CUI C03.0 Answer to Bidder's Questions 013.pdf
PDF 154 KB Posted
- Attached to
- USS Jacksonville Non-SUBSAFE Repair Work
- Solicitation number
- N4523A21R0800
About this file
This document contains a federal solicitation and related questions and answers file. The solicitation seeks non-SUBSAFE repair work including pipe and structural welding, interference removals, blanking of main ballast tanks and exterior tanks aboard the USS Jacksonville. The work will be performed at Puget Sound Naval Shipyard and Intermediate Maintenance Facility in Bremerton, Washington from September 1, 2021 to December 20, 2021. Questions from prospective offerors were due by April 21, 2021, with the Navy intending to award a firm-fixed-price contract in August 2021 to the responsible contractor with the lowest price and technically acceptable proposal. Offerors must be registered in the System for Award Management to receive award.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR CLARIFICATION
N4523A21R0800 USS Jacksonville Blanking Attachment J-7
DATE OF REQUEST: QUESTION NO:
REQUIREMENT: USS Jacksonville Blanking REQUISITION NO.: N4523A21R0800
ITEM NO:
TITLE: Small Bus SubK PSNS&IMF CONTRACTS POC & PHONE:
See POCs listed on RFP.
PARA. NO: PAGE NO:
PLANNER’S NAME: ATTACH. NO:
CONTRACTOR QUESTION: (ONE QUESTION PER PAGE)
DO NOT WRITE BELOW THIS LINE
SPEC CHG: Y/N DWG/REF CHG. Y/N RQMTS CHG: Y/N MAT'L CHG: Y/N
TECHNICAL REVIEW: SERIAL NO:
ALL BIDDER’S QUESTIONS MUST BE RECEIVED NO LATER THAN 12:00 P.M.
(PST),
21 April 2021
| ITEM NO: |
| PARA NO: L.1.b.8 |
| PAGE NO: 37 |
| CONTRACTOR QUESTION ONE QUESTION PER PAGE: Request clarification regarding location of the Small Business Subcontracting Plan. The table following Para L.1.b.6 identifies it was a part of Volume III, Section 4. Para L.1.b.8, however, identifies that it should be included in Volume 1. |
Request clarification regarding where the Small Business Subcontracting Plan should be included in the proposal.
Additionally, if it belongs Volume I, should offerers exclude pricing and only provide percentages?
| TECHNICAL REVIEW: |
| SERIAL NO: |
| ALL BIDDERS QUESTIONS MUST BE RECEIVED NO LATER THAN 1200 PM: The Small Business Subcontracting Plan shall be included in Volume III as stated in the table in section L on page 37 of the solicitation. |
Amendment 0004 to the N4523A21R0800 solicitation updates paragraph L.1.b.8 to match the table.