This is a specification document for the Operations Center Expansion project in Lancaster, Pennsylvania, prepared by the City of Lancaster Department of Public Works. The specifications cover temporary facilities and controls, temporary tree and plant protection, selective demolition, site cast-in-place concrete, site clearing, and earth moving. The project involves construction of five new buildings under a multiprime contract structure comprising General Construction, Mechanical, Electrical, Plumbing, and Fire Protection trades. A non-mandatory pre-bid conference is scheduled for October 7, 2026, at 9:00 AM at the Water Administration Building, with mandatory site visits available Monday through Friday between 8:00 AM and 4:00 PM. Bids are due online by October 28, 2026, at 11:00 AM through PennBid's website. All contract documents and solicitation details are available at no cost on PennBid.
The specifications establish comprehensive requirements for contractor responsibilities including temporary utility installation, site security, erosion and sedimentation control, tree and plant protection zones, demolition procedures, concrete placement and finishing, soil testing, and earthwork operations. The contractor is responsible for all utility services during construction at no cost to the owner. Concrete work must comply with ACI standards, with design mixes requiring approval at least 15 days prior to work commencement. Field testing by an independent geotechnical laboratory will be performed at owner expense. Building permits and associated inspections must be obtained through the Bureau of Building Code Administration. The project is subject to minimum wage requirements, Steel Products Procurement Act compliance, and federal and state discrimination protection laws. The City will determine the lowest responsible bidder based on submitted bids, with no set-asides specified in the available documentation.
View the file
Other files
Show 40 more
Latest 50 of 54 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Operations Center Expansion RGS 2025992-044
City of Lancaster - Department of Public Works
TEMPORARY FACILITIES AND CONTROLS 015000
SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes requirements for temporary utilities, support facilities, and security and protection facilities.
B. Related Requirements:
1. Section 321216 "Asphalt Paving" for construction and maintenance of asphalt pavement for temporary roads and paved areas.
2. Section 321313 "Concrete Paving" for construction and maintenance of cement concrete pavement for temporary roads and paved areas.
1.3 USE CHARGES
A. General: Installation and removal of and use charges for temporary facilities shall be included in the Contract Sum unless otherwise indicated. Allow other entities to use temporary services and facilities without cost, including, but not limited to, Owner's construction forces, Landscape
Architect, Engineer, occupants of Project, testing agencies, and authorities having jurisdiction.
B. Contractor is responsible for all utility services for the duration of the project. Owner will not provide or pay for any utility services needed for construction operations.
1.4 INFORMATIONAL SUBMITTALS
A. Site Plan: Show temporary facilities, utility hookups, staging areas, and parking areas for construction personnel.
B. Erosion- and Sedimentation-Control Plan: Show compliance with requirements of EPA and PA
DEP NPDES Construction General Permit or authorities having jurisdiction, whichever is more stringent.
C. Fire-Safety Program: Show compliance with requirements of NFPA 241 and authorities having jurisdiction. Indicate Contractor personnel responsible for management of fire-prevention program.
1.5 QUALITY ASSURANCE
A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.
B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits.
C. Accessible Temporary Egress: Comply with applicable provisions in the U.S. Architectural &
Transportation Barriers Compliance Board's ADA-ABA Accessibility Guidelines and
ICC/ANSI A117.1.
1.6 PROJECT CONDITIONS
A. Temporary Use of Permanent Facilities: Engage Installer of each permanent service to assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before Owner's acceptance, regardless of previously assigned responsibilities.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Chain-Link Fencing: Minimum 2-inch (50-mm), 0.148-inch- (3.8-mm-) thick, galvanized-steel, chain-link fabric fencing; minimum 6 feet (1.8 m) high with galvanized-steel pipe posts;
minimum 2-3/8-inch- (60-mm-) OD line posts and 2-7/8-inch- (73-mm-) OD corner and pull posts, with 1-5/8-inch- (42-mm-) OD top rails.
B. Portable Chain-Link Fencing: Minimum 2-inch (50-mm), 0.148-inch- (3.8-mm-) thick, galvanized-steel, chain-link fabric fencing; minimum 6 feet (1.8 m) high with galvanized-steel pipe posts; minimum 2-3/8-inch- (60-mm-) OD line posts and 2-7/8-inch- (73-mm-) OD corner and pull posts, with 1-5/8-inch- (42-mm-) OD top and bottom rails. Provide galvanized-steel bases for supporting posts.
2.2 TEMPORARY FACILITIES
A. Field Offices, General: Prefabricated or mobile units with serviceable finishes, temperature controls, and foundations adequate for normal loading.
B. Field Offices are not required. Contractor is responsible for furnishing its own field office if deemed necessary for construction operations. Location of field offices, if necessary, shall be approved by Owner.
C. Storage and Fabrication Sheds: Provide sheds sized, furnished, and equipped to accommodate materials and equipment for construction operations.
1. Store combustible materials apart from building.
2.3 EQUIPMENT
A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures.
PART 3 - EXECUTION
3.1 INSTALLATION, GENERAL
A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the
Work.
1. Locate facilities within the limit of disturbance per plan.
B. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.
3.2 TEMPORARY UTILITY INSTALLATION
A. General: Install temporary service or connect to existing service.
1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.
B. Sewers and Drainage: Provide temporary utilities to remove effluent lawfully.
1. Connect temporary sewers to municipal system as directed by authorities having jurisdiction.
C. Water Service: Install water service and distribution piping in sizes and pressures adequate for construction.
D. Water Service: Connect to Owner's existing water service facilities. Clean and maintain water service facilities in a condition acceptable to Owner. At Substantial Completion, restore these facilities to condition existing before initial use.
E. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking water for use of construction personnel. Comply with requirements of authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.
F. Electric Power Service: Connect to Owner's existing electric power service. Maintain equipment in a condition acceptable to Owner.
G. Electric Power Service: Provide electric power service and distribution system of sufficient size, capacity, and power characteristics required for construction operations.
1. Install electric power service overhead unless otherwise indicated.
2. Connect temporary service to Owner's existing power source, as directed by Owner.
3.3 SUPPORT FACILITIES INSTALLATION
A. General: Comply with the following:
1. Provide construction for temporary offices, shops, and sheds located within construction area or within 30 feet (9 m) of building lines that is noncombustible according to
ASTM E 136. Comply with NFPA 241.
2. Maintain support facilities until Landscape Architect/Engineer schedules Substantial
Completion inspection. Remove before Substantial Completion. Personnel remaining after Substantial Completion will be permitted to use permanent facilities, under conditions acceptable to Owner.
B. Temporary Roads and Paved Areas: Construct and maintain temporary roads and paved areas adequate for construction operations. Locate temporary roads and paved areas as indicated and within construction limits indicated on Drawings.
1. Provide dust-control treatment that is nonpolluting and nontracking. Reapply treatment as required to minimize dust.
C. Temporary Use of Permanent Roads and Paved Areas: Locate temporary roads and paved areas in same location as permanent roads and paved areas. Construct and maintain temporary roads and paved areas adequate for construction operations. Extend temporary roads and paved areas, within construction limits indicated, as necessary for construction operations.
1. Coordinate elevations of temporary roads and paved areas with permanent roads and paved areas.
2. Prepare subgrade and install subbase and base for temporary roads and paved areas according to Section 312000 "Earth Moving."
3. Recondition base after temporary use, including removing contaminated material, regrading, proofrolling, compacting, and testing.
4. Delay installation of final course of permanent hot-mix asphalt pavement until immediately before Substantial Completion. Repair hot-mix asphalt base-course pavement before installation of final course according to Section 321216 "Asphalt
Paving."
D. Traffic Controls: Comply with requirements of authorities having jurisdiction.
1. Protect existing site improvements to remain including curbs, pavement, and utilities.
2. Maintain access for fire-fighting equipment and access to fire hydrants.
E. Parking: Use designated areas of Owner's existing parking areas within the project footprint.
F. Dewatering Facilities and Drains: Comply with requirements of authorities having jurisdiction.
Maintain Project site, excavations, and construction free of water.
1. Dispose of rainwater in a lawful manner that will not result in flooding Project or adjoining properties or endanger permanent Work or temporary facilities.
2. Remove snow and ice as required to minimize accumulation.
G. Project Signs: Provide Project signs as indicated. Unauthorized signs are not permitted.
1. Identification Signs: Provide Project identification signs as directed by Owner.
2. Temporary Signs: Provide other signs as indicated and as required to inform public and individuals seeking entrance to Project.
a. Provide temporary, directional signs for construction personnel and visitors.
3. Maintain and touchup signs so they are legible at all times.
H. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Comply with requirements of authorities having jurisdiction.
I. Lifts and Hoists: Provide facilities necessary for hoisting materials and personnel.
1. Truck cranes and similar devices used for hoisting materials are considered "tools and equipment" and not temporary facilities.
3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Protection of Existing Facilities: Protect existing vegetation, equipment, structures, utilities, and other improvements at Project site and on adjacent properties, except those indicated to be removed or altered. Repair damage to existing facilities.
B. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction as required to comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
C. Temporary Erosion and Sedimentation Control: Provide measures to prevent soil erosion and discharge of soil-bearing water runoff and airborne dust to undisturbed areas and to adjacent properties and walkways, according to erosion- and sedimentation-control Drawings. Comply with requirements of 2003 EPA Construction General Permit or authorities having jurisdiction, whichever is more stringent and requirements specified in Section 311000 "Site Clearing."
1. Verify that flows of water redirected from construction areas or generated by construction activity do not enter or cross tree- or plant- protection zones.
2. Inspect, repair, and maintain erosion- and sedimentation-control measures during construction until permanent vegetation has been established.
3. Clean, repair, and restore adjoining properties and roads affected by erosion and sedimentation from Project site during the course of Project.
4. Remove erosion and sedimentation controls and restore and stabilize areas disturbed during removal.
D. Stormwater Control: Comply with requirements of authorities having jurisdiction. Provide barriers in and around excavations and subgrade construction to prevent flooding by runoff of stormwater from heavy rains.
E. Tree and Plant Protection: Comply with requirements specified in Section 015639 "Temporary
Tree and Plant Protection."
F. Pest Control: Engage pest-control service to recommend practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at Substantial
Completion. Perform control operations lawfully, using environmentally safe materials.
G. Site Enclosure Fence: Before construction operations begin, furnish and install site enclosure fence in a manner that will prevent people and animals from easily entering the site except by entrance gates.
1. Extent of Fence: As required to enclose entire Project site construction or portion determined sufficient to accommodate construction operations.
2. Maintain security by limiting number of keys and restricting distribution to authorized personnel. Furnish one set of keys to Owner.
H. Security Enclosure and Lockup: Install temporary enclosure around partially completed areas of construction. Provide lockable entrances to prevent unauthorized entrance, vandalism, theft, and similar violations of security. Lock entrances at end of each work day.
I. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.
J. Temporary Egress: Maintain temporary egress from existing occupied facilities as indicated and as required by authorities having jurisdiction.
K. Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses. Comply with
NFPA 241; manage fire-prevention program.
1. Prohibit smoking on the premises.
2. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition according to requirements of authorities having jurisdiction.
3. Develop and supervise an overall fire-prevention and -protection program for personnel at Project site. Review needs with local fire department and establish procedures to be followed. Instruct personnel in methods and procedures. Post warnings and information.
3.5 OPERATION, TERMINATION, AND REMOVAL
A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.
B. Maintenance: Maintain facilities in good operating condition until removal.
1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage.
C. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion.
D. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial
Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.
1. Materials and facilities that constitute temporary facilities are property of Contractor.
Owner reserves right to take possession of Project identification signs.
2. Remove temporary roads and paved areas not intended for or acceptable for integration into permanent construction. Where area is intended for landscape development, remove soil and aggregate fill that do not comply with requirements for fill or subsoil. Remove materials contaminated with road oil, asphalt and other petrochemical compounds, and other substances that might impair growth of plant materials or lawns. Repair or replace street paving, curbs, and sidewalks at temporary entrances, as required by authorities having jurisdiction.
3. At Substantial Completion, repair, renovate, and clean permanent facilities used during construction period.
END OF SECTION 015000
TEMPORARY TREE AND PLANT PROTECTION 015639
SECTION 015639 - TEMPORARY TREE AND PLANT PROTECTION
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
B. “City of Lancaster Tree Manual – Regulations and Standards for Arboriculture Work”, December 2014.
1.2 SUMMARY
A. Section includes general protection and pruning of existing trees and plants that are affected by execution of the Work, whether temporary or permanent construction.
B. Related Sections:
1. Section 015000 "Temporary Facilities and Controls" for temporary site fencing.
2. Section 311000 “Site Clearing” for removing existing trees and shrubs.
1.3 DEFINITIONS
A. Caliper: Diameter of a trunk measured as required by the “City of Lancaster Tree Manual”.
B. Tree-Protection Zone: Area surrounding individual trees or groups of trees to be protected during construction, indicated on Drawings.
C. Vegetation: Trees, shrubs, groundcovers, grass, and other plants.
1.4 ACTION SUBMITTALS
A. As required by the “City of Lancaster Tree Manual”.
1.5 INFORMATIONAL SUBMITTALS
A. Qualification Data: For qualified arborist and tree service firm.
B. Existing Conditions: Documentation of existing trees and plantings indicated to remain, which establishes preconstruction conditions that might be misconstrued as damage caused by construction activities.
1. Use sufficiently detailed photographs or videotapes.
2. Include plans and notations to indicate specific wounds and damage conditions of each tree or other plants designated to remain.
1.6 QUALITY ASSURANCE
A. Tree Service Firm Qualifications: An experienced tree service firm that has successfully completed temporary tree and plant protection work similar to that required for this Project and that will assign an experienced, qualified arborist to Project site during execution of the Work.
B. Preinstallation Conference: Conduct conference at Project site, as required by the “City of
Lancaster Tree Manual”.
1. Review methods and procedures related to temporary tree and plant protection including, but not limited to, the following:
a. Construction schedule. Verify availability of materials, personnel, and equipment needed to make progress and avoid delays.
b. Enforcing requirements for protection zones.
c. Arborist's responsibilities.
d. Field quality control.
2. Discuss existing preconstruction condition of trees to remain.
1.7 PROJECT CONDITIONS
A. The following practices are prohibited within protection zones:
1. Storage of construction materials, debris, or excavated material.
2. Parking vehicles or equipment.
3. Foot traffic.
4. Erection of sheds or structures.
5. Impoundment of water.
6. Excavation or other digging unless otherwise indicated.
7. Attachment of signs to or wrapping materials around trees or plants unless otherwise indicated.
B. Do not direct vehicle or equipment exhaust toward protection zones.
C. Prohibit heat sources, flames, ignition sources, and smoking within or near protection zones and organic mulch.
D. All additional project conditions specified by the “City of Lancaster Tree Manual”.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Topsoil: As specified on Drawings
B. Organic Mulch: As specified on Drawings
C. Protection-Zone Fencing: Chain-link fencing or material as required by the “City of Lancaster
Tree Manual” and the City Arborist.
D. Protection-Zone Signage: Shop-fabricated, rigid plastic or metal sheet with attachment holes pre-punched and reinforced; legibly printed with nonfading lettering and as follows:
1. Size and Text: As shown on Drawings
2. Lettering: As shown on Drawings.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Erosion and Sedimentation Control: Examine the site to verify that temporary erosion- and sedimentation-control measures are in place. Verify that flows of water redirected from construction areas or generated by construction activity do not enter or cross protection zones.
3.2 PREPARATION
A. Locate and clearly identify trees, shrubs, and other vegetation to remain or to be relocated.
B. Protect tree root systems from damage caused by runoff or spillage of noxious materials while mixing, placing, or storing construction materials. Protect root systems from ponding, eroding, or excessive wetting caused by dewatering operations.
C. All preparations as required by the “City of Lancaster Tree Manual”.
3.3 TREE PROTECTION ZONES
A. Protection-Zone Fencing: Install protection-zone fencing as required by the “City of Lancaster
Tree Manual” and in accordance with manufacturer instructions.
B. Protection-Zone Signage: Install protection-zone signage in visibly prominent locations in a manner approved by City of Lancaster Arborist.
C. Maintain protection zones free of weeds and trash.
D. Repair or replace trees, shrubs, and other vegetation indicated to remain or be relocated that are damaged by construction operations, in a manner approved by City of Lancaster Arborist.
E. Maintain protection-zone fencing and signage in good condition as acceptable to City of
Lancaster Arborist and remove when construction operations are complete and equipment has been removed from the site.
1. Do not remove protection-zone fencing, even temporarily, to allow deliveries or equipment access through the protection zone.
2. Temporary access is permitted subject to preapproval in writing by City of Lancaster
Arborist if a root buffer effective against soil compaction is constructed as directed by
City of Lancaster Arborist. Maintain root buffer so long as access is permitted.
3.4 EXCAVATION
A. General: Excavate at edge of protection zones and for trenches indicated within protection zones according to requirements in Section 312000 "Earth Moving."
B. Trenching near Trees: Where utility trenches are required within protection zones, hand excavate under or around tree roots or tunnel under the roots by drilling, auger boring, or pipe jacking. Do not cut main lateral tree roots or taproots; cut only smaller roots that interfere with installation of utilities. Cut roots as required for root pruning.
C. Redirect roots in backfill areas where possible. If encountering large, main lateral roots, expose roots beyond excavation limits as required to bend and redirect them without breaking. If encountered immediately adjacent to location of new construction and redirection is not practical, cut roots approximately 3 inches back from new construction and as required for root pruning, with approval of City of Lancaster Arborist.
D. Do not allow exposed roots to dry out before placing permanent backfill. Provide temporary earth cover or pack with peat moss and wrap with burlap. Water and maintain in a moist condition. Temporarily support and protect roots from damage until they are permanently relocated and covered with soil.
3.5 ROOT PRUNING
A. Prune roots that are affected by temporary and permanent construction only with approval of
City of Lancaster Arborist and per requirements of the “City of Lancaster Tree Manual”.
3.6 CROWN PRUNING
A. Prune branches that are affected by temporary and permanent construction only with approval of City of Lancaster Arborist and per requirements of the “City of Lancaster Tree Manual”.
3.7 REGRADING
A. Lowering Grade: Where new finish grade is indicated below existing grade around trees, slope grade beyond the protection zone. Maintain existing grades within the protection zone.
B. Raising Grade: Where new finish grade is indicated above existing grade around trees, slope grade beyond the protection zone. Maintain existing grades within the protection zone.
C. Minor Fill within Protection Zone: Where existing grade is 2 inches or less below elevation of finish grade, fill with topsoil. Place topsoil in a single uncompacted layer and hand grade to required finish elevations.
3.8 FIELD QUALITY CONTROL
A. Inspections: Contact City of Lancaster Arborist to direct plant-protection measures in the vicinity of trees, shrubs, and other vegetation indicated to remain and to prepare inspection reports.
3.9 REPAIR AND REPLACEMENT
A. General: Repair or replace trees, shrubs, and other vegetation indicated to remain that are damaged by construction operations, in a manner approved by City of Lancaster Arborist.
1. Submit details of proposed root cutting and tree and shrub repairs.
2. Have arborist perform the root cutting, branch pruning, and damage repair of trees and shrubs.
3. Treat damaged trunks, limbs, and roots according to arborist's written instructions.
4. Perform repairs within 24 hours.
5. Replace vegetation that cannot be repaired and restored to full-growth status, as determined by Landscape Architect and City of Lancaster Arborist.
B. Trees: Remove and replace trees indicated to remain that are in an unhealthy condition before the end of the corrections period as required by the City of Lancaster Arborist.
1. Provide new trees as required by City of Lancaster Arborist.
2. Plant and maintain new trees as specified in Section 329300 "Plants."
3.10 DISPOSAL OF SURPLUS AND WASTE MATERIALS
A. Disposal: Remove excess excavated material, displaced trees, trash and debris, and legally dispose of them off Owner's property.
END OF SECTION 015639
SELECTIVE DEMOLITION 024119
SECTION 024119 - SELECTIVE DEMOLITION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Demolition and removal of selected site elements.
B. Related Requirements:
1. Section 015639 "Temporary Tree and Plant Protection" for temporary protection of existing trees and plants that are affected by selective demolition.
2. Section 311000 "Site Clearing" for site clearing and removal of above- and below-grade improvements.
1.3 DEFINITIONS
A. Remove: Detach items from existing construction and dispose of them off-site unless indicated to be salvaged or reinstalled.
B. Remove and Reinstall: Detach items from existing construction, prepare for reuse, and reinstall where indicated.
C. Existing to Remain: Leave existing items that are not to be removed and that are not otherwise indicated to be salvaged or reinstalled.
1.4 MATERIALS OWNERSHIP
A. Unless otherwise indicated, demolition waste becomes property of Contractor.
1.5 PREINSTALLATION MEETINGS
A. Predemolition Conference: Conduct conference at Project site.
1. Inspect and discuss condition of construction to be selectively demolished.
2. Review areas where existing construction is to remain and requires protection.
1.6 INFORMATIONAL SUBMITTALS
A. Proposed Protection Measures: Submit report that indicates the measures proposed for protecting individuals and property. Indicate proposed locations and construction of barriers.
B. Schedule of Selective Demolition Activities:
1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity.
2. Interruption of utility services. Indicate how long utility services will be interrupted.
3. Coordination for shutoff, capping, and continuation of utility services with each utility company.
1.7 CLOSEOUT SUBMITTALS
A. Inventory: Submit a list of items that have been removed and salvaged.
1.8 FIELD CONDITIONS
A. Notify Landscape Architect/Engineer of discrepancies between existing conditions and Drawings before proceeding with selective demolition.
B. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.
1. If suspected hazardous materials are encountered, do not disturb; immediately notify
Landscape Architect/Engineer and Owner. Hazardous materials will be removed by Owner under a separate contract.
C. Storage or sale of removed items or materials on-site is not permitted.
D. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.
1. Maintain fire-protection facilities in service during selective demolition operations.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.
B. Standards: Comply with ANSI/ASSE A10.6 and NFPA 241.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that utilities have been disconnected and capped before starting selective demolition operations.
B. Verify that hazardous materials have been remediated before proceeding with building demolition operations.
C. Review record documents of existing construction provided by Owner. Owner does not guarantee that existing conditions are same as those indicated in record documents.
D. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.
E. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict.
Promptly submit a written report to Landscape Architect/Engineer.
3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS
A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.
1. Comply with requirements for existing services/systems interruptions specified in
Section 011000 "Summary."
B. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off utility services and mechanical/electrical systems serving areas to be selectively demolished.
1. Contractor will arrange to shut off indicated services/systems and notify Owner 72 hours in advance.
2. Arrange to shut off indicated utilities with utility companies.
3. Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC systems, equipment, and components indicated to be removed.
C. Refrigerant: Before starting demolition, remove refrigerant from mechanical equipment according to 40 CFR 82 and regulations of authorities having jurisdiction.
3.3 PREPARATION
A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
1. Comply with requirements for access and protection specified in Section 015000
"Temporary Facilities and Controls."
B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
1. Provide protection to ensure safe passage of people around selective demolition area and to and from occupied portions of building.
2. Provide temporary weather protection, during interval between selective demolition of existing construction on exterior surfaces and new construction, to prevent water leakage and damage to structure and interior areas.
3. Protect walls, ceilings, floors, and other existing finish work that are to remain or that are exposed during selective demolition operations.
4. Cover and protect furniture, furnishings, and equipment that have not been removed.
5. Comply with requirements for temporary enclosures, dust control, heating, and cooling specified in Section 015000 "Temporary Facilities and Controls."
C. Temporary Shoring: Provide and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.
1. Strengthen or add new supports when required during progress of selective demolition.
3.4 SELECTIVE DEMOLITION, GENERAL
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:
1. Dispose of demolished items and materials promptly.
B. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Landscape Architect/Engineer, items may be removed to a suitable, protected storage location during selective demolition and reinstalled in their original locations after selective demolition operations are complete.
3.5 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS
A. Concrete: Demolish in sections. Cut concrete full depth at junctures with construction to remain and at regular intervals using power-driven saw, then remove concrete between saw cuts.
3.6 DISPOSAL OF DEMOLISHED MATERIALS
A. Remove demolition waste materials from Project site.
1. Do not allow demolished materials to accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
3. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.
4. Comply with requirements specified in Section 017419 "Construction Waste Management and Disposal."
B. Burning: Do not burn demolished materials.
C. Disposal: Transport demolished materials off Owner's property and legally dispose of them.
3.7 CLEANING
A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.
END OF SECTION 024119
SITE CAST IN PLACE CONCRETE 033010
033010 – SITE CAST-IN-PLACE CONCRETE
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2
1.3 SUMMARY
A. Section Includes:
1. Cast-in-place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes.
B. Related Requirements:
1. Section 312000 “Earthwork” for drainage fill under slabs-on-grade.
2. Section 321313 “Concrete Paving” for exterior concrete paving including ve-hicular pavement, sidewalks, and curbs.
1.4 DEFINITIONS
1. Cementitious Materials: Portland cement alone or in combination with one or more of the following: blended hydraulic cement, fly ash, slag cement, other pozzolans, and silica fume; materials subject to compliance with requirements.
2. W/C Ratio: The ratio by weight of water to cementitious materials.
1.5 SUBMITTALS
A. Product Data: For each type of product.
1. Include data for proprietary materials, reinforcement and forming accessories, admixtures, patching compounds, joint systems, curing compounds, and others as requested by Designer.
B. Concrete Design Mixes: Provide design mixes for each type of concrete used on the project. Design mix must include substantiating data to verify reliability of proposed mix.
C. Steel Reinforcement Shop Drawings: Comply with ACI SP-066.
1. Include placing drawings that detail fabrication, bending, and placement.
2. Include bar sizes, lengths, materials, grades, bar schedules, stirrup spacing, bent bar diagrams, bar arrangement, splices and laps, mechanical connections, tie spacing, hoop spacing, and supports for concrete reinforcement.
3. Reproducing the Contract Drawings for submission as shop drawings will not be permitted.
1.6 QUALITY ASSURANCE
A. Installer Qualifications: A qualified installer who employs Project personnel qualified as ACI-certified Flatwork Technician and Finisher and a supervisor who is a certified ACI Concrete Flatwork Technician.
B. Concrete Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C 94 requirements for produc-tion facilities and equipment.
1. Manufacturer certified according to NRMCA’s “Certification of Ready Mixed
Concrete Production Facilities.”
1.7 DELIVERY, STORAGE, AND HANDLING
A. Steel Reinforcement: Deliver, store, and handle steel reinforcement to prevent bending and damage and to avoid damaging coatings on steel reinforcement.
1. Store reinforcement to avoid contact with earth.
B. Waterstops: Store waterstops under cover to protect from moisture, sunlight, dirt, oil, and other contaminants.
1.8 FIELD CONDITIONS
A. Protection of Footings Against Freezing: Cover completed work at footing level with sufficient temporary or permanent cover as required to protect footings and adjacent subgrade against possibility of freezing; maintain cover for time period as necessary.
B. Protect adjacent finish materials against spatter during concrete placement.
PART 2 - PRODUCTS
2.1 CONCRETE, GENERAL
A. ACI Publications: Comply with the following unless modified by requirements in the
Contract Documents.
1. ACI 301.
2. ACI 117.
2.2 MANUFACTURERS
A. In other Part 2 articles below, where titles introduce manufacturer lists, the following requirements apply to product selection.
1. Manufacturers: Subject to compliance with requirements, available manufactur-ers that may be incorporated into the Work include, but are not limited to, the products specified.
2.3 FORM MATERIALS
A. Forms for Exposed Finish Concrete: Form-facing panels that provide continuous, straight, smooth concrete surfaces. Furnish in largest practicable sizes to minimize num-ber of joints and to conform to joint system shown on drawings.
1. Plywood, metal, metal-framed plywood faced, or other approved panel- type materials.
B. Forms for Unexposed Finish Concrete: Plywood, lumber, metal, or other approved ma-terial. Provide lumber dressed on at least two edges and one side for tight fit.
C. Form-Release Agent: Commercially formulated form-release agent that does not bond with, stain, or adversely affect concrete surfaces and does not impair subsequent treat-ments of concrete surfaces.
1. Formulate form-release agent with rust inhibitor for steel form-facing materi-als.
D. Forms Ties: Factory-fabricated, adjustable-length, removable or snap-off metal form ties, designed to prevent form deflection and to prevent spalling concrete upon removal.
1. Furnish units that leave no corrodible metal closer than 1-1/2-inches to the plane of exposed concrete surface.
2.4 STEEL REINFOREMENT
A. Reinforcing Bars: ASTM A 615, Grade 60, deformed.
B. Low-Alloy-Steel Reinforcing Bars: ASTM A 706, deformed.
C. Welded-Wire Fabric: ASTM A 1064, welded steel wire fabric in mats only. Roll stock is prohibited.
2.5 REINFORCEMENT ACCESSORIES
A. Supports for Reinforcement: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars and welded-wire reinforcement in place.
1. Manufacture bar supports from steel wire, plastic, or precast concrete accord-ing to CRSI’s “Manual of Standard Practice,” specifications.
2.6 CONCRETE MATERIALS
A. Source Limitations:
1. Obtain each type or class of cementitious material of the same brand from same manufacturer’s plant.
2. Obtain aggregate from single source.
3. Obtain each type of admixture from single source from sin-gle manufacturer.
B. Cementitious Materials:
1. Portland Cement: ASTM C 150, Type I. Supplement with the following:
a. Fly Ash: ASTM C 618, Class F or C.
b. Ground Granulated Blast-Furnace Slag: ASTM C 989, Grade 100 or
120.
C. Normal Weight Aggregates: ASTM C 33, coarse aggregate or better, graded. Provide aggregates from a single source.
1. Maximum Coarse-Aggregate Size: For interior and exterior exposed surfaces use class designation 5S, 3/4-inch nominal. Do not use fine or coarse aggregates containing spalling-causing deleterious substances.
2. For slab on grade, use class 4S.
D. Water: ASTM C 94 and potable.
2.7 ADMIXTURES
A. Use only one manufacturer as a source for all admixtures. Various manu-facturers within a particular mix will not be permitted.
B. Air-Entraining Admixture: ASTM C 260, certified by manufacturer to be compatible with other required admixtures.
C. Water-Reducing Admixture: ASTM C 494, Type A, and containing not more than
0.1 percent chloride ions.
D. Water Reducing, Non-Chloride Accelerator Admixture: ASTM C 494, Type E, and containing not more than 0.1 percent chloride ions.
2.8 REPAIR MATERIALS
A. Bonding Compound: Acrylic or Styrene Butadiene.
B. Epoxy Adhesive: ASTM C 881, two-component material suitable for use on dry or damp surfaces. Provide material "Type", "Grade", and "Class" to suit project requirements.
2.9 RELATED MATERIALS
A. Expansion- and Isolation-Joint-Filler Strips: ASTM D 1751, asphalt-saturated cellulosic fiber.
B. Chemical Hardener/Sealer: Colorless aqueous solution containing a blend of magnesium flousilicate and zinc flousilicate combined with a wetting agent, containing not less than 2 lbs. of flousilicates per gal.
C. Absorptive Cover: Burlap cloth made from jute or kenaf, weighing approximately 9 oz.
per sq. yd., complying with AASHTO M 182, Class 2.
D. Moisture-Retaining Cover: One of the following, complying with ASTM C 171.
1. Waterproof paper.
2. Polyethylene film.
3. Polyethylene-coated burlap.
E. Liquid Membrane-Forming Curing Compound: Liquid type membrane-forming curing compound complying with ASTM C 309, Type I, Class A. Moisture loss not more than
0.055 gr./sq. cm. when applied at 200 sq. ft./gal.
1. Curing compound shall be compatible with the specified chemical hardener compound and will not affect the application of superficial floor finishes.
F. Silane/Siloxane Water Repellent: Water-based, VOC compliant silane/siloxane water repellent for the protection of horizontal and vertical surfaces of concrete from moisture intrusion and chemical attack of chloride salts.
1. Install horizontal concrete surfaces and column piers where indicated on the
Drawings.
G. Nonmetallic Shrinkage-Resistant Grout: Premixed, nonmetallic, noncorrosive, nonstain-ing product containing selected silica sands, Portland cement, shrinkage compensating agents, plasticizing and water-reducing agents, complying with CE-CRD-C621.
2.10 PROPORTIONING AND DESIGN OF MIXES
A. Prepare design mixes for each type and strength of concrete, proportioned on the basis of laboratory trial mixture or field test data, or both, according to ACI 301. If trial batch method used, use an independent testing facility acceptable to Landscape Architect / Engineer for preparing and reporting proposed mix designs. The testing facility shall not be the same as used for field quality control testing.
B. Submit written reports to Landscape Architect and Engineer of each proposed mix for each class of concrete at least 15 days prior to start of work. Include back-up data veri-fying that the mix design will exceed the required strength and f'cr equals design strength and factors as required in Section 5.3.2 of ACI 318. Do not begin concrete production until mixes have been reviewed by Landscape Architect.
C. Cementitious Material: Use fly ash and ground granulated blast-furnace slag as needed to reduce the total amount of Portland cement, which would otherwise be used, by not less than 40 percent. Limit percentage, by weight, of cementitious materials other than Portland cement in concrete as follows:
1. Fly Ash: 25 percent.
2. Ground Granulated Blast-Furnace Slag: 50 percent.
3. Combined Fly Ash and Granulated Blast-Furnace Slag: 50 percent Port-land cement minimum, with fly ash not exceeding 25 percent.
D. Concrete Mix Designs:
1. Footings: PennDOT Class A per Publication 408
E. Adjustment to Concrete Mixes: Mix design adjustments may be requested by Contractor when characteristics of materials, job conditions, weather, test results, or other circum-stances warrant; at no additional cost to Owner and as accepted by Landscape Architect and Engineer. Laboratory test data for revised mix design and strength results must be submitted to and accepted by Landscape Architect and Engineer before using in work.
F. Admixtures:
1. Use water-reducing admixture (super plasticizer) in concrete as required for placement and workability.
2. Use non-chloride accelerating admixture in concrete slabs placed at ambient temperatures below 50 deg F.
3. Use air-entraining admixture in exterior exposed concrete, unless otherwise in-dicated. Add air-entraining admixture at manufacturer's prescribed rate to result in concrete at point of placement having total air content with a tolerance of plus-or-minus 1-1/2 percent within the following limits:
a. Concrete structures and slabs exposed to freezing and thawing and de-icer chemicals: 5 to 7 percent.
b. Other concrete not exposed to freezing, thawing, or hydraulic pressure:
2 to 4 percent.
4. Use admixtures in strict compliance with manufacturer's directions.
2.11 CONCRETE MIXING
A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to ASTM
C 94, and furnish batch ticket information.
B. During hot weather, or under conditions contributing to rapid setting of concrete, a shorter mixing time than specified in ASTM C 94 may be required.
PART 3 - EXECUTION
3.1 FORMWORK INSTALLATION
A. Design, erect, shore, brace and maintain formwork, according to ACI 301, to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied, until structure can support such loads.
B. Design formwork to be readily removable without impact, shock or damage to cast-in-place concrete surfaces and adjacent materials.
C. Construct forms to sizes shapes, lines and dimensions shown, and to obtain accurate alignment, location, grades, level and plumb work in finished structures. Provide for openings, offsets, sinkages, keyways, recesses, moldings, reglets, chamfers, blocking, screeds, bulkheads, anchorages and inserts, and other features required in work. Use se-lected materials to obtain required finishes. Solidly butt joints and provide back-up at joints to prevent leakage of cement paste.
D. Construct forms for easy removal without hammering or prying against concrete sur-faces. Provide crush or wrecking plates where stripping may damage cast concrete sur-faces. Provide top forms for inclined surfaces where slope is too steep to place concrete with bottom forms only.
1. Install keyways, reglets, recesses, and the like, for easy removal.
2. Do not use rust-stained steel form-facing material.
E. Provide temporary openings for cleanouts and inspection ports where interior areas of formwork is inaccessible. Close openings with panels tightly fitted to forms and securely braced to prevent loss of concrete mortar. Locate temporary openings in forms at incon-spicuous locations.
F. Chamfer exposed corners and edges as directed by the Landscape Architect, using wood, metal, PVC or rubber chamfer strips fabricated to produce uniform smooth lines and tight edge joints.
G. Provisions for Other Trades: Provide openings in concrete formwork to accommodate work of other trades. Determine size and location of openings, recesses and chases from trades providing such items. Accurately place and securely support items built into forms.
H. Cleaning and Tightening: Thoroughly clean forms and adjacent surfaces to receive con-crete. Remove chips, wood, sawdust, dirt or other debris just before concrete is placed.
Retightening forms and bracing after concrete placement is required to eliminate mortar leaks and maintain proper alignment.
I. Coat contact surfaces of forms with form-release agent, according to manufacturers writ-ten instructions, before placing reinforcement.
1. Coat contact surfaces of wood rustications and chamfer strips with sealer be-fore placing reinforcement, anchoring devices, and embedded items.
3.2 INSTALLATION OF STEEL REINFORCEMENT
A. Comply with CRSI's “Manual of Standard Practice” for fabricating, placing, and sup-porting reinforcement.
1. Avoid cutting or puncturing vapor retarder during reinforcement placement and concreting operations. Seal all perforations, tears, etc. with manufacturer's rec-ommended tape.
B. Clean reinforcement of loose rust and mill scale, earth, ice, and other foreign materials that reduce bond to concrete.
C. Accurately position, support and secure reinforcement against displacement.
1. Locate and support reinforcement with bar supports to maintain minimum con-crete cover.
2. Do not tack weld crossing reinforcing bars.
D. Place reinforcement to obtain at least minimum coverages for concrete protection. Ar-range, space and securely tie bars and bar supports to hold reinforcement in position during concrete placement operations. Set wire ties so ends are directed into concrete, not toward exposed concrete surfaces.
E. Install welded wire fabric in mat form. Lap adjoining pieces at least one full mesh and lace splices with wire. Offset end laps in adjacent widths to prevent continuous laps in either direction.
3.3 JOINTS
A. Construct joints true to line, with faces perpendicular to surface plane of concrete.
B. Construction Joints: Locate and install construction joints as indicated, or if not indi-cated, locate so as not to impair strength and appearance of the structure, as acceptable Landscape Architect / Engineer. Consult with Landscape Architect / Engineer prior to locating construction joints.
1. Place joints perpendicular to main reinforcement. Continue reinforcement across construction joints unless otherwise indicated.
2. Provide keyways at least 1-1/2 inches deep where shown in construction joints in walls, slabs and between walls and footings; accepted bulkheads designed for this purpose may be used for slabs.
C. Isolation Joints in Slabs-on-Grade: Construct isolation joints in slabs-on-ground at points of contact between slabs-on-ground and vertical surfaces, such as column pedes-tals, foundation walls, grade beams and elsewhere as indicated.
D. Contraction (Control) Joints in Slabs-on-Grade: Construct contraction joints in slabs-on-ground to form panels of patterns and dimensions as shown on the drawings.
1. Form contraction joints by inserting premolded plastic, hardboard or fiberboard strip into fresh concrete until top surface of strip is flush with slab surface. After concrete has cured, remove inserts and clean groove of loose debris.
2. Contraction joints in unexposed floor slabs may be formed by saw cuts as soon as possible after slab finishing as may be safely done without dislodging aggre-gate.
E. If joint pattern not shown, provide joints not exceeding 20' in either direction and located to conform to bay spacing wherever possible (at column centerlines, half bays, third-bays) and as approved by the Landscape Architect.