IG_FDR_Request_Form.pdf
PDF 879 KB Posted
- Attached to
- Construction Management for Holly Street Bridge Seismic Retrofit & Rehabilitation Project (HBP)
- Solicitation number
- 2026-RFP-0213
- Issued by
- Los Angeles County, California
About this file
This is a Financial Document Review (FDR) Request Form issued by the California Department of Transportation's Independent Office of Audits and Investigations, applicable to Local Public Agencies (LPAs) contracting with Architectural & Engineering (A&E) consultants. The form is specifically designed for new proposed A&E consultant contracts valued at $1 million or greater, and for amendments involving additional subconsultants or changes to Indirect Cost Rates (ICR). The form requires LPAs to submit comprehensive financial documentation from prime consultants and all subconsultants with estimated contract costs of $500,000 and above. Financial document packages submitted between July 1, 2024 through June 30, 2025 must include ICR reports dated 2023 or newer. The form requests project identification information, contract amounts, consultant legal names, and participation amounts, along with verification that financial documents have been received according to specified requirements.
The submission requirements are categorized into four classification levels based on consultant financial documentation status. Category 1 requires a Cognizant Approval Letter from an approved reviewing agency; Category 2 applies to those requesting Safe Harbor Rate status and requires specific certifications and financial management system documentation; Category 3 requires a CPA Audited ICR Report and Schedule with supporting financial statements; and Category 4 applies to consultants with participation amounts of $500,000 or greater without a CPA report, requiring certification of indirect costs and financial management systems. Prime consultants must submit a CPA audited ICR report and schedule. The form notes that consultants with a current Caltrans-issued CT ID# may select "N/A" as their category and submit no additional documents. Submissions should be emailed to conformance.review@dot.ca.gov, and the Independent Office of Audits and Investigations reserves the right to request additional documentation as deemed necessary.
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Independent Office of Audits and Investigations - Financial Document Review Request Form - Revised 12/2024 1
INSPECTOR GENERAL
Financial Document Review (FDR) Request Form
• To be completed by Local Public Agencies (LPA) - one per contract.
• For new proposed Architectural & Engineering (A&E) consultant LPA contracts of $1 million or greater.
• For amendments, use only when there are additional subconsultants or changes in Indirect Cost Rate (ICR).
Email to:
conformance.review@dot.ca.gov California State Department of Transportation Independent Office of Audits and Investigations Attention: Financial Document Review Manager
Date:
Federal/State Project Number:
Check one: New Contract Amendment Other
A&E Contract Number: Total Contract or Amended Amount of:
Prime Consultant Full Legal Name:
Project Description:
List prime consultant and all Safe Harbor Rate (SHR) applicants below. In addition, list all subconsultants with estimated contract costs of $500,000 and above on this contract. Prime consultants must have a CPA audited ICR report and schedule. (Add pages if necessary.)
Consultant’s Legal Name Estimated Participation Amount Category CT ID# (if available)
I verify we received financial documents from the prime and subconsultants based on the requirements specified in this form’s checklist seen on following page.
Signature:
Name (Print): Title:
Name of Local Agency and Department:
Address:
Phone: Email:
mailto:conformance.review%40dot.ca.gov?subject=
Independent Office of Audits and Investigations - Financial Document Review Request Form - Revised 12/2024 2
CHECKLIST
FDR Requirements for A&E Consultant Indirect Cost Rate
• Requirements for total contract amount equal to or greater than $1,000,000.
• Prime and all subconsultant(s) with estimated contract costs of $500,000 and above must provide the documents marked below based on their applicable category.
Instructions
• LPAs are required to complete this form and include all applicable required documents upon submission.
• For financial document packages received between July 1, 2024 through June 30, 2025, the 2023 or newer
ICR must be submitted.
• CT ID#: This is an identification number issued by Caltrans upon review and acceptance of consultant’s
ICR(s) schedule for a specific fiscal year. The CT ID# ICR fiscal year end (FYE) must agree with the period when this form and financial documents are submitted as described above. Consultants with a current CT ID# shall include the CT ID# on page 1 of this form and select N/A as the Category; no additional documents are required at this time.
Please note: Items on this checklist may not be all inclusive. IOAI reserves the right to request additional documents as deemed necessary.
Type of Financial Documents and
Information for ICR FYE Proposed by
Consultant
CATEGORY 1:
Cognizant Approval
Letter from an approved reviewing agency for ICR FYE
Proposed
CATEGORY 2:
Requesting Safe
Harbor Rate
CATEGORY 3:
CPA Audited ICR
Report
CATEGORY 4:
Participation Amount of $500K or Greater and No CPA Report
Certification of Indirect Costs and Financial Management System Form
CPA Audited ICR Report and Schedule (Prime Consultant must have a CPA Audited ICR Schedule)
ICR Schedule with FAR References for Disallowed Costs (a)
Cognizant Approval Letter for the ICR FYE proposed
AASHTO Internal Control Questionnaire Appendix B
(a) See Table 8-1 of the AASHTO Audit Guide for a listing of common unallowable costs.
Post-Closing Trial Balance and Supplemental Reconciliation Schedule (to tie the proposed ICR Schedule to the Trial Balance)
Uncompensated Overtime Adjustments
Executive Compensation Analysis (ECA) of Eligibility of Contract Consultant Certification Safe Harbor Rate:
Management System Costs and Financial
Independent Office of Audits and Investigations - Financial Document Review Request Form - Revised 12/2024 3
Some or all of the documents listed below may be requested:
• Prior Year ICR Schedule
• Related Party Rent Analysis
• Chart of Accounts
• Income Statement
• Vacation/Sick Policy
• Bonus Policy
• Vehicle, Equipment, and Other Direct Costs Schedules
The following documents can be retrieved from https://oig.dot.ca.gov/resources:
• Certification of Indirect Costs and Financial Management System
• AASHTO Internal Control Questionnaire Appendix B
• Safe Harbor Rate – Consultant Certification of Eligibility of Contract Costs and Financial Management
System
Type of Financial Documents and
Information for ICR FYE Proposed by
Consultant
CATEGORY 1:
Cognizant Approval
Letter from an approved reviewing agency for ICR FYE
Proposed
CATEGORY 2:
Requesting Safe
Harbor Rate
CATEGORY 3:
CPA Audited ICR
Report
CATEGORY 4:
Participation Amount of $500K or Greater and No CPA Report https://ig.dot.ca.gov/resources
| Cat 2 2: Off |
| Cat 1 3: Off |
| Cat 2 3: Off |
| Cat 4 3: Off |
| Cat 2 4: Off |
| Cat 2 5: Off |
| Cat 3 5: Off |
| Cat 4 5: Off |
| Cat 1 9: Off |
| Cat 2 9: Off |
| Cat 3 9: Off |
| Cat 1 20: Off |
| Cat 2 20: Off |
| Cat 3 20: Off |
| Cat 1 15: Off |
| Cat 2 15: Off |
| Cat 3 15: Off |
| Cat 1 7: Off |
| Cat 3 7: Off |
| Cat 4 7: Off |
| Date1_af_date: |
| Fed / State Project Number: |
| Other Describe: |
| Total Contract or Amended Amount of: |
| Prime Consultant Full Legal Name:: |
| Other Check: Off |
| Amendment: Off |
| AE Contract Number: |
| Project Description: |
| New Contract: Off |
| Consultant Name 1: |
| Consultant Name 2: |
| Consultant Name 3: |
| Consultant Name 4: |
| Consultant Name 5: |
| Consultant Name 6: |
| Consultant Name 7: |
| Consultant Name 8: |
| Estimated Contract Costs 1: |
| Estimated Contract Costs 2: |
| Estimated Contract Costs 3: |
| Estimated Contract Costs 4: |
| Estimated Contract Costs 5: |
| Estimated Contract Costs 6: |
| Estimated Contract Costs 7: |
| Estimated Contract Costs 8: |
| Cat 1: [] |
| Cat 3: [] |
| Cat 4: [] |
| Cat 5: [] |
| Cat 6: [] |
| Cat 7: [] |
| Cat 8: [] |
| Cat 2: [] |
| Caltrans ICR Acceptance ID 1: |
| Caltrans ICR Acceptance ID 2: |
| Caltrans ICR Acceptance ID 3: |
| Caltrans ICR Acceptance ID 4: |
| Caltrans ICR Acceptance ID 5: |
| Caltrans ICR Acceptance ID 6: |
| Caltrans ICR Acceptance ID 7: |
| Caltrans ICR Acceptance ID 8: |
| Title: |
| Name Print: |
| Name of Local Agency and Department:: |
| Email: |
| Phone: |
| Address: |
| Cat 2 6: Off |
File details come from the government source that posted it. Updated .