This pre-construction checklist outlines requirements for a parking expansion project at a Veterans Affairs community-based outpatient clinic in Joliet, Illinois under solicitation number 36C77623B0049. The checklist specifies that the contractor must submit schedules and progress reports, comply with safety and labor standards provisions, and designate a project manager. Payments will be made monthly based on the value of completed work. The contracting officer is the only official authorized to bind the government and make changes to the contract. The document provides standard instructions for communication, correspondence, pay applications, and other procedural requirements for the awarded contractor to follow during the pre-construction phase.

View the file

Other files

File Type Posted
HCA Signed PCAC S30 - Cancellation of Bids - IFB - J.pdf PDF
S30 - Attachment - Abstract of Bids - Joliet.pdf PDF
Attachment 8 - Joliet Roof Report.pdf PDF
Attachment 6 - Joliet CBOC Elect. Add. 2 230726.pdf PDF
Attachment 2 - 09 06 00 Schedule for Finishes.pdf PDF
36C77623B0049 0005 - Joliet CBOC - RFIs-Wage Rates-Bid Opening.pdf PDF
Attachment 3 - AHU Heat Pipe Design Basis.pdf PDF
Attachment 4 - Joliet CBOC Arch RCPs Add. 2 230726.pdf PDF
Attachment 5 - Joliet CBOC Ceiling Diagrams 230726.pdf PDF
Attachment 7 - M601 - MECHANICAL SCHEDULES.pdf PDF
Attachment 1 - Technical Questions - Part 2.pdf PDF
Attachment 9 - Updated Wage Rates - Will County.pdf PDF
Attachment 1 - Technical Questions - Part 1.pdf PDF
Attachment 4 - Joliet Arch RCP.pdf PDF
36C77623B0049 0004 - Joliet CBOC - Extension and RFIs.pdf PDF
Attachment 5 - Joliet CBOC Laydown Areas.pdf PDF
Attachment 3 - Joliet CBOC Geotech Proposed Parking.pdf PDF
Attachment 2 - Infection Control Risk Assessment.pdf PDF
36C77623B0049 0003 - Joliet CBOC - Second Site Visit Sign-In.pdf PDF
Pre-Bid Site Visit 2 Sign-in 578-371.pdf PDF
36C77623B0049 0002 - Second Site Visit and RFI Extension.pdf PDF
36C77623B0049 0001 - Joliet CBOC - Site Visit Sign In.pdf PDF
Pre-Bid Site Sign-in 578-371.pdf PDF
S02 - ATCH 30 - Joliet_CBOC_Issued_for_Bid_A1_Struct_Part_8.pdf PDF
S02 - ATCH 32 - Contractor Safety - Environmental Form.pdf PDF
S02 - ATCH 8 - 7) Above Ceiling Entry and Wall Const Permits.pdf PDF
S02 - ATCH 14 - 13) 578-371 Phasing Plan.pdf PDF
S02 - ATCH 33 - Wage Rates - Will County 5.12.2.pdf PDF
S02 - ATCH 27 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_5.pdf PDF
S02 - ATCH 16 - 15) No Smoking Policy 10-1-19.pdf PDF
S02 - ATCH 23 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_1.pdf PDF
S02 - ATCH 15 - 14) 578-371 Specifications Book.pdf PDF
S02 - ATCH 2 - 1) Joliet CBOC Aerial Site Plan.pdf PDF
S02 - ATCH 34 - Site Visit Instructions.pdf PDF
S02 - ATCH 7 - 6) Dig Permit SOP Form.pdf PDF
S02 - ATCH 26 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_4.pdf PDF
S02 - ATCH 25 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_3.pdf PDF
S02 - ATCH 31 - Limitations on Subcontracting - Construction.pdf PDF
S02 - ATCH 11 - 10) Interim Life Safety Measures (ILSM).pdf PDF
S02 - ATCH 24 - Joliet_CBOC_Issued_for_Bid_A1_Arch_Part_2.pdf PDF
S02 - ATCH 17 - 16) Infection Control Barrier Sample.pdf PDF
S02 - ATCH 1 - 578-371 Construction SOW Final.pdf PDF
S02 - ATCH 6 - 5) Cutting Welding and Other Hot Work.pdf PDF
S02 - ATCH 13 - 12) OIT Horizontal Cable Requirements.pdf PDF
S02 - ATCH 18 - 17) Hines COVID-19 Guidelines.pdf PDF
S02 - ATCH 12 -11) Contractor PIV Instructions and Form.pdf PDF
S02 - ATCH 9 - 8) Pre-Construction Risk Assessment.pdf PDF
S02 - ATCH 21 - Joliet_CBOC_Project_Manual_Issued_for_Bid.pdf PDF
S02 - ATCH 29 - Joliet_CBOC_Issued_for_Bid_A1_MEP_Part_7.pdf PDF
S02 - ATCH 10 - 9) Infection Control Risk Assessment.pdf PDF
Show 40 more

Latest 50 of 57 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE-CONSTRUCTION CHECKLIST

PROJECT: __________________________________________________

DATE: ____________________ CONTRACT: _____________________

1. AUTHORITY OF GOVERNMENT PERSONNEL.

☐ a. The Contracting Officer is the only person authorized to bind the U.S.

Government, and then only to the extent of the authority invested in him/her by the appointment.

☐ b. The VA Project Manager is designated as the Contracting Officer's representative for the purpose of technical supervision and acceptance. The VA Project Manager is responsible for the inspection of the work called for in the contract schedules, including related specifications and contract terms regarding on-site work requirements. Pursuant to the delegation of authority (attached), the Project Manager does not have the authority to make changes to the contract in amount or time.

☐ c. The VA Project Manager for this project is _________________

☐ d. No other office or individual has the authority to act in any manner on behalf of the U.S. Government in the performance of this contract. The VA Project Manager will refer any changes or questions regarding this contract to the Contracting Officer.

2. CONTRACT PROGRESS SCHEDULES AND REPORTS:

☐ a. The Contractor shall submit a schedule of cost to the Contracting Officer within 10 calendar days after date of receipt of the Notice to Proceed.

The approved cost schedule will be one of the bases for determining progress payments for work completed. In accordance with FAR 52.236-1, Performance of Work by the Contractor, the schedule must indicate what portion(s) of the work the contractor intends to perform with his/her own workforce to meet the 15% requirement.

☐ b. The Contractor shall submit a progress chart, with in l O calendar days after issuance of a Notice to Proceed, which indicates the anticipated installation of work versus the elapsed contract time, which shall be represented in the form of a bar graph. The starting date of the schedule shall be the date of the Notice to Proceed and the ending date shall be the original contract completion date.

☐ c. Submittals, samples, and shop drawings. Project Engineer will explain distribution procedures

3. PAYMENT REQUESTS:

☐ a. Payments shall be made monthly by the VA according to the value of completed work from the Contractor's approved Schedule of Costs. All invoices should be submitted to Austin Texas as outlined in the contract. In accordance with the Prompt Payment Act, the fourteen (14) day timeframe for payment shall commence on the date a proper invoice is received by the CO. Included with the pay request shall be the payroll sheets for the Contractor and Subcontractors.

4. PROTECTION OF SURROUNDING AREA:

☐ a. In performing this contract, the Contractor shall provide for protecting the lives and health of employees and other persons, preventing damage to property, materials, supplies, equipment and avoiding work interruptions.

☐ b. Any damage caused by the Contractor or his personnel will be restored and repaired at the expense of the Contractor.

5. DAILY LOGS:

☐ a. The Contractor shall provide the VA Project Manager with daily logs.

Project Engineer will explain frequency. The daily log shall identify the number of laborers, supervisors and each branch of work and will be used to verify payrolls submitted.

6. SAFETY:

☐ a. The VA Safety Officer has the authority to stop work if a serious safety violation is being committed.

7. CHANGES:

☐ a. The Contracting Officer (CO), from information furnished by the COTR may, by a written order, make changes to the drawings and/or specifications that are within the general scope of the contract. No other person is authorized to make revisions, changes, or deletions from the contract.

☐ b. Proposals for changes in work shall be submitted to the Contracting Officer according to the requirements contained in Clauses 52.243-4 and 852.236-88 of the General Conditions. Proposals more than $1,000 must include:

1. Itemized breakdown of labor and material costs.

2. List of subcontractors performing the work.

3. Overhead & Profit percentages.

☐ c. Change Orders (Proceed Orders): There may be some instances (as described in Clause 52.343-4 of the General Conditions) where the need to proceed with a change in work is necessary. In these cases, written authorization will be issued by the Contracting Officer (CO) to proceed with the work. An equitable adjustment will be negotiated within 30 calendar days.

8. SUBCONTRACTORS:

☐ a. The Contractor shall submit a list of subcontractors which will include names and addresses and the nature of work involved (SF 1413). The Contracting Officer reserves the right to disapprove any proposed Subcontractor who has had prior record of unsatisfactory work at this site, or any Federal or non-Federal Agency.

9. LABOR STANDARDS PROVISONS AND PAYROLLS:

☐ a. A copy of the rates and wages shall be posted by the Contractor in a prominent place at the work site.

☐ b. Apprentices will be permitted to work only under a Bona Fide apprenticeship program. Concurrent with or prior to the first payroll listing, certificates of apprenticeship from a recognized council shall be submitted to the Contracting Officer.

10. CORRESPONDENCE:

a. All correspondence from the Contractor shall bear:

☐ (1) Contract Number

☐ (2) Project Title

☐ (3) Project Name

11. OTHER TOPICS SPECIFIC TO THIS PROJECT:

{Signature of Contracting Officer, (CO) Date

Signature of Project Manager, (COR) Date

Signature of Contractor Date:

PROJECT: 578-371 Parking Expansion at Joliet CBOC
DATE: 3/28/2023
CONTRACT:
c The VA Project Manager for this project is: Aaron Walsh
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 1:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 2:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 3:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 4:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 5:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 6:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 7:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 8:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 9:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 10:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 11:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 12:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 13:
11 OTHER TOPICS SPECIFIC TO THIS PROJECT 14:
Check Box1: Off
Check Box2: Off
Check Box3: Off
Check Box4: Off
Check Box5: Off
Check Box6: Off
Check Box7: Off
Check Box8: Off
Check Box9: Off
Check Box10: Off
Check Box11: Off
Check Box12: Off
Check Box13: Off
Check Box14: Off
Check Box15: Off
Check Box16: Off
Check Box17: Off
Check Box18: Off
Check Box19: Off
Check Box20: Off
Check Box21: Off

File details come from the government source that posted it. Updated .