Pre-Bid QA Ops Center Expansion 10072026.pdf

PDF 323 KB Posted

Attached to
B861-26-01 MULTIPRIME - NEW CONSTRUCTION Operations Facility Expansion Project
Solicitation number
US.254234
Issued by
Lancaster County, Pennsylvania

About this file

This file contains Pre-Bid Conference Notes for B861-26-01, a multiprime new construction Operations Facility Expansion Project issued by the City of Lancaster, Pennsylvania. The project consists of construction of five new buildings with five separate prime contracts covering General Construction, Mechanical, Electrical, Plumbing, and Fire Protection scopes of work. A non-mandatory pre-bid conference was held on October 7, 2026, at 9:00 AM at the project site, with attendance documentation provided. A mandatory site visit is required prior to bid submission, which must be coordinated with Mike Belfino, Water Distribution Manager, at 717.989.3695 or mbelfino@cityoflancasterpa.gov. Electronic bid submissions, including technical questions and substitution requests, must be submitted via the PennBID online platform. Bids were due October 28, 2026, at 11:00 AM. The City anticipates issuing Notice to Proceed in December 2026, with Substantial Completion targeted for March 2028 and Final Completion targeted for May 2028.

The project has an estimated overall value of approximately $8,000,000, with approximately 75% attributed to the General Construction Prime contract. The project requires approximately 9,000 cubic yards of imported fill to achieve required structural elevations. No adverse findings were reported from the Phase 1 Environmental Site Assessment, Geotechnical Report, and Fill Assessment. No Minority, Women, and Disadvantaged Business participation requirements apply to this project, though all bidders must complete all required forms. The General Construction Prime is responsible for site security, including installation and maintenance of an 8-foot tall fence topped with barbed wire. Permitting is underway with permits expected by the time of bid award. The City will determine the lowest responsible bidder based on submitted bids. Water treatment operations and campus roadway traffic must be maintained throughout construction.

View the file

Other files

File Type Posted
334100 - STORM UTILITY DRAINAGE PIPING.pdf PDF
C08 - Construction Plan.pdf PDF
2026-10-14 - CD Addendum 2.pdf PDF
B861-26-01 FINAL - MULTIPRIME Operations Facility Expansion Project.docx DOCX document
City of Lancaster 150 Pitney Road Phase 1 ESA Sept2026.pdf PDF
C05 - Site Civil Specifications Combined.pdf PDF
ES-LOD-NPDES.dwg DWG drawing
321723 - PAVEMENT MARKINGS.pdf PDF
CD-18 UTILITY PLAN.pdf PDF
C10 - Geotechnical Report.pdf PDF
Layout.dwg DWG drawing
Addendum 03 Arch Front End Specs.pdf PDF
2026-10-06 - Civil Addendum 1.pdf PDF
C03 - Operations Facilities Expansion - Bid Specs - Vol I.pdf PDF
2026-10-29 - ES Addendum 4.pdf PDF
25061 - Addendum 4 Arch-struct-MEP summary.pdf PDF
CD-17 UTILITY PLAN.pdf PDF
Existing.dwg DWG drawing
25-061 Pitney Rd Warehouse Arch-Structural-MEP Drawings Addendum 4.pdf PDF
25061 - Addendum 1.pdf PDF
ES.dwg DWG drawing
C06 - Pitney Rd Warehouse Arch-Structural-MEP Bid Set.pdf PDF
Pre-Bid Attendees Ops Center Expansion 10072026.pdf PDF
2026-10-29 - CD Addendum 4.pdf PDF
FINAL QA Report.pdf PDF
25-061 Pitney Rd Warehouse Arch-Structural-MEP Addendum 1.pdf PDF
312000 - EARTH MOVING.pdf PDF
2026-10-23 - CD Addendum 3.pdf PDF
Landscape.dwg DWG drawing
Demolition.dwg DWG drawing
B861-26-01 ADDENDUM 2 - MULTIPRIME Operations Facility Expansion Project.docx DOCX document
25-061 Pitney Rd Warehouse Arch-Structural-MEP Drawings Addendum 3.pdf PDF
133418-USER-Post Frame Building Systems-10-23-2026.pdf PDF
25061 - Addendum 3 Arch-struct-MEP summary.pdf PDF
C04 - Operations Facilities Expansion - Bid Specs - Vol II.pdf PDF
25-061 Pitney Rd Warehouse Arch-Structural-MEP Addendum 2.pdf PDF
323113 - CHAIN LINK FENCES AND GATES.pdf PDF
EG.dwg DWG drawing
Easements.dwg DWG drawing
2026-10-23 - ES Addendum 3.pdf PDF
Profiles-Utilities.dwg DWG drawing
2026-10-06 - ES Addendum 1.pdf PDF
C09 - Fill Assessment Summary.pdf PDF
329113 - SOIL PREPARATION.pdf PDF
C07 - ES Plan.pdf PDF
B861-26-01 BidTabulationReport.xlsx XLSX spreadsheet
Addendum 04 Arch MEP Specs.pdf PDF
C01 - Standard General Conditions of the Contract.pdf PDF
CD-16 UTILITY PLAN.pdf PDF
PG.dwg DWG drawing
Show 40 more

Latest 50 of 54 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

B861-26-01 MULTIPRIME – NEW CONSTRUCTION

Operations Facility Expansion Project

Pre-Bid Conference Notes

A non-mandatory pre-bid conference was held at the site on October 7, 2026, at 9:00a. Please see the attendance sheet for a record of those in attendance.

The following preliminary discussions were noted:

Electronic bid documents may be obtained by prospective bidders utilizing the PennBID online platform. All submissions, including technical questions, clarifying RFIs, and substitution requests, are to be submitted via PennBID to ensure that all parties are duly informed.

Attendance at the pre-bid conference is not required but a site visit prior to the submission of bids is required to be considered eligible to bid. Future site visits should be coordinated with Mike Belfino, Water Distribution Manager, by calling 717.989.3695 or emailing mbelfino@cityoflancasterpa.gov. If emailing, the subject line should read, “Operations Facility Expansion Project – Request for Site Visit.”

Minutes and sign-in sheet for the pre-bid conference will be distributed via formal Addendum via PennBID. If any information discussed on-site is later contradicted in the formal Addendum, bidders should defer to the information in the formal Addendum.

The intent is to commence construction as soon as the bidding and contracting processes are complete. As of this date the City anticipates issuing Notice to Proceed to all Primes in December 2026. Substantial Completion is targeted for March 2028, and Final Completion is targeted for May 2028.

The City is currently running the water main to the site and has recently installed two conduits for electric and two conduits for communication cabling. The electric and communications conduits are terminated in two quazite boxes along the driveway as shown as the Owner/Contractor demarcation point on the plans. The Owner’s site utility work is expected to be completed in October 2026.

There is no formal budget established for the project, but the estimated overall value of the project is approximately $8,000,000, with approximately 75% of that value attributable to the General Construction Prime contract.

All parties are reminded that this site will require imported materials to achieve the required structural elevations. Approximately 9,000 cubic yards of imported fill are estimated to be required.

A Phase 1 Environmental Site Assessment, Geotechnical Report, and Fill Assessment are included in the bid documents hosted on PennBID. No adverse findings have been reported to date.

Per the Contract Documents, the salt shed building is designed with a Gambrel-style roof and truss assembly. The Architect asked the group if there are any questions or comments on the salt shed roof as currently designed and if the Gambrel-style form introduces any known challenges. There were no responses from the group. As with all technical questions, any specific questions regarding the salt shed roof are to be submitted via PennBID.

Site drawings in CAD format will be issued in a forthcoming addendum.

There are no Minority, Women, and Disadvantaged Business participation requirements for the project, though all bidders are still required to complete all forms. A response of “N/A” is a sufficient response on form B7 if applicable.

Permitting for the project is underway and permits are expected to be in hand by the time the bid award is made.

Following these discussions, the group was afforded the opportunity to walk the project limits and inspect current conditions. During this walkthrough, the following items of note were discussed:

B861-26-01 MULTIPRIME – NEW CONSTRUCTION

Operations Facility Expansion Project

The General Construction Prime is responsible for site security, both to protect the project site as well as maintaining the security posture of the water campus. The GC is responsible for installing and maintaining an 8’ tall fence around the project site topped with barbed wire; concertina wire is not necessary.

Two rock construction entrances (RCEs) are shown on the plans.

All Prime Contractors and subcontractors for the project have a shared obligation to ensure that traffic is maintained on the roadway. Water treatment processes and operations will continue unabated during construction, and the roadway must remain clear and passable for all traffic through the campus.

The gravel driveway through the adjacent parkland for the sewer and gas connections as well as the in-ground quazite boxes for the electrical and communications connections were noted.

Security camera and access control devices and terminations shall be by Owner as referenced in Notes 15, 16, and 17 on Drawing E201.

With no further questions or discussion, the pre-bid conference adjourned at approx. 9:45a.

File details come from the government source that posted it. Updated .