CUI C03.0 Answer to Bidder's Questions 009.pdf
PDF 158 KB Posted
- Attached to
- USS Jacksonville Non-SUBSAFE Repair Work
- Solicitation number
- N4523A21R0800
About this file
This document contains a federal contract solicitation for non-SUBSAFE repair work on the USS Jacksonville. The solicitation is seeking proposals for a firm-fixed-price contract to perform non-SUBSAFE pipe and structural welding, interference removals including cabling and sound damping tile removal, and blanking of main ballast tanks and exterior tanks. The work will be performed at Puget Sound Naval Shipyard and Intermediate Maintenance Facility in Bremerton, Washington according to provided specifications and standards. The period of performance is from September 1, 2021 to December 20, 2021. Proposals are due by August 2021 and award will be made to the responsible offeror with the lowest price using a technically acceptable basis and in accordance with the Federal Acquisition Regulation.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR CLARIFICATION
N4523A21R0800 USS Jacksonville Blanking Attachment J-7
DATE OF REQUEST:
REQUIREMENT: USS Jacksonville Blanking
QUESTION NO: 013
REQUISITION NO.: N4523A21R0800
ITEM NO:
TITLE: Main Ballast Tank (MBT) 2A; welded cap install
PSNS&IMF CONTRACTS POC & PHONE:
See POCs listed on RFP.
PARA. NO: PAGE NO:
PLANNER’S NAME: ATTACH. NO:
CONTRACTOR QUESTION: (ONE QUESTION PER PAGE)
DO NOT WRITE BELOW THIS LINE
SPEC CHG: Y/N DWG/REF CHG. Y/N RQMTS CHG: Y/N MAT'L CHG: Y/N
TECHNICAL REVIEW: SERIAL NO:
ALL BIDDER’S QUESTIONS MUST BE RECEIVED NO LATER THAN 12:00 P.M.
(PST),
21 April 2021
| ITEM NO: 123-10-003 |
| PARA NO: 4.1 |
| PAGE NO: 2 |
| CONTRACTOR QUESTION ONE QUESTION PER PAGE: Paragraph 4.1 notes "Pipe P-11D has a 1/4" low point drain hole". Pipe P-11D is not affected by this WI. The pipe affected by this WI is P14S. |
Recommend issuing errata to correct.
| TECHNICAL REVIEW: Anna Lewis |
| SERIAL NO: |
| ALL BIDDERS QUESTIONS MUST BE RECEIVED NO LATER THAN 1200 PM: Pipe P14S is the correct pipe and will the spec will be updated on errata 4. |
| Date: 4/15/21 |
| Text3: Y |
| Text4: N |
| Text5: Y |
| Text6: N |