S02 Drawings 2 of 2 - 553-19-101.pdf

PDF 10 MB Posted

Attached to
Z1DA--Replace Parking Structures Elevators 553-19-101 Federal contract opportunity
Solicitation number
36C25022B0071
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10

About this file

This pre-solicitation notice announces the Department of Veterans Affairs' intent to issue an invitation for bids to replace parking structure elevators at the John D. Dingell Veterans Medical Center in Detroit, Michigan. The project entails furnishing all labor, materials, equipment, and supervision to complete the work according to drawings and specifications. The work is to be performed during normal business hours excluding federal holidays. The acquisition is reserved for verified service-disabled veteran-owned small businesses. The invitation for bids is scheduled for release on September 9, 2022 via SAM.gov, with a bid due date and other relevant dates to follow in the solicitation. The contract type will be firm-fixed-price with an anticipated award within 120 days of bid opening. The project magnitude is estimated between $5 million and $10 million. Questions should be directed to the named contracting specialist by email only.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--Replace Parking Structures Elevators 553-19-101, newest first.
File Type Posted
C08 - Revised Notice of Award- 553-19-101 - signed.pdf PDF
C08 Notice of Award - 553-19-101 - KO Signed.pdf PDF
S06 36C25022B0071 0005 - 553-19-101.pdf PDF
S06 OA intake hood attached to the stanchions.pdf PDF
S06 Sump Pump location.pdf PDF
S06 36C25022B0071 0004.pdf PDF
S06 Addendum1.pdf PDF
S06 36C25022B0071 0003 - 553-19-101.pdf PDF
S06 FA001 Drawing.pdf PDF
S06 Specification14 21 10 Modern. Traction Elev.pdf PDF
S06 36C25022B0071 0002.pdf PDF
S06 - Pre-Bid Site Visit Agenda - 553-19-101.pdf PDF
S06 J-A - Yale door locks and latch sets - 553-19-101 - KO Signed.pdf PDF
S06 J-A - Siemens Electrical Systems Components - 553-19-101 - KO Signed.pdf PDF
S06 J-A - Security 2000 card readers - 553-19-101 - KO Signed.pdf PDF
S06 J-A - Hilti Firestopping system - 553-19-101 - KO Signed.pdf PDF
S06 J-A - En-Gauge Fire Extinguisher Monitoring system - 553-19-101 - KO Signed.pdf PDF
S06 J-A - Siemens HVAC and BMS Components - 553-19-01 - KO Signed.pdf PDF
S06 36C25022B0071 0001 - 553-19-101.pdf PDF
S06 J-A - Simplex Fire Protection System - 553-19-101 - KO Signed.pdf PDF
S06 Pre-Bid Site Visit Attendance Log 553-19-101.pdf PDF
S02 36C25022B0071_1 - 553-19-101.pdf PDF
S02 Wage Determination - MI20220101 - 09-16-22 - 553-19-101.pdf PDF
S02 Project Specifications - 553-19-101.pdf PDF
S02 RFI Form - 553-19-101.doc DOC document
S02 Contractor EMR Certification Form - 553-19-101.docx DOCX document
S02 Drawings 1 of 2 - 553-19-101.pdf PDF
36C25022B0071.docx DOCX document
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DN

SD-B

SD-A.9

SD-A

SD-AA

SD-CC

SD-DD

SD-EE

1 SD-.9 SD-1 SD-1.6 SD-2SD-1.9 SD-2.3 SD-2.7 SD-2.8

EXISTING 3" UP TO RD

4" SD 4"

4" SD

4"

EXISTING 3" UP TO RD

4" SD

ELEVATOR LOBBY

SP601

STAIR #1

ELEV

101-1

ELEV

101-2

FUTURE ELEV

101-3

UNASSIGNED

CO

CO

CO

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

S S S S

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:2

A

M

PD103

5TH LEVEL PLUMBING DEMOLITION

PLAN - BUILDING 101

2 12WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

N O

R T H

0 2 4 8

Scale: 1/4" = 1'-0"

5TH LEVEL PLUMBING DEMOLITION PLAN - BLDG 101

1 REMOVE EXISTING PIPING AS INDICATED FOR

REROUTING ALONG WALLS.

DocuSign Envelope ID: A2E84575-819A-4324-B109-CAAD6666B90C

3/23/2022

ND-4 ND-3 ND-2.8 ND-2.7 ND-2.3 ND-2 ND-1.9 ND-1.8 ND-1.6 ND-1 ND-.9

ND-DD

ND-CC

ND-BB

ND-AA

ND-A.9

ND-A

ND-B

3" PD

ELEVATOR PIT

SP-2

SP-1

STAIR #1

STAIR #1

PUMP ROOM

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

S S S S

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:3

A

M

PD111

BASEMENT PLUMBING DEMOLITION

PLAN - BUILDING 102

3 12WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

N O

R T H

0 2 4 8

Scale: 1/4" = 1'-0"

BASEMENT PLUMBING DEMOLITION PLAN - BLDG 102

1 REMOVE EXISTING VERTICAL SUMP PUMPS,

MOTORS, AND RELATED PIPING AS INDICATED FOR

REPLACEMNT.

ND-2.8 ND-2.7 ND-2.3 ND-2 ND-1.9 ND-1.8 ND-1.6 ND-1 ND-.9 31

ND-CC

ND-BB

ND-AA

ND-A.9

ND-A

L

ND-B

EXISTING 3" UP TO RD

EXISTING 3" UP TO RD

STAIR #1

ELEVATOR LOBBY

NP601

ELEV

102-3

ELEV

102-2

FUTURE ELEV

102-1

UNASSIGNED

1 4"

4" SD

CO

CO

4" SD4" V

4" V

4" SD

CO

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

S S S S

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:3

A

M

PD113

5TH LEVEL PLUMBING DEMOLITION

PLAN - BUILDING 102

4 12WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

N O

R T H

0 2 4 8

Scale: 1/4" = 1'-0"

5TH LEVEL PLUMBING DEMOLITION PLAN - BLDG 102

1 REMOVE EXISTING PIPING AS INDICATED FOR

REROUTING ALONG WALLS.

UP

SD-A.9

SD-A

SD-AA

SD-2.3

101-SP-11

43" PD

SD-B

SD-A.9

SD-A

SD-AA

SD-CC

SD-DD

SD-EE

SD-.9 SD-1 SD-1.6 SD-2SD-1.9 SD-2.3 SD-2.7 SD-2.8

3" PD42

3 5

CO

3" PD 53" PD 5

3" PD 5 6

3" PD

5 3" PD

SEE P-501/DETAIL 3 FOR ELEVATION VIEW

101-TP-1

EXISTING 6" WASTE STACK UP;

8" WASTE STACK DOWN

8" SAN

3" PD

EXISTING 6" VENT UP

8" VENT STACK DOWN

8" SAN

ELEVATOR LOBBY

SP101

EMERGENCY ELEC

SP103

ELECTRICAL

SP102

SIGNAL

SP104

STAIR #1

SPS101

ELEV

101-1

ELEV

101-2

FUTURE ELEV

101-3

CORRIDOR

WOMEN

MEN

STAIR

Room

PROVIDE NEW 1/2" DCW BRANCH &

BALL VALVE FROM EXISTING DCW

TO SERVE NEW TRAP PRIMER

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

S S S S

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:5

A

M

P-101

ELEVATOR PIT AND LOWER LEVEL

PLUMBING PLANS - BUILDING 101

5 12WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

1 NEW SUMP PUMP IN EXISTING SUMP. PIPE TO

INDIRECT WASTE INTO EXISTING SANITARY PIPE.

SEE 2/P-501.

2 ROUTE NEW PIPING IN PIT TO AVOID CONFLICT

WITH STRUCTURE, ELEVATOR EQUIPMENT, ETC.

3 PIPING UP ON WALL TO BOTTOM OF EXISTING

STRUCTURE.

4 PIPING UP ON WALL AND THROUGH, JUST ABOVE

EXISTING MECHANICAL ROOM FLOOR LEVEL.

5 PIPING TIGHT TO STRUCTURE. ROUTE NEW PIPING

TO AVOID CONFLICT WITH STRUCTURE, CONDUITS,

EQUIPMENT, ETC.

6 PIPING IN GARAGE EXPOSED TO OUTSIDE AIR TO

BE HEAT TRACED.

7 3" PUMPED DISCHARGE INTO NEW 6" TRAP ARM.

SEE 3/P-501.

8 SUMP PUMP CONTROL PANEL ON WALL WITH

BOTTOM AT 4 FEET AFF.

9 CAREFULLY PENETRATE EXISTING GLAZED BRICK

EXTERIOR WALL TO ROUTE NEW DISCHARGE

PIPING INTO THE EXISTING MECHANICAL ROOM.

N O

R T H

0 2 4 8

N O

R T H

0 2 4 8

Scale: 1/4" = 1'-0"

ELEVATOR PIT PLUMBING PLAN - BLDG 101

Scale: 1/4" = 1'-0"

LOWER LEVEL PLUMBING PLAN - BLDG 101

SD-A.9

SD-A

SD-AA

SD-CC

SD-DD

SD-EE

1 SD-.9 SD-1 SD-1.6 SD-2SD-1.9 SD-2.3 SD-2.7 SD-2.8

EXISTING 3" UP TO RD

NEW 2" UP TO RD

CO

2" SD

4" SD

4" SD

4" SD

CO

EXISTING 3" UP TO RD

4" SD

ELEVATOR LOBBY

SP601

4" SD 1

2 2" SD

2" SD

CO

FIRE STANDPIPE AND HOSE CONNECTION

ELEV

101-1

STAIR #1

ELEV

101-2

FUTURE ELEV

101-3

UNASSIGNED

CO

CO

SD-B

SD-A.9

SD-A

SD-AA

SD-CC

SD-DD

SD-EE

1 SD-.9 SD-1 SD-1.6 SD-2SD-1.9 SD-2.3 SD-2.7 SD-2.8

EXISTING 3" RD

EXISTING 3" RD

RD-2

2" SD43

STAIR #1

SPS601

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

S S S S

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:5

A

M

P-103

5TH LEVEL AND LOBBY ROOF

PLUMBING PLANS - BUILDING 101

6 12WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RBK

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

N O

R T H

0 2 4 8

Scale: 1/4" = 1'-0"

5TH LEVEL PLUMBING PLAN - BLDG 101

N O

R T H

0 2 4 8

Scale: 1/4" = 1'-0"

LOBBY ROOF PLUMBING PLAN - BLDG 101

1 PIPING TIGHT TO STRUCTURE. ROUTE NEW PIPING

TO AVOID CONFLICT WITH STRUCTURE, CONDUITS,

EQUIPMENT, ETC.

2 PIPE UP. SEE 2/P-103 FOR CONTINUATION.

3 PIPE DOWN. SEE 1/P-103 FOR CONTINUATION.

4 PIPE UP. SEE 1/P-104 FOR CONTINUATION.

SD-A.9

SD-A

SD-AA

SD-CC

SD-DD

SD-EE

1 SD-.9 SD-1 SD-1.6 SD-2SD-1.9 SD-2.3 SD-2.7 SD-2.8

2" SD

2" SD

2" SD3

STAIR #1

ELEV MACHINE ROOM

SP701

SD-B

SD-A.9

SD-A

SD-AA

SD-CC

SD-DD

SD-EE

1 SD-.9 SD-1 SD-1.6 SD-2SD-1.9 SD-2.3 SD-2.7 SD-2.8

RD-1

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

S S S S

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:0

A

M

P-104

NEW PENTHOUSE AND PENTHOUSE

ROOF PLUMBING PLANS - BUILDING

7 12WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RBK

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

N O

R T H

0 2 4 8

N O

R T H

0 2 4 8

1 PIPE DOWN FROM ROOF DRAIN ABOVE. SEE 2/P-104

FOR CONTINUATION.

2 PIPING TIGHT TO STRUCTURE.

3 PIPING DOWN. SEE 2/P-103 FOR CONTINUATION.

Scale: 1/4" = 1'-0"

NEW PENTHOUSE PLUMBING PLAN - BLDG 101

Scale: 1/4" = 1'-0"

NEW PENTHOUSE ROOF PLUMBING PLAN - BLDG 101

ND-4

ND-3 ND-2.8 ND-2.7 ND-2.3 ND-2 ND-1.9 ND-1.8 ND-1.6 ND-1 ND-.9

ND-DD

ND-CC

ND-BB

ND-AA

ND-A.9

ND-A

ND-B

1102-SP-2

102-SP-1

3" PD

STAIR #1

ELEVATOR PIT

PUMP ROOM

2" PD

2" PD

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

S S S S

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:0

A

M

P-111

BASEMENT PLUMBING PLAN - BLDG 102

8 12WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

1 NEW SUMP PUMP TO REPLACE EXISTING PUMP IN

EXISTING SUMP.

2 CONNECT NEW PUMPS TO EXISTING PIPE. PROVIDE

NEW CHECK VALVES, UNIONS, AND ISOLATION

VALVES.

3 SEE 2/P-501, SIMILAR.

4 SUMP PUMP CONTROL PANEL WITH BOTTOM AT 4

FEET AFF.

N O

R T H

0 2 4 8

Scale: 1/4" = 1'-0"

BASEMENT PLUMBING PLAN - BLDG 102

ND-2.8 ND-2.7 ND-2.3 ND-2 ND-1.9 ND-1.8 ND-1.6 ND-1 ND-.9 31

ND-CC

ND-BB

ND-AA

ND-A.9

ND-A

L

ND-B

EXISTING 3" UP TO RD

EXISTING 3" UP TO RD

4" V

4" V

NEW 2" UP TO RD

STAIR #1

ELEVATOR LOBBY

NP601

ELEV

102-3

ELEV

102-2

FUTURE ELEV

102-1

UNASSIGNED

2 5

2" SD

4" SD

4" SD

CO

CO

4" SD

4" SD

2" SD

2" SD

FIRE STANDPIPE AND HOSE CONNECTION

4" SD

CO

CO

ND-2.8 ND-2.7 ND-2.3 ND-2 ND-1.9 ND-1.8 ND-1.6 ND-1 ND-.9 31

ND-DD

ND-CC

ND-BB

ND-AA

ND-A.9

ND-AL

ND-B

EXISTING 3" RD

EXISTING 3" RD

RD-2

2" SD 3 4

4" V

4" V 3 4 5

2" SD ?

STAIR #1

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

S S S S

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:1

A

M

P-113

5TH LEVEL AND LOBBY ROOF

PLUMBING PLANS - BUILDING 102

9 12WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

N O

R T H

0 2 4 8

N O

R T H

0 2 4 8

Scale: 1/4" = 1'-0"

5TH LEVEL PLUMBING PLAN - BLDG 102

1 PIPING TIGHT TO STRUCTURE. ROUTE NEW PIPING

TO AVOID CONFLICT WITH STRUCTURE, CONDUITS,

EQUIPMENT, ETC.

2 PIPE UP. SEE 2/P-113 FOR CONTINUATION.

3 PIPE DOWN. SEE 1/P-113 FOR CONTINUATION.

4 PIPE UP. SEE 1/P-114 FOR CONTINUATION.

5 EXTEND EXISTING 4" VENT FROM 1 FOOT ABOVE

EXISTING ROOF UP IN CHASE AND TERMINATE 1

FOOT ABOVE NEW ROOF.

Scale: 1/4" = 1'-0"

LOBBY ROOF PLUMBING PLAN - BLDG 101

ND-2.8 ND-2.7 ND-2.3 ND-2 ND-1.9 ND-1.8 ND-1.6 ND-1 ND-.9

ND-CC

ND-BB

ND-AA

ND-A.9

ND-A

ND-B

STAIR #1

ELEV MACHINE ROOM

NP701

4" V

4" V

2" SD 3

PIPING DOWN. SEE 2/P-113

FOR CONTINUATION.

2" SD

2" SD

STAIR #1

ND-2.8 ND-2.7 ND-2.3 ND-2 ND-1.8 ND-1 ND-.9 31

ND-DD

ND-CC

ND-BB

ND-AA

ND-A.9

ND-AL

ND-B

RD-1

4" VTR

4" VTR

4 6

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

S S S S

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:1

A

M

P-114

NEW PENTHOUSE AND PENTHOUSE

ROOF PLUMBING PLANS - BUILDING

10 12WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

N O

R T H

0 2 4 8

Scale: 1/4" = 1'-0"

NEW PENTHOUSE PLUMBING PLAN - BLDG 102

1 PIPING DOWN FROM ROOF DRAIN ABOVE. SEE

2/P-113 FOR CONTINUATION.

2 PIPING TIGHT TO STRUCTURE.

3 PIPING DOWN. SEE 2/P-113 FOR CONTINUATION.

4 EXTEND EXISTING 4" VENT FROM 1 FOOT ABOVE

EXISTING ROOF UP IN CHASE AND TERMINATE 1

FOOT ABOVE NEW ROOF.

5 PIPE UP. SEE 2/P-114 FOR CONTINUATION.

6 PIPE DOWN. SEE 1/P-114 FOR CONTINUATION.

N O

R T H

0 2 4 8

Scale: 1/4" = 1'-0"

NEW PENTHOUSE ROOF PLUMBING PLAN - BLDG 101

NOM. SIZE (IN.)

PIPE (FT.)

TUBING (FT.)

5 FT

THRU 3/4

1 1 1/4

1 1/2

HANGER ROD

INSULATION (VAPOR

BARRIER TYPE IS

REQUIRED FOR

LOW TEMPERATURE

PIPE)

PROVIDE HIGH

COMPRESSIVE

STRENGTH

INSULATION (9 PSF

MIN. DENSITY) UNDER

INSULATION SHIELD

INSULATION SHIELD AT

HANGER

WELD

SADDLE

ADJUSTABLE CLEVIS HANGER TYPE 1 - SEE

SPECIFICATIONS

ADJUSTABLE CLEVIS HANGER TYPE 43 - SEE

SPECIFICATIONS

1/2" DIA. HANGER RODS WITH 36"

MAX. SPACING ON EACH CHANNEL

BAND

1-5/8" 12 GAUGE CHANNEL

OR 2" x 2" x 1/4" ANGLE

NOTES:

SEE SPECIFICATIONS FOR

DETAILED HANGER

REQUIREMENTS. SIDE VIEW TRAPEZE HANGER

FOR UP TO 1000 LB. UNIFORM

LOAD

1" MAX.

PROVIDE INSULATION SHIELD &

INSERT FOR ALL PIPING (8" MIN.)

2 2 1/2 3 4 5 6 8 10 12

11 12 14 16 17 19 22 23

9 10 12 13 14 16 - -

NOTE: FOR TRAPEZE HANGER TAKE SPACING OF SMALLEST SIZE ON TRAPEZE

MAXIMUM PIPE/TUBING SUPPORT SPACING

ELECTRIC OUTLET NIPC

POWER SUPPLY

MULTI-PIN CONNECTOR

AND CORD IN CONDUIT

AS REQUIRED.

OLD ELEVATOR

MACHINE ROOM

FLOOR

JUNCTION BOX

GATE VALVE

3.

4.

5.

6.

2.

1.

1. SUBMERSIBLE EFFLUENT PUMP .

2. CHECK VALVE.

3. CONTROL SYSTEM AUDIBLE AND VISUAL

ALARM WHEN PUMP DOES NOT RUN DUE TO

HIGH AMPERAGE OR HIGH LIQUID CONDITION.

PROVIDE SILENCING BUTTON FOR AUDIBLE

ALARM BUILT INTO PANEL. PANEL SHALL

HAVE ADDITIONAL CONTACT FOR A REMOTE

ALARM LOCATION.

4. PROVIDE JUNCTION BOX WITH MULTI-PIN

CONNECTOR AND CORD IN LENGTHS AS

REQUIRED.

5. COMBINED POWER CABLE, PROBE CABLE

AND FLOAT CABLE (ALL 16' LONG).

6. HIGH LIQUID ALARM FLOAT WITH CLAMP

DEVICE TO MOUNT TO PUMP DISCHARGE

PIPING.

UNION, TYP.

REDUCER FITTING AS FUNNEL

1" AIR GAP MINIMUM

PUMP DISCHARGE CENTERED

OVER SANITARY WASTE PIPE

TRAP PRIMER DISCHARGE

OVER SANITARY WASTE PIPE

NEXT TO PUMPED DISCHARGE

CONNECT TO EXISTING PIPING

EXISTING 8" SAN

6" TRAP ARM BACKWATER VALVE

EXISTING 6" SAN UP

EXISTING 6" VENT UP

TRAP PRIMER

1/2" DCW FROM PIPING IN THIS AREA

3" VENT

Engineers Architects

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:1

A

M

P-501

PLUMBING DETAILS

11 12WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

Scale: No Scale

PIPE HANGER DETAIL

Scale: No Scale

ELEVATOR PIT SUMP PUMP DETAIL

Scale: No Scale

SUMP PUMP DISCHARGE TRAP DETAIL

5TH LEVEL

54' - 6"

NEW

P

.H . R

OOF

83' - 8"

NEW

P

.H . L

EVEL

72' - 4"

5TH LEVEL

54' - 6"

NEW

P

.H . R

OOF

83' - 8"

NEW

P

.H . L

EVEL

72' - 4"

RD-1

4" SD

4" SD

EXISTING 4"

FROM LOBBY

ROOF DRAINS

EXISTING FIRE

STANDPIPE

2" SD

NEW FIRE

STANDPIPE

RD-1

NEW FIRE

STANDPIPE

EXISTING 4"

FROM LOBBY

ROOF DRAINS

EXISTING FIRE

STANDPIPE

2" SD

4" SD

4" SD

4" V

4" V

4" V

4" V

4" VTR

4" VTR

Engineers Architects

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:2

A

M

P-901

STAIRWELL STORM DRAIN PIPING

ISOMETRICS

12 12WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

Scale: No Scale

STAIRWELL STORM DRAIN PIPING ISOMETRIC - BUILDING 101

Scale: No Scale

STAIRWELL STORM DRAIN PIPING ISOMETRIC - BUILDING 102

NORTH

N O R

TH

A/E ARCHITECT / ENGINEER

AAHX AIR TO AIR HEAT EXCHANGER

AB AIR BLENDER

AAV AUTOMATIC AIR VENT

ACC AIR-COOLED CONDENSER

ACCH AIR-COOLED CHILLER

ACCU AIR-COOLED CONDENSING UNIT

ACU AIR CONDITIONING UNIT

ACD AUTOMATIC CONTROL DAMPER,

MODULATING

ACD-TP AUTOMATIC CONTROL DAMPER,TWO

POSITION

AD ACCESS DOOR

AF AFTER FILTER

AFCV AIR FLOW CONTROL VALVE

AFF ABOVE FINISHED FLOOR

AFMD AIR FLOW MEASURING DEVICE

AFW AIR FOIL WHEEL (FAN)

AHU AIR-HANDLING UNIT

AMP AMPERAGE

AP ACCESS PANEL

APD AIR PRESSURE DROP

ARI AIR CONDITIONING AND

REFRIGERATION INSTITUTE

AS AIR SEPARATOR

ASME AMERICAN SOCIETY OF MECHANICAL

ENGINEERS

AW AIR WASHER

AXF AXIAL FLOW

B BOILER

BD BUTTERFLY DAMPER

BDD BACKDRAFT DAMPER

BDR BASE BOARD RADIATOR

BFP BACKFLOW PREVENTER

BFT BOILER PLANT FIRE TUBE

BHP BRAKE HORSEPOWER

BHW HOT WATER HEATING BOILER

BHX BOILER BLOWDOWN HEAT

EXCHANGER

BIW BACKWARD INCLINED WHEEL (FAN)

BSC BIOLOGICAL SAFETY CABINETS

BT BUFFER TANK

BTU BRITISH THERMAL UNIT

BTUH BRITISH THERMAL UNIT PER HOUR

C CENTIGRADE (CELSIUS)

CC COOLING COIL

CCD COOLING COIL CONDENSATE DRAIN

CENT CENTRIFUGAL

CFH CUBIC FEET PER HOUR

CFM CUBIC FEET PER MINUTE

CFT CUBIC FEET

CFP CHEMICAL FEED PUMP

CH CHILLER

CHWP CHILLED WATER PUMP

CHW CHILLER WATER

CHWR CHILLED WATER RETURN

CHWS CHILLED WATER SUPPLY

CI CAST IRON

CM CARBON MONOXIDE

CM CUBIC METER

CM/S CUBIC METER PER SECOND

CO CLEAN OUT

CO2 CARBON DIOXIDE

COMP COMPRESSOR UNIT

COP COEFFICIENT OF PERFORMANCE

CP CONDENSATE PUMP

CU CONDENSING UNIT

CUH CABINET UNIT HEATER

CV CONSTANT VOLUME

CW COLD WATER (POTABLE)

CHWCC CHILLED WATER COOLING COIL

D DAMPER - AUTOMATIC

D-1 OUTDOOR AIR DAMPER

D-2 RETURN AIR DAMPER

D-3 RELIEF AIR DAMPER

D-4 ECONOMIZER OUTDOOR AIR

DAMPER

dB DECIBELS Db DRY-BULB TEMPERATURE

DDC DIRECT DIGITAL CONTROLS

DEG DEGREE

DF DIFFUSER

DIA DIAMETER

DIW DEIONIZED WATER

DP DEW POINT TEMPERATURE

DP DIFFUSER PLATE

DPA DIFFERENTIAL PRESSURE

ASSEMBLY

DPS DIFFERENTIAL PRESSURE SENSOR

DX DIRECT EXPANSION

DXCC DIRECT EXPANSION COOLING COIL

EA EXHAUST AIR

EAT ENTERING AIR TEMPERATURE

ECC ENGINEERING CONTROL CENTER

EER ENERGY EFFICIENCY RATIO

EF EXHAUST FAN

EG EXHAUST GRILLE

EGS EMERGENCY GAS SHUTOFF

EH EXHAUST HOOD

EJ EXPANSION JOINT

EMD END OF MAIN DRIP (STEAM)

ENT ENTERING

ESP EXTERNAL STATIC PRESSURE

EWT ENTERING WATER TEMPERATURE

EX EXISTING

F FAHRENHEIT

F&T FLOAT AND THERMOSTATIC

F/SDPR COMBINATION FIRE SMOKE DAMPER

FA FREE AREA

FC FLEXIBLE CONNECTION

FCU FAN COIL UNIT (4 PIPE)

FCW FORWARD CURVED WHEEL (FAN)

FD FLOOR DRAIN

FD FIRE DAMPER

FF FINAL FILTER

FM FLOW METER

FPM FEET PER MINUTE

FPS FEET PER SECOND

FRP FIBER REINFORCED POLYESTER

FS FLOW SWITCH

FSTAT FREEZESTAT

FT FEET

FT-LB FOOT-POUND

FTR FIN TUBE RADIATION

FV FACE VELOCITY

GA GAUGE

GAL GALLONS

GH GRAVITY HOOD

GPD GALLONS PER DAY

GPH GALLONS PER HOUR

GPM GALLONS PER MINUTE

GS GALVANIZED STEEL

H HUMIDIFIER

H&CW HOT & COLD WATER

HAC HOUSEKEEPING AID CLOSET

HB HOSE BIBB

HC HEATING COIL

HD HEAD

HD HOOD

HHW HEATING HOT WATER

HHWC HEATING HOT WATER COIL

HHWP HEATING HOT WATER PUMP

HHWR HEATING HOT WATER RETURN

HHWS HEATING HOT WATER SUPPLY

HOA HAND/OFF/AUTOMATIC

HP HEAT PUMP

HP HORSEPOWER

HPDT HIGH PRESSURE DRIP TRAP

HPR HIGH PRESSURE RETURN (STEAM

CONDENSATE)

HPS HIGH PRESSURE SUPPLY (STEAM)

HRC HEAT RECOVERY COIL

HRD HEAT RECOVERY DEVICE

HRP HYDRONIC RADIANT (CEILING) PANEL

HRW HEAT RECOVERY WHEEL

HSTAT HUMIDISTAT

HUM HUMIDIFIER UNIT MOUNTED

HVU HEATING AND VENTILATING UNIT

HW HOT WATER

HWC HOT WATER COIL

HWUH HOT WATER UNIT HEATER

HX HEAT EXCHANGER

Hz HERTZ

I/O INPUT/OUTPUT

IAQ INDOOR AIR QUALITY

IBT INVERTED BUCKET TRAP

ICF IN-LINE CENTRIFUGAL FAN

ICU INTENSIVE CARE UNIT

ID INSIDE DIAMETER

IFB INTEGRAL FACE AND BYPASS

IN INCHES

IN HG INCHES OF MERCURY

IN WC INCH WATER COLUMN

IN WG INCH WATER GAUGE

IN-LB INCH-POUND

IPLV INTEGRATED PART LOAD VALUE

IRH INFRARED HEATER

IS INSECT SCREEN

IV INLET VANES

kg KILOGRAM kg/HR KILOGRAM PER HOUR kPa KILOPASCAL kW KILOWATT kWh KILOWATT HOUR

L LITER

L/s LITERS PER SECOND

LAT LEAVING AIR TEMPERATURE

LBS/HR POUNDS PER HOUR

LF LINEAR FOOT (FEET)

LH LATENT HEAT

LPR LOW PRESSURE RETURN (STEAM

CONDENSATE)

LPS LOW PRESSURE SUPPLY (STEAM)

LSD LINEAR SLOT DIFFUSER

LTCP LOCAL TEMPERATURE CONTROL

PANEL

LVG LEAVING

LVR LOUVER

LWT LEAVING WATER TEMPERATURE

M METER, SI UNIT

M/s METERS PER SECOND (OR

METERS/SECOND)

MA MIXED AIR

MAT MIXED AIR TEMPERATURE

MAV MANUAL AIR VENT

MAX MAXIMUM

MB MIXING BOX

MBH 1000 BTUH

MCA MINIMUM BRANCH CIRCUIT AMPACITY

MER MECHANICAL EQUIPMENT ROOM

MERV MINIMUM EFFICIENCY REPORTING

VALUE

MHP MOTOR HORSEPOWER

MIN MINIMUM

MM MILLIMETER

MOV MOTOR OPERATED VALVE

MPR MEDIUM PRESSURE RETURN (STEAM

CONDENSATE)

MPS MEDIUM PRESSURE SUPPLY (STEAM)

MTD MEAN TEMPERATURE DIFFERENCE

MVD MANUAL VOLUME DAMPER

NA NOT APPLICABLE

NC NOISE CRITERIA

NC NORMALLY CLOSED

NO NORMALLY OPEN

NOAA NATIONAL OCEANIC & ATMOSPHERIC

ADMINISTRATION

NOM NOMINAL

NPLV NON-STANDARD PART LOAD VALUE

NPSH NET POSITIVE SUCTION HEAD

NTS NOT TO SCALE

OA OUTSIDE AIR

OAI OUTSIDE AIR INTAKE

OD OUTSIDE DIAMETER

OR OPERATING ROOM

OSA OUTSIDE SUPPLY AIR

(CONDITIONED)

P PUMP

PC PUMPED CONDENSATE

PCF POUNDS PER CUBIC FOOT (FEET)

PD PRESSURE DROP

PF PRE-FILTER

PG PRESSURE GAGE

PHC PREHEAT COIL

PHCP PREHEAT COIL PUMP

PPM PARTS PER MILLION

PRV PRESSURE REGULATING VALVE

PSI POUNDS PER SQUARE INCH

PSIA POUNDS PER SQUARE INCH –

ABSOLUTE

PSIG POUNDS PER SQUARE INCH – GAGE

PSS PRIMARY SECONDARY SYSTEM

PSV PRESSURE SAFETY VALVE

R/E RETURN OR EXHAUST

RA RETURN AIR

RAT RETURN AIR TEMPERATURE

RDS ROOM DATA SHEETS

REA RELIEF AIR

RF RETURN FAN

RG RETURN GRILLE

RH RELATIVE HUMIDITY

RHC REHEAT COIL

RL REFRIGERANT LIQUID LINE

RLA RUN LOAD AMPERE

RPM REVOLUTIONS PER MINUTE

RS REFRIGERANT SUCTION

RTU ROOF TOP UNIT

RV RELIEF VALVE

SA SUPPLY AIR

SAD SOUND ATTENUATING DEVICE

SAT SUPPLY AIR TEMPERATURE

SC SHADING COEFFICIENT

SCFM STANDARD CUBIC FEET PER MINUTE

SCR SILICON CONTROLLED RECTIFIER

SD SMOKE DETECTOR

SD SUPPLY AIR DIFFUSER

SDPR SMOKE DAMPER

SDR SMOKE DAMPER (RETURN)

SDS SMOKE DAMPER (SUPPLY)

SEN SENSIBLE HEAT

SF SUPPLY FAN

SH STEAM HUMIDIFIER

SHC STEAM HEATING COIL

SI SQUARE INCHES

SP STATIC PRESSURE

SP GR SPECIFIC GRAVITY

SPD SUPPLY PROCESS AND

DISTRIBUTION

SPRV STEAM PRESSURE REDUCING VALVE

SPS STATIC PRESSURE SENSOR

SQ FT SQUARE FOOT (FEET)

SR SUPPLY AIR REGISTER

SS STAINLESS STEEL

SSR SOLID SEPARATOR

ST STEAM TRAP

SV STEAM SAFETY VALVE

SVS STEAM VENT SILENCER

T & PCV TEMPERATURE AND PRESSURE

CONTROL VALVE

TAB TESTING, ADJUSTING, BALANCE

TD TEMPERATURE DIFFERENCE

TDH TOTAL DYNAMIC HEAD

TDS TOTAL DISSOLVED SOLIDS

TP TRAP

TSP TOTAL STATIC PRESSURE

TSTAT THERMOSTAT

TU TERMINAL UNIT

UC UNDER CUT

UH UNIT HEATER

UL UNDERWRITERS LABORATORY

V VALVE

VAF VANE-AXIAL FAN

VAV VARIABLE AIR VOLUME

VD VOLUME DAMPER (MANUAL

OPPOSED BLADE)

VFD VARIABLE FREQUENCY DRIVE

VHA VETERANS HEALTH ADMINISTRATION

VI VIBRATION ISOLATOR

VP VACUUM PUMP

VPS VARIABLE PRIMARY SYSTEM

VR VACUUM (STEAM CONDENSATE)

RETURN

VSD VARIABLE SPEED DRIVE

VUH VERTICAL UNIT HEATER

W WATTS

Wb WET-BULB (TEMPERATURE)

WFCV WATER FLOW CONTROL VALVE

WFM WATER FLOWMETER

WFMD WATER FLOW MEASURING DEVICE

WG WATER GAGE

WPD WATER SIDE PRESSURE DROP

XT EXPANSION TANK

YR YEAR

CO2 CARBON DIOXIDE SENSOR

HUMIDISTAT OR HUMIDITY SENSOR

SUPPLY DIFFUSER

RETURN GRILLE

EXHAUST GRILLE

ROUND FLEX DUCT

EQUIPMENT TAG

LINEAR SLOT DIFFUSER

BALANCING DAMPER

FIRE DAMPER

SMOKE DAMPER

D

R INCLINED RISE, IN

DIRECTION OF AIRFLOW

INCLINED DROP, IN DIRECTION

OF AIRFLOW

CONNECT NEW DUCT

TO EXISTING

LIMIT OF DEMOLITION

VANED ELBOW (PROVIDE ALL

SQUARE OR RECTANGULAR

ELBOWS WITH VANES EVEN IF

SYMBOL IS MISSING)

STANDARD RADIUS ELBOW

(LONG RADIUS)

10x8 NEW DUCT (INSIDE

DIMENSIONS: WIDTH X DEPTH)

EXISTING DUCT TO REMAIN

EXISTING DUCT TO BE

DEMOLISHED

DUCT TRANSITION

END MOUNTED OR SIDEWALL GRILLE

SUPPLY

RETURN45°

45°

DN

DN

UP

UP

DNUP

STANDARD BRANCH SUPPLY OR

RETURN, NO SPLITTER (45° TAP)

SUPPLY DUCT (UP & DOWN)

EXHAUST DUCT (UP & DOWN)

RETURN DUCT (UP & DOWN)

S-60

S-15

CR-15

CHWS

CHWR

HIGH PRESSURE STEAM

PIPING (60 PSI AND ABOVE)

LOW PRESSURE STEAM PIPING

(15 PSI AND BELOW)

LOW PRESSURE STEAM

CONDENSATE RETURN

CHILLED WATER SUPPLY PIPING

CHILLED WATER RETURN PIPING

PIPE UP

PIPE DOWN

BOTTOM CONNECTION

TOP CONNECTION

CAPPED OR PLUGGED PIPE

GLOBE VALVE

GATE VALVE

BALL VALVE

STEAM SAFETY VALVE

PRESSURE REGULATING VALVE

WYE STRAINER VALVE

BALANCING VALVE

MODULATING TWO-WAY CONTROL

VALVE

STEAM TRAP

COND CONDENSATE DRAIN LINE

CR-60 HIGH PRESSURE STEAM

CONDENSATE RETURN

HWS

HWR

HEATING HOT WATER SUPPLY

PIPING

HEATING HOT WATER RETURN PIPING

RLS REFRIGERANT LINE SET (LIQUID

AND SUCTION)

CONNECT TO EXISTING PIPE

LIMIT OF DEMOLITION

INLINE CENTRIFUGAL PUMP

STEAM PRESSURE REDUCING

VALVE

DRAIN VALVE

TEST PLUG

SUPPLY

TERMINAL UNIT SUPPLY

DUCT BRANCH (CONICAL

TAP)

CHECK VALVE

FIRE / SMOKE DAMPER

VANED ELBOW (SHORT RADIUS) S-30

CR-30

MEDIUM PRESSURE STEAM

PIPING (16 PSI TO 59 PSI)

MEDIUM PRESSURE STEAM

CONDENSATE RETURN

THERMOSTAT OR TEMPERATURE SENSOR

TWO POSITION CONTROL VALVE

DIFFUSER TAG | DIFFUSER CFM

32-CU-4

EG-8 2000

MODULATING THREE-WAY

CONTROL VALVE

T

H

F

SD

FS

1. WORK SHALL CONFORM TO APPLICABLE LOCAL, STATE, AND NATIONAL CODES AND APPLICABLE VA STANDARDS.

2. INSTALL EQUIPMENT IN ACCORDANCE WITH MANUFACTURER'S WRITTEN RECOMMENDATIONS.

3. OBTAIN AND PAY FOR PERMITS, FEES, AND INSPECTIONS REQUIRED FOR THIS WORK.

4. PROVIDE NEW MATERIALS, EQUIPMENT AND PRODUCTS INCORPORATED IN THE WORK, OF A SUITABLE GRADE FOR THE PURPOSES INTENDED.

5. WHERE POSSIBLE, PROVIDE STANDARD PRODUCTS OF THE VARIOUS MANUFACTURERS EXCEPT WHERE SPECIAL CONSTRUCTION OR PERFORMANCE FEATURES ARE REQUIRED.

6. EQUIPMENT OR MATERIAL DEVIATIONS FROM INDICATED CONTRACT REQUIREMENTS SHALL BE SUBJECT TO THE APPROVAL OF THE COR. SUBMIT PROPOSED EQUIPMENT DEVIATIONS THAT ARE SIMILAR BOTH IN QUALITY AND CAPACITY TO THAT EQUIPMENT SPECIFIED, AS SOLELY DETERMINED BY THE COR.

7. PROVIDE MECHANICAL EQUIPMENT THAT IS LISTED AND LABELED BY UNDERWRITERS LABORATORIES (U.L.).

8. INSTALL EQUIPMENT AS INDICATED, ALLOWING FOR SUFFICIENT ACCESS AND CLEARANCE SPACE FOR EQUIPMENT MAINTENANCE, REPAIRS, AND REPLACEMENT.

9. INSTALL EQUIPMENT WITH PROPER CLEARANCES FOR REQUIRED PIPING AND ELECTRICAL SERVICES AND CONNECTIONS. INSTALL EQUIPMENT WITH REQUIRED ACCESS AND CLEARANCES IN ACCORDANCE WITH MANUFACTURER'S WRITTEN RECOMMENDATIONS AND APPLICABLE CODES AND STANDARDS.

10. COORDINATE LOCATION, INSTALLATION, AND ROUTING OF DUCTWORK, PIPING, AND EQUIPMENT WITH WORK OF ALL OTHER TRADES.

11. PROVIDE SUPPORT FOR MECHANICAL EQUIPMENT. COORDINATE SUPPORT LOCATIONS WITH ALL CONTRACTORS PRIOR TO INSTALLATION.

12. PROVIDE POWER CONNECTIONS TO EQUIPMENT PROVIDED UNDER THIS CONTRACT AS WORK OF DIVISION 26.

13. PROVIDE CONTROL WIRING FOR MECHANICAL EQUIPMENT AS WORK OF DIVISION 23.

14. DUCTWORK AND PIPING LAYOUTS AND LOCATIONS ARE SCHEMATIC. DO NOT SCALE THESE DRAWINGS. COORDINATE AND DETERMINE EXACT ROUTING OF DUCTWORK AND

PIPING IN THE FIELD.

15. FIELD VERIFY DIMENSIONS BY ACTUAL MEASUREMENT AND OBSERVATION BEFORE ORDERING OR FABRICATING DUCTWORK, PIPING OR EQUIPMENT.

16. NOTIFY COR REGARDING DISCREPANCIES BETWEEN CONTRACT DOCUMENTS AND EXISTING CONDITIONS OR DIMENSIONS BEFORE PERFORMING WORK. FAILURE TO VERIFY AND REPORT SHALL CONSTITUTE CONTRACTOR'S ACCEPTANCE OF EXISTING CONDITIONS AS FIT FOR THE PROPER EXECUTION OF THE WORK.

17. SEE ARCHITECTURAL DRAWINGS FOR FINAL LOCATION OF CEILING INSTALLED EQUIPMENT.

18. INSTALL DUCTWORK AND PIPING AS HIGH AS POSSIBLE AND AS CLOSE AS POSSIBLE TO BUILDING WALLS, CEILING AND FLOOR AND ROOF STRUCTURE. PROVIDE OFFSETS, FITTINGS, AND DIMENSIONAL TRANSITIONS NOT SHOWN BUT REQUIRED TO MAINTAIN MINIMUM CLEAR SPACE TO BUILDING SURFACES AT NO ADDITIONAL COST.

19. PATCH, PAINT AND CLEAN SURFACES SUSTAINING DAMAGE ASSOCIATED WITH MECHANICAL WORK OF THIS CONTRACT, UNLESS NOTED OTHERWISE.

20. SUBMIT BOUND SET OF OPERATING AND MAINTENANCE INSTRUCTIONS FOR EQUIPMENT AT COMPLETION OF PROJECT.

21. INSTALL ESCUTCHEONS IN ALL PLACES WHERE PIPING PENETRATES A WALL IN AN EXPOSED LOCATION.

22. MAKE A COMPLETE REVIEW OF DRAWINGS, INCLUDING SCHEDULES AND DETAILS, PRIOR TO BEGINNING MECHANICAL SYSTEM INSTALLATION. RESOLVE CONFLICTS WITH COR.

23. DRAWING PLANS, SCHEMATICS, AND DIAGRAMS INDICATE GENERAL LOCATION AND ARRANGEMENT OF PIPING SYSTEMS.

24. INSTALL PIPING INDICATED TO BE EXPOSED AND PIPING IN EQUIPMENT ROOMS AND SERVICE AREAS AT RIGHT ANGLES OR PARALLEL TO BUILDING WALLS. DIAGONAL RUNS ARE

NOT ACCEPTABLE UNLESS SPECIFICALLY INDICATED OTHERWISE.

25. INSTALL PIPING FREE OF SAGS AND BENDS.

26. INSTALL PIPING TO ALLOW APPLICATION OF INSULATION.

27. PIPING SHALL NOT BE ROUTED OVER TELECOM OR ELECTRICAL CLOSETS/ROOMS.

28. PREPARE DRAWINGS SHOWING MECHANICAL SYSTEMS AND EQUIPMENT FOR COORDINATION WITH WORK OF OTHER DIVISIONS AND WORK BY THE GOVERNMENT.

A. INCLUDE PLAN VIEWS, SECTIONS, AND ELEVATIONS, AS REQUIRED, TO FULLY COORDINATE ALL NEW WORK WITH ITSELF AND EXISTING CONDITIONS.

B. DRAWINGS SHALL SHOW ALL DUCTWORK, AIR DISTRIBUTION, MECHANICAL EQUIPMENT, MECHANICAL PIPING, FIRE PROTECTION PIPING, PLUMBING PIPING, CABLE TRAYS, LIGHTING FIXTURES, CEILING GRID AND HEIGHT, BEAMS AND JOISTS (WITH ELEVATIONS MARKED), ELECTRICAL CONDUIT LARGER THAN 2 INCHES IN DIAMETER AND OTHER

CEILING MOUNT DEVICES OR EQUIPMENT THAT PROTRUDE INTO THE CEILING CAVITY.

C. IF THERE ARE OUTSTANDING ISSUES THAT CANNOT BE RESOLVED, CONSULT WITH COR FOR GUIDANCE AND MAKE CORRECTIONS IN ACCORDANCE WITH DIRECTIONS GIVEN.

D. DO NOT BEGIN FABRICATION OR PLACE EQUIPMENT ORDERS UNTIL COORDINATION DRAWINGS HAVE BEEN APPROVED.

29. INSTALLATION COMMENCED PRIOR TO COORDINATION DRAWING APPROVAL IS TAKEN AT THE CONTRACTORS OWN RISK. MODIFY, MOVE OR RECONFIGURE WORK LACKING

COORDINATION AT NO ADDITIONAL COST

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

BRAND ITEM SPECIFICATION SECTION NOTES

HILTI FS1-FIRESTOP 07 84 00 BOTH SIDES OF FIRE-RATED WALLS, SMOKE BARRIERS, AND

FLOORS REGARDLESS OF FIRE RATING

DIVISION 08 - OPENINGS

BRAND ITEM SPECIFICATION SECTION NOTES

YALE LOCKS & DOOR HARDWARE 08 71 00 LARGE FORMAT 7-PIN REMOVABLE CORE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

BRAND ITEM SPECIFICATION SECTION NOTES

SIEMENS HVAC CONTROLS 23 09 23

SIEMENS BUILDING MANAGEMENT SYSTEM (BMS)

DIVISION 26 - ELECTRICAL

BRAND ITEM SPECIFICATION SECTION NOTES

SIEMENS ELECTRICAL 26 22 00

26 24 16 26 29 11 26 29 21 26 43 13

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

BRAND ITEM SPECIFICATION SECTION NOTES

SECURITY 2000 PHYSICAL SECURITY 28 13 00

28 23 00

SIMPLEX FIRE ALARM SYSTEM / VENDOR 28 31 00

EN-GAUGE EN-VISION OBSTRUCTION SENSOR 28 31 00 VA SUPPLIED / CONTRACTOR INSTALLED

Engineers Architects

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:0

A

M

M-001

MECHANICAL GENERAL INFORMATION

1 13WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

MECHANICAL ABBREVIATIONS

MECHANICAL LEGEND

MECHANICAL GENERAL NOTES

SOLE SOURCE LIST

SD-A

SD-AA

SD-CC

SD-DD

SD-EE

1 SD-.9 SD-1 SD-1.6 SD-2SD-1.9 SD-2.3 SD-2.7 SD-2.8 SD-3

1 2

ELEVATOR LOBBY

SP101

ELEVATOR LOBBY

SP101

STAIR #1

SPS101

STAIR #1

SPS101

ELECTRICAL

SP102

EMERGENCY ELEC

SP103

SIGNAL

SP104

FUTURE ELEV

101-3

ELEV

101-2

ELEV

101-1

101-EF-EX

101-EUH-EX 101-FC-LL-EX

101-CU-LL-EX

T

101-LVR-EX

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:4

A

M

MD101

LOWER LEVEL MECHANICAL

DEMOLITION PLAN - BUILDING 101

2 13WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

1 EXISTING UNIT HEATER TO REMAIN.

2 DEMOLISH EXISTING DX HVAC SYSTEM.

REFRIGERANT SHALL BE RECOVERED BY A

QUALIFIED CONTRACTOR.

3 DEMOLISH EXISTING HYDRAULIC PIPING THAT

SERVES THE HYDRAULIC ELEVATOR MACHINERY.

SEE AD101 FOR COORDINATION OF DEMOLITION.

4 EXISTING EXHAUST FAN AND INTAKE LOUVER

SYSTEM TO REMAIN.

Scale: 1/4" = 1'-0"

LOWER LEVEL MECHANICAL DEMOLITION PLAN - BLDG 101

N O

R T H

0 2 4 8

SD-B

SD-A.9

SD-A

SD-AA

SD-CC

SD-DD

SD-EE

SD-.9 SD-1 SD-1.6 SD-2SD-1.9 SD-2.3 SD-2.7 SD-2.8

SD-3

ELEVATOR LOBBY

SP601

STAIR #1

ELEV

101-1

ELEV

101-2

FUTURE ELEV

101-3

UNASSIGNED

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:4

A

M

MD103

5TH LEVEL MECHANICAL DEMOLITION

PLAN - BUILDING 101

3 13WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

1 DEMOLISH EXISTING OUTSIDE AIR INTAKE & HOOD.

SEE STRUCTURAL DRAWINGS FOR ADDITIONAL

COORDINATION.

N O

R T H

0 2 4 8

Scale: 1/4" = 1'-0"

5TH LEVEL MECHANICAL DEMOLITION PLAN - BLDG 101

ND-3 ND-2.8 ND-2.7 ND-2.3 ND-2 ND-1.9 ND-1.8 ND-1.6 ND-1 ND-.9 31

ND-CC

ND-BB

ND-AA

ND-A.9

ND-AL

ND-B

ELEVATOR LOBBY

NP101

ELEVATOR LOBBY

NP101

ELECTRICAL

NP102

EMERGENCY ELEC

NP103

SIGNAL

NP104

ELEV

102-3

ELEV

102-2

FUTURE ELEV

102-1

STAIR #1

NPS101

UNASSIGNED

NP105

STAIR #1

NPS101

102-CU-LL-EX

102-FC-LL-EX

102-EUH-EX

102-EF-EX

T

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:4

A

M

MD111

LOWER LEVEL MECHANICAL

DEMOLITION PLAN - BUILDING 102

4 13WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

Scale: 1/4" = 1'-0"

LOWER LEVEL MECHANICAL DEMOLITION PLAN - BLDG 102

N O

R T H

0 2 4 8

1 EXISTING UNIT HEATER TO REMAIN.

2 DEMOLISH EXISTING DX HVAC UNIT. REMAINING

REFRIGERANT SHALL BE REMOVED AND DISPOSED

OF BY A QUALIFIED CONTRACTOR.

3 DEMOLISH EXISTING HYDRAULIC PIPING THAT

SERVES THE HYDRAULIC ELEVATOR MACHINERY.

SEE AD112 FOR COORDINATION OF DEMOLITION.

4 EXISTING EXHAUST FAN AND INTAKE LOUVER

SYSTEM TO REMAIN.

ND-2.8 ND-2.7 ND-2.3 ND-2 ND-1.9 ND-1.8 ND-1.6 ND-1 ND-.9 31

ND-DD

ND-CC

ND-BB

ND-AA

ND-A.9

ND-A

ND-B

UNASSIGNED

NP602

FUTURE ELEV

102-1

ELEV

102-2

ELEV

102-3

ELEVATOR LOBBY

NP601

STAIR #1

NPS601

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:5

A

M

MD113

5TH LEVEL MECHANICAL DEMOLITION

PLAN - BUILDING 102

5 13WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

1 EXISTING INTAKE HOODS TO BE REMOVED.

CONTRACTOR TO INSTALL WIRE-MESH SCREENING

TO PROTECT OPENINGS DURING CONSTRUCTION.

Scale: 1/4" = 1'-0"

5TH LEVEL MECHANICAL DEMOLITION PLAN - BLDG 102

N O

R T H

0 2 4 8

SD-A

SD-AA

SD-CC

SD-DD

SD-EE

1 SD-.9 SD-1 SD-1.6 SD-2SD-1.9 SD-2.3 SD-2.7 SD-2.8 SD-3

101-CU-4

STAIR #1

ELEV

101-1

ELEV

101-2

FUTURE ELEV

101-3

ELEVATOR LOBBY

SP101

SIGNAL

SP104

EMERGENCY ELEC

SP103

ELECTRICAL

SP102

T

101-EF-EX

101-EUH-EX

T 101-MCHP-1

6x6

6x6

6x6

6x6 50RR-01

50SD-01

6x6

101-ERV-1

101-LVR-EX

S

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:1

A

M

M-101

LOWER LEVEL MECHANICAL PLAN -

BUILDING 101

6 13WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

Scale: 1/4" = 1'-0"

LOWER LEVEL MECHAINCAL PLAN - BUILDING 101

N O

R T H

0 2 4 8

1 INSTALL NEW MINI-SPLIT SYSTEM UNIT TO PROVIDE

COOLING FOR THE NEW OFFICE SPACE.

2 INSTALL NEW OUTDOOR CONDENSING UNIT

MOUNTED APPROXIMATELY 4' ABOVE GARAGE

DECK.

3 EXISTING ELECTRIC UNIT HEATER TO REMAIN.

4 EXISTING EXHAUST FAN AND INTAKE LOUVER

SYSTEM TO REMAIN.

5 CONTROL EXHAUST FAN FROM NEW OCCUPANCY

SENSOR. SEE ELECTRICAL PLANS FOR

CONNECTION DETAILS.

6 INSTALL NEW ENERGY RECOVERY VENTILATOR TO

PRE-CONDITION OUTSIDE AIR ENTERING THE

SPACE.

7 INSTALL NEW RETURN AIR REGISTER.

8 INSTALL NEW SUPPLY AIR REGISTER.

9 INSTALL NEW DDC T-STAT TO CONTROL NEW

MINI-SPLIT HEAT PUMP.

SD-B

SD-A.9

SD-A

SD-AA

SD-CC

SD-DD

SD-EE

SD-.9 SD-1 SD-1.6 SD-2SD-1.9 SD-2.3 SD-2.7 SD-2.8

ELEVATOR LOBBY

SP601

STAIR #1

ELEV

101-2

ELEV

101-1

FUTURE ELEV

101-3

STAIR #1

UNASSIGNED

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

S S S S

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:1

A

M

M-103

5TH LEVEL MECHANICAL PLAN -

BUILDING 101

7 13WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

N

KEY PLAN

SCALE: NO SCALE

BLUE

RED

1 INSTALL NEW OUTSIDE AIR INTAKE HOOD, AS

SHOWN, SEE ARCHITECTURAL DETAILS FOR

WATER-PROOFING & FLASHING REQUIREMENTS.

2 INSTALL NEW SHEET METAL ATOP EXISTING HOOD

SUPPORT STANCHIONS. NEW SHEET METAL TO

OVERHANG EXISTING SUPPORTS BY 12", ALL SIDES.

PAINT BOTTOM OF NEW SHEET METAL FLAT BLACK.

N O

R T H

0 2 4 8

Scale: 1/4" = 1'-0"

5TH LEVEL MECHANICAL PLAN - BLDG 101

SD-A

SD-AA

SD-CC

SD-DD

SD-EE

SD-.9 SD-1 SD-1.6 SD-2SD-1.9 SD-2.3 SD-2.7 SD-2.8

SD-3

101-HP-12

101-HP-2

101-HP-3

101-UH-1 4

ELEV MACHINE ROOM

SP701

STAIR #1

101-CU-1 5

101-CU-3

101-CU-2

T

T T T

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:2

A

M

M-104

NEW PENTHOUSE MECHANICAL PLAN -

BUILDING 101

8 13WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

Scale: 1/4" = 1'-0"

NEW PENTHOUSE MECHANICAL PLAN - BLDG 101

N O

R T H

0 2 4 8

1 NEW WALL LOUVERS SHALL BE INSTALLED TO

ACCOMMODATE NEW AIR INTAKE. SEE

ARCHITECTURAL DRAWINGS.

2 MOUNT NEW INDOOR MINI-SPLIT HEAT PUMP UNIT

HIGH ON WALL. LOCATE UNIT CLEAR OF

ELECTRICAL EQUIPMENT AND ELEVATOR

MACHINERY/ CONTROLS. ROUTE REFRIGERANT

PIPING DOWN THROUGH PENTHOUSE FLOOR AND

INTO THE PLENUM BELOW. CONNECT

REFRIGERANT PIPING TO OUTDOOR CONDENSING

UNIT. ROUTE AND HEAT TRACE CONDENSATE

FROM UNITS TO NEW PLENUM ROOF DRAIN.

3 NEW OUTDOOR CONDENSING UNIT MOUNTED ON

WALL RACK WITH BOTTOM AT 3 FEET ABOVE

EXISTING ROOF LEVEL.

4 NEW ELECTRIC UNIT HEATER SHALL BE INSTALLED

HIGH IN SPACE, HUNG FROM ROOF STRUCTURE.

5 INSTALL NEW DDC TEMPERATURE SENSOR AND

CONNECT TO BAS FOR SPACE TEMPERATURE

MONITORING/ALARM.

6 INSTALL NEW DDC TEMPERATURE CONTROL PANEL

ON WALL. COORDINATE EXACT LOCATION WITH

OTHER EQUIPMENT, PANELS, CONDUITS, PIPING,

AND STRUCTURE.

7 INSTALL NEW T-STAT TO CONTROL NEW MINI-SPLIT

HEAT PUMP UNIT.

ND-3 ND-2.8 ND-2.7 ND-2.3 ND-2 ND-1.9 ND-1.8 ND-1.6 ND-1 ND-.9 31

ND-CC

ND-BB

ND-AA

ND-A.9

ND-AL

ND-B

102-MCHP-1

102-CU-4

T

T

4 5

0SD-11

50RR-11

6x6 102-ERV-1

FUTURE ELEV

102-1

ELEV

102-2

ELEV

102-3

ELEVATOR LOBBY

NP101 ELECTRICAL

NP102

EMERGENCY ELEC

NP103

SIGNAL

NP104

STAIR #1

NPS101

102-LVR-EX

6x6

6x6

6x6

S

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:2

A

M

M-111

LOWER LEVEL MECHANICAL PLAN -

BUILDING 102

9 13WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

Scale: 1/4" = 1'-0"

LOWER LEVEL MECHANICAL PLAN - BLDG 102

N O

R T H

0 2 4 8

1 INSTALL NEW MINI-SPLIT SYSTEM UNIT TO PROVIDE

COOLING FOR THE NEW OFFICE SPACE.

2 INSTALL NEW OUTDOOR CONDENSING UNIT

MOUNTED APPROXIMATELY 4' ABOVE GARAGE

DECK.

3 EXISTING ELECTRIC UNIT HEATER TO REMAIN.

4 EXISTING EXHAUST FAN AND INTAKE LOUVER

SYSTEM TO REMAIN.

5 CONTROL EXHAUST FAN FROM NEW OCCUPANCY

SENSOR. SEE ELECTRICAL PLANS FOR CONNECTION

DETAILS.

6 INSTALL NEW ENERGY RECOVERY VENTILATOR TO

PRE-CONDITION OUTSIDE AIR ENTERING THE

SPACE.

7 INSTALL NEW RETURN AIR REGISTER.

8 INSTALL NEW SUPPLY AIR REGISTER.

9 INSTALL NEW DDC T-STAT TO CONTROL NEW

MINI-SPLIT HEAT PUMP.

ND-3

ND-2.8 ND-2.7 ND-2.3 ND-2 ND-1.9 ND-1.8 ND-1.6 ND-1 ND-.9 31

ND-DD

ND-CC

ND-BB

ND-AA

ND-A.9

ND-A

ND-B

ELEVATOR LOBBY

NP601

STAIR #1

ELEV

102-3

ELEV

102-2

FUTURE ELEV

102-1

STAIR #1

UNASSIGNED

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

S S S S

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95% CONSTRUCTION DOCUMENTS SUBMISSION4 08/23/2021

BID DOCUMENTS5 02/16/2022

/1

/2

:1

:2

A

M

M-113

5TH LEVEL MECHANICAL PLAN -

BUILDING 102

10 13WLF

REPLACE/ADD PARKING

STRUCTURE ELEVATORS

VAMC DETROIT 4646 JOHN R. ST.

DETROIT, MI 48201

FEBRUARY 16, 2022

BID DOCUMENTS

553-19-10118-319

101 & 102

RHA

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

BLUE

RED

Scale: 1/4" = 1'-0"

5TH LEVEL MECHANICAL PLAN - BLDG 102

N O

R T H

0 2 4 8

1 EXISTING OUTSIDE AIR INTAKES TO REMAIN.

INSTALL NEW SHEET METAL ATOP EXISTING HOOD

SUPPORT STANCHIONS. NEW SHEET METAL TO

OVERHANG EXISTING SUPPORTS BY 12", ALL SIDES.

PAINT BOTTOM OF NEW SHEET METAL FLAT BLACK.

ND-3 ND-2.8 ND-2.7 ND-2.3 ND-2 ND-1.9 ND-1.8 ND-1.6 ND-1 ND-.9

ND-CC

ND-BB

ND-AA

ND-A.9

ND-A

ND-B

102-HP-1

102-CU-1

102-HP-3

102-HP-2

102-CU-2

102-CU-3

102-UH-14

STAIR #1

NPS701

ELEV MACHINE ROOM

NP701

T

T T T

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

JOHN D. DINGELL

VA MEDICAL

CENTER

35 % SCHEMATIC DESIGN SUBMISSION 1 12/23/2020

65% DESIGN DESIGN SUBMISSION 2 04/02/2021

65% DESIGN DEVELOPMENT RE-SUBMISSION3 05/28/2021

95%…