This document contains a request for clarification regarding a solicitation for non-SUBSAFE repair work on the USS Jacksonville. The solicitation seeks a firm-fixed price contract to perform non-SUBSAFE welding, interference removals including cabling and sound damping tile, blanking of main ballast tanks and exterior tanks at Puget Sound Naval Shipyard. The work will be derived from document PSNS&IMF100-8779866 and is to adhere to NAVSEA standard items, SUBMEPP standards and MIL-STD-1689A for fabrication, welding and inspection. Sound damping tile inspection and removal is included, with reinstallation to be performed by the shipyard. The period of performance is from September 1, 2021 to December 20, 2021. The Navy intends to award the contract in August 2021 to the responsible contractor with the lowest price technically acceptable proposal.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR CLARIFICATION
N4523A21R0800 USS Jacksonville Blanking Attachment J-7
DATE OF REQUEST:
REQUIREMENT: USS Jacksonville Blanking
QUESTION NO: 010
REQUISITION NO.: N4523A21R0800
ITEM NO:
TITLE: Main Ballast Tank (MBT) 2 electrical interference; remove
PSNS&IMF CONTRACTS POC & PHONE:
See POCs listed on RFP.
PARA. NO: PAGE NO:
PLANNER’S NAME: ATTACH. NO:
CONTRACTOR QUESTION: (ONE QUESTION PER PAGE)
DO NOT WRITE BELOW THIS LINE
SPEC CHG: Y/N DWG/REF CHG. Y/N RQMTS CHG: Y/N MAT'L CHG: Y/N
TECHNICAL REVIEW: SERIAL NO:
ALL BIDDER’S QUESTIONS MUST BE RECEIVED NO LATER THAN 12:00 P.M.
(PST),
21 April 2021
| ITEM NO: 123-01-002 |
| PARA NO: 3.3 |
| PAGE NO: 2 & 3 |
| CONTRACTOR QUESTION ONE QUESTION PER PAGE: Paragraph 3.3 Directs "Remove interferences identified in paragraph 1.3.4 and 1.3.5 for locations listed in 1.2.1". Paragraph 1.2.1 is MBT 2A. Paragraph 1.3.4 & 1.3.5 are located in MBT 2B which is 1.2.2. Also, Paragraph 3.4 also directs removal of interferences in 1.3.5. |
Recommend issue errata to correct 3.3 to remove reference to 1.3.5 and correct location to 1.2.2.
| TECHNICAL REVIEW: Anna Lewis |
| SERIAL NO: |
| ALL BIDDERS QUESTIONS MUST BE RECEIVED NO LATER THAN 1200 PM: See errata 4 for corrections. |
| Date: 4/14/21 |
| Text3: Y |
| Text4: N |
| Text5: Y |
| Text6: N |