About this file

This document is an Attachment G Coefficient Breakdown Sheet - Sample, which provides a detailed cost breakdown for multiple project locations (Primary, Secondary, and Tertiary). The document shows pre-priced and non-pre-priced costs for each location, with consistent cost structures across ELIN A0001/A0002 (Primary Location), ELIN A0005/A0006 (Secondary Location), and ELIN A0009/A0010 (Tertiary Location). Each location has a bare cost of $4,000,000.00 with standardized percentage allocations for direct costs including Worker's Compensation Insurance (15%), Average Fixed Labor (16%), Project Overhead (8% for pre-priced, 18% for non-pre-priced), and Material/Equipment Mark-up (5%). Other costs include General & Administrative expenses (8%) and Profit (5%). The pre-priced coefficient is consistently 1.147, while the non-pre-priced coefficient is 1.282 across all locations, indicating a structured pricing model with predictable cost multipliers.

View the file

Other files

File Type Posted
N4019225R9006_Amd 0005.pdf PDF
Exhibit A_PPI Response Notice 4.pdf PDF
Attachment F_Coefficient Cost Breakdown_blank_rev1.xlsx XLSX spreadsheet
Attachment K - Section 01 00 00 - General Requirements (Continuation)_rev2.pdf PDF
Attachment E - Table 1. Sample ELIN Price Schedule - Gold_rev1.pdf PDF
Exhibit A_PPI Response Notice 3.pdf PDF
N4019225R9006_Amd 0004.pdf PDF
Attachment D - Table 1. Sample ELIN Price Schedule - Blue_rev1.pdf PDF
N4019225R9006_Amd 0003.pdf PDF
Exhibit A_PPI Response Notice 2.pdf PDF
N4019225R9006_Amd 0002.pdf PDF
Exhibit A_PPI Response Notice 1.pdf PDF
Attachment J_JOC Construction and Design Specifications (Technical RFP)_rev1_28AUG25.pdf PDF
N4019225R9006_Amd 0001.pdf PDF
Attachment K - Section 01 00 00 - General Requirements (Continuation)_rev1.pdf PDF
Attachment E - Table 2. Sample ELIN Price Schedule - Gold.pdf PDF
Attachment K_Section 01 00 00 - General Requirements (Continuation).pdf PDF
Attachment C_Price Proposal Schedule.xlsx XLSX spreadsheet
Attachment D - Table 1. Sample ELIN Price Schedule - Blue.pdf PDF
Attachment F_Coefficient Cost Breakdown_blank.xlsx XLSX spreadsheet
Attachment I_Past Performance Questionnaire (PPQ).docx DOCX document
Attachment J_JOC Construction and Design Specifications (Technical RFP)_19JUN25.pdf PDF
N4019225R9006 JOC Solicitation.pdf PDF
Attachment B_PPI Tracker.xlsx XLSX spreadsheet
Attachment G_Table 3. Sample Coefficient Breakdown.pdf PDF
Attachment H_Facilities Maintenance Construction Design Experience Project Data Sheet.docx DOCX document
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ELIN A0001 - Primary Location Pre-Priced Costs Materials Labor Equipment Amount

RS Means Bare Cost

(Presumed Annual Amount) $2,520,000.00 $1,400,000.00 $80,000.00 $4,000,000.00

DIRECT COSTS

Worker's Compensation Insurance 15% $210,000.00

Average Fixed Labor 16% $224,000.00

Project Overhead Pre-Priced 8% $112,000.00

Material Mark-up 5% $126,000.00

Equipment Mark-up 5% $4,000.00

City Cost Index (CCI) $0.00

SUBTOTAL $676,000.00

OTHER COSTS

General & Administrative 8% $112,000.00

Profit 5% 5% 5% $200,000.00

SUBTOTAL OTHER COSTS $312,000.00

TOTAL DIRECT & OTHER COSTS $988,000.00

Coefficient Factor 0.247

RS Means Bare Cost (Production/Discount - Factor) 0.900

PRE-PRICE COEFFICIENT 1.147

ELIN A0002 - Primary Location Non Pre-Priced Costs Materials Labor Equipment Amount

Non Pre-Priced Bare Costs

(Presumed Annual Amount) $252,000.00 $140,000.00 $8,000.00 $400,000.00

Worker's Compensation Insurance 15% $21,000.00

Average Fixed Labor 16% $22,400.00

Project Overhead Non Pre-Priced 18% $25,200.00

Material Mark-up 5% $12,600.00

Equipment Mark-up 5% $400.00

$0.00

SUBTOTAL $81,600.00

OTHER COSTS

General & Administrative 8% $11,200.00

Profit 5% 5% 5% $20,000.00

SUBTOTAL OTHER COSTS $31,200.00

TOTAL DIRECT & OTHER COSTS $112,800.00

BARE COST $400,000.00

NON PRE-PRICE COEFFICIENT 1.282

Attachment G

Coefficient Breakdown Sheet - SAMPLE

ELIN A0005 - Secondary Location Pre-Priced Costs Materials Labor Equipment Amount

RS Means Bare Cost

(Presumed Annual Amount) $2,520,000.00 $1,400,000.00 $80,000.00 $4,000,000.00

DIRECT COSTS

Worker's Compensation Insurance 15% $210,000.00

Average Fixed Labor 16% $224,000.00

Project Overhead Pre-Priced 8% $112,000.00

Material Mark-up 5% $126,000.00

Equipment Mark-up 5% $4,000.00

City Cost Index (CCI) $0.00

SUBTOTAL $676,000.00

OTHER COSTS

General & Administrative 8% $112,000.00

Profit 5% 5% 5% $200,000.00

SUBTOTAL OTHER COSTS $312,000.00

TOTAL DIRECT & OTHER COSTS $988,000.00

Coefficient Factor 0.247

RS Means Bare Cost (Production/Discount - Factor) 0.900

PRE-PRICE COEFFICIENT 1.147

ELIN A0006 - Secondary Location Non Pre-Priced Costs Materials Labor Equipment Amount

Non Pre-Priced Bare Costs

(Presumed Annual Amount) $252,000.00 $140,000.00 $8,000.00 $400,000.00

Worker's Compensation Insurance 15% $21,000.00

Average Fixed Labor 16% $22,400.00

Project Overhead Non Pre-Priced 18% $25,200.00

Material Mark-up 5% $12,600.00

Equipment Mark-up 5% $400.00

$0.00

SUBTOTAL $81,600.00

OTHER COSTS

General & Administrative 8% $11,200.00

Profit 5% 5% 5% $20,000.00

SUBTOTAL OTHER COSTS $31,200.00

TOTAL DIRECT & OTHER COSTS $112,800.00

BARE COST $400,000.00

NON PRE-PRICE COEFFICIENT 1.282

ELIN A0009 - Tertiary Location Pre-Priced Costs Materials Labor Equipment Amount

RS Means Bare Cost

(Presumed Annual Amount) $2,520,000.00 $1,400,000.00 $80,000.00 $4,000,000.00

DIRECT COSTS

Worker's Compensation Insurance 15% $210,000.00

Average Fixed Labor 16% $224,000.00

Project Overhead Pre-Priced 8% $112,000.00

Material Mark-up 5% $126,000.00

Equipment Mark-up 5% $4,000.00

City Cost Index (CCI) $0.00

SUBTOTAL $676,000.00

OTHER COSTS

General & Administrative 8% $112,000.00

Profit 5% 5% 5% $200,000.00

SUBTOTAL OTHER COSTS $312,000.00

TOTAL DIRECT & OTHER COSTS $988,000.00

Coefficient Factor 0.247

RS Means Bare Cost (Production/Discount - Factor) 0.900

PRE-PRICE COEFFICIENT 1.147

ELIN A0010 - Tertiary Location Non Pre-Priced Costs Materials Labor Equipment Amount

Non Pre-Priced Bare Costs

(Presumed Annual Amount) $252,000.00 $140,000.00 $8,000.00 $400,000.00

Worker's Compensation Insurance 15% $21,000.00

Average Fixed Labor 16% $22,400.00

Project Overhead Non Pre-Priced 18% $25,200.00

Material Mark-up 5% $12,600.00

Equipment Mark-up 5% $400.00

$0.00

SUBTOTAL $81,600.00

OTHER COSTS

General & Administrative 8% $11,200.00

Profit 5% 5% 5% $20,000.00

SUBTOTAL OTHER COSTS $31,200.00

TOTAL DIRECT & OTHER COSTS $112,800.00

BARE COST $400,000.00

NON PRE-PRICE COEFFICIENT 1.282

File details come from the government source that posted it. Updated .