TGI_3819P14203_T03_c0v0.pdf

PDF 25 KB Posted

Attached to
USS BLUE RIDGE (LCC-19) 5C1 DSRA TYCOM 1
Solicitation number
N6264925RA021
Issued by

About this file

This WebAIM Short Form Task Group Instruction (TGI) documents an operational test for Air Conditioning (A/C) Plant #5 on the USS Blue Ridge (LCC-19), scheduled for 29-AUG-2024. The document outlines specific work tasks for multiple teams, including contractor work, quality assurance (QA) work, support/field (S/F) work, and test work, all focused on conducting a tightness and operational test according to reference document TP 51425-3-301KTR. The task involves accomplishing and documenting the test, with additional requirements for conducting vibration analysis. Key personnel include Daisuke Enomoto (preparer), Riley Higa (approver), and Takehide Yaginuma (zone manager), with the task assigned Job Summary ID 142A0003.

View the file

Other files

File Type Posted
TGI_3819P59302A01_c1v1.pdf PDF
TGI_3819P14213A01_c0v0.pdf PDF
TGI_3819P14203_T04_c0v0.pdf PDF
TGI_3819P14206T01_c0v0.pdf PDF
TGI_3819P14206T02_c0v0.pdf PDF
TGI_3819P12393_A01_c0v0.pdf PDF
TGI_3819P12357_T01_c0v0.pdf PDF
TGI_3819P12341A01_c0v0.pdf PDF
TGI_3819P12340A01_c1v0.pdf PDF
TGI_3819P12336A01_c0v0.pdf PDF
TGI_3819P12312A01_c0v0.pdf PDF
TGI_3819P12305A01_c0v0.pdf PDF
TGI_3819P13506A01_c0v0.pdf PDF
TGI_3819P14203_A01_c2v1.pdf PDF
2.03 Solicitation N6264925RA0210002.pdf PDF
TGI_3819P14212A01_c0v0.pdf PDF
TGI_3819P14215A01_c0v0.pdf PDF
TGI_3819P51404A01_c0v0.pdf PDF
TGI_3819P14206T03_c0v0.pdf PDF
TGI_3819P12387A01_c0v1.pdf PDF
TGI_3819P14206A01_c0v2.pdf PDF
TGI_3819P12364A01_c0v0.pdf PDF
TGI_3819P13506A01_c0v0.pdf PDF
TGI_3819P14203_T04_c0v0.pdf PDF
TGI_3819P12321A01_c1v1.pdf PDF
TGI_3819P12342A01_c0v0.pdf PDF
TGI_3819P12336A01_c0v0.pdf PDF
TGI_3819P12320A01_c0v0.pdf PDF
TGI_3819P12354A01.pdf PDF
TGI_3819P12305A01_c0v0.pdf PDF
Attachment IV RFI (fillable).pdf PDF
TGI_3819P14211A01_c0v0.pdf PDF
TGI_3819P14214A01_c0v0.pdf PDF
TGI_3819P16729A02_c0v1.pdf PDF
TGI_3819P51405A01_c0v0.pdf PDF
TGI_3819P51401A01_c1v2.pdf PDF
TGI_3819P12388A01_c1v1.pdf PDF
TGI_3819P12393_A01_c0v0.pdf PDF
TGI_3819P14203_T01_c0v0.pdf PDF
TGI_3819P12318A01_c2v3.pdf PDF
TGI_3819P12335A01_c1v0.pdf PDF
TGI_3819P12357_A01_c0v0.pdf PDF
TGI_3819P12357_T01_c0v0.pdf PDF
TGI_3819P12340A01_c1v0.pdf PDF
TGI_3819P12323A01_c1v1.pdf PDF
TGI_3819P12341A01_c0v0.pdf PDF
TGI_3819P12312A01_c0v0.pdf PDF
Attachment VII Warranty Tracking Information.pdf PDF
Attachment IV RFI.docx DOCX document
Attachment III TYCOM1_GFP_List_V3.xlsx XLSX spreadsheet
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

29-AUG-2024 0927

20.14.15.0.8998 (August 2024) ICN: 3819P14203 KeyOp: T03

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 51425-3-301KTR TT T 1 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 51425

CU PHASE TITLE: A/C PLANT #5 (T & OP) - KTR

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 2

ES01NPNW * ES01NPNX * ES01NPNY * ES01NPNZ * ES01NPP0 * ES01NPP1 * ES01NPFP * ES01NPFN * ES01NPFK *

ES01NPFF * ES01NPFG * ES01NPFH * ES01NPFJ * ES01NPFL * ES01NPFM * EA05L094

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

ENOMOTO, DAISUKE 246.2 3152437296 14-AUG-2024

APPROVED BY: CODE: PHONE: DATE:

HIGA, RILEY 246.2 3152432291 26-AUG-2024

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EA05-L094 * ES01-NPFF * ES01-NPFG * ES01-NPFH * ES01-NPFJ * ES01-NPFK * ES01-NPFL * ES01-NPFM * ES01-NPFN *

ES01-NPFP * ES01-NPNW * ES01-NPNX * ES01-NPNY * ES01-NPNZ * ES01-NPP0

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

142A0003

Operational Test for A/C Plant #5 - KTR.

TGI Short Form

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

29-AUG-2024 0927

20.14.15.0.8998 (August 2024) (Continued) ICN: 3819P14203 KeyOp: T03

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 51425-3-301KTR TT T 1 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 51425

CU PHASE TITLE: A/C PLANT #5 (T & OP) - KTR

FOUO Pg 2 of 2

JCNs (Cont.):

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 TP 51425-3-301KTR AC PLANT #5 (T & OP) - KTR LAT Y

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

(V) Contractor work:

Accomplish/document the tightness & operational test in accordance with reference, TP 51425-3-301KTR.

22/KE PC N

(G) QA work:

Accomplish/document the tightness & operational test in accordance with reference, TP 51425-3-301KTR.

33/G1 QA N

(S) S/F work:

Accomplish/document the tightness & operational test in accordance with reference, TP 51425-3-301KTR.

/ EA05 N

Test work:

Conduct vibration analysis in accordance with reference, TP 51425-3-

301KTR.

46/J5 JN N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 3819P14203 KEY OP: T03