This document is a Task Group Instruction (TGI) for the USS BLUE RIDGE (LCC-19), specifically addressing cleaning, inspection, repair, and preservation of clean salt water ballast (tank 9-52-0-W) and fresh water ballast (tank 9-48-0-W). The TGI details a comprehensive maintenance process involving multiple locations including the ballast tanks, anti-roll tank, and several storerooms. Key technical requirements include commercial blast cleaning, visual inspections for structural integrity and coating condition, welding and plate repairs, removal of unused brackets and studs, and surface preparation and coating application.
The work is scheduled to begin on 1/12/2026 and complete by 5/15/2027, with specific procedural steps for cleaning (Level III cleanliness), surface preparation, repairs, and documentation. Special requirements include working near a fire zone boundary, necessitating a non-flammable closure, and potential lead hazard considerations. The instruction involves multiple technical disciplines including laborers, painters, welders, quality assurance personnel, and safety technicians, with various inspection and quality control measures integrated throughout the maintenance process.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
CUI: Public availability to be determined under 5 USC 552
TASK GROUP INSTRUCTION
AIM REV 20.11.4.0 (OCTOBER 2020)
TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:
NO.: TK 9-52-0-W&9-48-0-W AY A 0 0
SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE:
F/O - CLEAN, INSP, RPR, AND PSV CLEAN SW BLST (9-52-0-W) AND FW BLST (9-48-0-W)
PREPARING ACTIVITY:
PREPARED BY: CODE PHONE DATE
MASAHARU NAMEGAYA 231B. 315-243-4489 15-FEB-2024
APPROVED BY: CODE PHONE DATE
RYOUTA TAKAGI 231B. 315-243-4502 15-FEB-2024
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
REASON FOR WORK/NEED FOR CHANGE:
CHANGE INSTRUCTIONS:
SPECIAL REQUIREMENTS:
This work affects a fire zone boundary. Fabrication and/or staging of a non-flammable closure is required.
SURFMEPP
CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL III
WORK CERTIFICATION SIGNATURES
COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
ACCEPTANCE OF COMPLETED WORK
PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:
REQUIRED:☐YES ☒NO
RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
TGI NO.: TK 9-52-0-W&9-48-0-W AY A 0
FOUO
SHIP: LCC-19 CHG/VER: 0/0
LIST OF EFFECTIVE PAGES
SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.
1-6 J1-2 M-1
1. SCOPE/PURPOSE
1.1 Title: Clean Salt Water Ballast (9-52-0-W) and Fresh Water Ballast (Locked In) (9-48-0-W); clean, inspect, repair, and preserve
1.2 Location of Work:
1.2.1 Clean Salt Water Ballast (9-52-0-W)
1.2.2 Fresh Water Ballast (Locked In) (9-48-0-W)
1.2.3 Anti-Roll Tank (7-52-01-W)
1.2.4 SD Storeroom (7-48-0-A)
1.2.5 Storeroom (6-52-4-A)
1.2.6 Storeroom (6-52-5-A)
1.3 Identification:
1.3.1 Quantity (One EA), Clean Salt Water Ballast
Tank No.: 9-52-0-W Capacity: 46,915 Gallons
1.3.2 Quantity (One EA), Fresh Water Ballast (Locked In)
Tank No.: 9-48-0-W Capacity: 23,285 Gallons
1.3.3 Quantity (6 EA), Bracket in 9-48-0-W
Remarks: See Sketch Enclosure-01 for location details.
1.3.4 Quantity (One EA), Stud in 9-48-0-W
Remarks: See Sketch Enclosure-01 for location details.
1.3.5 Quantity (2 EA), Manhole Cover Plate (s) for 9-52-0-W
Manhole No(s): 7-53-1 and 7-55-2 Size: 15 Inches x 23 Inches Material: Steel
1.3.6 Quantity (2 EA), Manhole Cover Plate (s) and Air Vent Hose Connection (AVHC) Cover Plate(s) for 9-48-0-W Manhole No(s): 7-51-1 Size: 15 Inches x 23 Inches AVHC No(s).: 7-51-2 Size: 10 Inches Diameter Material: Steel
1.3.7 Quantity (2 EA), Bolting Ring for Manhole Cover Plate (s) for 9-48-0-W
FOUO
SHIP: LCC-19 CHG/VER: 0/0
Manhole No(s): 7-51-1 AVHC No(s).: 7-51-2 Material: Steel
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N
3 TM S9086-
CJ-STM-
010/CH-075
Fasteners 7 N
4 TM
SYSTEMS &
SPECIFICAT
IONS
SSPC Painting Manual Volume 2 - N
5 DWG 100-
2491003
SHELL PLTG & STGR FRAME 51
1/2 -102 1/4 CL TO 4 TH DECK
G Y AL
L
6 DWG 101-
2491012
CVK & Shell Long AFT FR 51 1/2 L Y AL L
7 DWG 101-
2491013
Floors FR 8-98 S Y 6,1 4,1
8 DWG 101-
2491021
WEBS FR 54, 56, 58, 60 & 62 J Y AL
L
9 DWG 102-
2491031
Inner Bottom PLTG FR 51 1/2 - 98 K Y AL L
10 DWG 103-
2491033
2 PLATF FR 52-98 J Y AL
L
11 DWG 114-
2491156
AGC19 TRANSV BHD FR 52 & 64 G Y AL
L
12 DWG 114-
2491161
DEEP TANK BHD FR 24, 48, 56, &
LONG BHD BEL 2ND PLATF FR
30-76
F Y AL
L
13 DWG 101-
2491011
CVK & SHELL LONG FR8-51-1/2 E Y AL
L
14 DWG 102-
2491030
INNER BOTTOM PLTG FR8-1/2 -
51-1/2
G Y AL
L
15 TM T-9630-
AB-MMD-
Corrosion Control Assessment and Maintenance Manual (CCAMM)
3 N
16 TM NAVSEA
4790/14
Tank and Void Structural and Coating Condition Survey (MRC G1N5)
- N
1.3.8 Quantity (6,230 SF), Entire Interior Surface of 9-52-0-W Remarks: The area includes tank side of manhole cover plate(s) and bolting ring(s).
1.4 Security Classification: None.
1.5 Initial Condition:
1.5.1 Critical Coated Area: CCNY-LCC19-009-25 for area listed in 1.3.8.
1.5.2 Potential Lead Hazard.
1.6 Contractor work start date: 1/12/2026
1.7 Contractor work completion date: 5/15/2027
2. REFERENCES:
FOUO
SHIP: LCC-19 CHG/VER: 0/0
3. APPENDICES:
3.1 Appendix “J” TGI Job Summary Information Sheet
3.2 Appendix "M" TGI Material List
3.3 Appendix “D” Deficiency Form
4. GENERAL REQUIREMENTS:
4.1 Not Applicable.
5. PROCEDURE:
5.1 Accomplish the requirements of 099-902YO of 2.2 for each tank listed in 1.3.1 and 1.3.2.
5.1.1 Accomplish the requirements of 009-107 of 2.1.
5.1.1.1 Ensure General Cleaning must be Level III.
5.1.2 Accomplish installation of each manhole cover for each tank listed in 1.3.1 and 1.3.2 in accordance with Figure 075-4-1 of 2.3.
5.2 Commercial blast clean each tank listed in 1.3.1. Accomplish each requirement of surface preparation SSPC- SP-6 of 2.4.
5.3 Accomplish a visual inspection of each tank listed in 1.3.1 for existing preservation coating, structural integrity, deterioration, pitting, each crack, and area of damage or distortion, including each sounding tube, tank vent, overflow, piping, structural member, and manhole cover, using 2.5 through 2.12 for guidance.
5.3.1 Submit one legible copy, in hard copy or approved transferrable media, of a report listing results of the requirements of 5.3 to the SUPERVISOR.
5.4 Weld fill, drill, and tap a total of 10 each stripped manhole cover bolting ring holes for each tank listed in 1.3.1 as designated by the SUPERVISOR. See 5.12.6.
5.4.1 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column A, Lines One through 7.
5.5 Repair each tank listed in 1.3.1, based on the report in 5.3.1 and CCIMS assessment report as designated by the SUPERVISOR, using 2.5 through 2.12 for guidance. See 5.12.5 through 5.12.7.
5.5.1 Vee-out and weld a total of one linear foot of each deteriorated and damaged weld. Each area of repair must include deck, bulkhead, shell plating, and overhead.
5.5.2 Chip and grind each surface flush in way of each repair.
5.5.3 Base metal weld buildup a total of 60 square inches of each plate defect in the tank.
5.5.3.1 For bidding purposes the base metal weld buildup must be one quarter inch thick.
5.5.3.2 Surface must be ground to sound metal prior to base metal weld buildup.
5.5.3.3 Fill each local pit and groove with weld material prior to application of each principal build up layer.
5.5.3.4 Grind each surface of completed base metal weld buildup smooth if greater than 1/8 inch above plate surface.
5.5.4 Remove existing, fabricate, and install new a total of 10 square feet of deteriorated plate.
FOUO
SHIP: LCC-19 CHG/VER: 0/0
5.5.5 Remove existing, fabricate, and install new a total of 4 linear foot of defective stiffener.
5.5.6 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column A, Lines One through 7.
5.5.6.1 Accomplish nondestructive testing in accordance with Line 11.
5.5.7 Accomplish the requirements of 009-25 of 2.1 for an air hose, water hose, or vacuum box test of each new insert weld seam. Allowable leakage: None.
5.6 Remove unused each existing bracket and stud listed in 1.3.3 and 1.3.4, using 2.5, 2.7, 2.11, 2.13, and 2.14 for guidance.
5.7 Accomplish the requirements of 009-32 of 2.1, including Table 4, Line(s) 17, for tank (7-52-01-W) side surface of each cover plate listed in 1.3.5.
5.8 Accomplish the requirements of 009-32 of 2.1, including Table 4, Line(s) 17, for tank side surface and Table 3, Line(s) 25, for storeroom side surface of each cover plate listed in 1.3.6.
5.9 Accomplish the requirements of 009-32 of 2.1 for each bolting ring listed in 1.3.7.
5.10 Accomplish the requirements of 009-32 of 2.1, including Table 4, Line(s) 17, for each area listed in 1.3.8.
5.10.1 Submit new coating data applied to the SUPERVISOR in accordance with 2.15 and 2.16.
5.11 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
5.12 Notes:
5.12.1 Planner: Code 231B M. Namegaya, 243-4489
5.12.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
5.12.3 2.16 is available on P:\C200\C225\Enclosures\C231\Tank and Void Structural and Coating Condition Survey
(MRC G1N5).
5.12.4 This TGI meets the intent of DDG CSWT File No. 123-111, 123-133, and 123-142.
5.12.5 CCIMS assessment of each tank listed in 1.3.1 will be accomplished by SRF-JRMC (TGI No.
3819P12338I01), and the Project team will provide the assessment report with engineering evaluation under DL process for front loading structure repair.
5.12.6 Removal and installation of interferences, and gas free operation, preservation of boundary spaces relating to front loading structure repair are not included in this TGI. They will be covered by a DL in the future based on Contractor submitted condition report.
5.12.7 Materials for structure members relating to front loading repair will be provided in the future as a DL based on Contractor submitted condition report.
5.12.8 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkheads normally used to control air flow in the event of a shipboard fire. A nonflammable closure is required in accordance with COMNAVSEASYSCOM MSG R 261400Z JUL 12. The closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper air flow onboard the ship.
FOUO
SHIP: LCC-19 CHG/VER: 0/0
5.12.9 SRF-JRMC will review and approve a Contractor submitted drawing or sketch and will issue additional documents with QA Form(s) relating to actual location of temporary access(es) related to removal and installation of lead ballast for documentation of welding, nondestructive testing, and compartment testing when OQE(s) are required.
5.12.10 Opening, initial cleaning, and closing of each space listed in 1.2.3 will be covered by TGI No.
3819P12335A01 (KTR TGI).
5.12.11 JCNs ER01-ZA00, ER01-ZAK6, ER01-ZAS6, ER01-ZAV9, and ES01-NPAF are related to this TGI.
5.13 Government Furnished Material (GFM): None.
5.14 SRF-JRMC will provide following service work: (TGI No. 3819P12338S02).
5.14.1 [C740] Crane and crane rigging service.
5.14.2 [X99E] Utility service, electrical.
5.14.3 [X99M] Utility service, including water supply, steam supply, and low pressure air supply except onboard blasting work.
5.14.4 [C106.1] Safety inspection for SRF-JRMC employees.
5.14.5 [C106.2] Gas free inspection for SRF-JRMC employees.
5.14.6 [C133] QA inspection for (G) symbol(s) and review of coating application data.
5.14.7 [C135] QA inspection for (G) symbol(s).
5.14.8 [C250] Technical support.
FOUO
J-1
SHIP: LCC-19 CHG/VER: 0/0
APPENDIX "J"
TGI JOB SUMMARY INFORMATION SHEET
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
TK 9-52-0-W&9-48-0-W AY A 0 0
CU PHASE TITLE:
F/O - CLEAN, INSP, RPR, AND PSV CLEAN SW BLST (9-52-0-W) AND FW BLST (9-48-0-W)
PRIMARY COMPONENT:
COMPONENT UNIT LIST (FOR ASSEMBLIES):
MANHOLE 7-55-2 HA BLST 9-48-0-W TK MANHOLE 7-53-1 HA AVHC CV 7-51-2 HA
BLST 9-52-0-W TK MANHOLE 7-51-1 HA
ATTACHMENT LIST:
1. ENCLOSURE-01 (3819P12338A01-Sketch.pdf) saved on 15-FEB-2024 0000.
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA ,TAKEHIDE
JO: KO: TOTAL MAN HRS: PLANNING ACCEPTANCE:
3819P12338 A01
TOTAL MAT’L COST TOTAL DURATION:
CU PHASE DESCRIPTION:
The purpose of this TGI is to clean, inspect, repair, and preserve clean salt water ballast (9-52-0-W) and fresh water ballast (locked in) (9-48-0-W)
Location of Work:
Clean Salt Water Ballast (9-52-0-W) Fresh Water Ballast (Locked In) (9-48-0-W) Anti-Roll Tank (7-52-01-W) SD Storeroom (7-48-0-A) Storeroom (6-52-4-A) Storeroom (6-52-5-A)
TASK NAME
SHOP TSD/WC TS CREW# MHRS
HIGH RAD
HOURS
RC
GRID#
5.1 LBR HRs 22 KE PC
5.2 PNTR HRs, ELEC HRs, QA HRs, SFTR HRs, RGRS HRs, WELD HRs
22 KE PC
5.3 SFTR HRs 22 KE PC
5.4 SFTR HRs, WELD HRs, PNTR HRs, QA HRs 22 KE PC
5.5 SFTR HRs, WELD HRs, QA HRs, CARP HRs 22 KE PC
5.6 SFTR HRs, WELD HRs, PNTR HRs 22 KE PC
5.7 PNTR HRs, QA HRs 22 KE PC
5.8 PNTR HRs, QA HRs 22 KE PC
5.9 PNTR HRs, QA HRs 22 KE PC
5.10 PNTR HRs, QA HRs 22 KE PC
5.11 PNTR HRs, QA HRs 22 KE PC
FOUO
J-2
SHIP: LCC-19 CHG/VER: 0/0
TASK NAME
SHOP TSD/WC TS CREW# MHRS
HIGH RAD
HOURS
RC
GRID#
Dewatering/Cleaning Work CFM for marine chemist, gaskets, fasteners, tank watch cost, and misc such as other consumable.
22 MQ CS
Structural Work CFM for tank watch cost, fire watch cost, MT inspection cost, compressor rental cost and fuel oil cost for air hose test, and misc such as electrode, and other consumable parts.
22 MQ CS
Preservation Work CFM for all paints, thinner, grits, disposal cost, chain block rental cost, fastener, tank watch cost, air compressor, dryer, fuel oil, air conditioning, and MISC such as covering material and other consumable.
22 MQ CS
Temporary Access Work CFM for compressor rental cost and fuel oil cost for air hose test, steel plate for padeye and backing strip, tank watch cost, fire watch cost, and misc such as electrode, and other consumable parts.
22 MQ CS
Process Funding Document 10 CT OM
FOUO
M-1
SHIP: LCC-19 CHG/VER: 0/0
APPENDIX “M”
TGI MATERIAL LIST
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
TK 9-52-0-W&9-48-0-W AY A 0 0
CU PHASE TITLE:
F/O - CLEAN, INSP, RPR, AND PSV CLEAN SW BLST (9-52-0-W) AND FW BLST (9-48-0-W)
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV
JOB ORDER: KEY OP:
3819P12338 A01
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
NOTES:
CUI: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR APPENDIX "D"
DEFICIENCY FORM
☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One)
2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
LCC-19 TK 9-52-0-W&9-48-0-W AY A 0
4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:
3819P12338 A01
7. DESCRIPTION:
8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
9. CORRECTIVE ACTION:
10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
FOR NON-NUCLEAR USE ONLY
11. RFD/RFW REQ’D ☐ LAR REQ'D ☐
ILS MOD REQ’D ☐
SRD/PLAN REV REQ'D ☐
DWG NO.: _____________________ S/A NO.: ___________________
12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:
SATISFACTORY:
13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
YES ☐ NO ☐
14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE:
15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
_________:YES ☐ NO ☐
16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE (DR ONLY)
DL’s ISSUED
(DR ONLY)
CUI: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
LCC-19 TK 9-52-0-W&9-48-0-W AY A 0
LOCATION DETAIL OF UNUSED BRACKET AND STUD IN 9-48-0-W
CL
FR 48FR 49FR 50FR 51FR 52
L1 (S)
L2 (S)
L4 (S)
L3 (S)
L1 (P)
L2 (P)
L3 (P)
L4 (P)
SHELL PLTG
PLAN VIEW 9-48-0-W
UNUSED BRACKETS
SEE DET-1
UNUSED BRACKETS
SEE DET-2
UNUSED BRAKCETS
SEE DET-3
UNUSED STUD
SEE DET-4
DET-1: UNUSED BRACKETS
OT FL FR52, LKG AFT
SKETCH
ENCLOSURE-013819P12338A01 SHEET 1 OF 2
FWD
SKETCH
ENCLOSURE-013819P12338A01 SHEET 2 OF 2
LOCATION DETAIL OF UNUSED BRACKET AND STUD IN 9-48-0-W
DET-2: UNUSED BRACKETS
SHELL PLTG FR52, LKG BOTTOM
FWD
DET-3: UNUSED BRACKETS
LONG ONE (P) FR50, LKG STBD
FWD
FWD
DET-4: UNUSED STUD
INNER BOTTOM FR50, INVERTED VIEW