a federally funded undertaking administered through the California Department of Transportation (Caltrans) under the Highway Bridge Program. The project encompasses seismic retrofitting and rehabilitation work on the existing Holly Street Bridge (Bridge No. 53C-1041), with comprehensive construction specifications supplementing the 2024 Caltrans Standard Specifications. Key project requirements include contractor-performed construction surveying, water pollution control work, environmental stewardship measures including tribal cultural resource monitoring, and management of hazardous materials including aerially deposited lead (ADL) and asbestos-containing construction materials (ACCM). The contract establishes strict time constraints prohibiting construction activities between 7:00 PM and 7:00 AM on weekdays, 5:00 PM and 7:00 AM on Saturdays, and all day Sunday. A critical interim milestone requires full reopening of Holly Street and Arroyo Boulevard to public vehicular traffic by April 30, 2028, in advance of the LA28 Olympic Games, with liquidated damages of $2,000 per calendar day for delays beyond this date. Overall project completion liquidated damages are set at $6,700 per calendar day for work extending beyond the specified contract time.

The specifications establish comprehensive Disadvantaged Business Enterprise (DBE) requirements under 49 CFR 26, mandating detailed monitoring, reporting, and commercially useful function verification throughout contract performance. The contractor must maintain performance bonds equal to at least 100 percent of the total bid and comply with Buy America requirements for materials. Supplemental work items for asbestos survey and testing, ADL survey and testing, and associated removal and compliance work are conditioned items that may be deleted upon completion of testing. Water pollution control work must comply with the Storm Water Pollution Prevention Plan and Construction General Permit, with the receiving water (Arroyo Seco Reach 2) listed as impaired for Indicator Bacteria and Trash under TMDL regulations. The project requires retention of an approved tribal cultural resource monitor from the Gabrieleno Band of Mission Indians-Kizh Nation for all ground-disturbing activities, with comprehensive protocols established for unanticipated discovery of cultural resources and human remains. Additional requirements address invasive shot hole borer prevention, material sourcing documentation, traffic control management with specific lane closure charts for Holly Street Bridge and North Arroyo Boulevard, and coordination with multiple utilities including Southern California Gas Company, Pasadena Department of Water and Power, AT&T, and Charter Communications.

View the file

Other files

File Type Posted
Construction_Management_for_Holly_Street_Bridge_Seismic_Retrofit_&_Rehabilitation_Project_(HBP).pdf PDF
Holly_Street_Bridge_Project_Plans.pdf PDF
Federal_Wage_Rates_2026-10-05.pdf PDF
CC_-_Sample-Cost-Proposal-1-For-Contracts-with-Cost-Plus-Fixed-Fee-or-Lump-Sum.pdf PDF
IG_Certification_Indirect_Costs_Financial_Management_System_v2.pdf PDF
CA_Safe_Harbor_Rate_(SHR)_Form.pdf PDF
Form-W-9_(for_reference).pdf PDF
FHWA-1273.pdf PDF
IG_FDR_Request_Form.pdf PDF
Holly_Street_2323_ISA_20190312.pdf PDF
MASTER_SERVICES_CONTRACT_(ENG).pdf PDF
Holly_Street_Bridge_–_Mitigation_Monitoring_and_Reporting_Program_(MMRP).pdf PDF
Exhibit_9-L_Bidders_Proposers_List.pdf PDF
Exhibit_B_-_Nondiscrimination_Assurances.pdf PDF
Equal_Employment_Opportunity_Certification.pdf PDF
Exhibit_12-G_Required_Federal-Aid_Contract_Language.pdf PDF
Civil_Litigation_History_Certification_ver02.pdf PDF
Title_VI_Assurances.pdf PDF
Noncollusion_DECLARATION.pdf PDF
CONFLICT_OF_INTEREST.pdf PDF
Levine_Act_Disclosure_Form.pdf PDF
DISQUALIFICATION_DISCLOSURE.pdf PDF
Declaration_of_Elibility_to_Contract_(not_debarred).pdf PDF
REQUIRED_FORMS_-_AAs_-_SIG-LEGAL-STATUS.pdf PDF
Unique_Entity_ID_(SAM).pdf PDF
DESIGNATED_REPRESENTATIVES.pdf PDF
Exhibit_A_-_Fair_Employment_Practices_Addendum.pdf PDF
IDENTITY_CONFIRMATION,_INCUMBENCY,_CERT_OF_SEC_OF_CORP,_AND_RESOLUTION.pdf PDF
Certification_Regarding_Lobbying.pdf PDF
Pasadena_Taxpayer_Protection_Amendment_Disclosure.pdf PDF
Public_Contract_Code_Disclosure.pdf PDF
Insurance_Requirements_Professional-Services.pdf PDF
Exhibit_10Q_-_Disclosure_of_Lobbying_Activities.pdf PDF
Holly_Street_Bridge_–_ISMND.pdf PDF
2025_QAP_-_Pasadena_(Revised2)_FINAL.pdf PDF
Emergency_FEMA_TC.pdf PDF
Disclosure_of_Lobbying_Activities.pdf PDF
Exclusive_Negotiation_Agreement__TEMPLATE.pdf PDF
Federal_Required_Certification_(4).pdf PDF
DoIT_Technical_Questionnaire.xlsx XLSX spreadsheet
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL SPECIAL PROVISIONS

2024 CALTRANS STANDARD

SPECIFICATIONS

HOLLY STREET BRIDGE SEISMIC

RETROFIT AND REHABILITATION

FEDERAL PROJECT NO.: 5064(078)

BRIDGE NO.:53C-1041

CITY PROJECT NO.: 73323

Prepared for:

Prepared by:

110 Blue Ravine Road

Folsom, CA 95630

October 5, 2026

9/30/2026

8/6/2025

The special provisions contained herein have been prepared by or under the direction of the following registered persons and are supplemental to the Caltrans 2024 Standard Specifications:

Jeremy Nottnagel, P.E. Date

Bridge Project Engineer

Matt Atkinson, P.E Date:

Roadway Project Engineer

Jose Ostdiek, P.E. Date:

Electrical

Prepared by the City of Pasadena Landscape Designer Date:

JEREMY

NOTTNAGEL

93270

3/31/2028

MATT

ATKINSON

82099

3/31/2028

JOSE

OSTDIEK

65334

9/30/27

Unless otherwise indicated, the project shall be completed in conformance with the State Standard Specifications, State Standard Specification Revisions, and any amendments thereto as set forth in these Special Provisions.

Wherever the term "Department" is used in the Caltrans Standard Specifications, Special Provisions, or other Contract documents incorporated into this Contract, the term "Department" shall mean the City, unless otherwise specified in the Contract documents.

ORGANIZATION

Special provisions are under headings that correspond with the main-section headings of the Standard Specifications. A main-section heading is a heading shown in the table of contents of the Standard Specifications.

Each special provision begins with a revision clause that describes or introduces a revision to the Standard Specifications.

Any paragraph added or deleted by a revision clause does not change the paragraph numbering of the Standard Specifications for any other reference to a paragraph of the Standard Specifications.

STANDARD PLANS LIST

The standard plan sheets applicable to this Contract include those listed below. When applicable, revised standard plans (RSPs) listed below are included in the project plans.

ABBREVIATIONS, LINES, SYMBOLS, AND LEGEND

A3A Abbreviations (Sheet 1 of 3)

A3B Abbreviations (Sheet 2 of 3)

A3C Abbreviations (Sheet 3 of 3)

A10A Legend - Lines and Symbols (Sheet 1 of 5)

A10B Legend - Lines and Symbols (Sheet 2 of 5)

A10C Legend - Lines and Symbols (Sheet 3 of 5)

A10D Legend - Lines and Symbols (Sheet 4 of 5)

A10E Legend - Lines and Symbols (Sheet 5 of 5)

PAVEMENT MARKERS, TRAFFIC LINES, AND PAVEMENT MARKINGS

A20A Pavement Markers and Traffic Lines - Typical Details

A20B Pavement Markers and Traffic Lines - Typical Details

A20C Pavement Markers and Traffic Lines - Typical Details

A20D Pavement Markers and Traffic Lines - Typical Details

A20F Pavement Markers and Traffic Lines - Typical Details

A24A Pavement Markings - Arrows

A24B Pavement Markings - Arrows and Symbols

A24C Pavement Markings - Symbols and Numerals

A24D Pavement Markings - Words

A24E Pavement Markings - Words

A24F Pavement Markings – Crosswalks Refer to Pasadena STD DWG S-709

A24G Pavement Markings - Yield Lines, Limit Lines, and Wrong Way Details (Pasadena STD DWG S-713 shall supersede for Limit Line ONLY)

A24H Pavement Markings - Arrows

A24J Pavement Markings - Speed Measurement

A24K Pavement Markings - Bicycle Obstruction Markings

EXCAVATION AND BACKFILL

A62A Excavation and Backfill - Miscellaneous Details

CURBS, DRIVEWAYS, DIKES, CURB RAMPS AND ACCESSIBLE PARKING

A87A Curbs and Driveways

A88A Curb Ramp Details

TEMPORARY CRASH CUSHIONS, RAILING AND TRAFFIC SCREEN

T1A Temporary Crash Cushion, Sand Filled (Unidirectional)

T1A1 Temporary Crash Cushion, Sand Filled (Unidirectional)

T1B Temporary Crash Cushion, Sand Filled (Bidirectional)

T2 Temporary Crash Cushion, Sand Filled (Shoulder Installations)

T3A Temporary Railing (Type K)

T3B Temporary Railing (Type K)

T3C Temporary Barrier System (Cross Bolt)

T3D Temporary Barrier System (Cross Bolt)

T3E Temporary Barrier System (Cross Bolt)

RSP T3F Temporary Barrier System (Cal F-23)

RSP T3F2 Temporary Barrier System (Cal F-23)

RSP T3G Temporary Barrier System (Staking or Anchoring)

RSP T3G2 Temporary Barrier System (Staking or Anchoring)

TEMPORARY TRAFFIC CONTROL SYSTEMS

T9 Traffic Control System Tables for Lane and Ramp Closures

T10 Traffic Control System for Lane Closure on Freeways and Expressways

T10A Traffic Control System for Lane Closure on Freeways and Expressways

T11 Traffic Control System for Lane Closure on Multilane Conventional Highways

T11A Traffic Control System for Changeable Lane Closure on Multilane Conventional Highways and Expressways

T12 Traffic Control System for Half Road Closure on Multilane Conventional Highways and Expressways

T13 Traffic Control System with Reversible Control on Two Lane Conventional Highways

T13A Traffic Control System Two Lane Conventional Highways

T13B Traffic Control System Two Lane Conventional Highways

T14 Traffic Control System for Ramp Closure

T15 Traffic Control System for Moving Lane Closure on Multilane Highways

T16 Traffic Control System for Moving Lane Closure on Multilane Highways

T17 Traffic Control System for Moving Lane Closure on Two Lane Highways

T18 Traffic Control System - Construction Work Zone Speed Limit Reduction on Freeways and Expressways

T19 Traffic Control System - Construction Work Zone Speed Limit Reduction on Conventional Highways

T20 Traffic Control System - Construction Work Zone Speed Limit Reduction Details

T21 Traffic Control System - Construction Work Zone Speed Limit Reduction Twenty-Four Hours a Day 7 Days a Week (24/7)

T22 Traffic Control System for Construction Work Zone Speed Limit Reduction on Two Lane Conventional Highways

TEMPORARY PEDESTRIAN ACCESS ROUTES

T30 Temporary Pedestrian Access Routes - Typical Sidewalk Closure and

Pedestrian Detour

T31 Temporary Pedestrian Access Routes - Typical Sidewalk Diversion Within Roadbed

T32 Temporary Pedestrian Access Routes - Typical Sidewalk/Crosswalk Closure and Pedestrian Detour

T33 Temporary Pedestrian Access Routes - Ramp

T34 Temporary Pedestrian Access Routes - Curb Ramp Options

TEMPORARY WATER POLLUTION CONTROL

T51 Temporary Water Pollution Control Details (Temporary Silt Fence)

T52 Temporary Water Pollution Control Details (Temporary Straw Bale Barrier)

T53 Temporary Water Pollution Control Details (Temporary Cover)

T54 Temporary Water Pollution Control Details (Temporary Erosion Control Blanket)

T55 Temporary Water Pollution Control Details (Temporary Erosion Control Blanket)

T56 Temporary Water Pollution Control Details (Temporary Fiber Roll)

T57 Temporary Water Pollution Control Details (Temporary Check Dam)

T58 Temporary Water Pollution Control Details (Temporary Construction Entrance)

T59 Temporary Water Pollution Control Details (Temporary Concrete Washout Facility)

T60 Temporary Water Pollution Control Details (Temporary Reinforced Silt Fence)

T61 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)

T62 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)

T63 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)

T64 Temporary Water Pollution Control Details (Temporary Drainage Inlet Protection)

T65 Temporary Water Pollution Control Details (Temporary High-Visibility Fence)

T66 Temporary Water Pollution Control Details (Temporary Large Sediment Barrier)

T67 Temporary Water Pollution Control Details (Temporary Construction Roadway)

BRIDGE DETAILS

B0-1 Bridge Details

B0-3 Bridge Details

B0-5 Bridge Details

B0-13 Bridge Details

JOINT SEALS

B6-21 Joint Seals (Maximum Movement Range = 2")

ROADSIDE SIGNS

RS1 Roadside Signs - Typical Installation Details No. 1

RS2 Pasadena STD DWG S-715

RS4 Roadside Signs - Typical Installation Details No. 4

CITY OF PASADENA – PUBLIC WORKS AND TRANSPORTATION

DEPARTMENT, STANDARD PLAN DRAWINGS

S-207 Concrete Base for Valve Cover S-406 Curb and Gutter S-408 Adjustment of Street Manhole Frame S-414 Intersection Curb Ramp S-421 PCC Sidewalk S-617 Shrub Planting S-709 Crosswalk Installation (Continental Crosswalk) S-710 Raise Pavement Marker Installation Detail S-713 Limit Line and Stop Pavement Markings S-716 Post Extension and Sign Mounting S-962 Street Light Standard Modifications and Equipment Mounting Locations for

Traffic Signals S-970 Traffic Signal Street Light Location S-971 Street Light Circuit Diagram 120 Volt Multiple S-973 Pull Box Street Light and Traffic Signal S-975 Multiple Relay for Post Top Lighting System

DIVISION I GENERAL PROVISIONS

1 GENERAL

Add to section 1-1.01:

Nonstandard Bid Items and Applicable Sections

Item code

Item description Applicable section

051241A CONTRACTOR PERFORMED CONSTRUCTION SURVEYING 5

130005A WATER POLLUTION CONTROL WORK 13

140000A ASBESTOS SURVEY AND TESTING 14

140000B AERIALLY DEPOSITED LEAD (ADL) SURVEY AND TESTING 14

146002A CULTURAL RESOURCE MONITOR 14

153250A REMOVE BOLLARD 15

170106A REMOVE TREE 17

511046A BONDED GROUT CONCRETE SURFACE 51

600001A COMPOSITE COLUMN CASING (CFRP) 60

780254A REPLACE ACCESS BOX FRAME AND COVER (UTILITY) 78

780258A REPLACE MANHOLE FRAME AND COVER (UTILITY) 78

782601A REMOVEABLE BOLLARD 78

839746A CONCRETE BARRIER (OPEN FACE) 83

839750A REMOVE METAL RAILING 83

The Contractor shall include a bid for all Supplemental Work Items identified in the bidder's proposal.

For bidding purposes, the Supplemental Work Items associated with hazardous materials shall be bid using the following assumptions:

• Concrete designated for asbestos-related Supplemental Work Items contains asbestos-containing material requiring handling and disposal in accordance with Section 14 and section 60

• Aerially Deposited Lead (ADL) concentrations are assumed to be less than 5.0 mg/L soluble lead and greater than 80 mg/kg total lead but not exceeding 320 mg/kg total lead.

Following completion of the hazardous materials testing described in Section 14, the Department may delete one or more Supplemental Work Items from the Contract if the test results indicate the work is not required.

Supplemental Work Items and Applicable Sections

Item code

Item description Applicable section

070030 Lead Compliance Plan 7

140003 Asbestos Compliance Plan 14

190139 Roadway Excavation (Aerially Deposited Lead)

600114A Bridge Removal (Portion)(Spandrel Columns)(Asbestos) 60

600115A Bridge Removal (Portion)(Deck)(Asbestos) 60

2 BIDDING

Add between the 1st and 2nd paragraphs of section 2-1.06B:

The Department makes the following supplemental project information available:

Supplemental Project Information

Means Description

Included in with the Bid Advertisement Documents

MMRP/ECR

Included with the project plans Holly Street As-Builts, Cross Sections

Add to section 2-1.09:

The item total for plant establishment work must be at least $20,000.

3 CONTRACT AWARD AND EXECUTION

Replace section 3-1.04 with:

Prior to award, any Bidder who has submitted a bid may file a protest with the Department against the awarding of the contract on the grounds that he or she is the lowest responsible Bidder meeting the Specifications. When a contract is not to be awarded to the lowest Bidder, the Bidder must be notified at least twenty-four (24) hours prior to awarding the contract. The right to protest a proposed award is afforded to any Bidder or proposer who claims it should have been awarded the agreement because it was the lowest responsible and responsive Bidder, or the highest-scored proposer meeting the Specifications.

This procedure specifies the process to be utilized by the City of Pasadena in resolving protests regarding this solicitation. In order for a protest to be considered by the City of Pasadena, it must be submitted in accordance with the procedures outlined in the FORMAL SOLICATION PROTEST PROCEDURE found at the following link: (https://ww5.cityofpasadena.net/finance/doing-business-with-the-city/). A protest submitted that is not in accordance with this procedure, may be returned to the submitting party without any further action by the City of Pasadena.

If the City awards the contract, an award is made to the lowest responsible bidder within the number of days shown in the following table:

https://ww5.cityofpasadena.net/finance/doing-business-with-the-city/

Days after bid opening Project estimated cost shown on the Notice to Bidders

45 < $200 million

The City may extend the specified award period if the Bidder agrees.

Replace section 3-1.05(2) with:

Performance bond to guarantee the faithful performance of the Contract. This bond must be equal to at least 100 percent of the total bid.

5 CONTROL OF WORK

Replace section 5-1.13B with:

5-1.13B Disadvantaged Business Enterprises

5-1.13B(1) General

Section 5-1.13B applies to a federal-aid contract.

Use each DBE as listed on the DBE Commitment form unless you receive Department prior authorization for termination under section 5-1.13B(2)(c). Ensure that all subcontracts and agreements with DBEs to supply labor or materials are performed under 49 CFR 26.

Maintain records of subcontracts made with DBE subcontractors and records of materials purchased from

DBE suppliers. Include in the records:

1. Name and business address of each DBE subcontractor, DBE vendor, and DBE trucking company, regardless of tier

2. Date of payment and total amount paid to each DBE business

If you are a DBE contractor, include the date of work performed by your own forces and the corresponding value of the work.

Before the 15th day of each month for the previous month's work, submit:

1. Monthly DBE Trucking Verification form

2. Monthly DBE Payment form

If a DBE is decertified before completing its work, the business must notify you in writing of the decertification date within 15 days of decertification. Notify the Engineer and submit the DBE's decertification notice within 2 business days of your receipt. Upon work completion, complete a

Disadvantage Business Enterprises (DBE) Certification Status Change form and submit within 10 days of

Contract acceptance.

Upon work completion, complete a Final Report – Utilization of Disadvantaged Business Enterprises

(DBE), First-Tier Subcontractors form and submit within 10 days of Contract acceptance. The Department withholds the greater of 10 percent of the DBE commitment or $10,000 until the form is submitted. The

Department releases the withhold upon submission of the completed form. If additional payments are made to a DBE after submittal of the completed form, submit an updated form to reflect such payments.

Failure to carry out requirements of 49 CFR 26 is a material breach of the Contract, which may result in the termination of the Contract or other remedy as the Department deems appropriate, such as:

1. Withholding monthly progress payments

2. Assessing sanctions

3. Applying liquidated damages

4. Disqualification from future bidding as nonresponsive

5-1.13B(2) Disadvantaged Business Enterprises

5-1.13B(2)(a) General

Section 5-1.13(B)(2) applies if a DBE goal is shown on the Notice to Bidders.

Certification as a DBE identifies if the business has the means to perform its work under assigned North

American Industry Classification System codes and work codes applicable to the type of work the DBE will perform on the Contract. Certification does not ensure the DBE will perform a commercially useful function on the Contract.

You are responsible for ensuring each DBE listed on the DBE Commitment form performs:

1. The description and value of the subcontracted work or material supplied as committed

2. A commercially useful function under 49 CFR 26.55 for committed work or materials

For DBE committed work, the Department only pays for work performed or supplied by the listed DBE and if a commercially useful function was performed by the listed DBE.

You are responsible to remediate noncompliant DBE work to meet your DBE commitment. Submit a DBE commitment remediation plan within 5 business days of the Engineer's request.

Pay your DBEs in conformance with section 5-1.13E.

Failure to promptly pay DBEs may result in a withholds corresponding to the value of the DBE's committed work from future progress payments. In addition, unpaid DBE amounts will not count towards your DBE commitment, which may result in equivalent withholds or deductions and a 2 percent penalty on the unpaid amount for every month payment is not made.

5-1.13B(2)(b) Commercially Useful Function

DBEs must perform a commercially useful function under 49 CFR 26.55 when performing work or supplying materials listed on the DBE Commitment form. The DBEs value of work will only count toward the DBE commitment if the DBE performs a commercially useful function under 49 CFR 26.55.

Provide written notification to the Engineer at least 15 days in advance of each DBE's initial performance of work or supplying materials for the Contract. Include the DBE's name, contract work to be performed, and the location, date, and time of where their work will take place.

Within 10 days of a DBE initially performing work or supplying materials on the Contract, submit your initial evaluation and validation of their performance of a commercially useful function using DBE

Commercially Useful Function Evaluation form. Include the following supporting information with your submittal:

1. Subcontract agreement with the DBE

2. Purchase orders

3. Bills of lading

4. Invoices

5. Proof of payment

Monitor your DBEs' performance of commercially useful function with quarterly evaluations and validations throughout their duration of work on the Contract using DBE Commercially Useful Function

Evaluation form. Submit your quarterly evaluation and validation DBE Commercially Useful Function

Evaluation forms by the 5th of the month for the previous three month's work. Include any additional supplemental supporting information with your submittal. If your DBE's work-start and -end dates for the

Contract exceed a three-month period, regardless of time not on the Contract, quarterly evaluations and validations are required.

Notify the Engineer immediately if you believe the DBE may not be performing a commercially useful function.

The Department will verify your DBEs performance of commercially useful functions by reviewing your initial and quarterly DBE Commercially Useful Function Evaluation forms, your submitted supporting information, field observations, and through select Department evaluations. The Department may evaluate DBEs and their commercially useful function performance at any time during the Contract. In such instances, the Department will provide written notice to you and your DBE at least 2 business days prior to the evaluation. You and your DBE must participate in the evaluation. Upon completing the evaluation, the Department will share the evaluation results with you and your DBE. The evaluation results may include items that must be remedied upon your receipt. If the Department determines the

DBE is not performing a commercially function you must suspend performance of the noncompliant work.

You and your DBEs must submit any additional commercially useful function related records and documents within 5 business days of Department request such as:

1. Proof of ownership or lease and rental agreements for equipment

2. Tax records

3. Employee rosters

4. Certified payroll records

5. Inventory rosters

Failure to submit required DBE Commercially Useful Function Evaluation forms or requested records and documents will result in withhold of payment for the value of work completed by the DBE.

If you and or the Department determine a listed DBE is not performing a commercially useful function in performance of their DBE committed work, suspend performance of the noncompliant portion of the work.

Submit a corrective action plan within 5 days of the noncompliant commercially useful function determination. The plan must identify how you will remediate when feasible or demonstrate commercially useful function compliance for the remaining portion of the DBE's work. Allow 5 days for plan review. The corrective actions must be implemented within 5 days of Engineer's authorization of your plan and prior to resumption of the noncompliant portion of the DBE's committed work.

If corrective actions cannot be accomplished to assure the DBE will perform a commercially useful function on the Contract, you may have good cause to request termination of the DBE under section 5-

1.13B(2)(c).

5-1.13B(2)(c) Termination

Termination of a DBE may be allowable for good cause reasons under 49 CFR 26.53(f)(3) with prior written authorization from the Department. You must provide documentation supporting good cause reasoning with your termination request. If the termination request is authorized by the Department, you must then either replace the DBE with another DBE or demonstrate good faith efforts to do so under 5-

1.13B(2)(d).

Use the following procedure to request the termination of a DBE or portion of their work:

1. Provide written notice to the DBE of your intent to use other forces or material sources and include one or more of the good cause reasons under 49 CFR 26.53(f)(3). Simultaneously send a copy of this written notice to the Engineer. Your written notice to the DBE must request they provide any response to both you and the Engineer.

2. Provide the DBE with 5 business days to respond to your written notice by either acknowledging their agreement or documenting their reasoning as to why the use of other forces or sources of materials should not occur. If the DBE does not respond within 5 business days, you may move forward with the request process as if the DBE had agreed to your written notice.

3. Submit your DBE termination request by written letter to the Engineer and include:

3.1. One or more good cause reasons identified under 49 CFR 26.53(f)(3) along with supporting documentation.

3.2. Your written notice to the DBE regarding the request, including proof of transmission and tracking documentation of your written notice.

3.3. The DBE's response to your written notice, if received. If a written response was not provided, provide a statement to that effect.

The Department will respond to your complete DBE termination request as follows:

1. Where the DBE has agreed in writing or fails to timely respond to your written notice, the Department will respond within 2 business days from receipt of your request.

2. Where the DBE has disagreed in writing with your written notice, the Department will meet with you and the DBE within 5 business days from receipt of your request. The Department will respond to your request within 5 business days from this meeting.

3. If you fail to provide a complete request for DBE termination the Department will identify deficiencies within 5 business days from receipt of your request.

If the Department authorizes your DBE termination request it will do so in writing.

Work performed by a firm other than the committed DBE or authorized replacement DBE without first obtaining Department authorization for termination will be a violation of these specifications and DBE federal regulations. Such violations will result in payment deductions for the value of the work associated with the noncompliant DBE commitment. In addition, if the committed DBE is also a listed subcontractor, the Department applies an additional penalty up to 10 percent of the value of the subject work as a permanent deduction.

5-1.13B(2)(d) Replacement

After receiving Department written authorization of your DBE termination request, you must obtain separate Department authorization of your replacement plan.

Your replacement plan must identify DBE replacement firms to perform the work or demonstrate that you have made a good faith effort to use DBE replacement firms. DBE replacement firms must:

1. Perform at least the same dollar amount of work as the terminated DBE to the extent needed to meet the DBE commitment

2. Possess certifications for the most specific available North American Industry Classification System codes and work codes applicable to the work the firm will perform on the Contract

3. Perform a commercially useful function under 49 CFR 26.55

Use the following procedure to request authorization of your replacement plan:

1. Submit a request to replace a DBE with other forces or material sources by written letter to the

Department which must include:

1.1. Description of remaining uncommitted item work made available for replacement DBE solicitation and participation.

1.2. The proposed DBE replacement firm's business information, the work they have agreed to perform, and the following:

1.2.1. Quote for bid item work and description of work to be performed

1.2.2. Proposed subcontract agreement and written confirmation of agreement to perform on the Contract

1.2.3. Revised Subcontracting Request form

2. If you have not identified a DBE replacement firm, submit documentation of your good faith efforts to use DBE replacement firms within 7 days of Department's authorization to terminate the DBE. You may request the Department's approval to extend this submittal period to a total of 14 days. The

Department considers your documented actions taken to identify a DBE replacement firm in determining whether a good faith effort was made under 49 CFR 26 app A. Submit documentation of actions taken to find a DBE replacement firm, such as:

2.1. Search results of certified DBEs available to perform the original DBE work identified and or other work you had intended to self-perform, to the extent needed to meet your DBE commitment

2.2. Solicitations of DBEs for performance of work identified in 2.1

2.3. Correspondence with interested DBEs that may have included contract details and requirements

2.4. Negotiation efforts with DBEs that reflect why an agreement was not reached

2.5. If a DBE's quote was rejected, provide your reasoning for the rejection, such as why the DBE was unqualified for the work, or why the price quote was unreasonable or excessive

2.6. Copies of each DBE's and non-DBE's price quotes for work identified in 2.1, as the Department may contact the firms to verify solicitation efforts and determine if the DBE quotes are substantially higher

2.7. Additional documentation that you believe supports your good faith effort

The Department will respond to your complete replacement plan as follows:

1. If a DBE replacement firm has been identified and required documentation has been provided, the

Department will respond within 2 business days from receipt of your plan

2. If a DBE replacement firm has not been identified, but good faith effort documents have been provided, the Department will respond within 5 business days from receipt of your plan

3. If you fail to provide a complete replacement plan, the Department will return your request and identify deficiencies within 5 business days from receipt of your plan

If the Department authorizes your replacement plan it will do so in writing.

Submit a revised Subcontracting Request form if your replacement plan is authorized.

DBE committed work performed by a nonauthorized firm, will be a violation of these specifications and

DBE federal regulations. Such violations will result in payment deductions for the value of the work associated with the DBE commitment. The Department will take a permanent deduction for the value of the DBE work that was not performed by the authorized DBE. In addition, if the associated work was also to be performed by a listed subcontractor, the Department applies an additional penalty up to 10 percent of the value of the subject work as a permanent deduction.

5-1.13B(3) Use of Joint Checks

You may use a joint check between the Contractor or lower-tier subcontractor and a DBE subcontractor purchasing materials from a material supplier if you obtain prior approval from the Department for your proposed use of joint checks upon submittal of a DBE Joint Check Agreement Request form.

To use a joint check, the following conditions must be met:

1. All parties, including the Contractor, must agree in writing to the use of a joint check

2. Entity issuing the joint check acts solely to guarantee payment

3. DBE must release the check to the material supplier

4. Department must authorize the request before implementation

5. Any party to the agreement must provide requested documentation within 10 days of the

Department's request for the documentation

6. Agreement to use a joint check must be short-term, not to exceed 1 year, allowing sufficient time needed to establish or increase a credit line with the material supplier

A request for a joint check agreement may be initiated by any party.

If a joint check is used, the DBE remains responsible for all elements of 49 CFR 26.55(c)(1).

Failure to comply with section 5-1.13B(3) disqualifies DBE participation and results in no credit and no payment to the Contractor for DBE participation.

A joint check may not be used between the Contractor or subcontractor and a DBE regular dealer, bulk material supplier, manufacturer, wholesaler, broker, trucker, packager, manufacturer's representative, or other persons who arrange or expedite transactions.

Replace “5-1.24 Construction Surveys” with:

5-1.24 Contractor Performed Construction Survey

Section 5-1.24 applies if a bid item for Construction Survey is shown on the Bid Item List.

The Contractor will provide the staking required for completion of the work.

Staking will consist of furnishing and setting construction stakes and markers by the Contractor to establish the lines and grades required for completion of the work as shown on the plans and as specified in the Standard Specifications and Special Provisions and as necessary for the Engineer to check lines, grades, alignment and elevation.

A construction survey must be performed by a Licensed Land Surveyor in the State of California as necessary to control the work. The Contractor will determine the work and staking required and must be verified by the Engineer. Construction stakes and marks must be furnished and set with accuracy adequate to ensure that the completed work conforms to the lines, grades, and section shown on the plans. You must reset any survey monumentation disturbed by construction.

All computations necessary to establish the exact position of the work from control points will be made by the Contractor. All computations, survey notes, and other records necessary to accomplish the work must be neat, legible, and accurate. Copies of such computation notes and other records must be furnished to the Engineer prior to beginning work that requires their use.

Construction stakes and/or survey control damaged from any cause during the progress of the work will be replaced by the Contractor at his expense, as required or at the direction of the Engineer. Construction must be removed from the site of work when no longer needed.

Upon completion of construction staking and prior to acceptance of the contract all computations, survey notes, and other data used to accomplish the work must be furnished to the Engineer and will become the property of Pasadena City.

The contract lump sum price paid for Construction Survey will include full compensation for furnishing all labor, materials, tools, equipment, and incidentals and doing all work involved in performing Construction Survey, as shown on the plans, as specified in the Standard Specifications and these special provisions, and as directed by Engineer.

Full compensation for furnishing and setting all other stakes necessary to construct the project will be considered as included in the prices paid for the various contract items of work, and no additional compensation will be allowed therefor.

Replace section 5-1.36C(2) with:

5-1.36C(2) Nonhighway Facility Protection

The utilities shown in the following table may interfere with the work and must be exposed or protected in place. Make arrangements with the utility owner (1) to conduct or witness all exposures or (2) to request temporary deactivation of the utility.

Utilities to Be Exposed and/or Protected in Place During Construction

Utility Location

So Cal Gas - Gas In the bridge and approaches

Pasadena DWP - Water In the bridge and approaches

Pasadena DWP - Electric In the bridge and approaches

AT&T - Telecommunications In the bridge and approaches

Charter – Cable Internet In the bridge and approaches

The utility information shown is incomplete. Utility location activities must be concurrent with construction activities. Make arrangements with the utility owners to coordinate activities.

6 CONTROL OF MATERIALS

Replace section 6-1.03B with:

6-1.03B Submittals

6-1.03B(1) General

Not Used

6-1.03B(2) Work Plan

For local material, such as rock, gravel, earth, structure backfill, pervious backfill, imported borrow, and culvert bedding, obtained from a (1) noncommercial source, or (2) source not regulated under California jurisdiction, submit a local material plan for each material at least 60 days before placing the material. The local material plan must include:

1. Certification signed by you and an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:

I am aware local material from a noncommercial source or a source not regulated under CA jurisdiction must be sampled and analyzed for pH and lead and may require sampling and analysis under section 6-1.03B(3) for other constituents of concern based on the land use history. I am aware that local material sources must not contain ADL at concentrations greater than 80 mg/kg total lead or equal to or greater than 5 mg/L soluble lead as determined by the Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II. I am aware that a maximum quantity of material may be excavated at the site based on the minimum number of samples taken before excavating at the site under section 6-1.03B(3).

2. Land use history of the local material location and surrounding property

3. Sampling protocol

4. Number of samples per volume of local material

5. QA and QC requirements and procedures

6. Qualifications of sampling personnel

7. Stockpile history

8. Name and address of the analytical laboratory that will perform the chemical analyses

9. Analyses that will be performed for lead and pH

10. Other analyses that will be performed for possible hazardous constituents based on:

10.1. Source property history

10.2. Land use adjacent to source property

10.3. Constituents of concern in the ground water basin where the job site is located

The plan must be sealed and signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State.

If the plan requires revisions, the Engineer provides comments. Submit a revised plan within 7 days of receiving comments. Allow 7 days for the review.

6-1.03B(3) Analytical Test Results

At least 15 days before placing local material, submit analytical test results for each local material obtained from a noncommercial source or a source not regulated under CA jurisdiction. The analytical test results must include:

1. Certification signed by an engineer who is registered as a civil engineer in the State or a professional geologist licensed as a professional geologist by the State stating:

The analytical testing described in the local material plan has been performed. I performed a statistical analysis of the test results using the US EPA's ProUCL software with the applicable 95 percent upper confidence limit. I certify that the material from the local material source is suitable for unrestricted use at the job site, it has a pH above 5.0, does not contain soluble lead in concentrations equal to or greater than 5mg/l as determined by the Waste Extraction Test (WET) Procedures, 22 CA Code of Regs § 66261.24(a)(2) App II, does not contain lead in concentrations above 80 mg/kg total lead, is free from all other contaminants identified in the local material plan, and will comply with the job site's basin plan and water quality objectives of the RWQCB.

2. Chain of custody of samples

3. Analytical results no older than 1 year

4. Statistical analysis of the data using US EPA’s ProUCL software with a 95 percent upper confidence limit

5. Comparison of sample results to hazardous waste concentration thresholds and the RWQCB's basin plan requirements and water quality objectives for the job site location

6-1.03B(4) Sample and Analysis

Sample and analyze local material from a (1) noncommercial source or (2) a source not regulated under CA jurisdiction:

1. Before bringing the local material to the job site

2. As described in the local material plan

3. Under US EPA Test Methods for Evaluating Solid Waste, Physical/Chemical Methods (SW-846)

The sample collection must be designed to generate a data set representative of the entire volume of proposed local material.

Before excavating at the (1) noncommercial material source or (2) a source not regulated under CA jurisdiction, collect the minimum number of samples and perform the minimum number of analytical tests for the corresponding maximum volume of local material as shown in the following table:

Minimum Number of Samples and Analytical Tests for Local Material

Maximum volume of imported borrow (cu yd)

Minimum number of samples and analytical tests

< 5,000 8

5,000–10,000 12 for the first 5,000 cu yd plus 1 for each additional 1,000 cu yd or portion thereof

10,000–20,000 17 for the first 10,000 cu yd plus 1 for each additional 2,500 cu yd or portion thereof

20,000-40,000 21 for the first 20,000 cu yd plus 1 for each additional 5,000 cu yd or portion thereof

40,000–80,000 25 for the first 40,000 cu yd plus 1 for each additional 10,000 cu yd or portion thereof

> 80,000 29 for the first 80,000 cu yd plus 1 for each additional 20,000 cu yd or portion thereof

Do not collect composite samples or mix individual samples to form a composite sample.

Analyze the samples using the US EPA's ProUCL software with a 95 percent upper confidence limit. All chemical analysis must be performed by a laboratory certified by the SWRCB's Environmental Laboratory Accreditation Program (ELAP).

The analytical test results must demonstrate that the local material:

1. Is not a hazardous waste

2. Has a pH above 5.0

3. Has an average total lead concentration, based upon the 95 percent upper confidence limit, at or below 80 mg/kg

4. Is free of possible contaminants identified in the local material plan

5. Complies with the RWQCB's basin plan for the job site location 6 Complies with the RWQCB's water quality objectives for the job site location

6-1.03C Local Material Management

Do not place local material until authorized.

If the Engineer determines the appearance, odor, or texture of any delivered local material suggests possible contamination, sample and analyze the material. The sampling and analysis is change order work unless (1) hazardous waste is discovered or (2) the analytical test results indicate the material does not comply with section 6-1.03B(3).

Dispose of noncompliant local material at an appropriately permitted CA Class I, CA Class II or CA Class III facility. You are the generator of noncompliant local materials.

Replace section 6-1.04 with:

6-1.04 BUY AMERICA

6-1.04A General

Buy America requirements do not apply to the following:

1. Tools and construction equipment used in performing the work

2. Temporary work that is not incorporated into the finished project

6-1.04B Crumb Rubber (Pub Res Code § 42703(d))

Furnish crumb rubber with a certificate of compliance. Crumb rubber must be:

1. Produced in the United States

2. Derived from waste tires taken from vehicles owned and operated in the United States

6-1.04C Steel and Iron Materials

Steel and iron materials must be melted and manufactured in the United States except:

1. Foreign pig iron and processed, pelletized, and reduced iron ore may be used in the domestic production of the steel and iron materials

2. If the total combined cost of the materials produced outside the United States does not exceed the greater of 0.1 percent of the total bid or $2,500, the material may be used if authorized

Furnish steel and iron materials to be incorporated into the work with certificates of compliance and certified mill test reports. Mill test reports must indicate where the steel and iron were melted and manufactured.

All melting and manufacturing processes for these materials, including an application of a coating, must occur in the United States. Coating includes all processes that protect or enhance the value of the material to which the coating is applied.

6-1.04D Manufactured Products

Iron and steel used in precast concrete manufactured products must meet the requirements of section 6-

1.04C regardless of the amount used.

Iron and steel used in other manufactured products must meet the requirements of section 6-1.04C if the weight of steel and iron components constitute 90 percent or more of the total weight of the manufactured product.

6-1.04E Construction Materials

The following construction materials must be produced in the United States under standards in 2 CFR

184.6:

1. Non-ferrous metals

2. Plastic and polymer-based products such as:

2.1. Polyvinylchloride

2.2. Composite building materials

3. Glass

4. Fiber optic cable including drop cable

5. Optical fiber

6. Lumber

7. Engineered wood

8. Drywall

All manufacturing processes for these materials as defined in 2 CFR 184.6 must occur in the United

States.

Furnish construction materials to be incorporated into the work with certificates of compliance with each project delivery. Manufacturer’s certificate of compliance must identify where the construction material was manufactured and attest specifically to compliance with its 2 CFR 184.6 standard.

Minor additions of articles, materials, supplies, or binding agents to these construction materials do not change the categorization of the construction material.

7 LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

Replace section 7-1.02K(6)(e) with:

7-1.02K(6)(e) Scaffolding

7-1.02K(6)(e)(i) General

Section 7-1.02K(6)(e) applies to scaffolding constructed:

1. Over traffic

2. On or suspended from a bridge

3. Within a distance equal to the scaffolding height plus 6 feet from the edge of a traveled way open to traffic

Scaffolding for the Holly Street Bridge may not extend within the arroyo seco channel or within 15ft of the channel walls.

Scaffolding walking surface must be solid and gap free to prevent tools, materials, and debris from falling into the Arroyo Seco Channel or Arroyo Seco Blvd.

Section 7-1.02K(6)(e) does not apply to scaffolding at sound walls, retaining walls, and buildings.

Submit 6 copies of scaffolding shop drawings and 1 copy of scaffolding calculations.

The shop drawings and calculations must be sealed and signed by:

1. Engineer who is registered as a civil engineer

2. Independent checker who is:

2.1. Registered as a civil engineer in the State of California.

2.2. Not employed by the same entity that prepared the drawings or calculations

The shop drawings must include:

1. Descriptions, calculations, and values for loads anticipated during scaffolding erection, use, and removal.

2. Methods and equipment for erecting, moving, and removing scaffolding.

3. Design details, including bolt layouts, welding details, and connections to existing structures.

4. Stress sheets showing summary of computed stresses in the scaffolding and in the connections between the scaffolding and existing structures. The computed stresses must include the effects of erection, movement, and removal of the scaffolding.

5. If manufactured scaffolding is used, include the manufacturer's:

5.1. Name, address, and telephone number

5.2. Written design load capacities for the scaffolding

Submit scaffolding drawings and calculations to the engineer for review and approval. The review will require 20 days for review.

Welding must comply with AWS D1.1 for steel and AWS D1.2 for aluminum.

7-1.02K(6)(e)(ii) Bridge Scaffolding

7-1.02K(6)(e)(ii)A General

Section 7-1.02K(6)(e)(ii) applies to construction loads, including scaffolding constructed on or suspended from a bridge.

Construction loads include scaffolding, construction equipment, personnel, and material. Construction loads must not exceed the available bridge load capacity of the existing bridge members. Scaffolding suspended from the arch must be supported within 2 feet of a spandrel columns or face of pier.

The bridge scaffolding dead load must not exceed 10psf.

Calculations must be stamped by a registered civil engineer and include:

1. Proposed construction loading plan and weights of each scaffolding construction component.

2. Detailed descriptions of the construction loading distribution to the girder system. Treat construction loads distributed to the girders and other components of the structural system as dead load. Include additional loads imposed on the existing structure during:

2.1. Scaffolding erection, movement, and removal

2.2. Construction while scaffolding is in place or being moved

3. Moment and shear construction load demand envelope at each bridge girder, stringer, arch rib and floor beam, if applicable.

4. Moment and shear demand envelope of each bridge girder based on the uniform load that represents the available bridge load capacity. Treat the uniform loading distribution as dead load.

5. Calculate the capacity of each bridge girder or structural element and compare against moment and shear demand envelopes.

6. Evaluations on the adequacy of the existing bridge components at and near the scaffolding attachment points to support the construction loading, including:

6.1. Scaffolding

6.2. Construction equipment and personnel

6.3. Materials

North Arroyo Boulevard and the pedestrian walking path must remain open during construction.

Temporary closures are allowed as indicated in section 12.

Add to the beginning of section 7-1.02M(2) with:

Locate flammable materials at east 50 feet away from equipment service, parking, and gas and oil storage areas. Each small mobile or stationary engine site must be cleared of flammable material for a radius of at least 15 feet from the engine.

Each area to be cleared and grubbed must be cleared and kept clear of flammable material such as dry grass, weeds, brush, downed trees, oily rags and waste, paper, cartons, and plastic waste. Before clearing and grubbing, clear a fire break at the outer limits of the areas to be cleared and grubbed. Other fire breaks may be ordered and are change order work.

If the fire danger rating reaches very high:

1. Falling of dead trees or snags must be discontinued.

2. No open burning is permitted and fires must be extinguished.

3. Welding must be discontinued except in an enclosed building or within an area cleared of flammable material for a radius of 15 feet.

4. Blasting must be discontinued.

5. Smoking is allowed only in automobiles and truck cabs equipped with an ashtray or in cleared areas immediately surrounded by a fire break unless prohibited by other authorities.

6. Vehicular travel is restricted to cleared areas except in case of emergency.

If the fire danger rating reaches extreme, take the precautions specified for a very high fire danger rating except smoking is not allowed in an area immediately surrounded by a firebreak and work of a nature that could start a fire requires that properly equipped fire guards be assigned to such operation for the duration of the work.

The Engineer may suspend work wholly or in part due to hazardous fire conditions. The days during this suspension are non—working days.

If field and weather conditions become such that the determination of the fire danger rating is suspended, section 7-1.02M(2) will not be enforced for the period of the suspension of the determination of the fire danger rating. The Engineer will notify you of the dates of the suspension and resumption of the determination of the fire danger rating.

8 PROSECUTION AND PROGRESS

Replace the row for Schedule in the table in the 2nd paragraph of section 8-1.03 with:

Schedule Baseline schedule and weekly statement of working days report

Replace Section 8-1.04B with:

Start job site activities within 60 calendar days after receiving notice that the Contract has been approved by the City Engineer authorized to represent the City.

Do not start job site activities until the City or it’s designee authorizes or accepts your submittal for:

1. CPM baseline schedule

2. WPCP or SWPPP, whichever applies

3. Temporary Support/Temporary Structures/Scaffolding shop drawings and calculations

4. Construction Staging and Traffic Control Plan

Do not start job site activities until the City or it’s designee has confirmed that all mitigation measures required per MMRP prior to start of construction has been completed

You may enter the job site only to measure controlling field dimensions and locating utilities. Such activities shall not constitute the Start of Job Site Activities and shall not establish the start of Contract Time.

Do not start other job site activities until all the submittals from the above list are authorized or accepted and the following information is received by the Resident Engineer:

1. Notice of Materials To Be Used.

2. Contingency plan for reopening closures to public traffic.

3. Written statement from the vendor that the order for electrical material has been received and accepted by the vendor. The statement must show the dates that the materials will be shipped.

4. Written statement from the vendor that the order for structural steel has been received and accepted by the vendor. The statement must show the dates that the materials will be shipped.

You may start job site activities before the 60th day after Contract approval if you:

1. Satisfy all requirements of this section before the 60th day

2. Receive authorization to start

The 60th calendar day following Contract approval is the last day specified to start job site activities.

Failure of the Contractor to obtain the required authorizations, acceptances, or information before the 60th calendar day does not extend the last day specified to start job site activities.

The Contractor shall be responsible for allowing sufficient time to prepare, submit, revise, and obtain authorization or acceptance of all required submittals and information before the 60th calendar day.

Delays resulting from the Contractor's failure to obtain the required authorizations, acceptances, or approvals, or provide the required information by the 60th calendar day, shall not entitle the…