About this file

This document is a Pre-Proposal Inquiries table for Solicitation N40192-25-R-9006, a Job Order Contract (JOC) for Naval Facilities Engineering Systems Command Marianas (NAVFACMAR). The solicitation covers construction and design services at various locations within NAVFACMAR's area of responsibility. The document contains three pre-proposal inquiries addressing key RFP details: (1) project submission requirements for demonstrating facilities maintenance/construction and design experience, (2) clarification on project completion date recency, and (3) Cybersecurity Maturity Model Certification (CMMC) implementation details. The government responses indicate that separate project data sheets are required for construction and design experiences, ongoing projects may be referenced with caveats, and CMMC certification levels will be implemented between 2025-2028, with specific requirements for Blue and Gold JOC contracts.

View the file

Other files

File Type Posted
Exhibit A_PPI Response Notice 4.pdf PDF
Attachment F_Coefficient Cost Breakdown_blank_rev1.xlsx XLSX spreadsheet
Attachment G_Table 3. Sample Coefficient Breakdown_rev1.pdf PDF
Attachment K - Section 01 00 00 - General Requirements (Continuation)_rev2.pdf PDF
N4019225R9006_Amd 0005.pdf PDF
Exhibit A_PPI Response Notice 3.pdf PDF
N4019225R9006_Amd 0004.pdf PDF
Attachment D - Table 1. Sample ELIN Price Schedule - Blue_rev1.pdf PDF
Attachment E - Table 1. Sample ELIN Price Schedule - Gold_rev1.pdf PDF
N4019225R9006_Amd 0003.pdf PDF
Exhibit A_PPI Response Notice 2.pdf PDF
N4019225R9006_Amd 0002.pdf PDF
Attachment J_JOC Construction and Design Specifications (Technical RFP)_rev1_28AUG25.pdf PDF
N4019225R9006_Amd 0001.pdf PDF
Attachment K - Section 01 00 00 - General Requirements (Continuation)_rev1.pdf PDF
Attachment C_Price Proposal Schedule.xlsx XLSX spreadsheet
Attachment D - Table 1. Sample ELIN Price Schedule - Blue.pdf PDF
Attachment F_Coefficient Cost Breakdown_blank.xlsx XLSX spreadsheet
Attachment I_Past Performance Questionnaire (PPQ).docx DOCX document
Attachment J_JOC Construction and Design Specifications (Technical RFP)_19JUN25.pdf PDF
N4019225R9006 JOC Solicitation.pdf PDF
Attachment B_PPI Tracker.xlsx XLSX spreadsheet
Attachment G_Table 3. Sample Coefficient Breakdown.pdf PDF
Attachment H_Facilities Maintenance Construction Design Experience Project Data Sheet.docx DOCX document
Attachment E - Table 2. Sample ELIN Price Schedule - Gold.pdf PDF
Attachment K_Section 01 00 00 - General Requirements (Continuation).pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP / SF 1442 SECTION SECTION TOPIC/TITLE PARAGRAPH PAGE

ITEM

DESCRIPTION/TO

PIC

1 08/27/25 Completed N4019225R9006_JOC_S olicitation

Section 00 21

Factor 2 - Experience

1. Facilities Maintenance / Construction Experience AND 2. Design Experience

13 & 14 Project submission

The Government states "If the same project is being used to demonstrate construction and design experience, submit separate Project Data Sheets for facilities maintenance / construction and design." Can the Government confirm that we are able to submit the same project for both 1.

Facilities Maintenance / Construction Design and 2. Design Experience.

Refer to submittal requirements as described in Factor 2 - Experience, paragraphs Facilities Maintenance/Construction Recency and Design Project Recency of the RFP.

0002 1

2 08/27/25 Completed N4019225R9006_JOC_S olicitation

Section 00 21

Factor 2 - Experience

13 & 14 The Government states that the "completion date was reached within the five (5) years immediately preceding the proposal due date." Can we reference on-going projects?

Refer to submittal requirements as described in Factor 2 - Experience, paragraphs 1. Facilities Maintenance/Construction Experience, Facilities Maintenance/Construction Recency, 2. Design Experience, and Design Project Recency of the RFP.

0002 1

3 08/27/25 Completed General Question The Government expects to implement CMMC into the Federal Acquisition Regulations as early as Oct 2025, given that CMMC has already been made a rule and a part of the Federal Register, and with full enforcement beginning between 2026 and 2028 for given certification levels. Advise if and when CMMC requirements will become part of the contract (if awarded), and advise which certification levels will be required for the Blue JOC and which certification levels will be required for the Gold JOC?

Via solicitation Amendment 0002, DFARS 252.204-7021, Contractor Compliance With the Cybersecurity Maturity Model Certification Level Requirement is removed as per Class Deviation 2025-O0006 signed 25 August 2025.

0002 1

QUESTION/COMMENT

RFP AMEND

PPI # PER

NOTICE

GOVERNMENT RESPONSE

PRE-PROPOSAL INQUIRIES RECEIVED IN RESPONSE TO SOLICITATION N40192-25-R-9006

JOB ORDER CONTRACT (JOC) at various locations to support Naval Facilities Engineering Systems Command Marianas’s (NAVFACMAR) area of responsibility (AOR)

RFI #

DATE

SUBMITTED

STATUS

(Completed/P ending)

REFERENCE

EXHIBIT A