B861-26-01 MULTIPRIME - NEW CONSTRUCTION Operations Facility Expansion Project
Solicitation number
US.254234
Issued by
Lancaster County, Pennsylvania

About this file

Summary

This is a Final QA Report documenting responses to 149 vendor questions submitted during the bidding phase for the City of Lancaster, Pennsylvania's Operations Facility Expansion Project, a multiprime construction contract. The project involves construction of five new buildings and is structured under five separate prime contracts: General Construction, Mechanical, Electrical, Plumbing, and Fire Protection. The original bid deadline was October 28, 2026, at 11:00 AM, which was subsequently extended to November 4, 2026, at 11:00 AM to allow bidders additional time for thorough document review and subcontractor coordination. A non-mandatory pre-bid conference was held on October 7, 2026, at 9:00 AM, with required site visits available Monday through Friday during business hours. The groundbreaking is expected on or before January 1, 2027, with substantial completion targeted for December 31, 2027, and final completion by March 31, 2028. The project is estimated between $7 million and $9 million total, with approximately 70 percent of work under the General Contract.

The QA responses clarify numerous technical, contractual, and administrative requirements across all building systems and trades. Notable determinations include that all excavation and rock removal is the General Contractor's responsibility; the City will carry Builder's Risk Insurance with a $5,000 deductible; the City will pay all permitting fees, utility costs, material testing, and special inspections; and all prime contractors and subcontractors must obtain a Unique Entity ID (UEI) from SAM.gov prior to contract execution, though registration is not required before bidding. The project involves specialized structures including a warehouse with pre-engineered metal building (PEMB) framing, a covered storage shed, a salt storage building, and a material storage building, with detailed specifications regarding collateral loads, interior liner panels, roof panels, and material finishes. Funding is subject to a RACP grant with specific state requirements, and the City will award the contract to the lowest responsible bidder meeting all qualifications and contract requirements.

View the file

Other files

File Type Posted
334100 - STORM UTILITY DRAINAGE PIPING.pdf PDF
C08 - Construction Plan.pdf PDF
2026-10-14 - CD Addendum 2.pdf PDF
B861-26-01 FINAL - MULTIPRIME Operations Facility Expansion Project.docx DOCX document
City of Lancaster 150 Pitney Road Phase 1 ESA Sept2026.pdf PDF
C05 - Site Civil Specifications Combined.pdf PDF
ES-LOD-NPDES.dwg DWG drawing
321723 - PAVEMENT MARKINGS.pdf PDF
CD-18 UTILITY PLAN.pdf PDF
C10 - Geotechnical Report.pdf PDF
Layout.dwg DWG drawing
Addendum 03 Arch Front End Specs.pdf PDF
2026-10-06 - Civil Addendum 1.pdf PDF
C03 - Operations Facilities Expansion - Bid Specs - Vol I.pdf PDF
2026-10-29 - ES Addendum 4.pdf PDF
25061 - Addendum 4 Arch-struct-MEP summary.pdf PDF
CD-17 UTILITY PLAN.pdf PDF
Existing.dwg DWG drawing
25-061 Pitney Rd Warehouse Arch-Structural-MEP Drawings Addendum 4.pdf PDF
25061 - Addendum 1.pdf PDF
ES.dwg DWG drawing
C06 - Pitney Rd Warehouse Arch-Structural-MEP Bid Set.pdf PDF
Pre-Bid Attendees Ops Center Expansion 10072026.pdf PDF
2026-10-29 - CD Addendum 4.pdf PDF
25-061 Pitney Rd Warehouse Arch-Structural-MEP Addendum 1.pdf PDF
312000 - EARTH MOVING.pdf PDF
2026-10-23 - CD Addendum 3.pdf PDF
Landscape.dwg DWG drawing
Demolition.dwg DWG drawing
B861-26-01 ADDENDUM 2 - MULTIPRIME Operations Facility Expansion Project.docx DOCX document
25-061 Pitney Rd Warehouse Arch-Structural-MEP Drawings Addendum 3.pdf PDF
133418-USER-Post Frame Building Systems-10-23-2026.pdf PDF
25061 - Addendum 3 Arch-struct-MEP summary.pdf PDF
C04 - Operations Facilities Expansion - Bid Specs - Vol II.pdf PDF
25-061 Pitney Rd Warehouse Arch-Structural-MEP Addendum 2.pdf PDF
323113 - CHAIN LINK FENCES AND GATES.pdf PDF
EG.dwg DWG drawing
Easements.dwg DWG drawing
Pre-Bid QA Ops Center Expansion 10072026.pdf PDF
2026-10-23 - ES Addendum 3.pdf PDF
Profiles-Utilities.dwg DWG drawing
2026-10-06 - ES Addendum 1.pdf PDF
C09 - Fill Assessment Summary.pdf PDF
329113 - SOIL PREPARATION.pdf PDF
C07 - ES Plan.pdf PDF
B861-26-01 BidTabulationReport.xlsx XLSX spreadsheet
Addendum 04 Arch MEP Specs.pdf PDF
C01 - Standard General Conditions of the Contract.pdf PDF
CD-16 UTILITY PLAN.pdf PDF
PG.dwg DWG drawing
Show 40 more

Latest 50 of 54 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Generated on Nov 02, 2026 9:31 AM EST - Nancy Miller

Public Q&A

#2 - Estimated Value

Vendor, Sep 17, 2026 10:47 AM EDT, Not Public - Pending

Do you have an estimated value for GC bonding?

Keyana Williams, Sep 18, 2026 2:13 PM EDT, Public - Answered

The project is estimated between $7 million and $9 million total, with roughly 70 percent of the work being under the General Contract.

#7 - Salt Storage Building

Vendor, Sep 17, 2026 1:34 PM EDT, Not Public - Pending

We have a salt storage structure that looks more like a conventional building from the outside, 4/12 pitch gable roof, vertical walls but achieves more interior volume than the high arch gambrel design by using a coffer truss, would this be an acceptable alternate? The ceiling height in the center area

(21' wide) would be 30' tall, the remaining areas on the left and right sides would be at 27'. 70' truss width, clear span. Thank you

Nancy Miller, Sep 24, 2026 11:47 AM EDT, Public - Answered

We are not interested in other design considerations at this time, and ask bidders to please bid the project as shown on the drawings and as specified.

#1 - Estimated Value

Vendor, Sep 17, 2026 2:12 PM EDT, Not Public - Pending

Is there an estimated value for the project and is there a breakdown per contract?

Keyana Williams, Sep 18, 2026 2:13 PM EDT, Public - Answered

The project is estimated between $7 million and $9 million total, with roughly 70 percent of the work being under the General Contract.

#5 - project

Vendor, Sep 21, 2026 9:22 AM EDT, Not Public - Pending

Will there be another walk thru for sub contractors

Keyana Williams, Sep 23, 2026 8:55 AM EDT, Public - Answered

There will be a walkthrough during the Pre-Bid Meeting, and bidders may be able to schedule other times if a mutually convenient time can be scheduled with the Owner’s Rep. These can be scheduled after the Pre-Bid Meeting. All bidders are encouraged to send representation to the Pre-

Bid, as this is a secure facility and access must be scheduled in advance and an escort provided.

#4 - multiprime

Vendor, Sep 21, 2026 2:43 PM EDT, Not Public - Pending

Please confirm that this is a 5 multi prime project.

Keyana Williams, Sep 23, 2026 8:54 AM EDT, Public - Answered

Confirmed

#3 - Specs

Vendor, Sep 21, 2026 2:45 PM EDT, Not Public - Pending

Are there front-end specs that would have the bidding documents, summaries of work, etc. ?

Keyana Williams, Sep 23, 2026 8:53 AM EDT, Public - Answered

These are uploaded into the project folders.

#8 - DIV 00 & 01

Vendor, Sep 22, 2026 8:53 AM EDT, Not Public - Pending

Are there specifications for Division 00 & 01?

Nancy Miller, Sep 24, 2026 11:51 AM EDT, Public - Answered

All front-end specifications are by the City and are included in the Bid Package and contract document C01 - Standard General Conditions of the Contract.

#6 - Anticipated Start

Vendor, Sep 23, 2026 3:04 PM EDT, Not Public - Pending

What is the anticipated start date?

Keyana Williams, Sep 23, 2026 4:05 PM EDT, Public - Answered

Groundbreaking is expected on or before January 1st, 2027.

#9 - Substantial Completion/rock excavation

Vendor, Sep 24, 2026 2:28 PM EDT, Public - Pending

What defines substantial completion- completion of all primes or per contract? Confirm mechanical rock breaking is the only acceptable means of rock excavation?

Keyana Williams, Sep 28, 2026 9:47 AM EDT, Public - Answered

Substantial completion is reached when the work is sufficiently complete under the contract documents for the owner to occupy or use it for its intended purpose. This applies to all building systems, and therefore, all prime contractors. This would be confirmed by a Punchlist Walkthrough with the Architect and Engineers of record.

Keyana Williams, Sep 28, 2026 9:48 AM EDT, Public - Answered

Rock removal other than mechanical removal will be subject to approvals by the Fire Department and Department of Public Works. For example, a blasting plan would need to be acceptable to the owner, Department of Public Works (Water Bureau), and Lancaster Bureau of Fire, and would require necessary approvals and permits.

Until such approvals can be provided, the bidder shall assume all rock removal will be mechanical, or otherwise the bidder shall bear the full risk of bidding with the intent of blasting or other removal methods.

#10 - Bid form Item 1-2

Vendor, Sep 24, 2026 4:20 PM EDT, Public - Pending

Is it the intent that Item 1-2 (Salt Shed) on the bid form be awarded with Item 1-1 as a single contract, or may the City award without it?

Nancy Miller, Sep 28, 2026 1:23 PM EDT, Public - Answered

The intent is to award the entire project, but the Shed must be priced separately due to funding requirements related to that specific building.

#11 - project

Vendor, Sep 26, 2026 10:28 AM EDT, Public - Pending

Does the electric contractor do their excavation for their own work.

Nancy Miller, Sep 28, 2026 1:23 PM EDT, Public - Answered

Per the bidding documents, excavation of all primes is by the GC, including rock removal.

#12 - project

Vendor, Sep 26, 2026 10:29 AM EDT, Public - Pending

Do each contractor remove their own trash off site

Nancy Miller, Sep 28, 2026 1:24 PM EDT, Public - Answered

Each contractor is required to perform their own housekeeping.

#13 - project

Vendor, Sep 26, 2026 12:00 PM EDT, Public - Pending

Who does the generator pad and is there a drawing for it ?

Keyana Williams, Oct 09, 2026 10:07 AM EDT, Public - Answered

B+H Response: The generator pad and all equipment pads shall be the work of the General

Contractor. The generator pad details are on sheet E002 issued in addendum 1.

#14 - electrical

Vendor, Sep 26, 2026 12:04 PM EDT, Public - Pending

Has the owner submitted a service & meter paper work for the new service. If so can we get the job number or the person in charge. So we know what the electric co. wants from us.

Nancy Miller, Oct 06, 2026 3:09 PM EDT, Public - Answered

A PPL work order has been initiated. Work order # is 14932537 and PPL Designer is noted as Qi

Tian.

#15 - electrical

Vendor, Sep 26, 2026 12:10 PM EDT, Public - Pending

Who pays for the temp power pole during construction? What size service is it to be and how many job trailers will there be.

What is the temp building lighting requirements

Nancy Miller, Oct 16, 2026 1:50 PM EDT, Public - Answered

The EC is responsible for the temporary power pole and and required equipment – material and labor. All physical work and coordination is to be performed by the EC; City will pay the electric bills to PPL.

The size of the temporary power shall be coordinated with GC and Architect.

The EC shall be responsible for construction site temp lighting and temp buildings lighting.

#16 - electrical

Vendor, Sep 27, 2026 11:22 AM EDT, Public - Pending

What floor boxes make do you want for office receptacle/data

Nancy Miller, Sep 30, 2026 4:39 PM EDT, Public - Answered

FLBC5500 by Arlington, or equivalent.

#17 - Permits

Vendor, Sep 28, 2026 1:28 PM EDT, Public - Pending

Please clarify responsibility for obtaining and paying all permit and plan-review fees, including the building permit and any mechanical, electrical, plumbing, fire protection, utility, and other required permits. Please identify any permit or review fees that will be paid or waived by the City of

Lancaster.

Keyana Williams, Oct 09, 2026 10:08 AM EDT, Public - Answered

All permitting, review, and inspection fees will be paid by the owner. The contractors are responsible for coordinating, preparing and submitting each of the necessary respective permits and inspections for their applicable trade(s) and contracts.

#18 - project

Vendor, Sep 29, 2026 9:43 AM EDT, Public - Pending

Does the city wave permit the cost of the permits

Keyana Williams, Oct 09, 2026 10:08 AM EDT, Public - Answered

All permitting, review, and inspection fees will be paid by the owner. The contractors are responsible for coordinating, preparing and submitting each of the necessary respective permits and inspections for their applicable trade(s) and contracts.

#19 - PEMB

Vendor, Sep 29, 2026 10:49 AM EDT, Public - Pending

Drawing S101 shows Warehouse interior PEMB column/support locations, and S102 identifies mezzanine beam loads applied to PEMB columns. Specification 13 34 19, paragraph 2.2.D.4, describes the primary frame as clear-span.

1. Please confirm whether the Warehouse PEMB shall include the interior columns shown on

S101, or be designed as a clear-span structure.

2. If interior columns are required, please confirm that the PEMB supplier shall design its columns and connections for the mezzanine reactions shown on S102.

3. Please confirm that the PEMB design loads stated in 13 34 19 and on the structural drawings are to be applied together. If any values conflict, please identify the governing criteria.

4. If the answer changes the column layout or reactions, will revised foundation drawings be issued for bidding?

Keyana Williams, Oct 09, 2026 10:10 AM EDT, Public - Answered

1. Interior columns will be utilized as shown on plan documents.

2. PEMB supplier shall design the mezzanine connections to the PEMB for the reactions shown on the drawings.

3. The PEMB design loads on the drawings are correct. If any conflicts arise for design load values between the structural drawings and design loads stated in specification section 13 34 19 an RFI is to be issued.

4. There is no change to column layout.

#20 - Specifications Vs Plans

Vendor, Sep 29, 2026 10:56 AM EDT, Public - Pending

If the plans and specification manuals have differing information, which should be followed?

Keyana Williams, Oct 09, 2026 10:10 AM EDT, Public - Answered

RFIs (request for information) are to be submitted for any discrepancies discovered in Bid

Documents. In the event of a conflict, the higher cost/quality option prevails unless determined otherwise by Engineer or Architect of record.

#21 - electrical

Vendor, Sep 29, 2026 11:00 AM EDT, Public - Pending

Contractor

Installs cat 6 data wire in building with no punch down on cable.

Installs 2 runs of conduit from IT room to under ground box per plan with pull line.

Nancy Miller, Oct 16, 2026 3:03 PM EDT, Public - Answered

EC to run data cabling from each location shown on plans to a punch-down patch panel located in the data rack inside IT Room W113. Rack and punch-down panel(s) to be provided and installed by Owner. Data cabling shall be labeled, terminated in accordance with the T568B wiring standard, and tested to industry standards by the EC.

1. The EC shall run One (1) CAT6 cable from each WAP and CCTV to the punch down panel/rack in IT room.

2. The EC shall run two (2) CAT6 cables from each wallplate/data-drop to the punch down

3. The EC shall terminate all cables – punch down panel at IT room, RJ45 keystone jacks at data drops, and RJ45 modular plugs at WAP and CTTV locations.

4. The EC shall be responsible for testing the CAT6 cables to the current industry standards after termination.

Note:

- All networking equipment (rack, punch-panel, WAP’s, CCTV Equip…) shall be provided by the customer.

- all RJ45 jacks, RJ45 plugs, and Keystone Plates shall be provided by the EC.

#22 - PEMB

Vendor, Sep 29, 2026 1:53 PM EDT, Public - Pending

Elevations A104 and A105 mention Alum. Trims, gutters, downspouts, fascia, etc. The PEMB trims are not aluminum materials. Will the standard trims work?

Nancy Miller, Oct 06, 2026 3:12 PM EDT, Public - Answered

Per specification 133419 sections 2.9_K & 2.13_E & 2.14_A, trims, gutters, downspouts, fascia, etc. are to be of same material as roof panels and adjacent wall panels. The aluminum material note on drawings will be omitted. Standard trims are acceptable, provided they are in compliance with specifications.

#23 - PEMB

Vendor, Sep 29, 2026 1:54 PM EDT, Public - Pending

What do we need to use for the collateral loads on the buildings?

Keyana Williams, Oct 09, 2026 10:10 AM EDT, Public - Answered

For all pre-engineered metal buildings, a collateral load of 8 PSF should be used plus an additional

5 PSF on roof areas as indicated on roof plans on sheet A100 to receive future solar panel loads.

#24 - PEMB

Vendor, Sep 29, 2026 1:55 PM EDT, Public - Pending

Will the PEMB standard 1’-4” endwall frame set back from steel line to center line of frame work, or do we need to hold a specific set back?

Keyana Williams, Oct 09, 2026 10:11 AM EDT, Public - Answered

The 1'-4" end wall set back may be assumed, the final set back will be determined by the PEMB as required for end wall frames.

#25 - PEMB

Vendor, Sep 29, 2026 1:57 PM EDT, Public - Pending

To verify, all columns on the warehouse building will be 0’-8” below finish floor, correct?

Keyana Williams, Oct 09, 2026 10:11 AM EDT, Public - Answered

The top of pier and interior footings will be 0'-8" below finished floor.

#26 - PEMB

Vendor, Sep 29, 2026 1:57 PM EDT, Public - Pending

We will need to add an additional frame line to break the 36'-8" span in the warehouse, will this work?

Keyana Williams, Oct 09, 2026 10:12 AM EDT, Public - Answered

An additional frame line at the 36’-8” span can be accommodated. Drawings will be revised in the next addendum to reflect this revision.

#27 - PEMB

Vendor, Sep 29, 2026 1:58 PM EDT, Public - Pending

What are the low eave heights for each building?

Nancy Miller, Oct 06, 2026 3:13 PM EDT, Public - Answered

Per details 2 & 3 on sheet A302, the main warehouse metal building eave height is 28'-0". The low eave of the mono-slope roof portion of the warehouse building is also 28'-0". Per details #1/A514 &

#4/A303, the covered shed metal building eave height is 24'-0" above the top of concrete pier level.

#28 - PEMB

Vendor, Sep 29, 2026 1:59 PM EDT, Public - Pending

Will the endwall frames of the Warehouse be the same rigid frames with an interior column or will post and beam frames work?

Keyana Williams, Oct 09, 2026 10:12 AM EDT, Public - Answered

Post and Beam frames are acceptable.

#29 - PEMB

Vendor, Sep 29, 2026 1:59 PM EDT, Public - Pending

Per the details on A511, it looks like the roof will overhang the wall panels by 2" (total 0’-3 ¼” overhang including wall panel depth), is this correct or do we need to use our standard eave and rake conditions in lieu of this 0’-3 ¼” overhang?

Nancy Miller, Oct 06, 2026 3:13 PM EDT, Public - Answered

Standard eave and rake condition is acceptable in lieu of overhang as detailed

#30 - PEMB

Vendor, Sep 29, 2026 2:04 PM EDT, Public - Pending

The specs call for a soffit panel, but I am not seeing any areas of soffit panels on the Warehouse.

Is this correct?

Nancy Miller, Oct 06, 2026 3:14 PM EDT, Public - Answered

Correct, soffit panels are not used on the warehouse. The material shed is to have soffit panel installed at roof overhangs on drawings #5 & #4 on sheet A514.

#31 - PEMB

Vendor, Sep 29, 2026 2:05 PM EDT, Public - Pending

The drawings are calling for specific size gutter and downspouts, but our standard gutters and downspouts will be larger than what is shown, is this acceptable?

Nancy Miller, Oct 16, 2026 3:04 PM EDT, Public - Answered

Yes; gutter and downspout sizes indicated are the minimum size allowable.

#32 - PEMB

Vendor, Sep 29, 2026 2:05 PM EDT, Public - Pending

Are we needing to provide our standard 12” ridge vents on the buildings? The specs and the roof plans mention ridge vents so I want to verify that these will work.

Nancy Miller, Oct 16, 2026 3:04 PM EDT, Public - Answered

Ridge vents are specified under Section 133419 – Pre-Engineered Metal Building Systems, 2.9 –

Accessory Materials – Walls and Roof. Net Free Ventilation Area: 12 square inches per linear foot minimum.

#33 - PEMB

Vendor, Sep 29, 2026 2:06 PM EDT, Public - Pending

Are interior liner panels required on any of the buildings?

Nancy Miller, Oct 06, 2026 3:14 PM EDT, Public - Answered

Yes, interior liner panels are to be provided for the warehouse building. Locations are specified on revised drawing #1/A101 issued in Addendum 1.

#34 - PEMB

Vendor, Sep 29, 2026 2:07 PM EDT, Public - Pending

The drawings do not show X bracing or portal frames. Should we use portal frames on the wall with the doors and X bracing on the opposite wall? What type of bracing are we needing to use for this building part?

Keyana Williams, Oct 09, 2026 10:13 AM EDT, Public - Answered

Provide portal frames at door locations and x bracing at back wall.

#35 - PEMB

Vendor, Sep 29, 2026 2:08 PM EDT, Public - Pending

Besides the large fans, there aren’t any other hanging loads that we need to account for on the warehouse building?

Nancy Miller, Oct 23, 2026 3:33 PM EDT, Public - Answered

There are no anticipated loads beyond what is shown on the Drawings. In addition to the fans, there are unit heaters, piping, conduit, sprinkler for MEP work. UH weights will be shown on

Addendum #3.

#36 - Minority, Women, and Disadvantaged Business Subcontractor's Compliance

Form

Vendor, Sep 29, 2026 3:25 PM EDT, Public - Pending

Does this project have a required goal percentage for Minority, Women, and Disadvantaged

Business Subcontractors? Or is this based off of a good faith effort only?

Nancy Miller, Oct 01, 2026 9:41 AM EDT, Public - Answered

There is no DBE required goal percentage.

#37 - Builder's Risk Insurance

Vendor, Sep 29, 2026 3:26 PM EDT, Public - Pending

Please confirm that Builder's Risk Insurance is the Prime Contractor's responsibility to carry in their bid.

Nancy Miller, Oct 20, 2026 4:23 PM EDT, Public - Answered

Builder’s Risk Insurance will be carried by the City and is not required to be carried by each individual Prime Contractor. If a claim is made under the City’s Builder’s Risk policy that is determined to be the result of negligence by one or more Prime Contractors, those responsible

Contractors shall be responsible for paying the applicable deductible under the Builder’s Risk policy

Ryan Hunter, Oct 27, 2026 10:29 AM EDT, Public - Answered

To clarify, the deductible of the Owner's Builder's Risk policy is anticipated to be $5,000.00.

#38 - Temporary Water and Electric

Vendor, Sep 29, 2026 3:28 PM EDT, Public - Pending

Section 015000 Temporary Facilities and Controls mentions that water service and electric service is available by connecting to the Owner's existing services. Who is responsible for the use charges for these utilities?

Nancy Miller, Oct 16, 2026 3:08 PM EDT, Public - Answered

See Section 011200 – Multiple Contract Summary, added in Addendum #2.

#39 - Subcontractor Requirements

Vendor, Sep 30, 2026 1:44 PM EDT, Public - Pending

Per the Instructions to Bidders, Article 13.03, each proposed subcontractor will be required to provide a SAM.gov Unique Entity ID (UEI). This may significantly limit the subcontractors who can bid this project. We as the prime bidder will hold a SAM.gov UEI and would represent the subcontractors working under us. Would it be acceptable if only the prime contractor has a

SAM.gov UEI?

Nancy Miller, Oct 01, 2026 9:53 AM EDT, Public - Answered

All Successful Bidders and subcontractors are required to have a Unique Identity ID (UEI), a 12-character alphanumeric ID assigned to an entity by SAM.gov. For contracts over $25,000, Successful Bidder (Prime) is also required to be registered on SAM.gov and maintain a current

SAM.gov registration until contract close-out.

The prime contractor must register fully if they intend to be awarded a City Contract, however subcontractors should use the “Get UEI Only” option on SAM.gov if they only need the identifier temporarily, for example, to appear as a subcontractor on another organization's bid.

UEI is assigned almost immediately, whereas Registration can take longer, as it goes through a vetting process to verify that the entity has not been debarred from doing business.

Nancy Miller, Oct 01, 2026 9:55 AM EDT, Public - Answered

Also adding that there is no cost to be assigned a UEI or to Register on SAM.gov.

#40 - Evaluation of Bid Proposals

Vendor, Sep 30, 2026 1:46 PM EDT, Public - Pending

In reference to the Invitation to Bidders, “The City will determine who is the lowest responsible bidder upon the basis of the bids submitted. The lowest responsible bidder need not be the bidder submitting the lowest dollar amount.” The same paragraph then lists criteria that the City will evaluate for each bidder. Please advise if this criteria will be weighted per a scoring matrix, such as 70% price, 10% past experience, etc. We would appreciate more direction on how this evaluation process will be conducted before investing time into bidding this project.

Nancy Miller, Oct 01, 2026 10:21 AM EDT, Public - Answered

Please see Article 20 of the Instructions to Bidders for further clarification regarding bid evaluation.

Bidders must meet or exceed the qualifications listed in Article 4, listing the requested information, at minimum, on the appropriate forms in the Experience Questionnaire. Furthermore, the awarded contractor must not be debarred from doing business in any State as per Article 3. The contract will be awarded to the "lowest responsible bidder” or the contractor who submits the lowest price that fully meets all contract requirements, and who also has the financial stability, qualifications, and track record to successfully perform the work. The is no weighted evaluation matrix.

#41 - Civil

Vendor, Sep 30, 2026 3:40 PM EDT, Public - Pending

There is no profile for MH-A28 to OS-1. The only information available for this pipe run is the chart in detail 5 of sheet ES-12 which has an incorrect outlet elevation (BOE). According to the profile

OS-2 to SW-A27 on sheet SW 41, the invert should be 260.56. It also appears the grate elevation for OS-1 should be 277.50. Please confirm.

Nancy Miller, Oct 06, 2026 3:15 PM EDT, Public - Answered

The profile showing OS-1 to M-A28 is located on Sheet SW-48 and is labeled cross-section A-A’.

The incorrect outlet elevation on Sheet ES-12 has been corrected to match the profiles.

The grate elevation for OS-1 is 275.50 as shown in the profile. The 277.50 elevation is the top of berm elevation.

#42 - Civil

Vendor, Sep 30, 2026 3:48 PM EDT, Public - Pending

Specification section 334100.3.6.B.5.b and 334100.3.6.B.5.c indicates low-pressure air testing.

Significant cost will be added to the project to perform these tests. Will air testing be required for storm sewer?

Nancy Miller, Oct 06, 2026 3:15 PM EDT, Public - Answered

Section 334100.3.6.5 has been revised to remove the “UNI-B-6” notation and notes a-c have been removed. Section 334100.3.6.C has been removed.

#43 - Civil

Vendor, Sep 30, 2026 3:49 PM EDT, Public - Pending

Specification 329113.2.1.D indicates topsoil particle size is to be a maximum of 1-inch.

Specification section 329113.3.2.D indicates native topsoil is to be screened. Will the 1-inch threshold be required and should the Contractor expect native topsoil will need to be screened to meet the Specifications?

Nancy Miller, Oct 06, 2026 3:16 PM EDT, Public - Answered

The max particle size listed under 329113.2.1.D has been revised to 2-inches. Section

329113.3.2.D has been removed.

#44 - Fencing

Vendor, Oct 01, 2026 10:06 AM EDT, Public - Pending

Drawing CD-22 indicates that the fencing is to be galvanized. Specification Section 323113 Chain

Link Fencing and Gates is indicating a Black Polymer Coating. Please advise which should be priced.

Nancy Miller, Oct 06, 2026 3:16 PM EDT, Public - Answered

All references in spec 323113 references a polymer coating have been removed. Drawing CD-22 remains unchanged – all fencing, mesh and fittings are to be galvanized.

#45 - electrical

Vendor, Oct 01, 2026 3:45 PM EDT, Public - Pending

Does the City have a fire alarm brand that we should get a quote for the fire alarm?

Nancy Miller, Oct 16, 2026 3:09 PM EDT, Public - Answered

The City does not have a preferred vendor or manufacturer for the fire alarm. The fire alarm system for this new facility shall be standalone and not tied into any other system on the campus.

#46 - Partition Type Schedule

Vendor, Oct 02, 2026 3:24 PM EDT, Public - Pending

Please provide partition schedule for Warehouse office.

Nancy Miller, Oct 22, 2026 8:28 AM EDT, Public - Answered

Partition schedule added to Sheet A102 in Addendum #2.

#47 - Gambrel-Style Roof on Salt Shed

Vendor, Oct 05, 2026 10:16 AM EDT, Public - Pending

The Gambrel-style roof and framing on the Salt Shed is not economical, nor something most

PEMB manufactures are willing to price. May the PEMB manufacturer redesign to a Gable-style roof and framing system to be more economical?

Nancy Miller, Oct 16, 2026 3:10 PM EDT, Public - Answered

An Alternate using a more typical post-frame system has been added in Addendum #2.

#48 - SCM-001

Vendor, Oct 07, 2026 7:47 AM EDT, Public - Pending

Not all the stone type is called out for SCM-001 on sheet SW-48 of 54, only the Riprap Aprons have a detail. Please advise on the type of stone for the unlabeled areas within the facility.

Nancy Miller, Oct 20, 2026 9:11 AM EDT, Public - Answered

The Emergency Spillway stone is described in Detail 4/SW-43. Information pertaining to rip-rap at the existing endwall within the basin has been added to Detail 3/SW-43

#49 - Storm Drain Restoration Detail

Vendor, Oct 07, 2026 7:50 AM EDT, Public - Pending

The pipe bedding detail on sheet SW-43 of 54 does not specify if the trench is to be backfilled with stone or dirt, as the water and sewer details do. Please confirm the storm drain trench backfill material under pavement.

Nancy Miller, Oct 20, 2026 9:12 AM EDT, Public - Answered

The pipe bedding detail does specify appropriate materials for layers in the trench.

#50 - Oil Separator Detail

Vendor, Oct 07, 2026 7:55 AM EDT, Public - Pending

Please provide a detail for the oil separator.

Nancy Miller, Oct 16, 2026 3:12 PM EDT, Public - Answered

Details have been provided in Addendum #2

#51 - BAS Controls

Vendor, Oct 07, 2026 8:39 AM EDT, Public - Pending

Please clarify how the new HVAC equipment associated with the City of Lancaster Operations

Facility Expansion is intended to be integrated into the City’s existing Building Automation System

(BAS), currently supported by Dynatech Controls. Please identify the required controls, communication protocol, and responsibility for BAS integration.

Nancy Miller, Oct 16, 2026 3:12 PM EDT, Public - Answered

It was deemed that the BAS system is not needed for this project and will operate individually.

#52 - Plumbing & HVAC Insulation Specifications

Vendor, Oct 07, 2026 9:09 AM EDT, Public - Pending

Please provide a schedule for both plumbing and HVAC, thank you.

Nancy Miller, Oct 23, 2026 3:34 PM EDT, Public - Answered

There is no schedule for insulation applications, please see specifications

#53 - Builders Risk

Vendor, Oct 08, 2026 1:42 PM EDT, Public - Pending

Must the builder’s risk have full limits for flood and earthquake, or would a sublimit be acceptable?

If so, what limit?

Nancy Miller, Oct 20, 2026 4:24 PM EDT, Public - Answered

Builder’s Risk Insurance will be carried by the City and is not required to be carried by each individual Prime Contractor.

#54 - Warehouse/Covered Shed Collateral Load

Vendor, Oct 08, 2026 2:04 PM EDT, Public - Pending

Please confirm the collateral load for the PEMB Warehouse and Covered Shed.

Nancy Miller, Oct 16, 2026 3:14 PM EDT, Public - Answered

For all pre-engineered metal buildings, a collateral load of 8 PSF should be used plus an additional

5 PSF on roof areas as indicated on roof plans on sheet A100 to receive future solar panel loads.

#55 - Warehouse Ceiling Fans Weight

Vendor, Oct 08, 2026 2:08 PM EDT, Public - Pending

Please confirm the weight of the two ceiling fans in the Warehouse.

Nancy Miller, Oct 23, 2026 3:34 PM EDT, Public - Answered

Refer to the HVLS Fan Schedule on Sheet H001. Weight listed at 220 lbs.

#56 - Toilet Accessories

Vendor, Oct 08, 2026 3:00 PM EDT, Public - Pending

Toilet fixture schedule provided but nothing is called out or labeled on the plans. Please advise.

Nancy Miller, Oct 16, 2026 3:14 PM EDT, Public - Answered

Sheet A401 has been updated in Addendum #2 to show toilet accessory locations.

#57 - Access Control

Vendor, Oct 08, 2026 6:02 PM EDT, Public - Pending

Please confirm if the Access Control System will be an addition to an existing system or if it will be completely new.

i. If existing system, please provide relevant information like System ID, manufacturer

Nancy Miller, Oct 23, 2026 3:36 PM EDT, Public - Answered

Access control will be tied into an existing enterprise-wide system utilizing Verkada hardware and software. Provision and installation of the access control hardware will be by Owner; EC is required to run one (1) 1" conduit w/ pullstring on interior of building from device box to the height

A.F.F. as designated on plans.

#58 - Video Surveillance

Vendor, Oct 08, 2026 6:04 PM EDT, Public - Pending

Please confirm if the Video Surveillance System will be an addition to an existing system or if it will be completely new.

i. If existing system, please provide all relevant information like System ID, manufacturer

- Please confirm exact camera types (dome, multisensory, dual lens, fisheye, etc) to provide, as markups show only one camera type based on symbols.

Nancy Miller, Oct 23, 2026 3:37 PM EDT, Public - Answered

Surveillance cameras will be tied into an existing enterprise-wide system utilizing Verkada hardware and software. Provision and installation of the cameras will be by Owner; EC is required to provide (1) CAT6 POE cable to each camera location shown on the plans, with the cable end terminated in an RJ45 modular plug and wired in accordance with the T568B wiring standard

#59 - Waterline

Vendor, Oct 09, 2026 9:28 AM EDT, Public - Pending

The utility plan calls out the 8" DICL water main as previously installed by City of Lancaster. If so, do we still need to complete trenching as called out on the demolition plans and full depth trench paving as called out on the layout plans?

Nancy Miller, Oct 20, 2026 9:12 AM EDT, Public - Answered

The Demolition and Layout Plans have been revised to identify trenching and paving that is not in scope.

#60 - Civil - CAD

Vendor, Oct 09, 2026 10:45 AM EDT, Public - Pending

Please provide the Civil CAD files if available.

Nancy Miller, Oct 20, 2026 9:12 AM EDT, Public - Answered

CAD files are provided as part of Addendum 2.

#61 - Civil

Vendor, Oct 09, 2026 2:21 PM EDT, Public - Pending

Is the paving scope going to be reduced or changed on the plans now that some of this work has been complete with the waterline?

Nancy Miller, Oct 20, 2026 9:13 AM EDT, Public - Answered

The Demolition and Layout Plans have been revised to identify trenching and paving that is not in scope.

#62 - Wash Bay

Vendor, Oct 12, 2026 9:11 AM EDT, Public - Pending

Print E101 show a standard exit sign in the wash bay area. Is this the correct fixture for this area or should the fixture and devices in this area be weather proof?

Nancy Miller, Oct 16, 2026 3:15 PM EDT, Public - Answered

All devices and fixtures in the Wash Bay shall be Wet Location listed.

Please see updated Light Fixture Schedule. (Addendum #2)

#63 - Lighting Control

Vendor, Oct 12, 2026 9:48 AM EDT, Public - Pending

I noticed that you have all of the lighting on the generator however do we need to add some GTD's to bypass the lighting controls in an emergency situation?

Nancy Miller, Oct 16, 2026 3:16 PM EDT, Public - Answered

There is a Life Safety ATS that will transfer all lighting power within the required 10 seconds. No

GTD’s shall be required.

#64 - Addendum tag covers information

Vendor, Oct 12, 2026 10:20 AM EDT, Public - Pending

Sheet SW-36, the addendum 1 triangle covers the quantity of trees. please reissue.

Nancy Miller, Oct 20, 2026 9:13 AM EDT, Public - Answered

The addendum tag has been relocated.

#65 - E101 RM W124 Light Switch

Vendor, Oct 12, 2026 10:38 AM EDT, Public - Pending

Print E101 Wash bay W124 shows a fire alarm pull station at the exterior door should this be a light switch? Electronic lighting controls typically do not survive in wash bays even when weather proof rated, can we switch this area t6o standard switches for the lighting controls. This would also be safer than have the lighting system shut down due to failure or not seeing motion.

Nancy Miller, Oct 16, 2026 3:16 PM EDT, Public - Answered

The Pull Station has been removed. All lighting controls in the Wash Bay shall be standard weatherproof 3-way switches. There shall be no automated lighting controls in Wash Bay.

#66 - GFCI Receptacles

Vendor, Oct 12, 2026 10:55 AM EDT, Public - Pending

Print E201 shows standard duplex receptacles in the following locations; Wash Bay W124, Laundry W117, Toilet W120 and Toilet W121. Do we need to make these GFCI receptacles and the should the wash bay receptacle be weatherproof rated? Do the receptacles in the storage areas also need to be GFCI receptacles?

Nancy Miller, Oct 16, 2026 3:17 PM EDT, Public - Answered

The following areas shall have GFCI receptacles - Wash Bay W124, Laundry W117, Toilet W120 and Toilet W121.

The devices in the Wash Bay shall be WR rated and have In-Use covers.

Warehouse receptacles do not require GFCI protection.

#67 - Data Cabling

Vendor, Oct 12, 2026 11:07 AM EDT, Public - Pending

Are we installing Cat 6 and/or optical fiber cabling for this project? At this point the prints only indicate data cabling installed for just WIFI Access antennas and CCTV cameras all other data outlets shown on the prints just get empty conduits, is this correct?

Nancy Miller, Oct 23, 2026 3:38 PM EDT, Public - Answered

Answer from RFI #21.

EC to run data cabling from each location shown on plans to a punch-down patch panel located in the data rack inside IT Room W113. Rack and punch-down panel(s) to be provided and installed by Owner. Data cabling shall be labeled, terminated in accordance with the T568B wiring standard, and tested to industry standards by the EC.

1. The EC shall run One (1) CAT6 cable from each WAP and CCTV to the punch down

2. The EC shall run two (2) CAT6 cables from each wallplate/data-drop to the punch down panel/rack in IT room.

3. The EC shall terminate all cables – punch down panel at IT room, RJ45 keystone jacks at data drops, and RJ45 modular plugs at WAP and CTTV locations.

4. The EC shall be responsible for testing the CAT6 cables to the current industry standards after termination.

Note:

- All networking equipment (rack, punch-panel, WAP’s, CCTV Equip…) shall be provided by the customer.

Nancy Miller, Oct 23, 2026 3:38 PM EDT, Public - Answered

- all RJ45 jacks, RJ45 plugs, and Keystone Plates shall be provided by the EC.

#68 - Paved Trail detail

Vendor, Oct 12, 2026 12:31 PM EDT, Public - Pending

Is this used anywhere? CD-8 shows replacement trail, but says to tie into gravel. Is just that section being paved?

Nancy Miller, Oct 20, 2026 9:14 AM EDT, Public - Answered

Yes, this detail is used where indicated on CD-8. The existing trail was constructed using the same detail. The labels will be revised in Addendum 2 to avoid confusion.

#69 - Pallet Racking

Vendor, Oct 12, 2026 2:18 PM EDT, Public - Pending

Please provide load information and where the pushback racking is supposed to be for the pallet racking.

Nancy Miller, Oct 23, 2026 3:40 PM EDT, Public - Answered

Pushback racking systems will not be used. Only Selective Pallet racking will be used in locations shown on the drawings. Loading for each rack level to be 10,000 lbs.

#70 - RFI #39 Follow-Up – Clarification of SAM.gov UEI Requirements and Timing

Vendor, Oct 13, 2026 8:17 AM EDT, Public - Pending

Following RFI #39, please clarify whether prime contractors and subcontractors must obtain a UEI and complete any applicable SAM.gov registration prior to bidding, or if this can be completed by the successful bidders after bids are submitted. Also, is there a location on the bid form where this information must be listed?

We are concerned that requiring this prior to bidding will discourage participation, particularly from subcontractors, resulting in fewer bidders, less competition, and ultimately higher project costs.

We respectfully request that the City consider allowing the apparent low bidders and their subcontractors to complete these requirements after bidding but prior to contract award. This would encourage greater participation and help protect the City's project budget.

Nancy Miller, Oct 16, 2026 3:38 PM EDT, Public - Answered

The City requires that all Prime contractors who are awarded a bid be registered on SAM.gov.

We highly recommend starting the process now because the registration process can take several weeks.

With that said, not being registered does not exclude anyone from bidding, however, registration of the contract awardees must be verified prior to contract execution.

For subcontractors, the UEI must be verified prior to contract execution. Subcontractors should use the “Get UEI Only” option on SAM.gov if they only need the identifier temporarily, for example, to appear as a subcontractor on another organization's bid. UEI is assigned almost immediately.

There is no cost to be assigned a UEI or to Register on SAM.gov

When completing the bid documents, if you have not completed registration, please note where you are in the process and that you understand that you will need to be registered prior to executing the contract.

#71 - Deduct Alternates

Vendor, Oct 13, 2026 8:41 AM EDT, Public - Pending

Eliminate: Construction Yard Structure- What is this referring to?

Nancy Miller, Oct 23, 2026 5:01 PM EDT, Public - Answered

The construction yard structure is the “covered shed” Pre-engineered metal building as labeled on the architectural drawings. This same structure is labeled as “covered storage” on the civil drawings. See key plan added to sheet A000 in Addendum 3 for reference of building/structure names.

#72 - 015000 – Temporary Facilities and Controls

Vendor, Oct 13, 2026 8:51 AM EDT, Public - Pending

Can we get a better description of what Prime Contractor owns the scope of work in the specification 015000 – Temporary Facilities and Controls

Nancy Miller, Oct 16, 2026 3:18 PM EDT, Public - Answered

See added Section 011200 – Multiple Contract Summary (issued in Addendum #2) for division of responsibilities.

#73 - Column Protectors

Vendor, Oct 13, 2026 9:06 AM EDT, Public - Pending

On Drawing A101 there are interior columns with the note “Column protectors – see specs” – these items cannot be found

Nancy Miller, Oct 16, 2026 3:18 PM EDT, Public - Answered

Column Protectors are specified under Section 133419 – Pre-Engineered Metal Building Systems.

For better clarity, these were relocated within the section to 2.9 L in Addendum #2.

#74 - Casework

Vendor, Oct 13, 2026 11:04 AM EDT, Public - Pending

Can casework be "build to" AWI standards without the AWI certification?

Nancy Miller, Oct 16, 2026 3:19 PM EDT, Public - Answered

Yes. Casework is to be built to AWI standards, but the AWI certification is not required.

#75 - Material Storage Shearwalls

Vendor, Oct 13, 2026 11:07 AM EDT, Public - Pending

Structural drawings call for 7/16 wall sheathing, architectural call for 5/8 wall sheathing. Please clarify.

Nancy Miller, Oct 16, 2026 3:19 PM EDT, Public - Answered

Wall sheathing may be 7/16” in accordance with structural drawings.

#76 - Donwspout boots

Vendor, Oct 13, 2026 11:09 AM EDT, Public - Pending

Please provide spec for what is required.

Nancy Miller, Oct 16, 2026 3:20 PM EDT, Public - Answered

Downspout boots are specified under Section 055000 – Metal Fabrications (2.9).

#77 - Salt Shed opening

Vendor, Oct 13, 2026 12:08 PM EDT, Public - Pending

Is there steel columns/beam at the opening to the salt shed? Structural drawings don't show anything. Architecturals show a beam and a plate and say refer to structural drawings.

Nancy Miller, Oct 16, 2026 3:20 PM EDT, Public - Answered

Posts are shown on the Addendum #2 drawings.

#78 - Bid Time Extension

Vendor, Oct 13, 2026 2:19 PM EDT, Public - Pending

I see the bid is currently due at 11:00 AM on 10/28. Would you consider moving the deadline to later in the day? Allowing additional time on bid day would give prime contractors more opportunity to receive and thoroughly review subcontractor pricing, potentially resulting in more competitive bids and lower overall project costs.

Nancy Miller, Oct 23, 2026 4:54 PM EDT, Public - Answered

We have extended the bid due date by one week to November 4, 2026 at 11:00 AM

#79 - Window Shades

Vendor, Oct 13, 2026 3:12 PM EDT, Public - Pending

There is a spec for window shades, but none are shown on the drawings. Please advise if there is any window shades on this project and where they are.

Nancy Miller, Oct 16, 2026 3:21 PM EDT, Public - Answered

Revised sheet A601 (Addendum #2) indicates that window shades shall be provided for all W01 windows in the project.

#80 - Alternate Deducts

Vendor, Oct 13, 2026 3:19 PM EDT, Public - Pending

The alternate deduct prices on the electrical bid form do not appear to pertain to the electrical contract. What do you want us to fill out for these prices? Should we put 0 or N/A?

#81 - Construction Yard Structure

Vendor, Oct 13, 2026 3:25 PM EDT, Public - Pending

For the alternate to eliminate the construction yard structure- is that the covered storage? If you eliminate that, do we pave where the structure would be or grass?

Nancy Miller, Oct 23, 2026 3:41 PM EDT, Public - Answered

Yes, this refers to the Covered Storage. The area will be paved if the structure is not constructed.

Nancy Miller, Oct 23, 2026 3:42 PM EDT, Public - Answered

The bid form and Earth Moving specification have been revised to differentiate between Bulk Rock and Trench Rock. 175 CY for Bulk Rock and 75 CY for Trench Rock.

#82 - Rock Unit Price

Vendor, Oct 14, 2026 9:12 AM EDT, Public - Pending

The bid form includes a line to provide a unit price and allowance for 250 CY of rock. Is this to be trench rock or bulk rock? There is a significant price difference between the two. Please consider making two lines, one for bulk rock with 200 CY and one for trench rock with 50 CY to be used for any rock removal based on the location of the rock.

Nancy Miller, Oct 23, 2026 3:42 PM EDT, Public - Answered

The bid form and Earth Moving specification have been revised to differentiate between Bulk Rock and Trench Rock. 175 CY for Bulk Rock and 75 CY for Trench Rock.

#83 - Unsuitable Soils

Vendor, Oct 14, 2026 9:13 AM EDT, Public - Pending

Please clarify how unsuitable soils will be handled if encountered on the site beyond design depths. Can a unit price and allowance be added for removal and replacement with suitable soils if encountered?

Nancy Miller, Oct 23, 2026 3:42 PM EDT, Public - Answered

Clarifying notes have been added to Sheets CD-12,CD-13, and CD-14. The Earth Moving

Specification 31 20 00 has also been revised. An allowance with unit price is now included on the bid form for remediation and/or removal and replacement of unsuitable soils beyond the depths indicated by the geotechnical report.

#84 - Summary of Work

Vendor, Oct 14, 2026 10:00 AM EDT, Public - Pending

Is there a Summary of Work to define the scope of each separate prime contract?

Nancy Miller, Oct 22, 2026 8:29 AM EDT, Public - Answered

Section 011200 – Multiple Contract Summary was added in Addendum #2

#85 - Surge Protection

Vendor, Oct 14, 2026 10:44 AM EDT, Public - Pending

I did not see any surge protection listed for panelboards A and LS. Being that the NEC is starting to require this do we need to add surge protection to the panelboards and if so can you provide a basis of design spec and manufacture for them?

Nancy Miller, Oct 23, 2026 3:43 PM EDT, Public - Answered

Surge protection is not required by code for this installation.

#86 - CU-1 Disconnect

Vendor, Oct 14, 2026 11:02 AM EDT, Public - Pending

Print E201 unit CU-1 show a disconnect with note 6 next to it, note 6 calls for a 100A, NEMA 4X, disconnect but the equipment schedule on print E002 only calls for a 30A disconnect. This note is also attached to the "Blend Boss" disconnect. Should the CU-1 disconnect be a 30A, NEMA 3R disconnect instead?

Nancy Miller, Oct 23, 2026 3:44 PM EDT, Public - Answered

The CU-1 disconnect switch shall be 30A-240V-2P-SN-NEMA-3R – 3#10+#10GRD-1/2”C.

#87 - NEMA 4X Disconnects

Vendor, Oct 14, 2026 11:08 AM EDT, Public - Pending

Print E201 notes 5 and 6 ask for NEMA 4X disconnects but do not specify stainless steel or regular steel. Do these disconnects need to be stainless since they are in a salt area? They make 4X disconnects in both stainless and regular steel. Does the disconnect for the garage door in this area also need to be NEMA 4X?

Nancy Miller, Oct 23, 2026 3:44 PM EDT, Public - Answered

Print E201, Note #’s 5 & 6 Disconnect Switches shall be NEMA-4X stainless steel. The garage door opener adjacent to the Brine Boss shall also be NEMA-4X stainless steel.

#88 - Pallet Rack

Vendor, Oct 14, 2026 11:15 AM EDT, Public - Pending

Is there a height, number of levels and weight capacity for beam level?

Nancy Miller, Oct 23, 2026 3:44 PM EDT, Public - Answered

Pallet rack and beam levels are indicated on detail #8 on sheet A512 for all pallet racking. Loading for each rack level to be 10,000 lbs.

#89 - Alternates

Vendor, Oct 14, 2026 11:28 AM EDT, Public - Pending

1. Please confirm that the construction yard structure that is eliminated in alternate 2-2 is labeled on the drawing as 'covered storage'. (If this alternate is taken this would provide gravel pavement in the whole yard and under the covered storage.)

2. For alternate 2-1 to eliminate the yard paving, please confirm this is also include the pavement under the covered storage area. (If this alternate is taken this would leave a fully paved lot.)

Nancy Miller, Oct 26, 2026 3:25 PM EDT, Public - Answered

1. Yes, the Construction Yard Storage is the same as the Covered Storage. If this structure is eliminated, its footprint will be paved in the same way as the Construction Yard.

2. Yes, the pavement elimination alternate means that the entire yard including the Cover

Storage will be left at the stone subbase level.

#90 - CU-2 Disconnect

Vendor, Oct 14, 2026 11:40 AM EDT, Public - Pending

Print E201 Note 12 calls for a NEMA 4X disconnect for CU-2, can this disconnect be NEMA 3R?

The disconnect for the main service next to it is NEMA 3R.

Nancy Miller, Oct 23, 2026 3:45 PM EDT, Public - Answered

CU-2 disconnect may be NEMA 3R.

#91 - Project Schedule

Vendor, Oct 14, 2026 11:48 AM EDT, Public - Pending

There is some gray area regarding the project schedule. Can this please be confirmed?

Award date:

Start Date: 1/1/27 (per RFI #6)

Substantial Completion:

Final Completion:

Nancy Miller, Oct 16, 2026 3:50 PM EDT, Public - Answered

Award date: On or before 12/27/26 (Bids will remain subject to acceptance for a period of ninety

(60) days after the date specified for the opening of bids (10/28/26) or the issuance of a notice of award, whichever occurs first. Per Article 19.01 of the Instructions to Bidders)

Start Date: 1/1/27 (per RFI #6) This is an estimation assuming that the City will not take the full 60 days to award.

Substantial Completion: 12/31/27 (per article 10 of Instructions to Bidders & Article 2 of the

Agreement.)

Final Completion: 3/31/28 (per article 10 of Instructions to Bidders & Article 2 of the Agreement.)

#92 - MEP Excavation

Vendor, Oct 14, 2026 11:52 AM EDT, Public - Pending

The documents indicate all excavation is by the GC.

1. Is this intended to mean 'by GC to within 5' of the building footprint?' MEPs generally own their own interior excavation for this type of work.

2. Who is responsible for setting beds and concrete duct banks?

3. Who is responsible for backfill and warning tape?

Nancy Miller, Oct 23, 2026 3:46 PM EDT, Public - Answered

1. Is this intended to mean 'by GC to within 5' of the building footprint?' MEPs generally own their own interior excavation for this type of work. All excavation and backfill to subgrade is by the GC.

Coordination will be required between the prime contractors to ensure proper layout, elevations, etc. are established. Each trade is responsible for layout for their work and coordination with the

GC for the needed excavation.

2. Who is responsible for setting beds and concrete duct banks? All setting beds, pipe bedding, conduit, pipe, duct banks, tracing wire, warning tape, and other trade-specific materials are by the applicable prime contractor for each trade.

3. Who is responsible for backfill and warning tape? Backfill (above conduit/duct banks, etc) by

GC. Setting bed, tracing wire, warning tape, and all associated materials by each trade.

#93 - Material Storage Building

Vendor, Oct 14, 2026 11:57 AM EDT, Public - Pending

Wall section (6/A514) calls for sheathing on the inside wall of the material storage building. Detail

(5/A514) does not call for any interior sheathing on the rear wall. Please confirm no plywood sheathing is required in this location.

Nancy Miller, Oct 23, 2026 3:46 PM EDT, Public - Answered

Plywood is to be used at this location. Architectural drawings are revised in Addendum #3 accordingly.

#94 - Testing

Vendor, Oct 14, 2026 12:02 PM EDT, Public - Pending

The Earthwork testing specification is clear that the owner is paying for the third party testing. Will the owner pay for all third party testing including concrete and masonry?

Nancy Miller, Oct 20, 2026 4:30 PM EDT, Public - Answered

All material testing and special inspections will be managed and paid by City.

#95 - Lintels

Vendor, Oct 14, 2026 12:08 PM EDT, Public - Pending

Will each prime be responsible to supply any lintels required for their openings?

Nancy Miller, Oct 23, 2026 3:47 PM EDT, Public - Answered

GC shall provide and install lintels for all openings. See updated Section 011200 – Multiple

Contract Summary in Addendum #3.

#96 - Access Doors

Vendor, Oct 14, 2026 12:09 PM EDT, Public - Pending

Will each prime supply and install access doors required for their work?

Nancy Miller, Oct 23, 2026 3:47 PM EDT, Public - Answered

GC shall provide and install access doors for all openings. See updated Section 011200 – Multiple

Contract Summary in Addendum #3.

#97 - Temp Fence

Vendor, Oct 14, 2026 12:13 PM EDT, Public - Pending

At the pre-bid meeting, we were told the temp. fence must have barbed wire. I do not see anything other than 6' high fence specified. For multiple reasons, including insurance issues, the only way to provide barbed wire will be to have a permanent type fence installed and then demolished when no longer needed. This will cr4ate significant cost increases. Will we be required to provide a barbed wire fence for temp fence?