This document contains a request for clarification and government responses regarding a solicitation for non-SUBSAFE repair work on the USS Jacksonville. The solicitation seeks a firm-fixed price contract to perform non-SUBSAFE welding, interference removals including cabling and sound damping tile, blanking of main ballast tanks and exterior tanks. The work will be performed at Puget Sound Naval Shipyard and Intermediate Maintenance Facility in Bremerton, Washington according to provided standards and quality requirements. The period of performance is from September 1, 2021 to December 20, 2021. The government intends to award the contract to the responsible offeror submitting the lowest priced, technically acceptable proposal in accordance with Federal Acquisition Regulation Part 15.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR CLARIFICATION
N4523A21R0800 USS Jacksonville Blanking Attachment J-7
DATE OF REQUEST:
REQUIREMENT: USS Jacksonville Blanking
QUESTION NO: 006
REQUISITION NO.: N4523A21R0800
ITEM NO:
TITLE: Contractor Facilities, provide
PSNS&IMF CONTRACTS POC & PHONE:
See POCs listed on RFP.
PARA. NO: PAGE NO:
PLANNER’S NAME: ATTACH. NO:
CONTRACTOR QUESTION: (ONE QUESTION PER PAGE)
DO NOT WRITE BELOW THIS LINE
SPEC CHG: Y/N DWG/REF CHG. Y/N RQMTS CHG: Y/N MAT'L CHG: Y/N
SERIAL NO:
ALL BIDDER’S QUESTIONS MUST BE RECEIVED NO LATER THAN 12:00 P.M.
(PST),
14 April 2021
| ITEM NO: 992-10-001 |
| PARA NO: 3.1.2 |
| PAGE NO: 1 |
| CONTRACTOR QUESTION ONE QUESTION PER PAGE: Government Response 002 requested dimensions of area provided for contractor use to determine maximum office size that could be used. The response referred to the paragraphs 3.4.5, 3.4.6, and 3.4.7. 3.4.5 referred to the lay down area in the dry-dock and 3.4.7 is the provided covered hot work area neither of which are an appropriate location for an office. 3.4.6 is the 400 SF lay down area on the pier. Is it governments intention that the KTR lay down area be used for the office as well? If so, what are the dimensions (L x W) of the lay down area for determination of usable office sizes. Otherwise, what are the dimensions (L x W) of the area reserved for the office trailers. |
| SERIAL NO: |
| ALL BIDDERS QUESTIONS MUST BE RECEIVED NO LATER THAN 1200 PM: There will be a 400 SF (20x20) area on the pier for the contractor. This was to allow for 10x20 stackable office trailers, the 8x10 conex box tool room and whatever else the contractor can fit in the space allotted. |