Attachment_L9_-_TOR_214-26_-_Task_Order_Pricing_Template_-_Revision_3.xlsx

XLSX spreadsheet 61 KB Posted

Attached to
Multiple Award Task Order Contract (MATOC) Federal contract opportunity
Solicitation number
NIHOF2013536
Issued by
Department of Health and Human Services National Institutes of Health

About this file

Attachment L9 - TOR 214-26 - Task Order Pricing Template - Revision 3

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Task Order Contract (MATOC), newest first.
File Type Posted
TOR_00-13_-_Revised_Drawings_-_dated_02-10-14.pdf PDF
Specification_Section_01_33_00_-_Revision_1.pdf PDF
Amendment_0005.docx DOCX document
Attachment_L5_-_TOR_13-00_-_Task_Order_Pricing_Template_-_Revision_3.xlsx XLSX spreadsheet
Attachment_L6__TOR_214-20__Statement_of_Work__Revision_3.pdf PDF
Section_H_-_Special_Contract_Requirements_-_Revision_1.pdf PDF
Section_G_-_Contract_Administration_Data_-_Revision_1.pdf PDF
SF_30_-_NIHOF2013536_-_Amendment_0004.pdf PDF
Amendment_0003.docx DOCX document
MATOC_Pre-Proposal_Conference_Sign-in_Sheet.pdf PDF
SF_30_-_NIHOF2013536_-_Amendment_0003.pdf PDF
MATOC_Pre-Proposal_Conference_Briefing.pptx PPTX presentation
Attachment_L9_-_TOR_214-26_-_Task_Order_Pricing_Template_-_Revision_2.xlsx XLSX spreadsheet
Attachment_L8_-_TOR_214-26_-_Statement_of_Work_-_Revision_2.pdf PDF
Attachment_L7_-_TOR_214-20_-_Task_Order_Pricing_Template_-_Revision_1.xlsx XLSX spreadsheet
Attachment_L9_-_TOR_214-26_-_Task_Order_Pricing_Template_-_Revision_1.xlsx XLSX spreadsheet
SF_30_-_NIHOF2013536_-_Amendment_0002.pdf PDF
Attachment_L5_-_TOR_13-00_-_Task_Order_Pricing_Template_-_Revision_2.xlsx XLSX spreadsheet
Amendment_0002.docx DOCX document
Attachment_L6_-_TOR_214-20_-_Statement_of_Work_-_Revision_2.pdf PDF
Attachment_L8_-_TOR_214-26_-_Statement_of_Work_-_Revision_1.pdf PDF
Statement_of_Work_-_Revision_1_-_01-24-14.pdf PDF
Specification_Section_01_35_26.docx DOCX document
Specification_Section_01_45_00.docx DOCX document
Section_J_-_List_of_Attachments_-_Revision_1.pdf PDF
Section_L_-_Instructions _Conditions _and_Notices_to_Offerors_-_Revision_1.pdf PDF
Attachment_L6_-_TOR_214-20_-_Statement_of_Work_-_Revision_1.pdf PDF
Section_E_-_Inspection_and_Acceptance_-_Revision_1.pdf PDF
SF_30_-_NIHOF2013536_-_Amendment_0001.pdf PDF
Attachment_L2_-_Past_Performance_Transmittal_Letter_-_Revision_1.docx DOCX document
Attachment_L5_-_TOR_13-00_-_Task_Order_Pricing_Template_-_Revision_1.xlsx XLSX spreadsheet
Attachment_L9_-_TOR_214-26_-_Task_Order_Pricing_Template.xlsx XLSX spreadsheet
Amendment_0001.docx DOCX document
New_Equipment_Submission_Worksheet_Template.xls XLS spreadsheet
Specification_Section_01_33_00.docx DOCX document
Attachment_L7_-_TOR_214-20_-_Task_Order_Pricing_Template.xlsx XLSX spreadsheet
FMB-NC_Engineering_Guidelines_and_Material_Requirements--Revision_C.pdf PDF
Attachment_L3_Past_Performance_Questionnaire.pdf PDF
Wage_Determination--NC130093--Highway.pdf PDF
Wage_Determination--NC130080--Heavy.pdf PDF
Attachment_L1_Experience_Summary_Sheet.pdf PDF
Certificate_of_Current_Cost_or_Pricing_Data.pdf PDF
Task_Order_Pricing_Template.xlsx XLSX spreadsheet
SF_1442.pdf PDF
Solicitation_NIHOF2013536_-_RTP_MATOC.pdf PDF
Disclosure_of_Lobbying_Activities.pdf PDF
Statement_of_Work--12-6-13.pdf PDF
Wage_Determination--NC130028--Building.pdf PDF
Wage_Determination--NC130019--Heavy_Dredging.pdf PDF
Attachment_L4_TOR_213-00--Statement_of_Work.pdf PDF
Show all 50

Multiple Award Task Order Contract (MATOC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TOR 214-26 - Base Price

TOR#214-26: North Plan HTHW Air Seperator Valve Replacment
Date:
Contractor:
QuantitiyMaterialLaborEquipmentSubcontractor
ItemNo.UnitUnit CostTotalTotal HrsRateTotal
Demolition
Valve removalEA
Insulation removalLF
All other demolltion work1LOT
Mechanical
14" High Performance Butterfly Valve installationEA
Bolt/Gasket kitEA
Valve Flange cleaning and refacingFLANGE
Insulation installationLF
Labeling/valve tags1LOT
All other mechanical work1LOT
Administrative
Task Order Management
Project Manager
Superintendent
Quality Control Manager

TOTAL LABOR HOURS * Labor hours and rates are crew rates and crew hours 0.0

TOTAL DOLLARS PRIOR TO TAX$0.00$0.00$0.00$0.00
SALES TAX$0.00$0.00
ELEMENT SUBTOTALS$0.00$0.00$0.00$0.00
Instructions:Task Order Subtotal$0.00
1) All costs for a line item within a category shall encompass all costs for that line item for the entire task orderField Overhead0.00%$0.00
2) Labor rates are to include fringe in accordance with the applicable Wage DeterminationsG & A0.00%$0.00
3) Subcontractor total shall include all costs associated with subcontractor (e.g. overhead/G&A/management/profit charged by subcontractor). The columns available for TaskProfit0.00%$0.00
Order Management of the Subcontractor will include only the amounts that the Prime Contractor is charging for management over and above what the Subcontractor is including.TOTAL (without bond)$0.00
4) Work required but not separately priced within a work category shall be included in the "All other work" itemBond0.000%$0.00
5) Sales tax only applies to material and rental equipment bought specifically for performance of the task order (contractor owned equipment is exempt)Grand Total$0
6) Task Order Subtotal = Material Element Subtotal + Direct Labor Element Subtotal + Equipment Subtotal + Subcontractor Element Subtotal
7) $30K - $150K (Payment Bond and Irrevocable Letter of Credit), over $150K (Payment and Performance Bonds)
[NOTE: Performance Bond is acceptable in lieu of Irrevocable Letter of Credit]
8) If a category of work is required to perform the SOW but not included on the Task Order Pricing Template, the contractor shall submit a question to the Contracting Officer
requesting clarification. The total proposed price shall include all work required to perform the Statement of Work (regardless of whether a question is asked).
9) The Administrative category is only for work that is supplemental to performing the work identified in the Statement of Work (e.g. on a larger task order if a contractor wishes
to have a Secretary perform submittal work and incorporate that as a direct cost instead of capturing that cost in Overhead or G&A).

&16Task Order Pricing Template

Option (1)

TOR#214-26: North Plan HTHW Air Seperator Valve Replacment
Date:
Contractor:
QuantitiyMaterialLaborEquipmentSubcontractor
ItemNo.UnitUnit CostTotalTotal HrsRateTotal
OPTION 1 - Replace Flanges (V-1)
Replace two 300 lb Class 14" flangesEA
Misc. welding and fitting materialEA
Weld TestingEA
All other work1LOT
Administrative
Task Order Management
Project Manager
Superintendent
Quality Control Manager

TOTAL LABOR HOURS * Labor hours and rates are crew rates and crew hours 0.0

TOTAL DOLLARS PRIOR TO TAX$0.00$0.00$0.00$0.00
SALES TAX$0.00$0.00
ELEMENT SUBTOTALS$0.00$0.00$0.00$0.00
Instructions:Task Order Subtotal$0.00
1) All costs for a line item within a category shall encompass all costs for that line item for the entire task orderField Overhead0.00%$0.00
2) Labor rates are to include fringe in accordance with the applicable Wage DeterminationsG & A0.00%$0.00
3) Subcontractor total shall include all costs associated with subcontractor (e.g. overhead/G&A/management/profit charged by subcontractor). The columns available for TaskProfit0.00%$0.00
Order Management of the Subcontractor will include only the amounts that the Prime Contractor is charging for management over and above what the Subcontractor is including.TOTAL (without bond)$0.00
4) Work required but not separately priced within a work category shall be included in the "All other work" itemBond0.000%$0.00
5) Sales tax only applies to material and rental equipment bought specifically for performance of the task order (contractor owned equipment is exempt)Grand Total$0
6) Task Order Subtotal = Material Element Subtotal + Direct Labor Element Subtotal + Equipment Subtotal + Subcontractor Element Subtotal
7) $30K - $150K (Payment Bond and Irrevocable Letter of Credit), over $150K (Payment and Performance Bonds)
[NOTE: Performance Bond is acceptable in lieu of Irrevocable Letter of Credit]
8) If a category of work is required to perform the SOW but not included on the Task Order Pricing Template, the contractor shall submit a question to the Contracting Officer
requesting clarification. The total proposed price shall include all work required to perform the Statement of Work (regardless of whether a question is asked).
9) The Administrative category is only for work that is supplemental to performing the work identified in the Statement of Work (e.g. on a larger task order if a contractor wishes
to have a Secretary perform submittal work and incorporate that as a direct cost instead of capturing that cost in Overhead or G&A).

&16Task Order Pricing Template

Option (2)

TOR#214-26: North Plan HTHW Air Seperator Valve Replacment
Date:
Contractor:
QuantitiyMaterialLaborEquipmentSubcontractor
ItemNo.UnitUnit CostTotalTotal HrsRateTotal
OPTION 1 - Replace Flanges (V-2)
Replace two 300 lb Class 14" flangesEA
Misc. welding and fitting materialEA
Weld TestingEA
All other work1LOT
Administration
Task Order Management
Project Manager
Superintendent
Quality Control Manager

TOTAL LABOR HOURS * Labor hours and rates are crew rates and crew hours 0.0

TOTAL DOLLARS PRIOR TO TAX$0.00$0.00$0.00$0.00
SALES TAX$0.00$0.00
ELEMENT SUBTOTALS$0.00$0.00$0.00$0.00
Instructions:Task Order Subtotal$0.00
1) All costs for a line item within a category shall encompass all costs for that line item for the entire task orderField Overhead0.00%$0.00
2) Labor rates are to include fringe in accordance with the applicable Wage DeterminationsG & A0.00%$0.00
3) Subcontractor total shall include all costs associated with subcontractor (e.g. overhead/G&A/management/profit charged by subcontractor). The columns available for TaskProfit0.00%$0.00
Order Management of the Subcontractor will include only the amounts that the Prime Contractor is charging for management over and above what the Subcontractor is including.TOTAL (without bond)$0.00
4) Work required but not separately priced within a work category shall be included in the "All other work" itemBond0.000%$0.00
5) Sales tax only applies to material and rental equipment bought specifically for performance of the task order (contractor owned equipment is exempt)Grand Total$0
6) Task Order Subtotal = Material Element Subtotal + Direct Labor Element Subtotal + Equipment Subtotal + Subcontractor Element Subtotal
7) $30K - $150K (Payment Bond and Irrevocable Letter of Credit), over $150K (Payment and Performance Bonds)
[NOTE: Performance Bond is acceptable in lieu of Irrevocable Letter of Credit]
8) If a category of work is required to perform the SOW but not included on the Task Order Pricing Template, the contractor shall submit a question to the Contracting Officer
requesting clarification. The total proposed price shall include all work required to perform the Statement of Work (regardless of whether a question is asked).
9) The Administrative category is only for work that is supplemental to performing the work identified in the Statement of Work (e.g. on a larger task order if a contractor wishes
to have a Secretary perform submittal work and incorporate that as a direct cost instead of capturing that cost in Overhead or G&A).

&16Task Order Pricing Template

Option (3)

TOR#214-26: North Plan HTHW Air Seperator Valve Replacment
Date:
Contractor:
QuantitiyMaterialLaborEquipmentSubcontractor
ItemNo.UnitUnit CostTotalTotal HrsRateTotal
OPTION 1 - Replace Flanges (V-3)
Replace two 300 lb Class 14" flangesEA
Misc. welding and fitting materialEA
Weld TestingEA
All other work1LOT
Administration
Task Order Management
Project Manager
Superintendent
Quality Control Manager

TOTAL LABOR HOURS * Labor hours and rates are crew rates and crew hours 0.0

TOTAL DOLLARS PRIOR TO TAX$0.00$0.00$0.00$0.00
SALES TAX$0.00$0.00
ELEMENT SUBTOTALS$0.00$0.00$0.00$0.00
Instructions:Task Order Subtotal$0.00
1) All costs for a line item within a category shall encompass all costs for that line item for the entire task orderField Overhead0.00%$0.00
2) Labor rates are to include fringe in accordance with the applicable Wage DeterminationsG & A0.00%$0.00
3) Subcontractor total shall include all costs associated with subcontractor (e.g. overhead/G&A/management/profit charged by subcontractor). The columns available for TaskProfit0.00%$0.00
Order Management of the Subcontractor will include only the amounts that the Prime Contractor is charging for management over and above what the Subcontractor is including.TOTAL (without bond)$0.00
4) Work required but not separately priced within a work category shall be included in the "All other work" itemBond0.000%$0.00
5) Sales tax only applies to material and rental equipment bought specifically for performance of the task order (contractor owned equipment is exempt)Grand Total$0
6) Task Order Subtotal = Material Element Subtotal + Direct Labor Element Subtotal + Equipment Subtotal + Subcontractor Element Subtotal
7) $30K - $150K (Payment Bond and Irrevocable Letter of Credit), over $150K (Payment and Performance Bonds)
[NOTE: Performance Bond is acceptable in lieu of Irrevocable Letter of Credit]
8) If a category of work is required to perform the SOW but not included on the Task Order Pricing Template, the contractor shall submit a question to the Contracting Officer
requesting clarification. The total proposed price shall include all work required to perform the Statement of Work (regardless of whether a question is asked).
9) The Administrative category is only for work that is supplemental to performing the work identified in the Statement of Work (e.g. on a larger task order if a contractor wishes
to have a Secretary perform submittal work and incorporate that as a direct cost instead of capturing that cost in Overhead or G&A).

&16Task Order Pricing Template

Pay Rates

4D4D4D4D4DGBGBGBGBGB
Base Year1st Option2nd Option3rd Option4th OptionBase Year1st Option2nd Option3rd Option4th Option
20122013201420152016
1AAProfessional Cat IProject Manager$94.54$98.32$102.25$106.34$110.601AAProfessional Cat IProject Manager$58.27
1ABProfessional Cat IIQC Manager$55.00$57.20$59.49$61.87$64.341ABProfessional Cat IIQC Manager$41.99
Professional Level 2Project Engineer$137.50$143.00$148.72$154.67$160.86Professional Level 2Project Engineer$127.50
1ACProfessional Cat IIINon-reg Engineer$95.15$98.96$102.91$107.03$111.311ACProfessional Cat IIINon-reg Engineer$95.00
1ADProfessional Cat IVSecretary, word pro$29.60$30.78$32.02$33.30$34.631ADProfessional Cat IVSecretary, word pro$18.08
1AEProfessional Cat VCat 2 Super$62.75$65.26$67.87$70.59$73.411AEProfessional Cat VCat 2 Super$41.99
1AFSkill Cat IForeman$39.62$41.20$42.85$44.57$46.351AFSkill Cat IForeman$32.30
1AGSkill Cat IIElectrician$32.35$33.64$34.99$36.39$37.841AGSkill Cat IIElectrician$37.45
1AHSkill Cat IIICarpenter$29.31$30.48$31.70$32.97$34.291AHSkill Cat IIICarpenter$26.29
HVAC Mechanics$30.03$31.23$32.48$33.78$35.13HVAC Mechanics$39.27
Plumbers$43.75$45.50$47.32$49.21$51.18Plumbers$38.68
Laborer$20.73$21.56$22.42$23.32$24.25Laborer$13.31
Pipefitter$43.75$45.50$47.32$49.21$51.18Pipefitter$58.10
Equipment operator$29.31$30.48$31.70$32.97$34.29Equipment operator$17.61
Truck driver$20.57$21.39$22.25$23.14$24.06Truck driver$19.25
Contractor: 4D
Contractor: Guerrero Builders

Bond Calc (1 Sheet)

Total Before Bond=ERROR:#REF!
Bond=ERROR:#REF!
Bond Percent=ERROR:#REF!
Grand Total with Bond=ERROR:#REF!
Calculations
Up to Amount
$ 100,000.00ERROR:#REF!$ 25.00ERROR:#REF!
$ 400,000.00ERROR:#REF!$ 15.00ERROR:#REF!
$ 2,000,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 9.00ERROR:#REF!
Total:ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Up to AmountERROR:#REF!
$ 100,000.00ERROR:#REF!$ 25.00ERROR:#REF!
$ 400,000.00ERROR:#REF!$ 15.00ERROR:#REF!
$ 2,000,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 9.00ERROR:#REF!
Total:ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Up to AmountERROR:#REF!
$ 100,000.00ERROR:#REF!$ 25.00ERROR:#REF!
$ 400,000.00ERROR:#REF!$ 15.00ERROR:#REF!
$ 2,000,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 9.00ERROR:#REF!
Total:ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Up to AmountERROR:#REF!
$ 100,000.00ERROR:#REF!$ 25.00ERROR:#REF!
$ 400,000.00ERROR:#REF!$ 15.00ERROR:#REF!
$ 2,000,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 9.00ERROR:#REF!
Total:ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Up to AmountERROR:#REF!
$ 100,000.00ERROR:#REF!$ 25.00ERROR:#REF!
$ 400,000.00ERROR:#REF!$ 15.00ERROR:#REF!
$ 2,000,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 9.00ERROR:#REF!
Total:ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Up to AmountERROR:#REF!
$ 100,000.00ERROR:#REF!$ 25.00ERROR:#REF!
$ 400,000.00ERROR:#REF!$ 15.00ERROR:#REF!
$ 2,000,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 9.00ERROR:#REF!
Total:ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Up to AmountERROR:#REF!
$ 100,000.00ERROR:#REF!$ 25.00ERROR:#REF!
$ 400,000.00ERROR:#REF!$ 15.00ERROR:#REF!
$ 2,000,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 9.00ERROR:#REF!
Total:ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Up to AmountERROR:#REF!
$ 100,000.00ERROR:#REF!$ 25.00ERROR:#REF!
$ 400,000.00ERROR:#REF!$ 15.00ERROR:#REF!
$ 2,000,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 9.00ERROR:#REF!
Total:ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Up to AmountERROR:#REF!
$ 100,000.00ERROR:#REF!$ 25.00ERROR:#REF!
$ 400,000.00ERROR:#REF!$ 15.00ERROR:#REF!
$ 2,000,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 9.00ERROR:#REF!
Total:ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Up to AmountERROR:#REF!
$ 100,000.00ERROR:#REF!$ 25.00ERROR:#REF!
$ 400,000.00ERROR:#REF!$ 15.00ERROR:#REF!
$ 2,000,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 9.00ERROR:#REF!
Total:ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Up to AmountERROR:#REF!
$ 100,000.00ERROR:#REF!$ 25.00ERROR:#REF!
$ 400,000.00ERROR:#REF!$ 15.00ERROR:#REF!
$ 2,000,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 9.00ERROR:#REF!
Total:ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Up to AmountERROR:#REF!
$ 100,000.00ERROR:#REF!$ 25.00ERROR:#REF!
$ 400,000.00ERROR:#REF!$ 15.00ERROR:#REF!
$ 2,000,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 9.00ERROR:#REF!
Total:ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Up to AmountERROR:#REF!
$ 100,000.00ERROR:#REF!$ 25.00ERROR:#REF!
$ 400,000.00ERROR:#REF!$ 15.00ERROR:#REF!
$ 2,000,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 9.00ERROR:#REF!
Total:ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!
Up to AmountERROR:#REF!
$ 100,000.00ERROR:#REF!$ 25.00ERROR:#REF!
$ 400,000.00ERROR:#REF!$ 15.00ERROR:#REF!
$ 2,000,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 10.00ERROR:#REF!
$ 7,500,000.00ERROR:#REF!$ 9.00ERROR:#REF!
Total:ERROR:#REF!ERROR:#REF!ERROR:#REF!ERROR:#REF!

Bond Calc (2 Sheet)

Total Before Bond=$0.00
Bond=$ - 0
Bond Percent=
Grand Total with Bond=$ - 0
Calculations
Up to Amount
$ 100,000.00$ - 0$ 25.00$ - 0
$ 400,000.00$ - 0$ 15.00$ - 0
$ 2,000,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 9.00$ - 0
Total:$ - 0$ - 01
Up to Amount$ - 0
$ 100,000.00$ - 0$ 25.00$ - 0
$ 400,000.00$ - 0$ 15.00$ - 0
$ 2,000,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 9.00$ - 0
Total:$ - 0$ - 01
Up to Amount$ - 0
$ 100,000.00$ - 0$ 25.00$ - 0
$ 400,000.00$ - 0$ 15.00$ - 0
$ 2,000,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 9.00$ - 0
Total:$ - 0$ - 01
Up to Amount$ - 0
$ 100,000.00$ - 0$ 25.00$ - 0
$ 400,000.00$ - 0$ 15.00$ - 0
$ 2,000,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 9.00$ - 0
Total:$ - 0$ - 01
Up to Amount$ - 0
$ 100,000.00$ - 0$ 25.00$ - 0
$ 400,000.00$ - 0$ 15.00$ - 0
$ 2,000,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 9.00$ - 0
Total:$ - 0$ - 01
Up to Amount$ - 0
$ 100,000.00$ - 0$ 25.00$ - 0
$ 400,000.00$ - 0$ 15.00$ - 0
$ 2,000,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 9.00$ - 0
Total:$ - 0$ - 01
Up to Amount$ - 0
$ 100,000.00$ - 0$ 25.00$ - 0
$ 400,000.00$ - 0$ 15.00$ - 0
$ 2,000,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 9.00$ - 0
Total:$ - 0$ - 01
Up to Amount$ - 0
$ 100,000.00$ - 0$ 25.00$ - 0
$ 400,000.00$ - 0$ 15.00$ - 0
$ 2,000,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 9.00$ - 0
Total:$ - 0$ - 01
Up to Amount$ - 0
$ 100,000.00$ - 0$ 25.00$ - 0
$ 400,000.00$ - 0$ 15.00$ - 0
$ 2,000,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 9.00$ - 0
Total:$ - 0$ - 01
Up to Amount$ - 0
$ 100,000.00$ - 0$ 25.00$ - 0
$ 400,000.00$ - 0$ 15.00$ - 0
$ 2,000,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 9.00$ - 0
Total:$ - 0$ - 01
Up to Amount$ - 0
$ 100,000.00$ - 0$ 25.00$ - 0
$ 400,000.00$ - 0$ 15.00$ - 0
$ 2,000,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 9.00$ - 0
Total:$ - 0$ - 01
Up to Amount$ - 0
$ 100,000.00$ - 0$ 25.00$ - 0
$ 400,000.00$ - 0$ 15.00$ - 0
$ 2,000,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 9.00$ - 0
Total:$ - 0$ - 01
Up to Amount$ - 0
$ 100,000.00$ - 0$ 25.00$ - 0
$ 400,000.00$ - 0$ 15.00$ - 0
$ 2,000,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 9.00$ - 0
Total:$ - 0$ - 01
Up to Amount$ - 0
$ 100,000.00$ - 0$ 25.00$ - 0
$ 400,000.00$ - 0$ 15.00$ - 0
$ 2,000,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 10.00$ - 0
$ 7,500,000.00$ - 0$ 9.00$ - 0
Total:$ - 0$ - 01