Technical Exhibit 2-2_Boiler_Quarterly.pdf

PDF 93 KB Posted

Attached to
Inspection, Testing and Maintenance (ITM) of Mechanical Equipment at USAG Humphreys
Solicitation number
W91QVN24R0007
Issued by

About this file

This document is a Technical Exhibit titled "Boiler Quarterly" that provides a detailed checklist of inspection and maintenance tasks to be performed on a hot water boiler on a quarterly basis. The checklist covers various components of the boiler system, including the flame failure detection system, pressure and temperature interlocks, fuel valves, flue pipe, safety relief valve, and burner controls. The document is likely part of a larger contract or solicitation for the inspection, testing, and maintenance of mechanical equipment at USAG Humphreys, as evidenced by the related federal contract opportunity.

The federal contract opportunity is for the Inspection, Testing and Maintenance (ITM) of Mechanical Equipment at USAG Humphreys, with a solicitation number of W91QVN24R0007. The contract is being issued by the Department of the Army Materiel Command Army Contracting Command, and responses are due by 24 May 24, 13:00 hrs, Korean Time.

View the file

Other files

File Type Posted
Revised Technical Exhibit 1-2_Air Conditioning Equipment.pdf PDF
AMENDMENT 3 W91QVN24R00070003.docx DOCX document
AMENDMENT 2 W91QVN24R00070002.docx DOCX document
ATTACHMENT 1 PWS (AMENDMENT 2).docx DOCX document
AMENDMENT W91QVN24R00070001.docx DOCX document
Technical Exhibit 3-11_Historical_Data_WorkOrder_Analysis.pdf PDF
Technical Exhibit 2-8_Fan Coil Unit_Semi Annually.pdf PDF
Technical Exhibit 2-3_Boiler_Annually.pdf PDF
Technical Exhibit 3-5_Historical_Data_AC-Minor.pdf PDF
Technical Exhibit 1-1 Boiler.pdf PDF
Technical Exhibit 3-2_Historical_Data_Boiler-Major.pdf PDF
Technical Exhibit 3-4_Historical_Data_Gas_Major.pdf PDF
Technical Exhibit 1-8_Gas line.pdf PDF
Technical Exhibit 3-7_Historical-Data_AC-Minor-YongIn.pdf PDF
Technical Exhibit 1-9_Gas Equipment list in mechanical room.pdf PDF
Technical Exhibit 3-1_Historical-Data_Boiler-Minor.pdf PDF
Technical Exhibit 4_IMCOM_Facility_Maintenance_Instruction.pdf PDF
Technical Exhibit 3-8_Historical-Data_AC-Minor-ICheon.pdf PDF
Technical Exhibit 2-6_Electric Hot Water Heater_Annually.pdf PDF
Technical Exhibit 1-6_Governor.pdf PDF
Technical Exhibit 1-7_Inside facility.pdf PDF
ATTACHMENT 1 PWS.docx DOCX document
SOLICITATION W91QVN24R0007.docx DOCX document
Technical Exhibit 2-12_Unit Heater_Semi Annually.pdf PDF
Technical Exhibit 2-13_Gas Infrared Tube Heater_Semi Annually.pdf PDF
Technical Exhibit 1-4_Heating Systems.pdf PDF
Technical Exhibit 2-4_Electric Heater_Semi Annually.pdf PDF
Technical Exhibit 2-11_Hot Water Storage Tank_Semi Annually.pdf PDF
Technical Exhibit 6_Garrison Accident Report.pdf PDF
Technical Exhibit 5_Excavation_Permit_Form.pdf PDF
Technical Exhibit 2-16_DX type_Quarterly.pdf PDF
TEs.PNG PNG image
Technical Exhibit 1-5_Unit Heater (Water Type).pdf PDF
Technical Exhibit 2-5_Electric Hot Water Heater_Monthly.pdf PDF
Technical Exhibit 2-10_Fuel Tank and Dike_Monthly.pdf PDF
Technical Exhibit 2-7_Energey Recovery Unit_Quarterly.pdf PDF
Technical Exhibit 3-3_Historical-Data_Gas-Minor.pdf PDF
Technical Exhibit 2-15_Chiller_Quarterly.pdf PDF
Technical Exhibit 3-6_Historical_Data_AC-Major.pdf PDF
Technical Exhibit 1-2_Air Conditioning Equipment.pdf PDF
Technical Exhibit 2-1_Boiler_Monthly.pdf PDF
Technical Exhibit 2-18_System HEAT PUMP AC_Quarterly.pdf PDF
Technical Exhibit 7_Safety Plan Review Checklist.pdf PDF
Technical Exhibit 3-9_Historical_Data_Kitchen-Minor.pdf PDF
Technical Exhibit 1-3_Kitchen Equipment and Mechanical Equipment.pdf PDF
Technical Exhibit 2-14_Warm Air Furnace_Semi Annually.pdf PDF
Technical Exhibit 2-17_Stand and Wall TYPE AC_Quarterly.pdf PDF
Technical Exhibit 3-10_Historical-Data_Kitchen-Major.pdf PDF
Technical Exhibit 2-9_Infrared Heater_Semi Annually.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technician :

MFR :

Step# CHK

Remark

Date :

Check flame failure detection system components, such as vacuum tubes, amplifier, and relays.

Hot Water Boiler (H.W.H.B & D.H.W.H)

Test high & low oil pressure & temperature interlocks.

Test high & low gas pressure & temperature interlocks.

Test operation of low water fuel cut-off devices.

Check hot water pressure gauges.

Check firing rate control and verify factory settings

Open limit switch and make aural and visual check of the pilot and/or main fuel valves; check valve position indicators

Check condition of flue pipe, damper & exhaust stack.

Check operation & condition of safety pressure relief valve.

Test low draft, fan, air pressure & damper position interlocks.

Check low fire start interlock.

Bldg No. :

Job Plan Title Quarterly

CAPACITY : MODEL :

Task

Inspect burner components IAW manufacturers instructions.

Make visual inspection of the igniter.

Check both pilot & main flame signal strength.

Check flame failure detection system. Close manual fuel supply pilot & main; check safety shutdown timing and log.

Check fuel lines & connections for damage.

Perform visual opacity checks IAW unmanned boiler SOP.

Inspect and clean or replace water column sightglass.

Check operation of mercury control switches (i.e., hot water temp limit atomizing or combustion air proving, etc.)

Make visual inspection of the flue, vent, stack or outlet dampers linkage for proper operation.

Check for proper operational response of burner to thermostat controls.

Check & lubricate burner & blower motors.

Check piping and wiring of all interlocks and shutoff valves.

HWB(Q)