CUI C03.0 Answer to Bidder's Questions 014.pdf
PDF 155 KB Posted
- Attached to
- USS Jacksonville Non-SUBSAFE Repair Work
- Solicitation number
- N4523A21R0800
About this file
This document contains a request for clarification and responses regarding a solicitation for non-SUBSAFE repair work on the USS Jacksonville. The solicitation seeks a firm-fixed price contract to perform non-SUBSAFE welding, interference removals including cabling and sound damping tile, blanking of main ballast tanks and exterior tanks. Work will be derived from document PSNS&IMF100-8779866 Rev - and performed at Puget Sound Naval Shipyard following NAVSEA, SUBMEPP and MIL-STD standards. The period of performance is from September 1, 2021 to December 20, 2021. Bidders' questions are due by April 21, 2021 and the government anticipates awarding a contract in August 2021 to the lowest priced technically acceptable offeror in accordance with FAR 15.101-2. All offerors must be registered in the System for Award Management to receive award.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR CLARIFICATION
N4523A21R0800 USS Jacksonville Blanking Attachment J-7
DATE OF REQUEST: QUESTION NO:
REQUIREMENT: USS Jacksonville Blanking REQUISITION NO.: N4523A21R0800
ITEM NO:
TITLE: Detailed Basis of Estimates PSNS&IMF CONTRACTS POC & PHONE:
See POCs listed on RFP.
PARA. NO: PAGE NO:
PLANNER’S NAME: ATTACH. NO:
CONTRACTOR QUESTION: (ONE QUESTION PER PAGE)
DO NOT WRITE BELOW THIS LINE
SPEC CHG: Y/N DWG/REF CHG. Y/N RQMTS CHG: Y/N MAT'L CHG: Y/N
TECHNICAL REVIEW: SERIAL NO:
ALL BIDDER’S QUESTIONS MUST BE RECEIVED NO LATER THAN 12:00 P.M.
(PST),
21 April 2021
| ITEM NO: N/A |
| PARA NO: L.3.D |
| PAGE NO: 41 |
| CONTRACTOR QUESTION ONE QUESTION PER PAGE: Request clarification regarding the location of the Detailed Basis of Estimate identified in Para L.3.D (Page 41) of the solicitation. The preceding paragraphs spoke specifically to the requirements for completing Attachment J-4 (pricing workbook), but a tab for a Detailed Basis of Estimates is not included in the J-4 spreadsheet posted to beta.sam. Does the Government intend to revise J-4, should offerers add an additional tab to the Excel file, or should all underlying assumptions with respect to the technical aspects of the work to be performed be included in the Cover Letter? |
| TECHNICAL REVIEW: Anna Lewis |
| SERIAL NO: |
| ALL BIDDERS QUESTIONS MUST BE RECEIVED NO LATER THAN 1200 PM: The government does not intend to revise the J-4 pricing workbook attachment. Please include basis of estimate's and supporting information in the volume III cover letter. |
Amendment 0004 to the N4523A21R0800 solicitation has increased the page limit (outlined in the table on page 36) for the volume III cover letter from 2 pages to 50 pages to accommodate this.
| Name 1: |
| Date: 4/14/21 |
| Text3: N |
| Text4: N |
| Text5: Y |
| Text6: N |