TGI_3819P14206T02_c0v0.pdf
PDF 25 KB Posted
- Attached to
- USS BLUE RIDGE (LCC-19) 5C1 DSRA TYCOM 1
- Solicitation number
- N6264925RA021
About this file
This document is a WebAIM Short Form Task Group Instruction (TGI) for the USS Blue Ridge (LCC-19), specifically focused on the Tightness & Operational Test for CHT Pump #1. The TGI is dated 22-AUG-2024 and involves contractor work, quality assurance (QA) work, and support/functional (S/F) work to accomplish and document the pump test in accordance with reference document TP 59311-3-301KTR. The task involves multiple work groups, including a contractor (22/KE PC), QA team (33/G1), and support functional team (ES01), with each group required to perform and document the tightness and operational test for the CHT Pump #1.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
22-AUG-2024 1011
20.14.15.0.8993 (August 2024) ICN: 3819P14206 KeyOp: T02
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 59311-3-301KTR TT T 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 59311
CU PHASE TITLE: CHT PUMP #1 (T & OP) - KTR
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 2
ES01NPEY * ES01NPGZ * ES01NPH0 * ES01NPH1 * ES01NPH2 * ES01NPH3 * ES01NPH4 * ES01NPH5 * ES01NPH6 *
ES01NPH7 * ES01NPH8 * ES01NPH9 * EM040899
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
MORITA, MATSUKI 246.2 3152432332 01-JUL-2024
APPROVED BY: CODE: PHONE: DATE:
OHTA, JASON Y. 246.2 3152435901 17-JUL-2024
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EM04-0899 * ES01-NPEY * ES01-NPGZ * ES01-NPH0 * ES01-NPH1 * ES01-NPH2 * ES01-NPH3 * ES01-NPH4 * ES01-NPH5 *
ES01-NPH6 * ES01-NPH7 * ES01-NPH8 * ES01-NPH9
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE U
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
142A0006
Tightness & Operational Test for CHT PUMP #1 - KTR.
TGI Short Form
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
22-AUG-2024 1011
20.14.15.0.8993 (August 2024) (Continued) ICN: 3819P14206 KeyOp: T02
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 59311-3-301KTR TT T 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 59311
CU PHASE TITLE: CHT PUMP #1 (T & OP) - KTR
FOUO Pg 2 of 2
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 TP 59311-3-301KTR CHT PUMP #1 (T & OP) - KTR LAT Y
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
(V) Contractor work:
Accomplish/document the tightness & operational test in accordance with reference, TP 59311-3-301KTR.
22/KE PC N
(G) QA work:
Accomplish/document the tightness & operational test in accordance with reference, TP 59311-3-301KTR.
33/G1 QA N
(S) S/F work:
Accomplish/document the tightness & operational test in accordance with reference, TP 59311-3-301KTR.
/ ES01 N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P14206 KEY OP: T02
File details come from the government source that posted it. Updated .