Attachment 1 - Technical Questions - Part 2.pdf

PDF 206 KB Posted

Attached to
Cancelled: Y1LZ--578-371 Construction - Parking Expansion at Joliet CBOC
Solicitation number
36C77623B0049
Issued by

About this file

This document contains technical questions and responses related to solicitation number 36C77623B0049 for construction work at the Joliet CBOC parking expansion project through the Department of Veterans Affairs. Key details include requirements for new site lighting, nurse call and fire alarm system work, mechanical, electrical and plumbing installation, roof replacement, and phased construction plans. The response document provides clarification on fixture schedules, infection control protocols, contractor responsibilities for materials testing and inspection, documentation requirements, and confirms Davis-Bacon Act and Buy American Act compliance. Site conditions, utility connections, working hours and restrictions are also addressed. The project has a competitive SDVOSB set-aside and is scheduled for award in FY2023.

View the file

Other files

File Type Posted
HCA Signed PCAC S30 - Cancellation of Bids - IFB - J.pdf PDF
S30 - Attachment - Abstract of Bids - Joliet.pdf PDF
Attachment 8 - Joliet Roof Report.pdf PDF
Attachment 6 - Joliet CBOC Elect. Add. 2 230726.pdf PDF
Attachment 2 - 09 06 00 Schedule for Finishes.pdf PDF
36C77623B0049 0005 - Joliet CBOC - RFIs-Wage Rates-Bid Opening.pdf PDF
Attachment 3 - AHU Heat Pipe Design Basis.pdf PDF
Attachment 4 - Joliet CBOC Arch RCPs Add. 2 230726.pdf PDF
Attachment 5 - Joliet CBOC Ceiling Diagrams 230726.pdf PDF
Attachment 7 - M601 - MECHANICAL SCHEDULES.pdf PDF
Attachment 9 - Updated Wage Rates - Will County.pdf PDF
Attachment 1 - Technical Questions - Part 1.pdf PDF
Attachment 4 - Joliet Arch RCP.pdf PDF
36C77623B0049 0004 - Joliet CBOC - Extension and RFIs.pdf PDF
Attachment 5 - Joliet CBOC Laydown Areas.pdf PDF
Attachment 3 - Joliet CBOC Geotech Proposed Parking.pdf PDF
Attachment 2 - Infection Control Risk Assessment.pdf PDF
36C77623B0049 0003 - Joliet CBOC - Second Site Visit Sign-In.pdf PDF
Pre-Bid Site Visit 2 Sign-in 578-371.pdf PDF
36C77623B0049 0002 - Second Site Visit and RFI Extension.pdf PDF
36C77623B0049 0001 - Joliet CBOC - Site Visit Sign In.pdf PDF
Pre-Bid Site Sign-in 578-371.pdf PDF
S02 - ATCH 30 - Joliet_CBOC_Issued_for_Bid_A1_Struct_Part_8.pdf PDF
S02 - ATCH 32 - Contractor Safety - Environmental Form.pdf PDF
S02 - ATCH 8 - 7) Above Ceiling Entry and Wall Const Permits.pdf PDF
S02 - ATCH 14 - 13) 578-371 Phasing Plan.pdf PDF
S02 - ATCH 33 - Wage Rates - Will County 5.12.2.pdf PDF
S02 - ATCH 27 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_5.pdf PDF
S02 - ATCH 16 - 15) No Smoking Policy 10-1-19.pdf PDF
S02 - ATCH 23 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_1.pdf PDF
S02 - ATCH 4 - 3) Pre-Con Checklist Rev 07.27.21.pdf PDF
S02 - ATCH 15 - 14) 578-371 Specifications Book.pdf PDF
S02 - ATCH 2 - 1) Joliet CBOC Aerial Site Plan.pdf PDF
S02 - ATCH 34 - Site Visit Instructions.pdf PDF
S02 - ATCH 7 - 6) Dig Permit SOP Form.pdf PDF
S02 - ATCH 26 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_4.pdf PDF
S02 - ATCH 25 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_3.pdf PDF
S02 - ATCH 31 - Limitations on Subcontracting - Construction.pdf PDF
S02 - ATCH 11 - 10) Interim Life Safety Measures (ILSM).pdf PDF
S02 - ATCH 24 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_2.pdf PDF
S02 - ATCH 17 - 16) Infection Control Barrier Sample.pdf PDF
S02 - ATCH 1 - 578-371 Construction SOW Final.pdf PDF
S02 - ATCH 6 - 5) Cutting Welding and Other Hot Work.pdf PDF
S02 - ATCH 13 - 12) OIT Horizontal Cable Requirements.pdf PDF
S02 - ATCH 18 - 17) Hines COVID-19 Guidelines.pdf PDF
S02 - ATCH 12 -11) Contractor PIV Instructions and Form.pdf PDF
S02 - ATCH 9 - 8) Pre-Construction Risk Assessment.pdf PDF
S02 - ATCH 21 - Joliet_CBOC_Project_Manual_Issued_for_Bid.pdf PDF
S02 - ATCH 29 - Joliet_CBOC_Issued_for_Bid_A1_MEP_Part_7.pdf PDF
S02 - ATCH 10 - 9) Infection Control Risk Assessment.pdf PDF
Show 40 more

Latest 50 of 57 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION # 36C77623B0049

PROJECT NAME: Joliet CBOC Parking Expansion

TECHNICAL QUESTIONS – PART 2 AND VA RESPONSE TRACKING SHEET

ITEM

NO. QUESTION GOVERNMENT RESPONSE

1. The light fixture schedule on E602 does not seem to match up to the actual fixtures shown on the floor plans (EL-100 and EL-101)

Some examples –

Fixture D2A, D2B Shown on floor plan EL100-N But not listed on fixture schedule on E602

Fixture F3A, F3B, F3C Shown on floor plans But only F3 is on fixture schedule

Fixture F3A – On EL100-N this fixture is indicated as a 2x2 lay-in On EL101-N this fixture is indicated as a can light

On EL101-N This plan has some F9 and F10 fixtures shown However, they are not listed on the fixture schedule

An incorrect Lighting Fixture Schedule was issued with the bid documents. We have inserted the correct fixture schedule on plans and will need to reissue the sheet or provide as an attachment the correct Lighting Fixture Schedule. See Joliet CBOC Elect. Add. 2 230726 attached.

2. What is the overall concept for the new site lighting that goes into the existing parking areas?

Obviously, these areas are already paved.

Does the pavement get removed and replaced, or are we supposed to directional bore new conduits under the existing paving ?

New conduit under existing paving will be required.

3. There is a nurse call riser on E507 Does this riser represent the new work we need to include in this bid?

I do not find any nurse call devices shown on any of the floor plans.

The nurse call devices will need to be removed and reinstalled as part of the ceiling demolition. The contractor must extend as required all conduit and wire to new locations as required by the renovation to include but not limited to Single Patient Stations, Double Stations, EM/LAV Stations with pull cords, Corridor Lights, Nurse Annunciator, Duty Station, Staff EM Station, Domeless Duty Controller, Master Nurse Console, Marquee, etc. The existing system must remain operational where patient care is ongoing. Some devices are hidden in-wall and ceilings which may be affected by renovations. This contractor shall coordinate all work as required to maintain existing nurse call system such that it is fully operational after construction. Contractor should estimate 25% of existing systems to be temporarily relocated/replaced for mechanical/electrical demolition/installation.

4. Please provide additional time for this procurement.

Projects of this size and complexity have had significantly longer procurement durations which benefit the VA by giving sufficient time for the contractors resulting in more accurate pricing.

Contract requires an FY23 award. Bid due date to be extended to 8/2/23 but cannot be pushed back any further.

5. Please confirm the superintendent shall not have any shared duties as a QCM, SSHO or any other roles on the project.

No single person can be the QCM, SSHO and Superintendent; contractor may have 2 people to fill all three roles (Ex. The Superintendent and SSHO is the same person).

6. Please confirm the SSHO shall not have any shared duties as a QCM, superintendent or any other role on the project.

No single person can be the QCM, SSHO and Superintendent; contractor may have 2 people to fill all three roles (Ex. The Superintendent and SSHO is the same person).

7. Please confirm the QCM shall not have any shared duties as a SSHO or superintendent.

No single person can be the QCM, SSHO and Superintendent; contractor may have 2 people to fill all three roles (Ex. The Superintendent and SSHO is the same person).

8. Please confirm if the VA can and will be flexible on the site phasing plan provided in this procurement.

Some flexibility will be granted for phasing based on specific construction limitations, however the contractor should budget to perform the phasing as provided. Phasing will not be adjusted solely for convenience.

9. Please confirm that the contractor is to supply all materials testing for the project.

Confirmed. All required materials testing as specified in the specification book shall be performed by the contractor.

10. Please confirm that all firestopping must be either installed by an FM global approved contractor, or a UL qualified firestop contractor certified.

Confirmed. This is a requirement.

11. Please confirm that the contractor is to include the services of a third party independent firestopping inspector in their bid.

Confirmed. This is a requirement.

12. Please confirm that firestopping installers accredited by a firestopping product manufacturer will not be approved by the VA unless they meet the FM global or UL qualifications referenced in section 07 84 00.

Confirmed. This is a requirement.

13. Please provide a site plan showing the contractor trailer and laydown area(s).

Any areas that do not impact parking are available. See “Joliet CBOC Laydown Areas” attachment. Note: Areas must be restored to current conditions at the end of the project.

14. Please confirm that contractor parking will be provided on site. This directly impacts pricing.

Contractors may park in laydown areas as needed. See “Joliet CBOC Laydown Areas” attachment. Note: Areas must be restored to current conditions at the end of the project.

15. Please confirm if this project is tax exempt. If so, will the VA provide the documentation to the prime contractor after award?

Yes, this project is tax exempt, and the VA will provide documentation following award.

16. Please confirm this project must meet the buy American act requirements.

Yes, please reference FAR 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT in the solicitation.

17. Please confirm level 4 finish for all finished gypsum board including patches.

Confirmed. Level 4 finish for all finished gypsum board in areas open to public view;

this includes patches.

18. Please confirm painting unless otherwise noted is to be

(3) coats (prime, body, and finish) and will be from "seam to seam" or to a change of materials where walls are patched and refinished.

Confirmed; painting unless otherwise noted is to be (3) coats (prime, body, and finish) and will be from "seam to seam" or to a change of materials where walls are patched and refinished.

19. Are we required to use plenum rated cabling for all areas? Can we use riser rated cabling in non-plenum spaces?

All electrical cabling shall be in conduit.

20. Will flexible metal conduit be allowed? Flexible metal conduit less than 6-ft is only allowed to connect devices to backbox.

21. Spec section 01 35 26 outlines the infection control classification as Class 1, however attachment 10 – Infection Control Risk Assessment calls out this project as being Class 4. Please confirm which infection control classification is required for this project.

Infection Control classification is dependent on the type of work and classification of the work area. See “Infection Control Risk Assessment” attachment for specifics. In general, any Construction efforts associated with the demolition of the remnant structure, new north wall or penthouse will be Class IV: D1. Construction efforts related to new construction or ductwork for interior, multi-room phases to be treated as Class III:

C1, C2, C6E and C6W. Single room construction will vary by case.

22. Please provide the core data of the existing roof. This information is needed for bidding purposes to determine the required number of dumpsters, equipment and manpower needed for the full roof replacement.

See Joliet Roof Report attached.

23. Please confirm that this project is a competitive Service- Disabled Veteran-Owned Small Business Set-Aside project and that any bonding provided by a contractor must be through a SDVOSB or SBA/VA APPROVED Mentor-Protege partnership under the SBA/VA Mentor- Protégé program in which the partnership has been approved prior to the bid date.

Yes, this project is a competitive SDVOSB set-aside and bonding must be through an SDVOSB or SBA/VA approved Mentor- Protégé partnership.

24. Please confirm that a large business not part of an SBA/VA APPROVED Mentor-Protégé team under the VA Mentor-Protégé program cannot provide a Payment & Performance bond for a SDVOSB.

Correct, a large business which is not part of an SBA/VA approved Mentor-Protégé partnership cannot provide a Payment and Performance bond for an SDVOSB. Bonding instruments must be issued for the firm submitting the bid, which will hold the government contract. Please reference VAAR 852.228-72, which states “Mentor firms are encouraged to assist protégé firms under VA's Mentor-Protégé Program in obtaining acceptable bid, payment, and performance bonds” however the Mentor firm cannot provide bonding in lieu of the Prime contractor.

25. Please confirm that a large business not part of an SBA/VA APPROVED Mentor-Protégé team under the VA Mentor-Protégé program cannot provide a bid guarantee for a SDVOSB.

Correct, a large business which is not part of an SBA/VA approved Mentor-Protégé partnership cannot provide a bid guarantee for an SDVOSB. Bid guarantees must be for the firm submitting the bid, which will hold the government contract.

26. Please provide a current soils report for the campus. Soils report for the north portion is available and will be provided. See “13974 - Joliet CBOC Geotech Proposed Parking 210920” attached.

27. Please confirm Contractor’s working hours for this project.

Typical contractor working hours are 7:00AM

– 3:30PM unless specifically noted in the design drawings; certain construction activities/phases may be restricted to specific time(s) of day. Ex: The portion of Phase C5 relating to demolition of the HVAC riser chase is to be performed over the weekend.

28. Please define off hours, we assume off hours to be second shift work but need confirmation.

Confirmed. Off-hours describes second shift work, typically between 4:00PM to 12:00AM.

Overnight and weekend work will be specifically identified if necessary.

29. Section 01 00 00 general requirements “alterations includes that the GC will provide a thorough survey of areas in which work is to be done with the COR and VA representative in attendance”. Please confirm that the VA staff will schedule and have the time to do these surveys without delaying the contractor as these thorough surveys are extremely time-consuming.

Existing conditions surveys to occur on off-hours or on weekends. Contractors to provide a minimum 3 weeks’ notice to ensure VA staff availability.

30. Please confirm per section 01 00 00 that contractor is to provide a commercial photographer/subcontractor with 3 years’ experience and that indexing/navigation will use AutoCAD drawings to be interactive online.

Typically, this has been waived on most other VA projects as most facilities do not have the capabilities to utilize AutoCAD.

Commercial Photographer not required. Site Superintendent, SSHO or QCM may take photos as necessary.

31. Please confirm the pre-determined intervals in which the photographic documentation is to be done.

Photos of the job site to be taken daily and included in the contractor’s daily report. No requirements on the type/resolution of photos.

32. Please provide a list of what work is to be included with the photographic documentation.

No photographic documentation required beyond daily reports.

33. Please confirm that contractor is to provide online hosting, security measures and redundant server back-up of the photographic documentation for the duration of the project.

The only required 3rd party site is the FTP file sharing system for submittals, RFIs, daily logs etc. See Section 01 33 23 – 1.6 Submittal Format and Transmission.

34. Can the contractor QC manager serve as the photographer if they meet the requirement of having experience photographing construction projects. The term “Commercial Photographer” is vague, has no licensing requirements or any other information required.

No Commercial Photographer required.

35. Can the QC manager serve as the photographer for the demonstration and training recordings? The term “Commercial Photographer” is vague, has no licensing requirements or any other information required.

No Commercial Photographer required.

36. Please consider waiving the requirement for AISC certification for steel erection.

AISC certification required as specific in bid documents.

37. Is there a proprietary DIV28 Fire Alarm contractor at the facility? If so, please provide company and point of contact.

Joliet uses Edwards Fire Alarm Panels; any contractor familiar with Edwards panels may be used.

38. The lighting schedule does NOT match the new fixtures shown on the lighting drawing. There are several fixtures on the floor plans that aren’t on the schedule.

Fixtures that are on the schedule and floor plan don’t match up with their description. Please provide an accurate lighting schedule or floor plan in order to properly quote new light fixtures and lighting controls.

See response to RFI #1 and attached revised lighting schedule. See Joliet CBOC Elect. Add.

2 230726 attached.

39. Please provide the manufacturer or provider for the security system currently on site.

OnGuard system for the alarms and Milestone for the cameras.

40. Do any rooms require room pressure monitors? Any existing room pressure monitors shall remain and be connected to new control system. No new room pressure monitors are anticipated.

41. Are controls being replaced on all VAVs or only VAVs that are new to the new duct work?

All VAV air terminal units are shown in the bid docs to be removed and replaced with new.

42. Are any FCU controls needing to be replaced? We are not aware of any FCU in the building.

The DX split system Liebert AC unit in the IT room is existing to remain with no control upgrades.

43. Does the new hot water system to be installed require the controls contractor to install new controls or will it come with its own on-board controls as part of its package?

This is up to the bidding contractor, however typically the preference is for the boiler manufacturer to provide packaged control system for staging and operation of multiple boilers and associated equipment.

44. If the new hot water heating system does come with its own on-board controls system, will it come with a BACnet interface card to tie into the BAS?

Yes, if providing factory control package for boiler system it shall be provided with BACnet interface for connection to new control system and allow for full monitoring and control of the boiler plant remotely at the engineer workstation.

45. Please refer to the motor schedule on E601 Several of the motors do not show what panel they are to be fed from.

We will need that information, please.

The schedule will be corrected to show the correct panels and issued with our RFI responses. See M601 - MECHANICAL SCHEDULES attached.

46. Can we shut down the front vestibule to remove existing

AHU?

Any shutdowns to the front entrance to be performed off-hours or weekends. Consider using the existing areaways at the east for removal of existing AHUs.

47. What are the working hours for the exterior demolition work? How early can the work begin?

Exterior demolition to occur between 8:00AM – 7:00PM. To be determined by City of Joliet. Contractor responsible for all permits for construction.

48. Can demolition work be completed while patients are present?

It is anticipated that patient areas that can be safely occupied will be in use during demolition activities. The proposed phasing schedule and plans illustrate those areas to be occupied/unoccupied.

49. The COR mentioned the City of Joliet possibly wanting some of the limestone for historic buildings, who will facilitate that?

A local church will pick-up the limestone.

Contractor to pile it by the side of the road at the construction site.

50. Has the old hospital area been abated? Building should have been abated before demolition, but contractor is bidding as-is condition. Reach out to Silvercross, Will County or the demolition contractor:

Brandenburg.

51. Are there soils borings and soils test results? Yes, see “13974 - Joliet CBOC Geotech Proposed Parking 210920” attached.

52. Are there ICRA requirements for interior areas during exterior demo?

Yes, any interior room adjacent to exterior construction that may potentially be impacted shall be blocked off with ICB. Those spaces shall be treated as a Class III.

53. How many phases are the VA anticipating? VA anticipates 13 distinct phases. Note:

Many phases overlap.

54. Does any of the work need to be done outside of normal working hours?

Yes, Phase C5 relating to demolition of the HVAC riser chase is to be performed over the weekend. Contractor should anticipate off-hours (2nd shift) work for the entirety of Phase C5.

55. Is there enough room in the ceiling area for the new ductwork and piping with the existing duct and piping not being removed until everything is running?

The new heating water piping may be able to be installed with existing ductwork and steam piping in place. We do not anticipate that the majority of the ductwork can be installed without first demolishing the existing ductwork, therefore the phasing plan which is presented in the bid documents.

The ductwork design as presented in the bid documents assumes demo of existing ductwork prior to install of the majority of the new ductwork. Phases C6E and C6W are separated such that the entire area is demolished, replaced, and turned back over in a single period (~7 weeks).

56. There is nothing on the drawing about the Snow melt system for the front entrance, does it use steam and a heat exchanger?

Provide a new shell & tube heat exchanger sized for existing snowmelt area and to match existing steam heat exchanger capacity – approximately 1000 SF of snowmelt in the drive thru area. Provide new hot water heating piping and controls to connect to new hot water heating system main piping in corridor west of the existing mech room – Approximately 40 LF of 1 ¼” copper piping with ball isolation valves, control valve, and associated accessories.

57. Are contractors expected to use a temporary boiler or are those connections on the drawings for future MP 101N?

A temporary boiler system is anticipated due to the need to shut down the steam plant and replace it with new heating water boilers, while heating and/or terminal unit reheat is needed year-round. Bidders shall include in their pricing the ability to heat and ventilate the building for the duration of construction schedule which will most likely require a temporary hot water boiler system during steam plant demo and new construction and commissioning. Refer to phasing drawings GC-001 through GC-011

58. On M 601 AHU note #6 says the humidifier manifold is internal to the unit rated at 725 lbs./ph., the humidifier is rated for 300lbs/ph. Is that the correct manifold?

Please confirm.

The steam distribution manifold should be 300 lb/hr to match the steam generating humidifier.

59. On M 504 #8 detail there are no circuit setters for the VAV coils. Is that correct?

We do not feel the need for circuit setter is needed for these small coils which typically have 2-position control valve

60. Is the contractor responsible for replacing the domestic water heater? If so, please provide specifications and updated drawing to show this work.

No, existing water heater to remain.

61. Drawings in C1.1 has info about existing contour lines.

Please provide new drawing for C1.1- Topographic survey which clearly shows proposed contour lines?

There are spot elevations on the drawings that show design intent. Proposed contours would provide additional information, but nothing that should impact the bidder’s cost.

Updated drawings could be provided as part of the construction process.

Delinquent RFIs

62. Please confirm the concrete apron is to receive #6 bars at 8" on center

Driveway apron shall be per Detail 1 /Sheet C7.0

63. Please confirm sidewalk is to receive #4 bars at 12" on center

Sidewalk shall be per Detail 4/Sheet C7.0

64. Please indicate where details 9 through 12 on C7.0 take place on the drawings or if they are not applicable to this contract

Those details are applicable at all concrete sidewalk locations.

65. I am having an issue with the lighting schedule. On the fixture schedule, it is calling for an F3- 4"recessed light. However, on the prints themselves, they are showing an F3 should be a 2x2 lay in. They are also calling for D2 fixture which is not on the fixture schedule

See Joliet CBOC Elect. Add. 2 230726 attached.

66. How are we going to phase the boiler room to remove the old boilers and install the new boilers, and keep everything running?

See RFI #57 response.

67. How are we going to work around the delivery times for the equipment for the project?

Lead times should be part of the contractor’s schedule. Contractor to let VA know of long lead-time items and impacts to the project schedule. See Section G) 5) in the SOW.

68. How many phases are we anticipating?

See RFI #53 response.

69. Does any of the work need to be done on Overtime?

See RFI #54 response.

70. Is there enough room in the ceiling area for the new ductwork and piping with the existing duct and piping not being removed until everything is running?

See RFI #55 response.

71. There is nothing on the drawing about the Snow melt system for the front entrance, it uses steam and a heat exchanger?

See RFI #56 response.

72. Who is responsible for ceiling removal and infectious control for the project?

The contractor is responsible for all ceiling removal/replacement and all required infection control for the project. See Phasing drawings for details.

73. Are planning on using a temporary boiler or are those connections on the drawings for future MP 101N?

See RFI #57 response.

74. Detail #4 on drawing M 504 is not correct?

This is not a question. Contractor will provide shop drawings for all equipment.

75. On M 601 AHU note #6 says the humidifier manifold is internal to the unit rated at 725 lbs/ ph ,the humidifier is rated for 300lbs/ph is that the correct manifold?

See RFI #58 response.

76. On M 504 #8 detail there are no circuit setters for the VAV coils is that correct?

See RFI #59 response.

77. Are we replacing the domestic water heater there was nothing on the drawings?

See RFI #60 response.

78. Provide additional schedule and pertinent Bid Documentation relating to the Air to Air Heat Pipe Assembly as part of AHU.

The air handling unit is to be provided with heat pipe energy recovery section. See AHU Heat Pipe Design Basis attached.

79. It appears an Additional or supplemental Schedule information defining conditions for the Inlet/outlet of each Supply and Exhaust paths for Summer and Winter Peak Design loads i.e.) DbF/WbF, CFM (either Std or at Altitude) are needed.

These additional defining conditions are not anticipated to affect the bidding and are rather questions for the design team once project is awarded. Design intent is for AHU to have heat pipe energy recovery system to meet code requirements. A portion of the basis of design AHU heat pipe heat recovery section is included for reference.

80. The door vendor is indicating the specified slider door by Nabco is called out to be 73”. The minimum frame width for the Nabco is 76”. Please confirm that Door 001 can have a 76” width if the Nabco GT1400-02 is wanted. Or please issue a new BOD for a slider that can be 73”W.

The door frame is to be 76”.

The 73” as shown in the door schedule refers to the width of the door itself and does not include the frame.

81. Please reference spec section 08 80 00 section 3.8.

The spec states 1” overall unit thickness, however, with the outboard lite minimum thickness at ~1/4”(0.23 inch) thick and both lites used for the inboard laminated lite with a minimum thickness of ~1/4”(0.23 inch) thick, the overall unit size will exceed 1”. Are the laminated IGUs required to be 1” thick overall or will a thicker overall unit be acceptable to accommodate the laminated inboard requirements?

The overall unit thickness will be larger than 1” due to the laminated glass.

Figure on a unit thickness of ~1 5/16”.

Disregard references to a 1” unit thickness.

82. (Reference RFI #81) - If these must be 1” overall and cannot be thicker, please provide a revised spec for this glass.

See RFI #81 response.

83. (Reference RFI #81) - For the Low-E coating, the spec calls out First surface and Second surface.

Low E coating to be applied to the second surface.

84. (Reference RFI #81) - Which surface should the Low-E coating be applied?

See RFI #83 response.

85. As it relates to the ceiling and mechanical demo, how are we to treat the existing fire protection system? No modifications or adjustments are shown or indicated in the contract documents. The contract documents show installing new legs of the system within the mechanical penthouse and the new area for the entry and elevator lobby.

The sprinklers in the demolished corridor and vestibule are to be reworked to match the new work scope. The penthouse sprinkler system is new. Contractor should estimate 25% of existing systems to be temporarily relocated/replaced for mechanical demolition/installation.

86. The Reflected Ceiling Demo Drawings indicate all the ceiling tile grid and edge trim is to remain. The new Reflected Ceiling plans show new grid at ACT-2 and ACT-3. A majority of the ceiling is called out as ACT-1. The entire mechanical system is being replaced throughout the building, and the ceiling grid will need to be removed to install the mechanical system(s). Please confirm that all ceiling gride and edge trim is to be removed to accommodate the installation of the new mechanical system

See Joliet CBOC Ceiling Diagrams 230726 and Joliet CBOC Arch RCPs Add. 2 230726 attached.

ACT1: The intent is to keep the grid & trim, replacing only the ceiling tiles as indicated on the drawings.

ACT2: Replace tile, grid, & trim as indicated on the drawings.

ACT3: Replace tile, grid, & trim as indicated on the drawings. Cleanroom ceiling tiles.

87. Please provide more information on the types of USG ACT-1, ACT-2 and ACT-3 ceiling systems for pricing purposes.

Grid & Trim ACT2 & ACT3: USG Donn DX 15/16” system Tile ACT1 & ACT2: USG ‘Mars’ 86785HRC, SLT edge profile.

Tile, Cleanroom, ACT3: USG ‘Mars’ 86169CR, Square edge profile.