- Adams County, Asotin County, Benton County, Chelan County, Clallam County, Clark County, Columbia County, Cowlitz County, Douglas County, Ferry County, Franklin County, Garfield County, Grant County, Grays Harbor County, Island County, Jefferson County, King County, Kitsap County, Kittitas County, Klickitat County, Lewis County, Lincoln County, Mason County, Okanogan County, Pacific County, Pend Oreille County, Pierce County, San Juan County, Skagit County, Skamania County, Snohomish County, Spokane County, Stevens County, Thurston County, Wahkiakum County, Walla Walla County, Whatcom County, Whitman County, Yakima County, Asotin City, Clarkston City, Clarkston Heights-Vineland CDP, West Clarkston-Highland CDP, Benton City, Chelan City, Chelan Falls CDP, Clallam Bay CDP, Lewisville CDP, Rock Island City, Pacific Beach CDP, Whidbey Island Station CDP, Mercer Island City, Pacific City, Bainbridge Island City, Kingston CDP, Kitsap Lake CDP, Kittitas City, Klickitat CDP, Okanogan City, Anderson Island CDP, Fort Lewis CDP, Fox Island CDP, Herron Island CDP, Ketron Island CDP, North Fort Lewis CDP, Raft Island CDP, Stevenson City, Hat Island CDP, Lake Stevens City, Snohomish City, Spokane City, Spokane Valley City, Puget Island CDP, Garfield Town, Yakima City, Washington
About this file
This document is Questions & Answer #2 related to Competitive Solicitation No. 2024-05: Training Positive Community Framework, issued by the Washington Traffic Safety Commission (WTSC). The solicitation is for WTSC to award an Agency Contract for positive traffic safety culture training and technical support. The document provides responses to questions related to the scope of the required services, data security requirements, training event logistics, and contract terms. Key changes to the solicitation documents are also identified.
The contract requires the successful bidder to provide an assessment of WTSC staff and Target Zero Managers by December 31, 2024, which may be extended to January 31, 2025. The contract also requires the bidder to meet with the WTSC program director up to two times per month. The WTSC will be responsible for arranging and paying for the training event venues, equipment, and participant travel and lodging.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
Question & Answer #2
Competitive Solicitation No. 2024-05: Training Positive Community Framework
This document is posted to capture the questions received during the question & answer period for Competitive Solicitation No. 2024-05: Training Positive Community Framework. This document is the official response to the questions received.
Questions or responses included in this document require changes to the solicitation documents. The solicitation has been updated in 2.8_Exhibit D_Contract_2024-05 on WEBS as 2.8_Exhibit D_Contract_2024-05 V2 and the change is detailed below in row 7 of the question document.
Prior Amendments:
N/A
Any additional questions regarding this solicitation must be directed to the Procurement Coordinator listed below.
Abby Williams
(360) 515-2381 awilliams@wtsc.wa.gov mailto:awilliams@wtsc.wa.gov
Rev 4/13/2016 Page 2 of 5
Question Response Did this change the solicitation?
Exhibit B-1: Are responses limited to the space available in the PDF document’s column labeled “Written Response”?
Yes responses must be entered in the “Written Response” areas. The documents are now uploaded in Word format.
NO
Exhibit B-1: Page 5, Req ID #2: The initial paragraph states “around all steps of the PCF framework including Step 7.” However, notes in the Written Response column only reference “skills associated with Step 7.” Can you clarify?
That is correct. For that question, we are asking bidders to only provide relevant information regarding step 7 of the Positive Culture Framework.
NO
Exhibit B-2: Page 3, Question
2. The first, second, and third paragraphs refer to “applying the principles of the Positive Culture Framework.” Can you clarify what is meant by these principles? Are these principles the tasks and activities associated with the 7 steps?
WTSC has adopted the Positive Culture Framework as presented and taught by the Montana State University Center for Health and Safety Culture. Please refer to their website for more details on this approach to traffic safety. https://chsculture.org/positive-culture-framework/. It may be helpful to specifically see this training guide:
https://chsculture.org/training-materials/
NO
https://chsculture.org/positive-culture-framework/ https://chsculture.org/positive-culture-framework/ https://chsculture.org/training-materials/
Rev 4/13/2016 Page 3 of 5
Exhibit B-3: Page 9, Data security requirements. As this contract does not involve the bidder to perform financial services on behalf of the WTSC nor does this contract involve providing computer/network/cloud services, can the requirements for annual security certifications (specifically, (a) AICPA Statement of Standards for Attestation Engagement (SSAE) No. 18 SOC 1 Type II fiscal year cycle audit report; (b) SOC 2 Type I report in accordance with AICPA AT 101; and (c) attestation that Bidder’s Services are in compliance with WaTech Security Policy
141.10 – Securing Information Technology Assets) be waived? If so, how is Exhibit B-3 to be signed? If this is to be handled in the contract negotiation process, how is Exhibit B-3 to be signed?
If there is an issue with this clause, complete and submit Exhibit E_Contract Issues List.
Exhibit B-3 is to be signed as directed in the solicitation instructions.
NO
Exhibit C: Pages 3 and 4, Regarding the training events for WTSC Program Managers and Target Zero Managers:
are all costs for the venues (including audio/visual equipment), food, lodging, and travel for the participants covered by the WTSC (i.e., the bidder has no responsibility for these costs)?
WTSC assumes responsibility for locating and reserving the venue and paying any fees for its use including audio visual expenses.
The costs of travel, food and lodging for all staff/TZMs attending as students is also paid for by the WTSC.
NO
Rev 4/13/2016 Page 4 of 5
Exhibit D (Contract):
Page 3, Project Goal #1 states the assessment of WTSC staff and Target Zero Managers is to be submitted by Dec 31, 2024.
- Project Goal #1 states the assessment includes WTSC staff.
Does this include all WTSC staff or only Program Managers?
- Is the summary of knowledge, skills and application to be provided at the individual or group level? If group level, by what groups?
- If the anticipated award date is not until Dec 9 (and possibly could be delayed due to negotiations on insurances or other matters) and WTSC staff and/or TZMs may be out due to holiday breaks, can the deadline be extended to January 31, 2025?
Regarding the question about Goal #1 – The assessment is only meant to include WTSC Program Managers (not all WTSC staff) and Target Zero Managers.
The summary of knowledge, skills and application is intended to guide phase 2 of the project so the assessment needs to provide sufficient detail to guide the specific training needs of WTSC Program Managers and Target Zero Managers. WTSC would defer to the expertise of the successful bidder on how they would provide their assessment to WTSC.
Regarding the possibility of extending the deadline of phase 1 due to timing of the full execution of an agreement, this is not an unreasonable request and the WTSC would entertain extending the deadline. If this change was agreed on by both parties, an amendment would be created and signed to document this contractual change, consistent with WTSC requirements.
Exhibit D (Contract): Page 25, last row of the table states that the contractor will meet weekly with the program director.
However, page 2 of Exhibit C (Cost proposal bid price), the first row of table in Phase 2 states these meetings will be “up to two times per month.”
Can you clarify the expectation for the frequency of these meetings?
This was an oversight in the contract – Exhibit D. The language in Exhibit D, on page 25, should match what is written in Exhibit C so that they match. The intended frequency of meetings with the Program Director is up to two times per month.
YES
Rev 4/13/2016 Page 5 of 5
Exhibit D (Contract): Page 25, first row of the table states “2) provide analysis of results as requested.” As the SWS has an enormous volume of data and covers a wide range of behaviors, beliefs, and other indicators, can you clarify any limitations on “analysis of results as requested”? This could entail extensive time and is very difficult to budget.
For an example of the type of data analysis this section is referring to, please see Target Zero Managers - Washington Traffic Safety Commission. This website provides a link to all Target Zero Manger Regions. Each region has a Region Data Summary which is what has been produced in the past. Target Zero Managers and Program Managers used this analysis.
https://wtsc.wa.gov/target-zero-managers/