This is a Task Group Instruction (TGI) for the USS Blue Ridge, detailing a maintenance project to replace the peel and stick nonskid system in the Passage 7-72-2-L area. The work involves replacing approximately 13 square feet of deck plating on the second platform deck, including vertical surfaces up to 6 inches from the deck, located between Frames 72 and 74 on the port side. The project is scheduled for a contractor work period from 7/21/2026 to 10/21/2027, with specific requirements including conforming to MIL-PRF-24667, Type XI, Composition PS for the nonskid deck covering.

The SRF-JRMC (Ship Repair Facility - Japan Regional Maintenance Center) will provide supporting services including crane and rigging, utility services (electrical, low pressure air, water, and steam), safety inspections, gas-free inspections, and quality assurance inspections. The task involves painters, carpenters, and quality assurance personnel, with potential lead hazards noted. The project is part of the naval vessel maintenance program, with detailed specifications outlined in the accompanying sketch (Enclosure-01) showing the precise location and dimensions of the work area.

View the file

Other files

File Type Posted
TGI_3819P59302A01_c1v1.pdf PDF
TGI_3819P14213A01_c0v0.pdf PDF
TGI_3819P14203_T04_c0v0.pdf PDF
TGI_3819P14206T01_c0v0.pdf PDF
TGI_3819P14206T02_c0v0.pdf PDF
TGI_3819P12393_A01_c0v0.pdf PDF
TGI_3819P12357_T01_c0v0.pdf PDF
TGI_3819P12341A01_c0v0.pdf PDF
TGI_3819P12340A01_c1v0.pdf PDF
TGI_3819P12336A01_c0v0.pdf PDF
TGI_3819P12312A01_c0v0.pdf PDF
TGI_3819P12305A01_c0v0.pdf PDF
TGI_3819P13506A01_c0v0.pdf PDF
TGI_3819P14203_A01_c2v1.pdf PDF
2.03 Solicitation N6264925RA0210002.pdf PDF
TGI_3819P14212A01_c0v0.pdf PDF
TGI_3819P14215A01_c0v0.pdf PDF
TGI_3819P51404A01_c0v0.pdf PDF
TGI_3819P14206T03_c0v0.pdf PDF
TGI_3819P12387A01_c0v1.pdf PDF
TGI_3819P14206A01_c0v2.pdf PDF
TGI_3819P12364A01_c0v0.pdf PDF
TGI_3819P13506A01_c0v0.pdf PDF
TGI_3819P14203_T04_c0v0.pdf PDF
TGI_3819P12321A01_c1v1.pdf PDF
TGI_3819P12342A01_c0v0.pdf PDF
TGI_3819P12336A01_c0v0.pdf PDF
TGI_3819P12320A01_c0v0.pdf PDF
TGI_3819P12354A01.pdf PDF
TGI_3819P12305A01_c0v0.pdf PDF
Attachment IV RFI (fillable).pdf PDF
TGI_3819P14211A01_c0v0.pdf PDF
TGI_3819P14214A01_c0v0.pdf PDF
TGI_3819P16729A02_c0v1.pdf PDF
TGI_3819P51405A01_c0v0.pdf PDF
TGI_3819P51401A01_c1v2.pdf PDF
TGI_3819P12388A01_c1v1.pdf PDF
TGI_3819P12393_A01_c0v0.pdf PDF
TGI_3819P14203_T01_c0v0.pdf PDF
TGI_3819P12318A01_c2v3.pdf PDF
TGI_3819P12335A01_c1v0.pdf PDF
TGI_3819P12357_A01_c0v0.pdf PDF
TGI_3819P12357_T01_c0v0.pdf PDF
TGI_3819P12340A01_c1v0.pdf PDF
TGI_3819P12323A01_c1v1.pdf PDF
TGI_3819P12341A01_c0v0.pdf PDF
TGI_3819P12312A01_c0v0.pdf PDF
Attachment VII Warranty Tracking Information.pdf PDF
Attachment IV RFI.docx DOCX document
Attachment III TYCOM1_GFP_List_V3.xlsx XLSX spreadsheet
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

20-AUG-2024 1015

20.14.12.0.8874 (April 2024) ICN: 3819P14215 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 7-72-2-L DC A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 64511

CU PHASE TITLE: *F/O - REPLACE PEEL AND STICK NONSKID SYSTEM IN 7-72-2-L

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 3

ES01NPJB

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

HAGA, MASAMICHI 231B 3152432513 06-APR-2024

APPROVED BY: CODE: PHONE: DATE:

NAKANO, SEIICHI 231B 3152434519 06-APR-2024

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

ES01-NPJB

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE 7-72-2-L 7 U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

142A0015

1 SCOPE/PURPOSE:

1.1 Title: Peel and Stick Nonskid System in 7-72-2-L; replace

1.2 Location of Work:

1.2.1 Passage (7-72-2-L)

1.3 Identification:

1.3.1 Quantity (13 SF), Second Platform Deck Plating in 7-72-2-L, Frames between 72 and 74, including vertical surface up to height of 6 inches from deck in and around peel and stick deck covering area, Port

Remarks: See Sketch Enclosure-01 for location detail

1.4 Security Classification: None.

TGI Short Form

20-AUG-2024 1015

20.14.12.0.8874 (April 2024) (Continued) ICN: 3819P14215 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 7-72-2-L DC A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 64511

CU PHASE TITLE: *F/O - REPLACE PEEL AND STICK NONSKID SYSTEM IN 7-72-2-L

FOUO Pg 2 of 3

CU PHASE DESCRIPTION (Cont.)

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1.5 Initial Condition:

1.5.1 Potential Lead Hazard.

1.6 Contractor work start date: 7/21/2026

1.7 Contractor work completion date: 10/21/2027

2. PROCEDURE:

2.1 Accomplish the requirements of 009-32 of Ref. No. One, including Table 2, Line(s) 25, for each area listed in 1.3.1.

2.1.1 Accomplish the requirements of 009-26 of Ref No. One, including Attachment G, for installation of new peel and stick nonskid deck covering. Application of peel and stick nonskid deck covering must conform to MIL-PRF-24667, Type XI, Composition PS.

2.2 Notes:

2.2.1 Planner: Code 231B M. Haga, 243-2513

2.2.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598

2.2.3 JCN ES01-NPJB is related to this TGI.

2.3 Government Furnished Material (GFM): None.

2.4 SRF-JRMC will provide the following service work: (TGI No. 3819P14215S02)

2.4.1 [C740] Crane and crane rigging service.

2.4.2 [X99E] Utility service, electrical.

2.4.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.

2.4.4 [C106.1] Safety inspection for SRF-JRMC employees.

2.4.5 [C106.2] Gas free inspection for SRF-JRMC employees.

2.4.6 [C133] QA inspection for (G) symbol(s).

20-AUG-2024 1015

20.14.12.0.8874 (April 2024) (Continued) ICN: 3819P14215 KeyOp: A01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: CMPT 7-72-2-L DC A 0 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 64511

CU PHASE TITLE: *F/O - REPLACE PEEL AND STICK NONSKID SYSTEM IN 7-72-2-L

FOUO Pg 3 of 3

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

2.1 PNTR HRs, CARP HRs, QA HRs 22/KE PC N

CFM for all paints, peel and stick nonskid, thinner, sampler/analyze lead, and misc such as covering materials, and other consumables.

22/MQ CS N

Process Funding Document. 10/CT OM N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

ATTACHMENT LIST

TITLE FILE NAME SAVED DATE

ENCLOSURE-01 3819P14215A01-Sketch.pdf 07-MAR-2024 0000

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 3819P14215 KEY OP: A01

Sketch

3819P14215A01 ENCLOSURE-01 Sheet 1 of 2

DETAIL 2-A

Sketch

3819P14215A01 ENCLOSURE-01 Sheet 2 of 2

DETAIL PLAN VIEW 2-A

PASSAGE 7-72-2-L

8”

24”

20”

FR 72 BHD 73.5

24”

FR 73