Section_G_-_Contract_Administration_Data_-_Revision_1.pdf
PDF 28 KB Posted
- Attached to
- Multiple Award Task Order Contract (MATOC) Federal contract opportunity
- Solicitation number
- NIHOF2013536
About this file
Section G - Contract Administration Data - Revision 1
View the file
Other files for this federal contract opportunity
Show all 50
Multiple Award Task Order Contract (MATOC) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP Number : NIHOF2013536
- 2 -
SECTION G - CONTRACT ADMINISTRATION DATA
ARTICLE G.1. CONTRACTING OFFICER'S REPRESENTATIVE (COR)
The following Contracting Officer's Representative (COR) will represent the Government for the purpose of this contract:
will be identified on each individual task order.
The COR is responsible for: (1) monitoring the Contractor's technical progress, including the surveillance and assessment of performance and recommending to the Contracting Officer changes in requirements; (2) interpreting the statement of work and any other technical performance requirements; (3) performing technical evaluation as required; (4) performing technical inspections and acceptances required by this contract; and (5) assisting in the resolution of technical problems encountered during performance.
The alternate COR is responsible for carrying out the duties of the COR only in the event that the COR can no longer perform his/her duties as assigned.
The Contracting Officer is the only person with authority to act as agent of the Government under this contract. Only the Contracting Officer has authority to: (1) direct or negotiate any changes in the statement of work; (2) modify or extend the period of performance; (3) change the delivery schedule; (4) authorize reimbursement to the Contractor for any costs incurred during the performance of this contract; or (5) otherwise change any terms and conditions of this contract.
The Government may unilaterally change its COR designation.
ARTICLE G.2. KEY PERSONNEL, HHSAR 352.242-70 (January 2006)
The key personnel specified in this contract are considered to be essential to work performance. At least 30 days prior to diverting any of the specified individuals to other programs or contracts (or as soon as possible, if an individual must be replaced, for example, as a result of leaving the employ of the Contractor), the Contractor shall notify the Contracting Officer and shall submit comprehensive justification for the diversion or replacement request (including proposed substitutions for key personnel) to permit evaluation by the Government of the impact on performance under this contract. The Contractor shall not divert or otherwise replace any key personnel without the written consent of the Contracting Officer. The Government may modify the contract to add or delete key personnel at the request of the Contractor or Government.
(End of Clause)
The following individual(s) is/are considered to be essential to the work being performed hereunder:
Name Title Project Manager Project Superintendent
ARTICLE G.3. TASK ORDER PROCEDURE
This contract provides for the issuance of Task Orders on a negotiated basis as follows:
a. General
Only the Contracting Officer may issue Task Orders to the Contractor, providing specific authorization or direction to perform work within the scope of the contract and as specified in the Statement of Work. Unless specifically authorized by the Contracting Officer, the Contractor shall not commence work until a fully executed
- 3 -
Task Order has been awarded. The Contractor may incur costs under this contract in performance of task orders and task order modifications issued in accordance with this ARTICLE.
No other costs are authorized unless otherwise specified in the contract or expressly authorized by the Contracting Officer.
b. Requesting Task Order Proposals.
The Contracting Officer or a designated official may solicit responses to requirements from Contractors within a technical area covered by a task order requirement in writing. A Task Order Request for Proposals (TORFP) will be prepared and issued for each task order requirement.
Generally, the TORFP will include, but is not limited to, the following:
1. Statement of Work;
2. Reporting Requirements and Deliverables (if applicable);
3. Proposal Due Date and how to deliver Proposals;
4. Period of Performance of Task Order;
5. Evaluation Factors for Award (if other than Price and Past Performance on previous task orders, with Price being more important than Past Performance)
All contract clauses contained in this contract shall be incorporated in the TORFP and the resultant task order. If conflicts exist between the contract clauses and the information outlined in the task order, the contract language takes precedence over the information in the task order.
Contractors are not required to propose on all TORFPs. Those eligible Contractors that decide not to submit a proposal shall advise the Contracting Officer, in writing, of their intention not to submit a proposal on or before the closing date and time established in the TORFP. An election not to propose on a given TORFP will not negatively affect or prohibit a Contractor from competing on future TORFPs.
c. Competitive Ordering Process.
1. All Contractors will receive e-mail notification advising of the availability of each proposed task order requirement. All proposed task orders will incorporate all terms of this contract unless otherwise specified in the proposed task order.
2. Contractors will be provided an adequate time to prepare and submit responses based on the Contracting Officer's consideration of the estimated dollar value and complexity of proposed task order. Responses will not be considered a proposal as defined in FAR Part 15. However, the Contractor shall provide information sufficient for consideration in accordance with FAR Part 16.
3. Price will be an evaluation criteria in all task orders. The Contractor will provide their best price for the individual task order in their initial proposal. There are no pre-established labor rates, etc. included within the contract. The Contractor will utilize the Task Order Pricing Template when providing their price for each individual task order. The Contractor shall provide material cost, direct labor rates, direct labor hours, direct labor cost, equipment cost, and subcontractor cost for each item established on the Task Order Pricing Template. The Government will provide a Task Order Pricing Template for each task order with the TORFP filled in with the categories of work that are anticipated. If the Contractor identifies other categories of work that were not identified (other than administrative), the Contractor shall request clarification from the Government prior to submitting a proposal. If the category of work is to be subcontracted, the Contractor may be required to provide back-up documentation for that work. The back-up documentation will be the multiple quotations received by the offeror, or an explanation as to why there were not multiple quotations received. The Contractor is not required to provide the backup documentation for subcontractors unless
- 4 -it is requested by the Government during negotiations. (this evaluation criteria is applicable to all task orders).
4. The Government may include evaluation criteria in the TORFP other than price and past performance (e.g. Design-Build Task Order), the following includes a list of potential evaluation criteria (this list is not all encompassing):
• Understanding of the requirements;
• Experience and capability on similar tasks;
• Technical approach, methods and procedures for satisfying the requirements with a discussion of potential problems to be encountered and proposed solutions and/or risk mitigation strategies.
• Procedures for assuring quality of work, products, and deliverables;
• Plan for managing the task order, including meeting requirements and schedules, and performance measures (if applicable);
• Staffing plan with skill levels and level of effort for each individual proposed;
• References to evaluate past performance on previous contracts/task orders not awarded under the
MATOC
d. Evaluation and Award of Task Order Proposals
The Government will evaluate the Task Order proposals against the requirements of the TORFP.
Specifically, price, past performance on previous task orders, and any other factors specifically identified in the TORFP will be used for evaluation of each proposal. In addition, the TORFP will identify the basis for selecting a contractor for award. Generally, price will be more important than past performance. However, each TORFP will specify how the award decision will be made.
Upon completion of evaluations, the Contracting Officer will issue a task order to the Contractor whose proposal is most advantageous to the government
The Contracting Officer will notify all MATOC contractors of the selection decision in writing (via e-mail).
e. Fair Opportunity
1. In accordance with FAR 16.505(b)(1)(i), each awardee will be given a fair opportunity to be considered for each order issued over $3,000 unless the following exception(s) apply:
i. The agency need for the supplies or services is so urgent that providing a fair opportunity would result in unacceptable delays.
ii. Only one awardee is capable of providing the supplies or services required at the level of quality required because the supplies or services ordered are unique or highly specialized.
iii. The order must be issued on a sole-source basis in the interest of economy and efficiency because it is a logical follow-on to an order already issued under the contract, provided that all awardees were given a fair opportunity to be considered for the original order.
iv. It is necessary to place an order to satisfy a minimum guarantee.
2. All awardees will be given a fair opportunity to be considered in accordance with the FAR as follows:
i. For orders exceeding $3,000 up to the simplified acquisition threshold, in accordance with FAR 16.505(b)(1)(ii);
ii. For orders exceeding the simplified acquisition threshold up to $5 Million, in accordance with 16.505(b)(1)(iii); and,
- 5 -
iii. For orders exceeding $5 Million, in accordance with FAR 16.505(b)(1)(iv).
ARTICLE G.4. EQUITABLE ADJUSTMENTS DUE TO CHANGES
a. The Contractor shall submit a proposal for all changes in the work within 10 days from the effective date of the change order or request for proposal. With each proposal for a change involving an increase or decrease in the amount of the contract, the Contractor shall submit separately an itemized breakdown that will include but not be limited to the following:
1. Material quantities and unit price. (Separated into trades)
2. Labor Costs (Separate into labor classifications and hourly rates)
3. Construction Equipment
4. Workmen's Compensation
5. Overhead
6. Profit
7. Employment taxes under FICA, FUTA and SUTA
8. Bond (Prime Contractor only)
9. Sales Tax
10. Direct Performance Time of Change
11. Impact on Schedule, if any.
12. Impact Costs, if any.
b. In considering proposals for changes involving added work, omitted work, or any combination thereof, estimates will be checked in detail by the NIH, utilizing unit prices where specified or agreed upon, with the view of arriving at equitable adjustments.
c. When the necessity to proceed with a change does not allow sufficient time to properly check a proposal, or because of failure to reach an agreement, NIH Contracting Officer may direct the Contractor to proceed immediately with the work.
d. Proposals and breakdown should be submitted as promptly as possible, but in no event later than 10 days.
e. All proposals shall be submitted in accordance with the requirements of FAR 15.8. Should a proposal cost exceed $700,000 for a change, certified cost or pricing data should be submitted on SF1411 in a format which satisfies the requirements of FAR 15.804-6. When certified cost or pricing data are required, the contractor shall submit an executed Certificate of Current Cost or Pricing Data as soon as practicable after price agreement is reached.
f. Allowable overhead, profit, and percentages are given at the end of this paragraph. These percentages shall be limited to three tiers only and shall be considered to include, but not limited to, all insurance other than FICA, FUTA, SUTA and Workmen's Compensation, field and office supervisors and assistants, use of small tools, incidental job burdens, and general office expense. Incidental job burdens include, but are not limited to, review and coordination, and estimating and expediting relative to contract changes that are associated with field and office supervision.
- 6 -
No percentages for overhead and profit shall be allowed on FICA, FUTA or SUTA. The percentages for overhead and profit to be allowed by NIH may vary according to the nature, extent, and complexity of work involved, but in no case shall exceed the following:
The percentages of overhead to be allowed by the Contracting Officer will be 10% for all contract changes performed by prime contractor personnel and 5% for all contract change work performed by subcontract personnel.
The percentage for profit to be allowed by NIH will vary according to the nature, risk, extent, and complexity of work involved, but in no case shall exceed 10%. Percentages for overhead and profit will be as follows:
Overhead Profit To subcontractors and/or to the Contractor for work performed with his own forces 10% 1% - 10%
To Contractor on work performed by other than his own forces... 5% 1% - 5%
The percentage of profit is to be negotiated. The burden is on the contractor to propose and justify to the Government the percentage of profit to be paid on each modification to the contract.
On proposals involving both increases and decreases in the amount of the contract, overhead and profit will be allowed on the net increases only. On net decreases, corresponding overhead and profit will be deducted.
When change proposals are not submitted with a Time Impact Analysis, it is mutually agreed that the particular change order, modification, delay or Contractor request does not require an extension of the contract time (or milestone).
g. The percentages in (f) above are the maximums that will be paid. The burden is on the contractor to propose and justify to Government the percentages paid on each modification to the contract.
h. Any proposal for delay and impact costs that is not submitted with 7 calendar days prior to the completion date identified on the individual task order will not be considered. This requirement is in addition to the scheduling updates required for construction of the project. If there are circumstances which prevent the contractor from ascertaining delay for impact during this time, a status update including, but not limited to, and explanation as to why the contractor cannot yet know the extent of the impact and a critical path analysis shall be submitted within this time and at 3 day intervals thereafter with the final proposal due date for any impact as close of business (COB) one business day prior to the completion date identified in the task order. If this is not done, a claim for delay will not be considered unless special circumstances are shown. This requirement is necessary to enable the Government to respond to any claims for delay in light of conditions then current and take any necessary action within the period of performance of the task order.
ARTICLE G.5. INVOICE SUBMISSION
a. Invoice Instructions for NIH Fixed-Price Type Contracts, NIH(RC)-2, are attached and made part of this contract.
The Contractor shall follow the attached instructions and submission procedures specified below to meet the requirements of a "proper invoice" pursuant to FAR Subpart 32.9, Prompt Payment.
1. Payment requests shall be submitted to the offices identified below. Do not submit supporting documentation (e.g., receipts, time sheets, vendor invoices, etc.) with your payment request unless specified elsewhere in the contract or requested by the Contracting Officer.
The original invoice shall be submitted to the following designated billing office:
- 7 -
National Institutes of Health Office of Financial Management Commercial Accounts 2115 East Jefferson Street, Room 4B-432, MSC 8500 Bethesda, MD 20892-8500
E-Mail: ORFOAInvoice3Way@mail.nih.gov
1. The Contractor shall submit an electronic copy of the payment request to the approving official instead of a paper copy. The payment request shall be transmitted as an attachment via e-mail to the address listed above in one of the following formats: MSWord, MS Excel, or Adobe Portable Document Format (PDF). Only one payment request shall be submitted per e-mail and the subject line of the e-mail shall include the Contractor's name, contract number, and unique invoice number.
[Note: The original payment request must still be submitted in hard copy and mailed to the designated billing office to meet the requirements of a "proper invoice."]
2. Please scan your invoice along with the necessary backup documentation (not to exceed 30MB) as one single attachment.
3. Save your invoice attachment in the following format: YourVendorName_Invoice number (e.g., if your Vendor name is AE Construction Inc. and you are submitting Invoice 123456, Save your invoice attachment as 'AE Construction, Invoice 123456') Note: Please do not use special characters such as (#,$%*&!) when saving your attachment.
4. Send an email with your invoice attached (invoice and all supporting backup as one attachment) to our invoice processing email distribution mailbox: ORFOAInvoice3Way@mail.nih.gov. In the subject line of your email, please use the same format 'YourVendorName, Invoice number'. (e.g., AE Construction, Invoice 12345)
5. You will receive an automated email reply confirming that our Invoice processing received your invoice for processing. If you do not receive an email notification within 24 hours, it indicates that we did not receive your invoice for processing. In which case double check (1) that your email contained the scanned attachment of your invoice and that (2) you sent it to our inbox at ORFOAInvoice3Way@mail.nih.gov. Only resend an invoice if you have not received an email confirmation within 24 hours. If you have any questions or concerns please call the Intake Center at 301-402-0878.
6. OFM will return invoices to the contractor in the event (1) the information contained in the Header Text field on the PRISM award document does not match the information contained on the invoice;
or (2) the performance period/completion date indicated in the invoice is not in agreement with the period of performance/completion date set forth in the award document. ENSURE THAT ALL
INVOICES SUBMITTED MEET THESE CRITERIA OR YOUR INVOICE WILL BE REJECTED.
b. Inquiries regarding payment of invoices shall be directed to the designated billing office, (301) 496-6088.
ARTICLE G.6. PROVIDING ACCELERATED PAYMENT TO SMALL BUSINESS
SUBCONTRACTORS
a. The Government encourages the contractor to pay small business subcontractors along an accelerated timetable to the maximum extent practicable. The Government recommends payment to small business subcontractors within 15 days of receipt of proper documentation.
b. Include the substance of this article, include this paragraph (b), in all subcontracts with small business concerns.
c. This policy does not modify the application or operation of the Prompt Payment.
- 8 -
ARTICLE G.7. GOVERNMENT PROPERTY
If this RFP will result in the acquisition or use of Government Property provided by the contracting agency or if the Contracting Officer authorizes in the preaward negotiation process, the acquisition of property (other than real property), this ARTICLE will include applicable provisions and incorporate the HHS Publication, entitled, "HHS Contracting Guide for Contract of Government Property," which can be found at:
http://www.hhs.gov/hhsmanuals/logisticsmanual/Appendix Q_HHS Contracting Guide.pdf.
Government Property will be addressed on individual task orders as applicable.
ARTICLE G.8. POST AWARD EVALUATION OF CONTRACTOR PERFORMANCE
a. Contractor Performance Evaluations
Interim and final evaluations of Contractor performance will be prepared on this contract in accordance with FAR Subpart 42.15. The final performance evaluation will be prepared at the time of completion of work. In addition to the final evaluation, interim evaluation(s) will be prepared each year prior to exercising the option.
Interim and final evaluations will be provided to the Contractor as soon as practicable after completion of the evaluation. The Contractor will be permitted thirty days to review the document and to submit additional information or a rebutting statement. If agreement cannot be reached between the parties, the matter will be referred to an individual one level above the Contracting Officer, whose decision will be final.
Copies of the evaluations, Contractor responses, and review comments, if any, will be retained as part of the contract file, and may be used to support future award decisions.
b. Electronic Access to Contractor Performance Evaluations
Contractors may access evaluations through a secure Web site for review and comment at the following address:
http://www.cpars.gov
c. Task Order Past Performance Evaluations
Contractors will receive a Past Performance Evaluation on each task order the contractor is awarded. The Government will utilize a SF 1420, Performance Evaluation - Construction Contracts, for all task orders. The past performance evaluations for task orders will be utilized in determining the best value for future task order awards. The past performance evaluations for individual task orders will not be entered in the CPARS system, but will be used when developing the overall contract past performance evaluation in CPARS.
Task Order evaluations will be provided to the Contractor as soon as practicable after completion of the evaluation. The Contractor will be permitted thirty days to review the document and to submit additional information or a rebutting statement. If agreement cannot be reached between the parties, the matter will be referred to an individual one level above the Contracting Officer, whose decision will be final.
Copies of the evaluations, Contractor responses, and review comments, if any, will be retained as part of the contract file, and may be used to support future award decisions. Additionally, the task order evaluations will be utilized when doing the Interim and Final Contractor Performance Evaluations