Technical Exhibit 2-3_Boiler_Annually.pdf

PDF 98 KB Posted

Attached to
Inspection, Testing and Maintenance (ITM) of Mechanical Equipment at USAG Humphreys
Solicitation number
W91QVN24R0007
Issued by

About this file

The provided document is a Technical Exhibit outlining the annual inspection and maintenance tasks for a hot water boiler system. The key tasks include visual inspections, functional testing, adjustments, and cleaning/reconditioning of various boiler components such as the flue, dampers, fuel valves, safety switches, and water treatment. The tasks are organized into a detailed 42-step checklist to be performed by a technician.

This Technical Exhibit is related to Solicitation Number W91QVN24R0007 for the Inspection, Testing and Maintenance (ITM) of Mechanical Equipment at USAG Humphreys. The solicitation is issued by the Department of the Army Materiel Command Army Contracting Command, with a proposal submission deadline of 24 May 24, 13:00 hrs, Korean Time.

View the file

Other files

File Type Posted
Revised Technical Exhibit 1-2_Air Conditioning Equipment.pdf PDF
AMENDMENT 3 W91QVN24R00070003.docx DOCX document
AMENDMENT 2 W91QVN24R00070002.docx DOCX document
ATTACHMENT 1 PWS (AMENDMENT 2).docx DOCX document
AMENDMENT W91QVN24R00070001.docx DOCX document
Technical Exhibit 3-11_Historical_Data_WorkOrder_Analysis.pdf PDF
Technical Exhibit 2-8_Fan Coil Unit_Semi Annually.pdf PDF
Technical Exhibit 3-5_Historical_Data_AC-Minor.pdf PDF
Technical Exhibit 1-1 Boiler.pdf PDF
Technical Exhibit 3-2_Historical_Data_Boiler-Major.pdf PDF
Technical Exhibit 3-4_Historical_Data_Gas_Major.pdf PDF
Technical Exhibit 1-8_Gas line.pdf PDF
Technical Exhibit 3-7_Historical-Data_AC-Minor-YongIn.pdf PDF
Technical Exhibit 1-9_Gas Equipment list in mechanical room.pdf PDF
Technical Exhibit 3-1_Historical-Data_Boiler-Minor.pdf PDF
Technical Exhibit 2-2_Boiler_Quarterly.pdf PDF
Technical Exhibit 4_IMCOM_Facility_Maintenance_Instruction.pdf PDF
Technical Exhibit 3-8_Historical-Data_AC-Minor-ICheon.pdf PDF
Technical Exhibit 2-6_Electric Hot Water Heater_Annually.pdf PDF
Technical Exhibit 1-6_Governor.pdf PDF
Technical Exhibit 1-7_Inside facility.pdf PDF
ATTACHMENT 1 PWS.docx DOCX document
SOLICITATION W91QVN24R0007.docx DOCX document
Technical Exhibit 2-12_Unit Heater_Semi Annually.pdf PDF
Technical Exhibit 2-13_Gas Infrared Tube Heater_Semi Annually.pdf PDF
Technical Exhibit 1-4_Heating Systems.pdf PDF
Technical Exhibit 2-4_Electric Heater_Semi Annually.pdf PDF
Technical Exhibit 2-11_Hot Water Storage Tank_Semi Annually.pdf PDF
Technical Exhibit 6_Garrison Accident Report.pdf PDF
Technical Exhibit 5_Excavation_Permit_Form.pdf PDF
Technical Exhibit 2-16_DX type_Quarterly.pdf PDF
TEs.PNG PNG image
Technical Exhibit 1-5_Unit Heater (Water Type).pdf PDF
Technical Exhibit 2-5_Electric Hot Water Heater_Monthly.pdf PDF
Technical Exhibit 2-10_Fuel Tank and Dike_Monthly.pdf PDF
Technical Exhibit 2-7_Energey Recovery Unit_Quarterly.pdf PDF
Technical Exhibit 3-3_Historical-Data_Gas-Minor.pdf PDF
Technical Exhibit 2-15_Chiller_Quarterly.pdf PDF
Technical Exhibit 3-6_Historical_Data_AC-Major.pdf PDF
Technical Exhibit 1-2_Air Conditioning Equipment.pdf PDF
Technical Exhibit 2-1_Boiler_Monthly.pdf PDF
Technical Exhibit 2-18_System HEAT PUMP AC_Quarterly.pdf PDF
Technical Exhibit 7_Safety Plan Review Checklist.pdf PDF
Technical Exhibit 3-9_Historical_Data_Kitchen-Minor.pdf PDF
Technical Exhibit 1-3_Kitchen Equipment and Mechanical Equipment.pdf PDF
Technical Exhibit 2-14_Warm Air Furnace_Semi Annually.pdf PDF
Technical Exhibit 2-17_Stand and Wall TYPE AC_Quarterly.pdf PDF
Technical Exhibit 3-10_Historical-Data_Kitchen-Major.pdf PDF
Technical Exhibit 2-9_Infrared Heater_Semi Annually.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technician :

MFR :

Step# CHK

18 Make visual inspection of the flue, vent, stack or outlet dampers linkage for proper operation.

Perform visual opacity checks IAW unmanned boiler SOP.

Check condition of flue pipe, damper & exhaust stack.

Check operation & condition of safety pressure relief valve.

Test low draft, fan, air pressure & damper position interlocks.

Check low fire start interlock.

Test high & low oil pressure & temperature interlocks.

Test high & low gas pressure & temperature interlocks.

Test operation of low water fuel cutoff devices.

Check hot water pressure gauges.

Inspect and clean or replace water column sightglass.

Check operation of mercury control switches (i.e., hot water temp limit atomizing or combustion air proving, etc.)

Check fuel lines & connections for damage.

Open limit switch and make aural and visual check of the pilot and/or main fuel valves; check valve position indicators

Hot Water Boiler (H.W.H.B & D.H.W.H)

Bldg No. : Date :

Job Plan Title Annual

Task

Make visual inspection of the igniter.

Check both pilot & main flame signal strength.

Check flame failure detection system. Close manual fuel supply pilot & main; check safety shutdown timing and log.

Check firing rate control and verify factory settings.

CAPACITY : MODEL :

Step# CHKTask

Remark

Test fuel valve interlock switch IAW manufacturers instructions.

Perform leakage test on pilot & main gas and/or fuel valves IAW manufacturers instructions.

Test purge switch IAW manufacturers instructions.

Check and adjust boiler water chemicals

Test low fire start interlock IAW manufacturers instructions.

Test air/steam interlock IAW manufacturers instructions.

Test burner position interlock IAW manufacturers instructions.

Check dual fuel change over control.

Recondition or replace low water fuel cutoff device.

Test high limit & operating temperature or steam pressure controls.

Test safety/safety relief valves IAW ASME boiler & pressure vessel code, sections VI and VII.

Clean gas train drip leg & oil system atomizers & strainers; vacuum boiler.

Wash and layup boiler.

For pilot and/or main fuel valves Check all coils & diaphragms; test all other operating parts of all safety shutoff & control valves.

Check for proper operational response of burner to thermostat controls.

Check & lubricate burner & blower motors.

Check flame failure detection system components, such as vacuum tubes, amplifier, and relays.

Check piping and wiring of all interlocks and shutoff valves.

Inspect burner components IAW manufacturers instructions.

Check combustion chamber for air & gas leaks.

Conduct pilot turndown test IAW manufacturers instructions.

Replace vacuum tubes, scanners, or flame rods IAW manufacturers instructions.

Test for hot refractory hold in.

Conduct a combustion test of the firing rate control; verify factory settings.

HWB(A)