S02 - ATCH 10 - 9) Infection Control Risk Assessment.pdf

PDF 256 KB Posted

Attached to
Cancelled: Y1LZ--578-371 Construction - Parking Expansion at Joliet CBOC
Solicitation number
36C77623B0049
Issued by

About this file

This document is an Infection Control Risk Assessment for a construction project to expand parking at the Joliet Community Based Outpatient Clinic. The project involves work in all areas of the clinic from December 2023 through November 2024.

The assessment establishes four construction activity types - A through D - involving different levels of dust and four corresponding infection control risk groups. It provides a matrix to determine the appropriate project class based on the construction activity type and risk group of the area. Higher project classes involve more stringent infection control procedures. Class I requires basic precautions while Class IV, for work in highest risk areas like operating rooms, necessitates additional measures including terminal cleaning inside and outside containment barriers.

The document outlines specific infection control actions required for each project class, covering containment, barriers, ventilation, personal protective equipment, cleaning and waste removal procedures. Signatures are required from the contractor, project planner and infection control personnel to acknowledge the assessment. The related federal contract opportunity was cancelled for the parking expansion construction work at the Joliet CBOC to be performed under the infection control guidelines provided in the risk assessment.

View the file

Other files

File Type Posted
HCA Signed PCAC S30 - Cancellation of Bids - IFB - J.pdf PDF
S30 - Attachment - Abstract of Bids - Joliet.pdf PDF
Attachment 8 - Joliet Roof Report.pdf PDF
Attachment 6 - Joliet CBOC Elect. Add. 2 230726.pdf PDF
Attachment 2 - 09 06 00 Schedule for Finishes.pdf PDF
36C77623B0049 0005 - Joliet CBOC - RFIs-Wage Rates-Bid Opening.pdf PDF
Attachment 3 - AHU Heat Pipe Design Basis.pdf PDF
Attachment 4 - Joliet CBOC Arch RCPs Add. 2 230726.pdf PDF
Attachment 5 - Joliet CBOC Ceiling Diagrams 230726.pdf PDF
Attachment 7 - M601 - MECHANICAL SCHEDULES.pdf PDF
Attachment 1 - Technical Questions - Part 2.pdf PDF
Attachment 9 - Updated Wage Rates - Will County.pdf PDF
Attachment 1 - Technical Questions - Part 1.pdf PDF
Attachment 4 - Joliet Arch RCP.pdf PDF
36C77623B0049 0004 - Joliet CBOC - Extension and RFIs.pdf PDF
Attachment 5 - Joliet CBOC Laydown Areas.pdf PDF
Attachment 3 - Joliet CBOC Geotech Proposed Parking.pdf PDF
Attachment 2 - Infection Control Risk Assessment.pdf PDF
36C77623B0049 0003 - Joliet CBOC - Second Site Visit Sign-In.pdf PDF
Pre-Bid Site Visit 2 Sign-in 578-371.pdf PDF
36C77623B0049 0002 - Second Site Visit and RFI Extension.pdf PDF
36C77623B0049 0001 - Joliet CBOC - Site Visit Sign In.pdf PDF
Pre-Bid Site Sign-in 578-371.pdf PDF
S02 - ATCH 30 - Joliet_CBOC_Issued_for_Bid_A1_Struct_Part_8.pdf PDF
S02 - ATCH 32 - Contractor Safety - Environmental Form.pdf PDF
S02 - ATCH 8 - 7) Above Ceiling Entry and Wall Const Permits.pdf PDF
S02 - ATCH 14 - 13) 578-371 Phasing Plan.pdf PDF
S02 - ATCH 33 - Wage Rates - Will County 5.12.2.pdf PDF
S02 - ATCH 27 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_5.pdf PDF
S02 - ATCH 16 - 15) No Smoking Policy 10-1-19.pdf PDF
S02 - ATCH 23 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_1.pdf PDF
S02 - ATCH 4 - 3) Pre-Con Checklist Rev 07.27.21.pdf PDF
S02 - ATCH 15 - 14) 578-371 Specifications Book.pdf PDF
S02 - ATCH 2 - 1) Joliet CBOC Aerial Site Plan.pdf PDF
S02 - ATCH 34 - Site Visit Instructions.pdf PDF
S02 - ATCH 7 - 6) Dig Permit SOP Form.pdf PDF
S02 - ATCH 26 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_4.pdf PDF
S02 - ATCH 25 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_3.pdf PDF
S02 - ATCH 31 - Limitations on Subcontracting - Construction.pdf PDF
S02 - ATCH 11 - 10) Interim Life Safety Measures (ILSM).pdf PDF
S02 - ATCH 24 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_2.pdf PDF
S02 - ATCH 17 - 16) Infection Control Barrier Sample.pdf PDF
S02 - ATCH 1 - 578-371 Construction SOW Final.pdf PDF
S02 - ATCH 6 - 5) Cutting Welding and Other Hot Work.pdf PDF
S02 - ATCH 13 - 12) OIT Horizontal Cable Requirements.pdf PDF
S02 - ATCH 18 - 17) Hines COVID-19 Guidelines.pdf PDF
S02 - ATCH 12 -11) Contractor PIV Instructions and Form.pdf PDF
S02 - ATCH 9 - 8) Pre-Construction Risk Assessment.pdf PDF
S02 - ATCH 21 - Joliet_CBOC_Project_Manual_Issued_for_Bid.pdf PDF
S02 - ATCH 29 - Joliet_CBOC_Issued_for_Bid_A1_MEP_Part_7.pdf PDF
Show 40 more

Latest 50 of 57 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Infection Control Risk Assessment for Construction / Renovation Projects Project Name: Parking Expansion at Joliet CBOC Project or Work-Order Number: 578-371

Project Manager or COR: Aaron Walsh Extension: 21152

Building Number: Joliet CBOC Floor(s)/Room(s): All

Start date: ~12/2023 Projected completion date: ~11/2024

Construction Activity Infection Control Risk Group

☐ TYPE A: DUST LEVEL Low

Non-invasive activity, low noise, no vibration.

☐ GROUP 1: LOW

Office areas, FMS areas, all non-patient care areas.

☐ TYPE B: DUST LEVEL: Moderate to High

Small scale, short duration, low-moderate noise, low-moderate vibration.

☐ GROUP 2: MEDIUM

All other patient care areas including general medicine floors, ultrasound, Rehab, Occupational Therapy.

☐ TYPE C: DUST LEVEL Moderate to High

Requires more than one work shift (independent of working days) to complete, low-moderate noise, moderate–high vibration

☒ GROUP 3: MEDIUM/HIGH

ED, Radiology/MRI, admissions, food service areas, laboratories.

☒ TYPE D: DUST LEVEL High

Major demolition and construction activities. Requires consecutive work shifts, moderate-high noise, moderate-high vibration

☐ GROUP 4: HIGHEST

Operating rooms, SPS, ICU’s, Outpatient areas, oncology, anesthesia, post anesthetic recovery, all endoscope areas, Pharmacy, Renal Dialysis

Project Class Determination Matrix Construction Activity Type →

Risk Group

Type

“A”

Type

“B”

Type

“C”

Type

“D”

Group 1 I II II III

Group 2 I II III IV

Group 3 I III III IV

Group 4 III IV IV IV Contractors Actions by Project Class

All personnel will have Emergency Preparedness training/posting/ID card.

CLASS

I

1. Execute work to minimize air-borne dust dispersed into atmosphere from construction operations.

2. Immediately replace any ceiling tile displaced for visual inspection.

3. Contain construction waste before transport in tightly covered containers.

4. Clean work area upon completion of task including wiping surfaces with disinfectant.

5. Contact EMS for appropriate preparation for return to operation(s).

CLASS

II

In addition to above:

6. Post the signed ICRA at the entrance.

7. Isolate work area from patients/staff. Use appropriate temporary barriers and more permanent containment methods (i.e., seal holes in walls, tape gaps in doors, etc.)

8. Water mist work surfaces to control dust while cutting.

9. Block off and seal supply air vents. Place filter over return/exhaust vents.

10. Place dust mat or wipe feet at entrance/exit of work area.

11. Wet mop and/or vacuum w/HEPA filtered vacuum before leaving work areas.

CLASS

III

In addition to above:

12. Install barriers to create a negative pressure ante room and/or workroom.

13. Maintain negative air pressure in work area at all times until completion utilizing HEPA-equipped air filtration units.

14. Vacuum personnel with HEPA vacuum before leaving. Or, Don-Doff coveralls each time leaving work site. All wear shoe covers changed each time exiting the area.

15. Vacuum the entire work area with HEPA vacuums or wet mop with disinfectant at the completion of project.

16. Do not remove barriers until completed project is inspected by Safety, IC-Team, EMS, and Area Manager.

17. Carefully remove barriers to minimize spread of dirt and debris. Contact EMS for final clean.

CLASS

IV

In addition to above:

18. Provide a disinfectant wipe down of any tool carts or waste transports prior to leaving the containment area.

19. Do not remove barriers until terminal clean is performed inside work zone and barriers are included in the cleaning process.

20. Perform 2nd terminal cleaning after removal of barriers. Contact EMS for final clean.

Signatures Date

Contractor’s Signature:

(Projects Only)

Project Planner or

Maintenance Worker Signature:

Supervisor Signature:

Infection Control:

VHAHINWalshA Oval

VHAHINWalshA Oval

VHAHINFraidR Typewritten Text 03/30/2023

2023-03-28T15:05:39-0500
AARON WALSH
2023-03-30T07:54:43-0500
Richard F Fraider 3548196