S02 - ATCH 9 - 8) Pre-Construction Risk Assessment.pdf

PDF 193 KB Posted

Attached to
Cancelled: Y1LZ--578-371 Construction - Parking Expansion at Joliet CBOC
Solicitation number
36C77623B0049
Issued by

About this file

This document is a pre-construction risk assessment for a parking expansion project at the Joliet Community Based Outpatient Clinic. The Department of Veterans Affairs will undertake demolition and construction work to expand parking facilities, repair building infrastructure, and renovate existing spaces. Key aspects of the project include removing remnants of a prior hospital structure, repairing walls and replacing roofs, upgrading mechanical systems and relocating air handling units, and developing surrounding land. The assessment identifies various safety and environmental risks posed by construction activities and outlines mitigation plans. Hazards addressed relate to noise, vibration, emergency response, hazardous materials, confined spaces, utility disruptions, infection risks, and effects on adjacent areas. The contractor must implement dust barriers, maintain negative air pressure, and follow debris removal procedures. Upon completion, the signature of the contractor and the COR/CSO will confirm that identified risks have been addressed according to the assessment.

View the file

Other files

File Type Posted
HCA Signed PCAC S30 - Cancellation of Bids - IFB - J.pdf PDF
S30 - Attachment - Abstract of Bids - Joliet.pdf PDF
Attachment 8 - Joliet Roof Report.pdf PDF
Attachment 6 - Joliet CBOC Elect. Add. 2 230726.pdf PDF
Attachment 2 - 09 06 00 Schedule for Finishes.pdf PDF
36C77623B0049 0005 - Joliet CBOC - RFIs-Wage Rates-Bid Opening.pdf PDF
Attachment 3 - AHU Heat Pipe Design Basis.pdf PDF
Attachment 4 - Joliet CBOC Arch RCPs Add. 2 230726.pdf PDF
Attachment 5 - Joliet CBOC Ceiling Diagrams 230726.pdf PDF
Attachment 7 - M601 - MECHANICAL SCHEDULES.pdf PDF
Attachment 1 - Technical Questions - Part 2.pdf PDF
Attachment 9 - Updated Wage Rates - Will County.pdf PDF
Attachment 1 - Technical Questions - Part 1.pdf PDF
Attachment 4 - Joliet Arch RCP.pdf PDF
36C77623B0049 0004 - Joliet CBOC - Extension and RFIs.pdf PDF
Attachment 5 - Joliet CBOC Laydown Areas.pdf PDF
Attachment 3 - Joliet CBOC Geotech Proposed Parking.pdf PDF
Attachment 2 - Infection Control Risk Assessment.pdf PDF
36C77623B0049 0003 - Joliet CBOC - Second Site Visit Sign-In.pdf PDF
Pre-Bid Site Visit 2 Sign-in 578-371.pdf PDF
36C77623B0049 0002 - Second Site Visit and RFI Extension.pdf PDF
36C77623B0049 0001 - Joliet CBOC - Site Visit Sign In.pdf PDF
Pre-Bid Site Sign-in 578-371.pdf PDF
S02 - ATCH 30 - Joliet_CBOC_Issued_for_Bid_A1_Struct_Part_8.pdf PDF
S02 - ATCH 32 - Contractor Safety - Environmental Form.pdf PDF
S02 - ATCH 8 - 7) Above Ceiling Entry and Wall Const Permits.pdf PDF
S02 - ATCH 14 - 13) 578-371 Phasing Plan.pdf PDF
S02 - ATCH 33 - Wage Rates - Will County 5.12.2.pdf PDF
S02 - ATCH 27 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_5.pdf PDF
S02 - ATCH 16 - 15) No Smoking Policy 10-1-19.pdf PDF
S02 - ATCH 23 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_1.pdf PDF
S02 - ATCH 4 - 3) Pre-Con Checklist Rev 07.27.21.pdf PDF
S02 - ATCH 15 - 14) 578-371 Specifications Book.pdf PDF
S02 - ATCH 2 - 1) Joliet CBOC Aerial Site Plan.pdf PDF
S02 - ATCH 34 - Site Visit Instructions.pdf PDF
S02 - ATCH 7 - 6) Dig Permit SOP Form.pdf PDF
S02 - ATCH 26 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_4.pdf PDF
S02 - ATCH 25 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_3.pdf PDF
S02 - ATCH 31 - Limitations on Subcontracting - Construction.pdf PDF
S02 - ATCH 11 - 10) Interim Life Safety Measures (ILSM).pdf PDF
S02 - ATCH 24 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_2.pdf PDF
S02 - ATCH 17 - 16) Infection Control Barrier Sample.pdf PDF
S02 - ATCH 1 - 578-371 Construction SOW Final.pdf PDF
S02 - ATCH 6 - 5) Cutting Welding and Other Hot Work.pdf PDF
S02 - ATCH 13 - 12) OIT Horizontal Cable Requirements.pdf PDF
S02 - ATCH 18 - 17) Hines COVID-19 Guidelines.pdf PDF
S02 - ATCH 12 -11) Contractor PIV Instructions and Form.pdf PDF
S02 - ATCH 21 - Joliet_CBOC_Project_Manual_Issued_for_Bid.pdf PDF
S02 - ATCH 29 - Joliet_CBOC_Issued_for_Bid_A1_MEP_Part_7.pdf PDF
S02 - ATCH 10 - 9) Infection Control Risk Assessment.pdf PDF
Show 40 more

Latest 50 of 57 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Policy Memorandum 578-12-138A-076 (R2)

July 16, 2018

Attachment A

Pre-Construction/Safety Risk Assessment

Location of Construction (Bldg. No. /Room No.): Joliet CBOC Project No.: 578-371

Project Title: Parking Expansion at Joliet CBOC

Project Coordinator: Aaron Walsh Project Start Date: ~12/2023

Contractor Performing Work: TBD Estimated Duration: ~81 Weeks

Supervisor: Richard Fraider Telephone: (708) 202-8387 x21152

Description of Project: Demolish and remove the remnant structure left behind from the Silver Cross hospital demolition, repair the north wall and replace the roof, convert the existing boilers to a hot water system, relocate and upgrade the Air Handling Units (AHUs) from the basement mechanical room to a newly constructed penthouse above the ambulance bay, and to develop the surrounding land of the Joliet CBOC.

Construction Activities

The following projects do not require completion of the Pre-Construction/Safety Risk Assessment form:

1. Painting and installation of new wallpaper in business offices and non-patient areas.

2. Painting in a patient room, if closed for painting and less than 3 square feet of wall area is to be patched and painted. Contractor shall replace the air filter for the room’s air conditioning unit upon completion of painting.

3. Installation of a soap dispenser/needle box/paper towel holder in a patient room

4. Repair of a window blind.

5. Ceiling tile replacement for areas less than ten (10) 2’ x 2’ tiles, if not in business offices and non-patient areas.

6. Ceiling tile replacement for areas less than five (5) 2’ x 2’ tiles in a patient area, if patient is out of the immediate area and clean up can be accomplished before patient returns.

7. Minimal repair of Nurse Call System/TV/Bed/Telephone.

8. Checking or replacing of electric outlet.

9. Replacing a light bulb.

10. Unstopping sink/commode with no water on floor.

11. Unstopping commode when water on floor requires maintenance to have Housekeeping clean area immediately.

12. Repair of a medical gas outlet. (Front Body)

13. Taking air balance measurement readings.

14. Checking air conditioning unit/system.

15. Intermediate jobs that create a moderate amount of dust inside the room with negative air pressure maintained in the room via use of HEPA-equipped unit with minimum 10 ACH and all air discharged outside. The

HEPA unit must continue running 2 hours after completion of job and Housekeeping must clean room before the HEPA unit is removed from room. All work and use of HEPA unit must be documented and copies forwarded to Infection Prevention and Safety. NOTE: All duct vents to be sealed off during work!

Yes No Will there be noise generated that will impact a department adjacent to, above, or below the construction area?

X a. If so, these departments must be notified.

X b. How are you going to reduce the noise to an acceptable level? Construction being phased and services relocated.

Yes No Will there be vibration generated that will impact a department adjacent to, above, or below the construction area?

X a. If so, these departments must be notified each time this type of work will be performed.

X b. How are you going to reduce the vibration to an acceptable level? Construction being phased and services relocated.

Yes No Are Emergency Procedures in place and posted on each job for accidental events that could greatly impact Patient Care or Life Safety to the facility?

X Typically included items in these procedures are:

• Emergency telephone numbers of key departments.

• A contingency plan describing the location of main valves, switches, and controls.

• A contingency plan for unexpected outages.

Environment

Yes No Are any of the following environmental hazards present?

X Will hazardous chemicals be used on this project? How will fumes and odors be controlled? Material

Safety Data Sheets (MSDS) are required.

Reference: Hazard Communication Program 578-03-001-034 (R-1) dated January 13, 2012

X Is asbestos abatement required on this job? If so, notify Safety at the Pre-Construction Meeting.

Reference: Asbestos Management Program 578-03-001-046 (R-1) dated January 30, 2012

X Will there be hot work (welding, brazing, soldering) done on this project? If so, then a Hot Work

Permit must be posted on the job site. All hot work must have a fire watch assigned to each area while the hot work is being performed.

Reference: Cutting, Welding, and other Hot work Policy 578-03-001-089 (R-2)

X Will there be work performed above the ceiling? Will repair/construction activities involve penetration in to existing walls, ceilings, door frames, or doors? If so, must apply for an Above Ceiling Entry and

Wall Construction Permit.

Reference: Above Ceiling Entry and Wall Construction Permits 578-07-001-102 (R-2) dated December

27, 2011

X Will confined space entry be required on this project? If so, the VAMC Confined Space Entry Program must be followed.

Reference: Confined Space Program 578-12-138S-047 dated May 2, 2012

Utility Failures

Yes No Will any of the following systems be out of service at any time during the project?

X • Fire alarm (For outages greater than 4 hours, Interim Life Safety Measures must be implemented.)

X • Sprinkler (For outages greater than 4 hours, Interim Life Safety Measures must be implemented.)

X • Electrical

X • Domestic water (For outages greater than 2 weeks, affected domestic water systems will be flushed 5 times the plumbing volume to ensure no residual contaminants i.e. Legionella.)

X • Oxygen X • Sewage

X • HVAC

* The contractor must provide the COR a minimum of 3 weeks’ notice prior to a scheduled utility outage.

Yes No

X Will there be any work that will require activation of the Interim Life Safety Measures (ILSM) during this project? Other work may require ILSMs, but typical work requiring ILSM implementation are:

• Any construction that impacts an exit or stairs

• Any construction that impacts major breaches in a fire or smoke wall

• Taking the main fire protection system out of service (sprinkler)

• Taking the main fire alarm system out of service

• Taking the “area” fire or fire alarm systems out of service for more than 4 hours within a 24-hour period

Implementation of the ILSM requires a fire watch and the ILSM forms to be completed.

Additional Safety Concerns

Yes No

X Will construction affect exit routes from occupied areas adjacent to construction site?

X Will the project affect traffic patterns in area? If yes, explain plan. Detailed Phasing plan created as part of the design.

X Will the project involve the deployment of a crane to deliver equipment over occupied facilities?

• Must submit a Lift Safety Plan and the Hines VA Hospital Planned Critical Lift Plan & Crane Permit to the Safety Office for approval a minimum of 3 weeks prior to the arrival of the crane on Hines VA

Hospital. Follow the Safety Office’s Lift Safety Plan format and include the following information:

crane specifications, crane inspection list, and crane staff training record/certification. Contractors shall maintain and present the following items prior to crane start (items can be kept in crane cab): crane certifications, crane registration, fire extinguisher, and crane operating and safety manual.

The following must be completed prior to any construction activities:

• Construct separation walls prior to project start.

• Fire protection systems must remain intact.

• Provide extra fire extinguishers in work areas.

• Maintain exit lights in work area.

• Maintain negative air pressure in construction area (24/7) throughout project duration.

• Maintain means to monitor and ensure negative pressure via barometer / magnahelix.

• There cannot be any return air from within the construction area to the rest of the building.

• Redirect egress routes; do not allow egress routes to pass through construction areas.

• Provide and maintain “Construction Area-Do No Enter” signs on doors leading into the construction area.

• Maintain up-to-date daily logs and maintain a current Hot Work Permit.

• Provide and install no-slip mats at doors exiting construction area.

• All debris removal must be by covered cart.

• Maintain a clean and orderly work area.

• Determine how, if at all, this project will affect the departments above, below, and adjacent to this project?

Air Quality and Infection Prevention

Construction activity types are defined by the amount of dust that is generated, the duration of the activity, and the amount of shared HVAC systems. Contact Hines VA’s Safety and Infection Prevention Departments if any activity is questionable under these guidelines.

Yes No

X Will dust be generated during this project?

If yes, explain location of and plan for interim dust barriers or attach floor plan with barriers clearly marked. Most work occurring outdoors. Indoors work is separated by Edge Guard system and impacted services are relocated.

X Is work occurring in an area defined by Infection Control as being at risk for Tuberculosis?

If yes, explain location of and plan for notification of floor staff and PPE for assigned contractors, attach floor plan with barriers clearly marked.

X Will debris removal be necessary? If yes, explain plan for debris removal and control. Contractor to provide debris removal plan prior to work start.

X Negative airflow ventilation and filtration in place and assessed for effectiveness.

X Exhaust fans in-place and functioning.

X Air supply duct to area closed and HEPA filtration unit in-place and functioning in adjacent patient care area?

X Will work be done in a sterile area? If so, how will sterile atmosphere be maintained (to include access in/out of the work area)?

Type A Inspections and Non-Invasive Activities or Small Scale/Short Duration Activities. (Refer to Infection Control Risk Assessment for Type Selection)

Yes No

X Removal of ceiling tiles for visual inspection (limited to 1 tile per 50 square feet) X Painting (excludes sanding)

X Wall covering—Describe work to be done: Minor interior demolition and construction, to include new wall base, handrails, corner guards etc.

X Electrical trim work. Describe: Minor interior demolition and construction, to include new outlets and data drops.

X Minor plumbing. Describe: Demolition of deadlegs and old drain lines. Replacement of faucets.

Type B Small Scale, Short Duration Activities that create minimal dust. ( Refer to Infection Control Risk

Assessment for Type Selection)

Yes No

X Installation of telephone and computer cabling X Access to chase spaces X Sanding of walls for painting or wall covering (minor repairs—excludes sanding for drywall finishing)

Type C Any work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies. (Refer to Infection Control Risk Assessment for Type Selection)

Yes No

X Sanding of walls--drywall finishing X Removal of floor coverings ceiling tiles casework Describe:

X Cutting of walls or ceiling. Describe: Renovation of northeast entrance and new office/storage spaces.

X New wall construction X Minor ductwork or electrical work above ceilings X Major cabling activities X Activity cannot be completed within a single work shift

Type D Major demolition and Construction Projects. (Refer to Infection Control Risk Assessment for

Type Selection)

Yes No

X Will require heavy demolition or removal of a complete ceiling system X New construction

Contractor Signature COR / CSO Signature Safety Signature

Date: Date: Date:

Safety Service Recommendations (as needed):

2023-03-28T15:11:53-0500
AARON WALSH

File details come from the government source that posted it. Updated .