Section 09 65 00 Resilient Flooring.pdf
PDF 31 KB Posted
- Attached to
- DLA Fitness Center Renovation Federal contract opportunity
- Solicitation number
- 1430
About this file
This section specification outlines resilient flooring requirements for the DLA Fitness Center Renovation project solicited by the Department of the Army Corps of Engineers Engineering District Norfolk as solicitation 1430. Luxury vinyl tile meeting ASTM F1700 Class III printed film with a 0.022 inch wear layer and 0.244 inch overall thickness is required for the fitness center floors. Wall base must meet ASTM F1861 Type TS or TP and be 4 inches high with a 1/8 inch thickness. Flooring and accessories must achieve indoor air quality certifications from organizations like FloorScore or SCS. Adhesives must meet emissions or VOC content standards from certification bodies like SCAQMD or GS-36. The specification also defines requirements for moulding, surface preparation, fire resistance, submittals, testing, warranties, installation and protection.
View the file
Other files for this federal contract opportunity
Show all 32
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONVERT B32, BAYS F-G FOR FITNESS CENTER W91236-19-R-0023
DEFENSE SUPPLY CENTER RICHMOND (DSCR)
SECTION 09 65 00
RESILIENT FLOORING
08/10
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E648 (2017a) Standard Test Method for Critical Radiant Flux of Floor-Covering Systems Using a Radiant Heat Energy Source
ASTM F1482 (2015) Installation and Preparation of Panel Type Underlayments to Receive Resilient Flooring
ASTM F1700 (2018a) Standard Specification for Solid Vinyl Floor Tile
ASTM F1861 (2016) Standard Specification for Resilient Wall Base
ASTM F710 (2019) Standard Practice for Preparing Concrete Floors to Receive Resilient Flooring
CALIFORNIA DEPARTMENT OF PUBLIC HEALTH (CDPH)
CDPH Standard Method v1.1 (2010; Version 1.1) Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources using Environmental Chambers
GREEN SEAL (GS)
GS-36 (2013) Adhesives for Commercial Use
SCIENTIFIC CERTIFICATION SYSTEMS (SCS)
SCS SCS Global Services (SCS) Indoor Advantage
SOUTH COAST AIR QUALITY MANAGEMENT DISTRICT (SCAQMD)
SCAQMD Rule 1168 (2017) Adhesive and Sealant Applications
UNDERWRITERS LABORATORIES (UL)
UL 2818 (2013) GREENGUARD Certification Program For Chemical Emissions For Building Materials, Finishes And Furnishings
SECTION 09 65 00 Page 1
AMENDMENT 001
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00.00 50 SUBMITTAL
PROCEDURES:
SD-02 Shop Drawings
Resilient Flooring and Accessories ; G
SD-03 Product Data
Resilient Flooring and Accessories ; G
Adhesives
Sheet Vinyl Flooring
Luxury Vinyl Tile
Recycled content for Luxury Vinyl Tile ; S
Rubber Tile
Solid Vinyl Tile
Wall Base
SD-04 Samples
Resilient Flooring and Accessories ; G
SD-06 Test Reports
Moisture, Alkalinity and Bond Tests ; G
SD-07 Certificates
Indoor Air Quality for Luxury Vinyl Tile ; S
Indoor Air Quality for Wall Base ; S
Indoor Air Quality for Adhesives ; S
SD-08 Manufacturer's Instructions
Surface Preparation ; G
Installation ; G
SD-10 Operation and Maintenance Data
Resilient Flooring and Accessories ; G
SECTION 09 65 00 Page 2
1.3 CERTIFICATES
1.3.1 Indoor Air Quality
Submit required indoor air quality certifications and validations in one submittal package.
1.3.1.1 Floor Covering Materials
Provide Sheet Vinyl Flooring , Rubber Tile , Solid Vinyl Tile , and wall base products certified to meet indoor air quality requirements by FLOORSCORE, UL 2818 (Greenguard) Gold, SCS Global Services Indoor Advantage Gold or provide certification by other third-party programs. Provide current product certification documentation from certification body.
1.3.1.2 Adhesives, Caulking and Sealants
Provide products certified to meet indoor air quality requirements by UL 2818 (Greenguard) Gold, SCS Global Services Indoor Advantage Gold or provide certification or validation by other third-party programs that products meet the requirements of this Section. Provide current product certification documentation from certification body. When product does not have certification, provide validation that product meets the indoor air quality product requirements cited herein.
1.4 ENVIRONMENTAL REQUIREMENTS
Maintain areas to receive resilient flooring at a temperature above 68 degrees F and below 85 degrees F for 3 days before application, during application and 2 days after application, unless otherwise directed by the flooring manufacturer for the flooring being installed. Maintain a minimum temperature of 55 degrees F thereafter. Provide adequate ventilation to remove moisture from area and to comply with regulations limiting concentrations of hazardous vapors.
1.5 SCHEDULING
Schedule resilient flooring application after the completion of other work which would damage the finished surface of the flooring.
1.6 WARRANTY
Provide manufacturer's standard performance guarantees or warranties that extend beyond a one year period.
1.7 EXTRA MATERIALS
Provide extra flooring material of each color and pattern at the rate of 5 tiles for each 1000 tiles and 5 square feet for each 1000 square feet of sheet flooring installed. Provide extra wall base material composed of 20 linear feet of each type, color and pattern. Package all extra materials in original properly marked containers bearing the manufacturer's name, brand name, pattern color name and number, production run, and handling instructions. Provide extra materials from the same lot as those installed. Leave extra stock at the site in location assigned by Contracting Officer.
SECTION 09 65 00 Page 3
PART 2 PRODUCTS
2.1 LUXURY VINYL TILE LVT-1
Conform to ASTM F1700 Class III printed film with a minimum wear layer thickness 0.022 inch (22 mil) and minimum overall thickness 0.244 inch .
Provide 7 by 48 inch tile. Provide tile with a factory protective finish that enhances cleanability and durability.
Provide Luxury Vinyl Tile containing a minimum of 35 percent recycled content. Provide data identifying percentage of recycled content for Luxury Vinyl Tile .
Provide certification of indoor air quality for Luxury Vinyl Tile .
2.2 WALL BASE
Conform to ASTM F1861, Type TS (vulcanized thermoset rubber) or Type TP (thermoplastic rubber), Style A (straight - installed with carpet), and Style B (coved - installed with resilient flooring) , and Style C (butt toe cove installed with 1/8 inch thick flooring). Provide 4 inch high and a minimum 1/8 inch thick wall base. Provide job formed corners in matching height, shape, and color.
Provide certification of indoor air quality for Wall Base .
2.3 MOULDING
Provide tapered mouldings of vinyl or rubber and types as recommended by flooring manufacturer for both edges and transitions of flooring materials specified. Provide vertical lip on moulding of maximum 1/4 inch . Provide bevel change in level between 1/4 and 1/2 inch with a slope no greater than 1:2.
2.4 ADHESIVES
Provide adhesives for flooring, base and accessories as recommended by the manufacturer and comply with local indoor air quality standards. Submit manufacturer's descriptive data, documentation stating physical characteristics, and mildew and germicidal characteristics.
Provide non-aerosol adhesive products used on the interior of the building (defined as inside of the weatherproofing system) that meet either emissions requirements of CDPH Standard Method v1.1 (limit requirements for either office or classroom spaces regardless of space type) or VOC content requirements of SCAQMD Rule 1168 . Provide aerosol adhesives used on the interior of the building that meet either emissions requirements of CDPH Standard Method v1.1 (use the office or classroom requirements, regardless of space type) or VOC content requirements of GS-36. Provide certification or validation of indoor air quality for adhesives .
2.5 SURFACE PREPARATION MATERIALS
Provide surface preparation materials, such as panel type underlayment, lining felt, and floor crack fillers as recommended by the flooring manufacturer for the subfloor conditions. Comply with ASTM F1482 for panel type underlayment products. Use one of the following substrates:
a. Concrete.
SECTION 09 65 00 Page 4
2.6 CAULKING AND SEALANTS
Provide caulking and sealants in accordance with Section 07 92 00 JOINT
SEALANTS.
2.7 MANUFACTURER'S COLOR, PATTERN AND TEXTURE
Provide color, pattern and texture for resilient flooring and accessories as indicated on the drawings. Provide floor patterns as specified on the drawings. Provide flooring in any one continuous area or replacement of damaged flooring in continuous area from same production run with same shade and pattern. Submit scaled drawings indicating patterns (including location of patterns and colors) and dimensions. Submit manufacturer's descriptive data and three samples of each indicated color and type of flooring, base, mouldings, and accessories sized a minimum 2-1/2 by 4 inch .
Submit Data Package 1 in accordance with Section 01 78 23.00 50 OPERATION
AND MAINTENANCE DATA.
2.8 FIRE RESISTANCE TESTING REQUIREMENTS
Provide a minimum average critical radiant flux of 0.45 watts per square centimeter for flooring in corridors and exits when tested in accordance with ASTM E648.
PART 3 EXECUTION
3.1 EXAMINATION
Examine and verify that site conditions are in agreement with the design package. Report all conditions that will prevent a proper installation .
Do not take any corrective action without written permission from the Government. Work will proceed only when conditions have been corrected and accepted by the installer. Submit manufacturer's printed installation instructions for all flooring materials and accessories, including preparation of substrate, seaming techniques, and recommended adhesives.
3.2 SURFACE PREPARATION
Provide a smooth, true, level plane for surface preparation of the flooring, except where indicated as sloped. Floor to be flat to within 3/16 inch in 10 feet . Prepare subfloor in accordance with flooring manufacturer's recommended instructions. Prepare the surfaces of lightweight concrete slabs (as defined by the flooring manufacturer) as recommended by the flooring manufacturer. Comply with ASTM F710 for concrete subfloor preparation. Floor fills or toppings may be required as recommended by the flooring manufacturer. Install underlayments, when required by the flooring manufacturer, in accordance with manufacturer's recommended printed installation instructions. Comply with ASTM F1482 for panel type underlayments. Before any work under this section is begun, correct all defects such as rough or scaling concrete, chalk and dust, cracks, low spots, high spots, and uneven surfaces. Repair all damaged portions of concrete slabs as recommended by the flooring manufacturer.
Remove concrete curing and sealer compounds from the slabs, other than the type that does not adversely affect adhesion. Remove paint, varnish, oils, release agents, sealers, waxes, and adhesives, as required by the flooring product in accordance with manufacturer's printed installation instructions.
SECTION 09 65 00 Page 5
Amendment 001**************************************************************
3.3 MOISTURE, ALKALINITY AND BOND TESTS
Determine the suitability of the concrete subfloor for receiving the resilient flooring with regard to moisture content, pH level, and adhesion by relative humidity, alkalinity tests, and bond testing. Conduct two relative humidity tests at each location in each bay designated to receive resilient flooring in accordance with ASTM F2170. Conduct the first ASTM F2170 relative humidity test at the beginning of work in a bay and before the HVAC is turned off. Conduct a second ASTM F2170 relative humidity test just prior to floor finish installation and after the HVAC is turned back on and the bay is dehumidified to determine any changes in the relative humidity of the slab since the first test. Conduct alkalinity testing as recommended by the flooring manufacturer or a minimum of one test per location . Conduct alkalinity testing at the locations in each bay designated to receive resilient flooring. Determine the compatibility of the resilient flooring adhesives to the concrete floors by a bond test in accordance with the flooring manufacturer's recommendations. Conduct bond testing at the locations in each bay indicated to receive resilient flooring (one minimum per location) . Submit to the COR copies of the test reports for relative humidity, alkalinity content of concrete slab, and bond test stating date of test, person conducting the test, and the area tested.
****************************************************************Amendment 001
3.4 GENERAL INSTALLATION
Do not install building construction materials that show visual evidence of biological growth.
3.5 PLACING LUXURY VINYL TILES
Install flooring and accessories in accordance with manufacturer's printed installation instructions. Prepare and apply adhesives in accordance with manufacturer's directions for installation method specified. Keep tile lines and joints square, symmetrical, tight, and even. Keep each floor in true, level plane, except where slope is indicated. Vary edge width as necessary to maintain full-size tiles in the field, no edge tile to be less than one-half the field tile size, except where irregular shaped rooms make it impossible. Cut flooring to fit around all permanent fixtures, built-in furniture and cabinets, pipes, and outlets. Cut, fit, and scribe edge tile to walls and partitions after field flooring has been applied.
3.6 PLACING MOULDING
Provide moulding where flooring termination is higher than the adjacent finished flooring and at transitions between different flooring materials. When required, locate moulding under door centerline.
Moulding is not required at doorways where thresholds are provided.
Secure moulding with adhesive as recommended by the manufacturer. Prepare and apply adhesives in accordance with manufacturer's printed directions.
Anchor aluminum moulding to floor surfaces as recommended by the manufacturer.
SECTION 09 65 00 Page 6
3.7 PLACING WALL BASE
Install wall base in accordance with manufacturer's printed installation instructions. Prepare and apply adhesives in accordance with manufacturer's printed directions. Tighten base joints and make even with adjacent resilient flooring. Fill voids along the top edge of base at masonry walls with caulk. Roll entire vertical surface of base with hand roller, and press toe of base with a straight piece of wood to ensure proper alignment. Avoid excess adhesive in corners.
3.8 CLEANING
Immediately upon completion of installation of flooring in a room or an area, dry and clean the flooring and adjacent surfaces to remove all surplus adhesive. Clean flooring as recommended in accordance with manufacturer's printed maintenance instructions and within the recommended time frame. As required by the manufacturer, apply the recommended number of coats and type of polish and finish in accordance with manufacturer's written instructions.
3.9 PROTECTION
From the time of installation until acceptance, protect flooring from damage as recommended by the flooring manufacturer. Remove and replace flooring which becomes damaged, loose, broken, or curled and wall base which is not tight to wall or securely adhered.
-- End of Section --
SECTION 09 65 00 Page 7
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 09 65 00 Page 8
| 09 65 00 - RESILIENT FLOORING |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SUBMITTALS |
| 1.3 CERTIFICATES |
| 1.3.1 Indoor Air Quality |
| 1.3.1.1 Floor Covering Materials |
| 1.3.1.2 Adhesives, Caulking and Sealants |
| 1.4 ENVIRONMENTAL REQUIREMENTS |
| 1.5 SCHEDULING |
| 1.6 WARRANTY |
| 1.7 EXTRA MATERIALS |
| PART 2 PRODUCTS |
| 2.1 LUXURY VINYL TILE LVT-1 |
| 2.2 WALL BASE |
| 2.3 MOULDING |
| 2.4 ADHESIVES |
| 2.5 SURFACE PREPARATION MATERIALS |
| 2.6 CAULKING AND SEALANTS |
| 2.7 MANUFACTURER'S COLOR, PATTERN AND TEXTURE |
| 2.8 FIRE RESISTANCE TESTING REQUIREMENTS |
| PART 3 EXECUTION |
| 3.1 EXAMINATION |
| 3.2 SURFACE PREPARATION |
| 3.3 MOISTURE, ALKALINITY AND BOND TESTS |
| 3.4 GENERAL INSTALLATION |
| 3.5 PLACING LUXURY VINYL TILES |
| 3.6 PLACING MOULDING |
| 3.7 PLACING WALL BASE |
| 3.8 CLEANING |
| 3.9 PROTECTION |
File details come from the government source that posted it. Updated .