NDOW Licensing System - RFP - Attachment 4.1.3 Calendar of Activities.docx

DOCX document 58 KB Posted

Attached to
Licensing System
Solicitation number
72DOW-S3941
Issued by
Churchill County, Nevada

About this file

This is a Calendar of Activities attachment for the Nevada Department of Wildlife (NDOW) Licensing System RFP, detailing the annual operational schedule and key dates for the contractor responsible for managing licensing, registrations, and hunting/fishing activities. The calendar outlines approximately 80 major events occurring between December 2027 and October 2028, including vessel registration renewals (approximately 36,000 postcards), application periods for various hunts (Spring Turkey, Big Game, waterfowl, sage grouse, and dove), online testing and validation phases, drawing events, results releases, harvest questionnaire deadlines, and regulatory compliance activities. Critical regulatory deadlines are fixed dates that cannot be modified, while other activities such as reminder emails and testing periods offer flexibility. Key operational milestones include Spring Turkey application opening on January 19, 2028 with an January 31 deadline; Big Game application opening March 27, 2028 with a May 10 deadline; and multiple waterfowl and migratory bird application periods throughout the year. The contractor is responsible for system testing, configuration file updates according to Commission Regulations, processing approximately 62,000 mailed guidebooks, managing customer notifications via email and text, charging credit cards for fees, operating the Alternate Program for tag distribution, and maintaining interfaces with external systems including the Integrated Wildlife Violation Correction System (IWVCS) and Hunter Education Module.

The calendar does not specify pricing terms, set-asides, incumbent contractor information, or funding amounts. However, it demonstrates that the contractor must maintain continuous operational capability throughout the calendar year, with particular intensity during application and draw periods. The contractor shares certain responsibilities with NDOW and points of sale (POS) partners, particularly for testing, validation, and system interface operations. The calendar indicates that revenue processing and customer transaction management are critical functions, as credit card charges are processed immediately following draw results releases. The document reflects a complex regulatory environment with multiple Commission Meetings scheduled throughout the year to set seasons, quotas, and regulations that directly impact the licensing system's configuration and operational schedule.

View the file

Other files

File Type Posted
NDOW Licensing System - RFP - Attachment 4.1.5 Project Kick Off_Project Management_Design Process.docx DOCX document
NDOW Licensing System - RFP - Attachment 4.1.7 Implementation Timeline.docx DOCX document
Question 33 - NV fulfillment - Vessel products.pdf PDF
72DOW-S3941-RFP_Licensing_Services.docx DOCX document
NDOW Licensing System - RFP - Attachment 4.1.1 Draw_Product_Program_Functionality Requirements.docx DOCX document
72DOW-S3941-Vendor-Information-Response.pdf PDF
Terms-and-conditions-for-services~2.pdf PDF
Standard-form-contract~1.docx DOCX document
Quote Instructions.pdf PDF
Question 33 - NV fulfillment - Licensing products.pdf PDF
Question 32 - NV annual sales by location.pdf PDF
Question 75 - 2025 Call center volume by month.pdf PDF
Question 66 - 2025 Call center volume by month.pdf PDF
72DOW-S3941-reference-questionnaire.docx DOCX document
Goals_Objectives and Scope of Work.docx DOCX document
72DOW-S3941-Certification-regarding-lobbying.pdf PDF
72DOW-S3941-Insurance.pdf PDF
72DOW-S3941-RFP_Licensing_Services~1.docx DOCX document
NDOW Licensing System - RFP - Attachment 4.1.4 Software_State Resources_State Requirements_Misc.docx DOCX document
NDOW Licensing System - RFP - Attachment 4.1.2 System_Technical_Functional Requirements.docx DOCX document
NDOW Licensing System - RFP - Attachemnt 4.3.3 Cost Schedule.docx DOCX document
NDOW Licensing System - RFP - Attachment 4.1.6 Product List.xlsx XLSX spreadsheet
72DOW-S3941 Licensing System-Evaluators and Criteria Weights.doc DOC document
TIE Completion Memo - NDOW - 1904 - NDOW Licensing System -RFP - Revision 0 - 4461.pdf PDF
Question 15 - NV Applications received by day 2025-2026.pdf PDF
Bid 72DOW-S3941_Questions_NDOWanswers.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NDOW Licensing System RFP – Calendar of Activities – Attachment 4.1.3

4. ATTACHMENTS

4.1.3 CALENDAR OF ACTIVITIES

The calendar provided is to inform Vendors of the calendar of events related to products, application periods, and draws that NDOW provides on an annual basis so that vendors may accurately plan implementation. Some item dates are open to date flexibility such as reminder emails, testing, application openers. Other dates are set in regulation and may not fluctuate from the date provided such as application deadlines, new product sales dates, draw results release dates.

Anticipated Date
Responsible Party
Calendar Event
December 1, 2027
NDOW/Contractor
Vessel Registration Renewal notices out. Approximately 36,000 postcard notices are mailed to the public.
December 1, 2027
Contractor
Annual Angler harvest questionnaire is open to all customers with a valid fishing or combination license in the past year.
December 1, 2027
NDOW/Contractor
Vessel Registration and Title sales go live
December 15, 2027
Contractor
Update and review the Spring Turkey Configuration file according to Commission Regulation.
January 1, 2028
Contractor
County vessel sales semi-annual registration report due to NDOW Fiscal staff. A report on all vessel registrations sold by county in the previous six months.
January 1, 2028
Contractor
US Coastguard annual vessel registration report due to NDOW Law Enforcement staff. A report on all vessel registrations sold in the prior year.
January 1- 30, 2028
Contractor
Final courtesy big game harvest questionnaire reminder emails and texts sent to customers.
January 5, 2028
NDOW/Contractor
Test online application site for Spring Turkey.
January 4, 2028
NDOW/Contractor
Provide lists of licensed master guides for PIN assignment.
January 15, 2028
Contractor
Update and review the Restricted Non-Resident Guided Mule Deer Hunt (NRGH) Configuration file according to Commission Regulation.
January 19, 2028
Contractor
Spring Turkey application period opens to the public.
January 21 and 22, 2028
Informational
Commission Meeting Big Game Season setting in Reno Nevada. Involves regulations that affect upcoming draws and application period dates.
January 25, 2028
NDOW/ Contractor
Test Internet online application site process for NRGH.
January 31, 2028
Contractor
11 pm application deadline for 2028 Spring Turkey
January 31, 2028
Contractor
Big Game harvest questionnaire deadline.
February 1, 2028
Contractor
Spring Turkey Bonus Point only application period opens to the public.
February 1, 2028
Contractor/POS
Mountain lion tag sales open for the upcoming mountain lion season.
February 1, 2028
Contractor
Big Game non-return of harvest questionnaire Administrative Penalty applied to customer accounts, email notices sent out.
February 1 to May 10, 2028
Contractor
Sales of harvest questionnaire Administrative Penalty. Payment deadline is the same as Big Game application deadline according to Commission Regulation.
February 4, 2028
NDOW/Contractor
Test for validation review of the Spring Turkey draw.
February 7, 2028
Contractor
NRGH application period is open to the public.
February 7, 2028
Contractor
11 pm application deadline for Spring Turkey Bonus Point only.
February 15, 2028
Contractor
Update and review the Big Game Configuration file according to Commission Regulation.
February 16, 2028
Contractor
Spring Turkey drawing.
February 18, 2028
Contractor
Spring Turkey online results released, emails sent to applicants, credit cards are charged for tag fees.
February 28, 2028
Contractor
Swan harvest questionnaire deadline.
March 1, 2028
Contractor
Angler harvest questionnaire deadline.
March 1, 2028
NDOW/ Contractor /POS
IWVCS Interface
March 1, 2028
NDOW/ Contractor /POS
Hunter Education Module Interface
March 1, 2028
NDOW/ Contractor
Furbearer harvest questionnaires become active to all customers holding a trapping license.
March 1, 2028
NDOW/Contractor
Issue deferred tags to customers and adjust bonus point balances.
March 6, 2028
NDOW/Contractor
Test online application site for Big Game.
March 6, 2028
Contractor
11 pm application deadline for 2028 NRGH.
March 7, 2028
NDOW/Contractor
Test for validation review of the NRGH draw.
March 10 to 11, 2028
Informational
Commission Meeting in Las Vegas Nevada. Migratory Bird and Swan Season setting.
March 15, 2028
Contractor
NRGH drawing.
March 17, 2028
Contractor
NRGH online results released, emails sent to applicants, credit cards are charged for tag fees.
March 27, 2028
Contractor
Big Game application period is open to the public.
April 1, 2028
NDOW/Contractor
Big Game Application guidebooks are mailed to past applicant households. Approximately 62,000 guidebooks are mailed.
April 17 to May 23, 2028
NDOW/Contractor
Tests for validation review of the Big Game draw. Multiple tests ran during this timeframe.
May 10, 2028
Contractor
11 pm application deadline for 2028 Big Game.
May 12 to 13, 2028
Informational
Commission Meeting in Las Vegas Nevada. Big Game Quota setting.
May 15, 2028
NDOW/Contractor
Update and validate Big Game draw configuration with Commission approved quotas.
May 22, 2028
Contractor
Update and review the Overton Wildlife Management Area Dove Configuration file according to Commission Regulation.
May 24, 2028
Contractor
Big Game drawing.
May 26, 2028
Contractor
Big Game online results released, emails sent to applicants, credit cards are charged for tag fees.
May 26 to June 2, 2028
Contractor
7-day electronic tag return period for customers to digitally return their tags before tag printing and fulfillment.
May 26 to the end of the hunting seasons
Contractor
The Alternate Program is active, tags are awarded to customers through the Alternate Program until two weeks before the close of the hunting seasons.
May 29, 2028
Contractor
Update and review the Second Draw Configuration file according to Commission Regulation.
May 29, 2028
NDOW/Contractor
Test online application site for Second Draw.
May 31, 2028
NDOW/ Contractor
Furbearer harvest questionnaire deadline.
May 31, 2028
NDOW/ Contractor
Spring Turkey harvest questionnaire deadline.
May 31, 2028
NDOW/Contractor
Adjust bonus point balances for PIW tag holders.
June 1, 2028
NDOW/ Contractor
Furbearer non-return of harvest questionnaire Administrative Penalty applied to customer accounts holding a trapping license, email notices sent out.
June 1, 2028
NDOW/ Contractor
Spring Turkey non-return of harvest questionnaire Administrative Penalty applied to customer accounts, email notices sent out.
June 5, 2028
Contractor
Second Draw application period opens to the public.
June 5, 2028
NDOW/Contractor
Test online application site for Overton WMA Dove.
June 12, 2028
Contractor
11 pm application deadline for 2028 Second Draw.
June 13, 2028
NDOW/Contractor
Test for validation review of the Second Draw.
June 15, 2028
NDOW/Contractor
Test online site for First Come First Serve sales.
June 21, 2028
Contractor
Second drawing.
June 23, 2028
Contractor
Second Draw online results released, emails sent to applicants, credit cards are charged for tag fees.
June 23 to 24, 2028
Informational
Commission Meeting in rural Nevada. Upland Game Season Setting, includes Spring Turkey
June 26, 2028
Contractor
Overton WMA Dove application period opens to the public.
June 26, 2028
Contractor
Update and review the Sheldon Sage Grouse Configuration file according to Commission Regulation.
July 1, 2028
Contractor
Federal E-duck stamps are available for purchase to customers.
July 1, 2025
Contractor
HIP registrations are available to customers.
July 1, 2028
Contractor
Snowcock permits are available for purchase to customers.
July 1, 2028
Contractor
County vessel sales semi-annual registration report due to NDOW Fiscal staff. A report on all vessel registrations sold by county in the previous six months.
July 10, 2028
Contractor
11 pm application deadline for 2028 Overton WMA Dove.
July 10, 2028
NDOW/Contractor
Test online application site for Sheldon Sage Grouse.
July 11, 2028
NDOW/Contractor
Test for validation review of the Overton WMA Dove draw.
July 17, 2028
Contractor
Update and review the Swan Configuration file according to Commission Regulation.
July 17, 2028
Contractor
Update and review the Overton Wildlife Management Area Waterfowl Configuration file according to Commission Regulation.
July 17, 2028
Contractor
Update and review the Key Pittman Wildlife Management Area Waterfowl Configuration file according to Commission Regulation.
July 18, 2028
Contractor
The First Come First Serve program is available to customers. Date of opener depends on date tags become available.
July 26, 2028
Contractor
Overton WMA Dove drawing.
July 28, 2028
Contractor
Overton WMA Dove online results released, emails sent to applicants, credit cards are charged for tag fees.
July 31, 2028
NDOW/Contractor
Test online application site for Swan.
July 31, 2028
NDOW/Contractor
Test online application site for Overton WMA Waterfowl.
July 31, 2028
NDOW/Contractor
Test online application site for Key Pittman WMA Waterfowl.
July 31, 2028
Contractor
Sheldon Sage Grouse application period is open to the public.
July 31, 2028
NDOW/Contractor
Adjust bonus point balances based on no application for two-years rule.
August 11 to 12, 2028
Informational
Commission Meeting in rural Nevada. Licensing vendor presentation of the Big Game Draw report and statistics.
August 14, 2028
Contractor
11 pm application deadline for 2028 Sheldon Sage Grouse.
August 15, 2028
NDOW/Contractor
Test for validation review of the Sheldon Sage Grouse draw.
August 21, 2028
Contractor
Swan application period opens to the public.
August 21, 2028
Contractor
Overton WMA Waterfowl application period opens to the public.
August 21, 2028
Contractor
Key Pittman WMA Waterfowl application period opens to the public.
August 23, 2028
Contractor
Sheldon Sage Grouse drawing.
August 25, 2028
Contractor
Sheldon Sage Grouse online results released, emails sent to applicants, credit cards are charged for tag fees.
September 4, 2028
Contractor
11 pm application deadline for 2028 Swan.
September 4, 2028
Contractor
11 pm application deadline for 2028 Overton WMA Waterfowl.
September 4, 2028
Contractor
11 pm application deadline for 2028 Key Pittman WMA Waterfowl.
September 5, 2028
NDOW/Contractor
Test for validation review of the Swan draw.
September 5, 2028
NDOW/Contractor
Test for validation review of the Overton WMA Waterfowl draw.
September 5, 2028
NDOW/Contractor
Test for validation review of the Key Pittman Waterfowl draw.
September 20, 2028
Contractor
Swan drawing.
September 20, 2028
Contractor
Overton WMA Waterfowl drawing.
September 20, 2028
Contractor
Key Pittman Waterfowl drawing.
September 22 to 23, 2028
Informational
Commission Meeting in Las Vegas Nevada. Fishing Seasons and Bag Limits.
September 22, 2028
Contractor
Swan online results released, emails sent to applicants, credit cards are charged for tag fees.
September 22, 2028
Contractor
Overton WMA Waterfowl online results released, emails sent to applicants, credit cards are charged for tag fees.
September 22, 2028
Contractor
Key Pittman WMA Waterfowl online results released, emails sent to applicants, credit cards are charged for tag fees.
October 20, 2028
Contractor
Carson Lake and Pasture permits are available for purchase to customers.
October 31, 2028
NDOW/ Contractor
Sheldon Sage Grouse harvest questionnaire deadline.

Attachment 4.1.3 – Calendar of Activities NDOW Licensing System RFP. - Page 2