This document is a Questions and Answers (Q&A) file from a federal construction contract solicitation for MCB Camp Lejeune, submitted between June 12, 2026, and June 30, 2026.

The project involves design-bid-build construction of multiple buildings and site work at Stone Bay, MCB Camp Lejeune, North Carolina. Key requirements include: liquidated damages of $12,750.08 per day; QC specialists employed by the prime contractor (not subcontractors); no desired phasing—all four projects must be turned over simultaneously; MARSOC compound access requiring secondary security processing with employee rosters submitted to NAVFAC Construction Manager; RRR training required due to known UXO sites; no archaeology oversight unless artifacts are discovered; no geotechnical report will be provided; and bidders must assume offsite disposal at RCRA D facilities for approximately 70,000 tons of non-hazardous surplus soil. Critical environmental considerations include PFAS contamination near the landfill (requiring minimized excavation and dewatering) and tree-cutting moratoriums during April 15–July 31 and December 15–February 15 to protect bats. The Construction Security Plan (CSP) applies project-wide, requiring US persons, daily badging, two-layer fencing with Entry Control Points, prohibited privately-owned vehicles inside the construction fence, and escorted access during final construction phases of the secure Battalion Headquarters facility. Interior Design and audiovisual services require in-person meetings for orientations and presentations but allow virtual "over-the-shoulder" reviews. Air barrier testing is required on multiple buildings. The contractor must provide temporary utilities, all permits except water/sewer/stormwater (government-procured), and infrastructure for Electronic Security Systems while the government provides ESS equipment, cabling, programming, and commissioning. Commissioning and testing costs must not be less than 5 percent of total procurement and construction costs per definable feature of work.

View the file

Other files

File Type Posted
P1550 PPI RESPONSES 5.pdf PDF
AMENDMENT 0010 - N4008526R0138.pdf PDF
AMENDMENT 0009 - N4008526R0138.pdf PDF
AMENDMENT 0008 - N4008526R0138.pdf PDF
WD NC20260010.pdf PDF
1701820 Continuation Sheet_0004.pdf PDF
AMENDMENT 0006- 26R0138.pdf PDF
1701820dwg_Revision_0004_A2.pdf PDF
P1550 PPI RESPONSES 3.pdf PDF
AMENDMENT 0005 - 26R0138.pdf PDF
13 34 19.pdf PDF
1701820 Continuation Sheet.docx DOCX document
AMENDMENT 0004 - 26R0138.pdf PDF
1701820dwg_Revision_0003_A2.pdf PDF
AMENDMENT 0003 - 26R0138.pdf PDF
1701820dwg01of01.pdf PDF
1701820 Continuation Sheet .docx DOCX document
P1550 PPI RESPONSES 2.pdf PDF
08 33 23.pdf PDF
AMENDMENT 0002 - 26R0138.pdf PDF
1701820dwg_Revision_0001_A2-A3-Site.pdf PDF
03 30 00.pdf PDF
P1550 Site Visit Sign-in Sheet.pdf PDF
26 32 15.00.pdf PDF
26 56 00.pdf PDF
1701820 Continuation Sheet 2026.06.04.docx DOCX document
Construction Site Visit MARSOC Access List.xlsx XLSX spreadsheet
AMENDMENT 0001 - 26R0138.pdf PDF
Attachment C - Price Proposal Form REVISED.docx DOCX document
P1550 PPI RESPONSES 1.pdf PDF
Attachment I - DOD-CUI_Non-Disclosure Agreement.pdf PDF
Attachment D - Construction and Design Experience Project Data Sheet.docx DOCX document
Attachment G - SPCD.docx DOCX document
Solicitation - N4008526R0138.pdf PDF
1701820 A1 - FINAL_1.pdf PDF
1701820 A2 - FINAL_2.pdf PDF
1701820 A3 - FINAL_3.pdf PDF
1701820 SPC -FINAL.pdf PDF
1701820 SITE - FINAL_v2_4 Flattened 1 of 2.pdf PDF
Attachment E - Past Performance Questionnaire.pdf PDF
Attachment C - Price Proposal Form.docx DOCX document
Attachment A - Pre-Proposal Inquiry (PPI) Log.xlsx XLSX spreadsheet
1701820 SITE - FINAL_v2_4 Flattened 2 of 2.pdf PDF
Attachment B - PIEE Vendor Access Instructions.pdf PDF
Attachment H -Small Business Subcontracting Plan.docx DOCX document
Attachment F - Historical Small Business Utilization.docx DOCX document
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date Submitted

Reference Question Response

Page Section Paragraph

6/12/2026 Solicitation Solicitation does not include the Liquidated Damages daily rate as it notes this will be provided via forthcoming Amendment. Rate was not provided with Amendment

1. Please provide Liquidated Damages daily rate.

$12,750.08/day

6/15/2026 Specifications 01 45 00 1.7 QUALITY CONTROL (QC) SPECIALISTS Provide a separate QC Specialist at the work site for each of the areas as listed in the Matrix listed below, who must assist and report to the QC Manager and who must have no duties other than their assigned quality control duties. These individuals or specialized technical companies are directly employed by the Prime Contractor and cannot be employed by a supplier or subcontractor on this project.

Please consider that these QC specialist be employed by subcontractors and not the Prime Contractor.

Provide the QC specialists as required by the matrix and employed by the Prime

6/16/2026 Solicitation (RFP) & Amend 1

Phasing; is there a desired phasing for this project that we can portray in our solicitation schedule?

No desired phasing specified.

6/16/2026 N/A Will the government accept partial BOD on individual buildings or are all four projects required to be turned over at the same time at the end of construction.

No desired phasing specified.

6/16/2026 01 14 00 1.3.1.2 The installation access is heavily geared toward typical DBIDS processes. There is no additional instructions for special MARSOC access and those protocols. Please provide the pass/tag requirements for secondary MARSOC access.

1. Stone Bay Access (Outer Perimeter): Access to Stone Bay requires a valid Common Access Card (CAC) or a Defense Biometric Identification System (DBIDS) / Business Access Identification Badge obtained in accordance with Section 01 14 00, Paragraph 1.3.1.2.

2. MARSOC Compound Access (Inner Perimeter): Entry requires secondary security processing, where prime contractors must submit the names of their employees and subcontractors using the attached MARSOC access roster (excel spreadsheet) to the NAVFAC Construction Manager, who then forwards the information to the MARSOC Security Office.

Contractors may update the access roster each week if needed, ensuring all changes are submitted by Thursday to enable access the following Monday.

6/16/2026 General Are there any known PFAS conditions that the contractor needs to consider to comply with to achieve this work?

Yes, a known release of PFAS in the vicinity of the work is associated with the landfill (as shown on the existing conditions sheets). The excavations and anticipated dewatering locations must be designed and construced to minimized the generation of surplus soils and the volume of dewatering that requires treatment when working in the vicinity of the Former rifle Range Chemical Dump/Landfill located North of main project site.

6/16/2026 01 14 00 1.5 Are there any known UXO conditions that the contractor needs to consider to comply with to achieve this work?

RRR training is required due to working on MCB Camp Lejeune. A known UXO site is located along the Access Road to the site North of the former P1291 construction site that requires RRR training. No additional requirements for UXO is known.

6/16/2026 CS100,

CS107, CS110

01 57 19 3.4.1 There are several locations marked as Archeological sites, including one that is inside of Areas 10 & 13. 01 57 19 3.4.1 provides language on the archaeological resources which eludes to just doing due diligence. Please confirm that the contractor is required to obtain outside resources for Archeologist support to include reports, studies or monitoring.

Due diligence is required during ground disturbing activities. No archaeology oversight is required (unless an unforseen artifact is identified

- follow instructions within 01 57 19 specification.)

6/16/2026 Site Visit Can the government provide as-builts for the recent previously built projects in the vicinity of this work to include the boat ramp, electrical infrastructure, stormwater controls, road project and fenced in lot.

As-builts for adjacent projects are not part of this soliciation package.

6/16/2026 Site Visit The proposed project site required special gate access to enter. There does not appear to be specification or drawing notes that indicate how this gate will be accessed and what protocols the contractor must abide by for entering / working.

Please provide these stipulations and hours of operation.

The KTR must submit a written request in accordance with Section 01 14 00, Part 1.2.

Once received, the CM and MARSOC Physical Security will allow the KTR to daisy-chain a clearly labeled construction lock on the gate in question. It will be the KTR’s responsibility to maintain security protocols provided by the Government.

6/16/2026 01 32 17.00 20 1.10.1.8 Please confirm that the allowable project duration has been coordinated with the specification requirements, notably 01 32 17.00, 1.10.1.8 Adverse Weather Lost Work Days as the .10 inch mark is an extremely low variable when considering the amount of rainfall averaged in the projects area. For instance under this low value the GC would likely need to plan for 1/3 of the days in multiple months as anticipated lost time via a weather calendar.

Bid per RFP.

6/16/2026 01 32 17.00 20 1.10.1.8 Please indicate the NOAA location closest to the project as multiple locations are within the vicinity of the project.

Bid per RFP.

6/16/2026 01 32 17.00 20 1.10.1.10.1 d.

Under the section it states "The value of commissioning, testing and closeout WBS section may not be less than 10 percent of the total costs for procurement and construction activities." Please confirm that this 10% value only pertains to A.

Subcontracted scope values and B. MEP scope of work.

The value of commissioning, testing and closeout WBS section may not be less than 5 percent of the total costs for procurement and construction activities for that correlating definable feature of work

(DFOW)

6/16/2026 As Required What involvement does the General Contractor have in procuring Civil Permits including but not limited to Utility, Stormwater or Erosion Control permits. Who is responsible for paying the Construction Stormwater Permit Annual Fee?

Water, sewer, stormwater, and erosion/ sedimentation permits will be procured by the government. All other permits and reoccuring annual fees are the responsibility of the contractor.

6/16/2026 01 50 00 3.2.1 Temporary Utilities. The following statement is made in the specifications which is not typical. What is typical is that the GC pays for electrical fees on site. Please confirm. "Reasonable amounts of water and electricity from the nearest outlet will be provided free of charge for pursuance of work within a facility under this contract. If the nearest available outlet cannot be utilized by the Contractor because of improper voltage, insufficient current, improper pressure, incompatible connectors, etc., it shall be the responsibility of the Contractor to provide temporary utilities as required."

There is no known existing water or power source at the P1550 site boundaries, it shall be the responsibility of the Contractor to provide temporary utilities as required.

6/16/2026 N/A Please provide geotechnical report of this project? Geotech report will not be provided, bid per RFP.

6/16/2026 12 00 01.00 20 3.1 The statement "Provide Interior Design FF&E services and deliverables in accordance with FC 1-300-09N, UFC 3-120-10" Is the contractor to include in the base bid A/V design services within base bid price even if, the A/V CLIN Option is not awarded to contractor?

AV requirements are called out in 01 30 02.00 22.

6/16/2026 12 00 01.00 20 3.1.2.1 In order to properly budget travel, is the FF&E Interior Design Orientation Meeting required to be in person?

Yes.

6/16/2026 12 00 01.00 20 3.1.2.2.1 In order to properly budget travel, is the FF&E Interior Design Over the Shoulder Meeting required to be in person?

The "Over the Shoulder" will be held virtually, the Presenation to the Activity will be held in person.

6/16/2026 12 00 01.00 20 3.1.2.7 In order to properly budget travel, is the Pre-Final FF&E and CEQ Packages Submittal Review Meeting required to be in person?

Yes.

6/16/2026 12 00 01.00 20 3.1.2.6 In order to properly budget travel, is the Best Value Determination (BVD) Analysis "Over the Shoulder Review" required to be in person?

This meeting is a review of the results of the responses to each BVD RFQ Package and is virtual.

6/16/2026 01 30 02.00 22 1.4.1 The statement "The AV designer of record, hereafter referred to as the prime contractor's AV designer" Is the contractor to include in the base bid A/V design services within base bid price even if, the A/V CLIN Option is not awarded to contractor?

No.

6/16/2026 01 30 02.00 22 1.5.1 In order to properly budget travel, is the Audiovisual Requirements (AV Design Orientation) Meeting required to be in person?

Yes.

6/16/2026 01 30 02.00 22 1.5.2 In order to properly budget travel, is the AV "Over the Shoulder" Review required to be in person?

No

6/16/2026 01 30 02.00 22 1.5.3 In order to properly budget travel, is the AV "AV Concept Presentation" Review required to be in person?

Yes.

6/16/2026 01 30 02.00 22 1.5.4 In order to properly budget travel, is the AV Best Value Determination (BVD) Analysis "Over the Shoulder Review" required to be in person?

No.

6/16/2026 01 30 02.00 22 Can the Audio-Visual Orientations, Interviews and BVD meetings be in tandem with equivalent FF&E meetings? It is more efficient and generally not a lessor product to have a single design lead run and capture the items via these processes and have a A/V designer in the office complete the technical piece and the bid process.

Yes.

6/16/2026 01 45 00 1.5.12 The schedule of special inspections attached after 01 45 00 notes spray fire resistant materials. Spray fire proofing is not found in the drawings or specs. Please confirm that spray fire proofing and inspection is not required for this project?

The Schedule of Fire Protection System Inspections by FPQC Specialist after Section 01 45 00 does not have the "Verify proper installation of fireproofing" checked and the Scedhule of Special Inspections after Section 01 45 35 does not have the "Fire PRotection - Sprated Fire- Resistant Materiuals Section" checked; therefore, there are no inspection of fireproofing required.

6/16/2026 01 45 00 1.7.1 A Fire Protection Quality Control Specialist is indicated but there is also a Qualified Fire Protection Engineer in Specifications 21 13 13 and 28 31 76. Please verify that the FPQC can be the same entity as the QFPE.

The contractor's FPQC and QFPE are the same entity.

6/16/2026 01 30 00 1.9.1 Facilitated (Formal) Partnering - partnering meetings can carry a sizeable cost to them to book spaces and bring in consultants. F. states "Host follow-on Partnering Sessions at three- to six-month intervals or more frequently if needed and lasting generally a half day or less. Please provide a an estimated amount of these meetings as the specifications can widely fluctuate and this needs to be properly budgeted.

Assume semi-annual partnering for bidding purposes.

6/16/2026 (A1) S-003, A-502

6.0.1 S-003, 6.0.1 lists that "STRUCTURAL METAL STUDS MUST BE COLDFORMED AND OF

MINIMUM AND GAGE AS SHOWN ON THE PLANS - FINAL DESIGN PER DELEGATED

DESIGN ENGINEER. ANY SIZES SHOWN ARE FOR BUDGET PRICING PURPOSES ONLY."

Please indicate how the contractor is to price this scope of work when this is a design bid build project and delegated design cannot be accomplished at this stage.

Is the government going to compensate the contractor for changes between stated sizes/spacing? Further, if the contingency is on the contractor to fill these gaps what is the proposed contingency to be carried since the risk is unknown.

Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

6/16/2026 (A2) S-003, A-502

6.0.1 S-003, 6.0.1 lists that "STRUCTURAL METAL STUDS MUST BE COLDFORMED AND OF

MINIMUM AND GAGE AS SHOWN ON THE PLANS - FINAL DESIGN PER DELEGATED

DESIGN ENGINEER. ANY SIZES SHOWN ARE FOR BUDGET PRICING PURPOSES ONLY."

Please indicate how the contractor is to price this scope of work when this is a design bid build project and delegated design cannot be accomplished at this stage.

Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

Is the government going to compensate the contractor for changes between stated sizes/spacing? Further, if the contingency is on the contractor to fill these gaps what is the proposed contingency to be carried since the risk is unknown.

6/16/2026 (A3) S-003, A-501

6.0.1 S-003, 6.0.1 lists that "STRUCTURAL METAL STUDS MUST BE COLDFORMED AND OF

MINIMUM AND GAGE AS SHOWN ON THE PLANS - FINAL DESIGN PER DELEGATED

DESIGN ENGINEER. ANY SIZES SHOWN ARE FOR BUDGET PRICING PURPOSES ONLY."

Please indicate how the contractor is to price this scope of work when this is a design bid build project and delegated design cannot be accomplished at this stage.

Is the government going to compensate the contractor for changes between stated sizes/spacing? Further, if the contingency is on the contractor to fill these gaps what is the proposed contingency to be carried since the risk is unknown.

Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

6/16/2026 26 13 00 2.1.3.2 & 2.1.4

Please indicate whether the government wants the contractor to provide a fully automated switch solution or manual. The drawings do not indicate this and these spec sections may be providing conflicting information.

Whether the required switching is automated or manual depends on code requirements.

The plan sheets show motion sensors shown in certain areas which are defined on sheet E- 001, with notes on the plan sheets, and a detail on sheet E- 503 which describes the sensor operational requirements. In other areas, there are only manual switches. The specs reinforce the drawings and do not appear to contradict what is depicted on the drawings. Not every space has the same switching solution because of code requirements.

Submit proposals in accordance with RFP, 6/16/2026 TS Dwgs Plan Note 2 Note 2 lists "MANHOLE MAY REQUIRE EXPANSION TO ACCOMMODATE NEW CONDUITS. COORDINATE WITH BASE TELEPHONE FOR DUCTBANKS" How will the government handle the scope and cost of the expansion of the manholes if necessary? If this potential scope is going to be required to be accounted for with this proposal, please provide more information to determine this added scope to include as-builts, photos, etc.

KTR is to assume that telecom manholes will need to be replaced with a size appropriate for the proposed work. Coordinating with Base Telephone for duct banks is required for all MH as new duct is being installed in existing active MHs with active cables, 6/16/2026 01 35 29.13 What is the relevancy of adding this specification to the design package? What contamination is to be accounted for?

There is no known contamination at the site.

However, CL has provided this section for inclusion in CL projects to establish procedures should contamination be encountered during the work.

6/19/2026 CD Dwgs (Typ)

Key Note 1 Key Note 1. states to demolish the existing gravel road. If the material on this road is salvaged clean, screened and is tested; is it acceptable to reuse this material for new construction hardscapes/other (outside of the scope of the new road that is to be installed before this is removed).

Salvaging the existing material to be removed is acceptable as long as the existing road remains in service to the boat dock during construction of the new road.

6/19/2026 CD100 Note 16.1 Notes 16.1 (16.1.1. & 16.1.2. and 16.1.3) Please provide guidance to when the project will be awarded so that can properly account for the clearing restrictions via this note. If these notes are not relevant please offer new instruction. 16.1.3 indicates that further barriers or relief to these dates would be issued in 2024. How do that guidance change these notes?

There are still two tree cutting moratoriums to protect bats in eastern North Carolina. The moratoriums restrict cutting/trimming trees > 3” diameter at breast height during:

15 April – 31 July (summer active season – this covers both the maternity and pup rearing season)

AND

15 December – 15 February (winter torpor season)

Essentially, following these moratoriums will allow us to informally consult with U.S.

Fish & Wildlife Service (USFWS) to get a lesser effects determination on our action, and this is generally a faster process.

It can take 3-4 months to formally consult with USFWS should there be a need to cut/trim trees during the moratorium timeframes. Since formal consultation can severely hold up project progress, we typically advise against this course of action unless there are legitimate safety concerns (i.e. removal of danger trees).

6/19/2026 CD100 Note 6 Note 6 lists that the contractor must clear a minimum of 10' either side of the proposed security fence and are required to maintain throughout the duration.

Please provide better instructions to the level of clearing needed to install new fence line as this is not required to be grubbed.

Refer to note 5 on CD100. The area 10' outside of the security fence is considered project area is is required to be grubbed.

6/19/2026 CG140 &141 Key Notes 3 & 4 Please indicate where tree protection fence starts and stops (key note 4) as well as the super silt fence (key note 3) as these lines appear to be the same marking and start/stop and do not overlap from the plans.

Tree Protection fence is shown with a 'TP' in the line and Super Silt Fence is shown with a 'SSF' in the line

6/19/2026 CU Dwgs Note #3 & Various Key Notes

The drawing sheets call for a series of natural gas work by Piedmont Natural Gas through the government. Please clarify the demarcation point to where the contractor owns the scope going into the building.

The contractor is responsible for the house piping on the building side of the NG meter.

6/19/2026 CU Dwgs Note #3 & Various Key Notes

The drawing sheets call for a series of natural gas work by Piedmont Natural Gas through the government. Are these designed locations where Piedmont Natural Gas is to install their scope or only a suggestion and this is required to be coordinated by them during construction?

Designs shown on civil drawings are suggestions.

Peidmont NG should coordinate the final design and construction.

6/19/2026 CU Dwgs Note #3 & Various Key Notes

The drawing sheets call for a series of natural gas work by Piedmont Natural Gas through the government. What level of coordination is required by the contractor during construction and will the government supervise that coordination?

Typically, the CM communicates gas requirements, proposed startup schedule to the PWD/Utilities Director. The civil site plan, mechanical equipment schedule w/ projected gas loads, and an in-service need date are essential to build the utility service mod request package. The utilities director will coordinate with NAVFAC MIDLANT UTIL/AQ to secure the mod. The contractor may coordinate installation with the NG utility following execution of the mod.

6/19/2026 CU104 Key Note 34 Key note 34 says to coordinate with ES105 for further lifts station information. Is this meant to say coordinate with ES104?

Key note 34 should be corrected to read 'See sheet ES107 for more information.

6/19/2026 Civil Dwgs There are notes on the plans for wetlands being present. Outside of following these permitted drawings and utilizing NCDENR best practices where applicable by the drawing notes; what is the contractors involvement with any permits, closeout of permits, controls not indicated or specified beyond what is identified by the drawings?

Contractor’s involvement shall be in accordance with RFP, specifications, drawings, and all amendments. The contractor is responsible for following applicable permit requirements and providing test reports and as-builts for permit closeout/ final certification.

6/19/2026 CU114 Typ. Key Note 4 & 6 Please confirm that borings are required where indicated and that road cuts are or are not allowed as a substitute. The borings cost more to accomplish especially when installing wet utilities and

Correct. Borings (directional or jack and bore) will be rquired in the locations indicated. Open cuts of the roadway will not be allowed.

6/19/2026 C-528 Pump Station Note 12

What scope of work is the contractor responsible for under base bid as it relates to SCADA or Telemetry and it also mentions to coordinate with the Contracting Officer

This duplex station is considered a low flow station and will not require to be added to SCADA.

6/19/2026 S-101 Typ of all Buildings

The following notes are provided as Rigid Frame and Pre-Engineered Building Notes;

1. FOUNDATION HAS BEEN DESIGNED FOR REACTIONS INDICATED. BUILDING

MANUFACTURER MUST SUBMIT LOAD AND COLUMN REACTIONS TO ENGINEER

FOR REVIEW PRIOR TO CONSTRUCTION OF FOUNDATION

2. CONTRACTOR MUST COORDINATE ALL EQUIPMENT TO BE SUPPORTED FROM

THE STRUCTURE WITH THE METAL BUILDING SUPPLIER BEFORE CONSTRUCTION

3. CONTRACTOR MUST COORDINATE ALL WALL AND ROOF OPENING SIZES AND

LOCATION WITH METAL BUILDING SUPPLIER BEFORE OPENINGS ARE CUT.

Please confirm that the government and their delegated A/E reviewers are prepared to review PEMB shops amongst these other submittals concurrently and within a reasonable time period and just after award in order to not impede the schedule. These notes constitute coordination with many trades that are not necessarily brought in this early for a design-bid-build pursuit and the overall PEMB submittal package will drastically impact procurement notably foundations.

Submit proposals in accordance with RFP, 6/19/2026 A-108 (A3) Please confirm that air barrier testing is required on the A3 building. If so has the design (product selections) for translucent panels and overhead doors been considered as these items will lend to major potential leakage not to mention PEMBs also have there limitations. Will concessions for this potential leakage or the ability to tape up these items be allowed if testing is required? There is a lot of risk involved in this scope. Recommend that this is not tested but resources are rather put to inspections of the air barrier installations.

Testing is required. Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

6/19/2026 A-141 (A2) Please confirm that air barrier testing is required on the A2 building. If so has the design (product selections) for translucent panels and overhead doors been considered as these items will lend to major potential leakage not to mention PEMBs also have there limitations. Will concessions for this potential leakage or the ability to tape up these items be allowed if testing is required? There is a lot of risk involved in this scope. Recommend that this is not tested but resources are rather put to inspections of the air barrier installations.

Testing is required. Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

6/19/2026 A-103 (A2) Construction Keynotes

Revisions via Amendment 2. Please look at Construction Keynotes 1 & 2. Both appear to be missing on the sheet.

See revised sheet.

6/19/2026 A-105 (A2) Construction Keynotes

Please review Construction Keynotes #3 & 5 the tags appear incorrectly placed on this page and are missing from where these items should be placed.

See revised sheet.

6/19/2026 A-106 (A2) Construction Keynotes

Numerous issues with Construction Keynotes 6-8. Please review and add where necessary.

See revised sheet.

6/19/2026 A-107 (A2) Construction Keynotes

Revisions via Amendment 2. Please look at Construction Keynotes 1 & 2. Both appear to be missing on the sheet.

See revised sheet.

6/19/2026 A-108 (A2) Construction Keynotes

Numerous issues with Construction Keynotes 6-8. Please review and add where necessary.

See revised sheet.

6/19/2026 A-109 (A2) Construction Keynotes

Construction Keynotes are missing from this sheet See revised sheet.

6/19/2026 A-110 (A2) Construction Keynotes

Review Construction Keynotes, many are listed but missing from the sheets. See revised sheet.

6/19/2026 A-111 (A2) Construction Keynotes

Review Construction Keynotes, many are listed but missing from the sheets. Ones that are provided are misapplied in areas.

See revised sheet.

6/19/2026 A-113 (A2) Construction Keynotes

Construction Keynotes are missing from this sheet See revised sheet.

6/19/2026 A-204 (A2) Construction Keynotes

Construction Keynote #18 Clearing Barrel; please confirm if these are CFCI, GFCI or

FF&E

CFCI.

6/19/2026 A Dwgs (Typ) -(A2)

Construction Keynotes

Storage Cages are listed throughout this building as FF&E. There is a specification for Wire Mesh Partitions. Please clarify that all Wire Mesh Items in Buildings A2-1 and A2-2 are in the FF&E package.

Incorrect. Storage cages and wire mesh partitions are not the same. Wire mesh partitions are in the Base Bid.

6/19/2026 A505 (A2) C3/A505 (A2): Please confirm that the Fluid Applied Air Barrier (07 27 26) stops at the top of the slab. This detail is hard to see where it starts/stops and is similar of other details.

Per the referenced detail, transition to compatible below grade dampproofing at the top of the floor slab.

6/19/2026 A505 (A2) C3/A505 (A2): As a follow-on to the previous PPI; confirm that there is no perimeter or below grade waterproofing required for this building.

Per the referenced detail, transition to compatible below grade dampproofing at the top of the floor slab.

6/19/2026 A513 (A2) B3/A513 (A2): Please confirm that TV brackets are CFCI and not part of the A/V package.

TV Brackets are not included in the AV Package.

6/19/2026 A607 (A2) B3/A607 (A2): What is the purpose of the bird screen on the inside of the translucent panels so that we are applying this detail correctly.

Details A3 and B3 are mislabeled. These are louver details that require bird screen.

6/19/2026 I-101 (A2) Typ

CFCI Furniture Legend

Please confirm CF1, CF2 and CF3 Televisions are in fact CFCI and not part of the Audio-Visual package.

That is correct. CF1, CF2 and CF3 Televisions are CFCI

6/19/2026 I-101 (A2) Typ

CFCI Furniture Legend

Please confirm CF4 & CF5 Markerboards are in fact CFCI and not part of the Furniture package.

That is correct. CF4 & CF5 Markerboards are CFCI

6/19/2026 10 22 13 2.6 The specification lists "slide up type, mounted in standard mesh panel reinforced with channel tracks. Opening must be 24 inches wide by 15 inches high unless otherwise indicated. Provide two spring loaded latches, operable only from the inside, to lock window in open and closed positions." Please confirm all of these features are warranted for this application.

Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

6/19/2026 10 22 13 Furnish wire mesh partitions for Building A1, Battalion/Dept Storage 193. Nominal partition height is 14 feet, 0 inches with wire mesh caps. Are we sure that the owner wants to have a 14’ height for team cages? Recommendation from vendors to control security and specialization is these are 10’ height and add a ceiling it will be more secure and cost the same.

Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

6/19/2026 10 22 13 2.7.1 Please confirm that woven wire mesh cages are required and welded cages are or are not acceptable.

Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

6/17/2026 Specification 33 40 00

2.4 Local RCP manufacturers have advised that they cannot guarantee their products will pass hydrostatic, leakage, infiltration, and exfiltration testing requirements due to the inherent porous nature of concrete pipe. As a result, suppliers are unwilling to provide pricing while these testing requirements remain in the specification.

Please confirm whether the hydrostatic, leakage, infiltration, and exfiltration testing requirements for RCP may be removed.

Concur. This requirement can be removed.

6/17/2026 Specification 33 40 00

2.3.5 Local precast structure manufacturers have advised that they cannot provide quotations for storm structures with booted/resilient pipe connections when connecting to reinforced concrete pipe (RCP). Suppliers indicate that resilient connectors are not compatible with the porous surface characteristics of RCP and therefore cannot guarantee the performance of the connection. Please confirm whether the resilient connector (booted connection) requirement may be removed for RCP connections to storm structures.

Concur. This requirement may be removed. Please seal the annulus at the pipe connection with non-shrink grout.

6/17/2026 Offer Schedule CLIN 0001H is the Unit Price for undercut and temporary stockpiling of geotechnically unsuitable subgrade soils and replacement with imported Structural Fill material or with NCDOT #57 crushed stone, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. Disposal of surplus soil media will be covered under a separate CLIN. CLIN 0001H has an estimated quantity of 4,000 CY. CLIN 000I is the Unit Price for

Confirming that no soil disposal costs are to be included in CLIN 0001H. All surplus soil media disposal costs are included in CLIN 0001I.

handling, temporary stockpiling, sampling, analysis and disposal of non-hazardous surplus soil media at a licensed facility, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. CLIN 0001I has an estimated quantity of 70,000 TONS. Please confirm that the disposal of all non-hazardous surplus soil media on the project will be paid for under CLIN 0001I and that no disposal of non-hazardous surplus soil media is to be included in

CLIN 0001E.

6/18/2026 Amendment #0002 reissued 38 drawings labeled as CUI. This requirement will preclude the majority of contractors and trade partners from proposing or contracting on this project as very few are CMMC Level 2 certified. Please confirm whether this requirement is absolutely necessary.

In accordance with USOW memo of 7/13/26, this project will be at CMMC Level 2 (Self).

Per USOW memo: CMMC Level 2 is aligned with NIST SP 800-171 Rev 2. The CMMC Level 2 self-assessment requirement is designed to provide insight into the offeror’s compliance with security requirements for Controlled Unclassified Information (CUI). The Program Managers and requiring activities may require additional cybersecurity protections as commensurate with law and regulation.

6/25/2026 A-304 Drawing Set A1, cut section C3/A-304 shows keynote #4 as a depressed slab for raised access flooring. Please confirm that no waterproofing is required for this depressed slab location. If waterproofing is required, please provide a detail (showing extent and termination) and a product specification section (not currently provided).

Waterproofing is not required.

Continuous water stop at any construction joints is required.

6/25/2026 A-506, A-507 Drawing set A1 A-506, A-507, and several other drawings reference building expansion joints in metal wall panels, gypsum walls, and CMU walls. Please provide a specification section 07 95 00 describing all of the types of required building expansion joint products.

07 95 00 is not a UFGS Specification Section. Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

6/25/2026 A-501 08 34 02 Drawing set A1, drawing A-501 wall type A5 calls for a 1/2" ballistic rated panel (8'- 0" high). When reviewing specification section 08 34 02 "Bullet-Resistant Components" it appears to only mention bullet-resistant glass/window components. Please provide a specification section or product type for the 1/2" ballistic rated panel.

Reference 08 34 02 paragraph 2.4.

6/25/2026 C258 n/a n/a The drawing on C-258 shows 2 condition points both labeled “Buildout”. Are we to supply pumps that can meet both conditions, or do we supply a pump for the initial condition (Left) but can achieve the buildout condition (Right) via impeller or motor swap. This is important because there would be a change of HP required.

Pump voltage is 208v, 3ph as indicated on electrical site drawings.

A4 on Sheet C-528 is a table of the upgrades required for the P-1219 lift station. The left side of the table is the existing lift station setup. The right side of the table is the changes that are required to handle the additional flow from this project and the P-1538 project. The contractor is responsible for supplying a pump that will meet the requirements of the upgrades shown on the right side of the table.

6/25/2026 C258 33 32 16 n/a Please confirm voltage required on table A4 for P1219 pump station upgrades. Table says 3/208 but specifications say 3/460.

Pump voltage is 208v, 3ph as indicated on electrical site drawings.

6/25/2026 CG100 Please provide unflattened vector files created from CAD files for the civil plans. The plans that are provided are flattened.

A4 on Sheet C-528 is a table of the upgrades required for the P-1219 lift station. The left side of the table is the existing lift station setup. The right side of the table is the changes that are required to handle the additional flow from this project and the P-1538 project.

The contractor is responsible for supplying a pump that will meet the requirements of the upgrades shown on the right side of the table.

6/25/2026 A1 - I117 Amendment 3 issued a revision to Bn HQ A1 - 1-117 which did not come as a secure file nor does it have any CUI marking. Previously this drawing was part of a CUI package. Please advise if the entirety of the A1 drawing set can be treated as non-

CUI.

The whole set of Bn HQ A1 - 1-117 would need to be treated as CUI.

6/25/2026 Attachment C Price Proposal

CLIN 1H includes replacement of geotechnically unsuitable subgrade with imported structural backfill or imported No. 57 crushed stone. There is a cost difference between structural fill and No. 57 stone and the offeror has no way to identify where the quantity of unsuitable soil will be located and the backfill required.

Please confirm offerors should price all replacement as No. 57 stone for this CLIN.

Base bids on providing 3,000 CY of Imported Structural Fill and 1,000 CY of Imported No.

57 Crushed Stone.

6/25/2026 01 30 02.00 20 1.42 01 30 02.00 20 - 1.42 notes, "As a separately priced option, the Prime Contractor shall provide the services of a Certified Technology Specialist - Design (CTS-D), other than the A/E's AV Designer, to function as Prime Contractor's AV Designer, to prepare and provide the Final, Best Valued AV Package and procurement data based on the Concept AV package." There is no "separately priced option" for CTS-D.

Please either add an item for this to the bid form or advise under which CLIN this should be priced. Please also indicate if a CTS-D is required in additional to an AVIZA Certified Technical Specialist - Design certification.

CLIN 0002 is the separately priced option for AV equipment procurement by the CTS-D. The AVIXA Certified Technology Specialist - Design is a CTS-D and required for the BVD determination.

6/25/2026 01 35 26 & 01 35 29.13

01 35 26 requires 1 SSHO for the project site. 01 35 29.13 also notes the requirements of a Safety and Health Manager (who must be an Industrial Hygienist) and an SSHO. 01 35 29.13 - 1.5.2.2 notes that the SSHO can have collateral duties in addition to SOH related duties. Please confirm: 1) only 1 SSHO is required full-time onsite to meet both 01 35 26 and 01 35 29.13 responsibilities and 2) a Safety and Health Manager is not required full-time on site.

A Level One SSHO having on the job experience with multi facility projects exceeding $50M & 10 years cumulative experience as SSHO. An industrial hygienist is NOT required.

6/25/2026 01 45 00 01 45 00 - 1.7 includes an Experience Matrix for QC Specialists. Section 2-1 Qualification and 2-2 Experience can be interpreted differently. For instance, for the Civil QC it notes, 2-1: 2-1. Graduate Civil Engineer or Construction Manager with a professional engineer registration, and 2-2. 2 years experience in the type of work being performed on this project or technician with 5 years related experience.

Please confirm this means the contractor is to provide a Graduate Civil Engineer or Construction Manager with a PE registration and 2 years of experience in the type of work being performed OR a technical (no degrees or PE) with 5 years of related

Delete Civil QC Specialist;

Delete Electrical QC Specialist;

Delete Submittal person as submittal clerk; Delete Low Voltage Specialty QC Specialist experience. This would also apply for the remainder of the QC specialists including Mechanical, Electrical, & Structural.

6/25/2026 01 45 00 01 45 00 - 1.7 includes an Experience Matrix for QC Specialists. For Civil QC, section 2-1 notes a Graduate Civil Engineer or Construction Manager with a professional engineer registration. If the person is a Graduate Civil Engineer do they need to possess a Professional Engineer Registration and only a Construction Manager graduate must have a professional engineer registration? Note typically the Construction Manager graduate does not have a Professional Engineer registration.

Delete Civil QC Specialist;

Delete Electrical QC Specialist;

Delete Submittal person as submittal clerk; Delete Low Voltage Specialty QC Specialist

6/25/2026 01 45 00 01 45 00 - 1.7 requires both a Telecommunications and Low-Voltage Specialties/ESS QC specialist with the same Qualification, Experience, and Area of Responsibility and Frequency. Please confirm only one person is required for both these positions.

Delete Civil QC Specialist;

Delete Electrical QC Specialist;

Delete Submittal person as submittal clerk; Delete Low Voltage Specialty QC Specialist

6/25/2026 12 00 01.00 20 Per 12 00.01 00 20 - Offerors are to include in the base bid an Interior Designer to validate, complete the FF&E design and perform a BVD. There is only one Option for the Planned MOD of FF&E for all 4 buildings, however, there are 3 base bid CLINS for the Buildings. Which Base Bid CLIN should offerors include the costs for the Interior Design services?

Base bid CLIN 003 is indicated as "Option Item No. 2: Price for providing work in connection with labor, material, equipment, transportation, and supervision required for the Furniture, Fixtures and Equipment (FF&E), complete in accordance with the drawings and specifications, but excluding work provided in another priced line item"

6/25/2026 Price Proposal Form

There are unit price line items for non-hazardous soil disposal. Please confirm that we are to assume all groundwater that is pumped for dewatering is considered clean and will not need to be treated. If the water is considered contaminated and will need to be treated, it is unknown how many gallons of water will be encountered. Please provide a unit price line item for testing and treating of contaminated groundwater and a quantity in gallons.

Bid per price schedule. Areas of known groundwater contamination are included in the site drawings (the utility run located to the Northwest of the project site - the only time you should encounter known groundwater contamination is within this area.) No additional CLIN will be provided and this must be included within the base bid.

6/25/2026 Amendment #3 PPI Responses

The PPI responses stating "The shielding test parameters must be stipulated by the AO. We asked this question during design but never received an answer", does not provide clarity to the scope of work and could risk major impact to the cost and schedule of the project. Please review and provide response to the previously submitted PPI:

Power line filters do not appear to be included in spec 13 47 00 or drawings. Please provide details and specifications for rf power line filters. If power line filters are not included, RF specialists will likely not guarantee the secured area's specified attenuation because it will fail.

Power line filters are not included in the design.

6/25/2026 Amendment #3 PPI Responses

The PPI responses stating "The shielding test parameters must be stipulated by the AO. We asked this question during design but never received an answer", does not provide clarity to the scope of work and could risk major impact to the cost and schedule of the project. Please review and provide response to the previously submitted PPI:

Section 3.2.2 Attenuation requirements states "Achieve radio frequency attenuation through a combination of materials and standoff that is equal to or greater than 100 meters of free space over the frequency range of 30 MHz to 6 GHz". Please confirm the level of attenuation the secured space should achieve in dB when tested.

Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

6/25/2026 Price Proposal Form

The PPI responses stating "The shielding test parameters must be stipulated by the AO. We asked this question during design but never received an answer", does not provide clarity to the scope of work and could risk major impact to the cost and schedule of the project. Please review and provide response to the previously submitted PPI:

IEEE 299, 5.1 Overview specifically reads: This standard defines a test procedure but does not define the frequencies at which the measurements should be made, nor does it define the minimum shielding effectiveness that constitutes pass/fail.

The owner shall define these frequencies and all pass/fail requirements.

IEEE 299, Annex D further explains that shielded enclosures can have a wide range of uses, and be constructed from welded steel enclosures, to demountable test

Submit proposals in accordance with RFP, cells. D.2 Performance Requirements goes on to read: The selection and application of methods described herein is the responsibility of the parties associated with the enclosure: principally the owner and the owner’s representatives. It would not be possible to fully test in accordance with this standard if the standard requires procedures or techniques that are inappropriate or incompatible with the particular enclosure involved. Upon review of the shielding enclosure for this project with several experienced shielding vendors meeting the requirements of 13 47 00 and respective attenuations specified, the consensus is that the IEEE 299 testing requirements need to be tailored/suited for this application, and more specific pass/fail requirements need to be defined.

Please provide an updated IEEE 299 testing plan that is tailored to this project.

6/25/2026 CU100 CLIN 0001I could represent a significant pricing swing for 70,000 TN. The CLIN language includes stockpiling, sampling, analysis, and disposal of non-hazardous material at a licensed facility, priced per ton. This wording suggests the material may be contaminated and require off-base disposal, potentially at a Subtitle D landfill. Based on this language, we assume the material will need to be transported off base to an approved disposal facility rather than being disposed of at one of the two on-base dump locations identified in the specifications. Please confirm whether this assumption is correct. Additionally, please clarify the anticipated contaminants that should be assumed for pricing and disposal purposes. Should bidders assume the potential presence of PFAS, petroleum hydrocarbons, VOCs, SVOCs, metals, or other contaminants? Specifically, should PFAS-impacted material be included in the scope and pricing assumptions for this CLIN?

Bid as specified assuming offsite disposal at a RCRA D facility is required; due to the volume of soil, on base disposal is prohibited.

Based on site history, no PFAS releases have occurred in or within the vicinity of the site.

Site specific data should be included as an Attachment to the 01 57 19 specifications to provide data for the contractors to bid upon and select an existing facility that will receive the waste.

6/25/2026 C-258 1) The drawing on C-258 shows us 2 condition points, both labeled “Buildout”.

Please clarify which one will be the actual buildout. Are we to supply pumps that can meet both conditions, or do we need to supply a pump for the initial condition (Left) BUT can achieve the buildout condition (Right) via impeller or motor swap?

This is important because there would be a change of HP required.

2) Please confirm voltage is 3/208 as stated on drawing. Specs state 3/460.

Pump voltage is 208v, 3ph as indicated on electrical site drawings.

A4 on Sheet C-528 is a table of the upgrades required for the P-1219 lift station. The left side of the table is the existing lift station setup. The right side of the table is the changes that are required to handle the additional flow from this project and the P-1538 project. The contractor is responsible for supplying a pump that will meet the requirements of the upgrades shown on the right side of the table.

6/25/2026 Amendment #3 PPI Responses

The PPI responses stating "The shielding test parameters must be stipulated by the AO. We asked this question during design but never received an answer", does not provide clarity to the scope of work and could risk major impact to the cost and schedule of the project.

Please review and provide response to the previously submitted PPI: Section 13 47 00 is calling for the shielded spaces to meet the effectiveness of what appears to be in the range of +60-80dB ranges and KHz frequencies listed in its respective sections “when tested” per IEEE 299, NSA 65-6, MIL-STD-285. Section 3.2.2 doesn’t specifically mention the IEEE 299 testing, but it is assumed to be required. The General Contractor and the Shielding Specialist Subcontractor are comfortable to test the shielded space per IEEE 299 standards, however, there is no performance guarantee that can be provided for a field built facility. The shielding effectiveness test results will be provided in a confidential manner, but may show small local failure points in the shielding. Any potential failure points, in the confidential report, will be provided for information only. As discussed in IEEE 299, the testing standard is built around six-sided, continuously welded steel enclosures, bolted together panel enclosures, etc. When trying to use rFOIL sheets, cut and applied on a construction site, around obstacles, openings, etc, it doesn’t yield the same level of shielding results as a pre-fabricated, continuously welded, six-sided box.

Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

6/25/2026 Amendment #3 PPI Responses

The PPI responses stating "The shielding test parameters must be stipulated by the AO. We asked this question during design but never received an answer", does not provide clarity to the scope of work and could risk major impact to the cost and schedule of the project. Please review and provide response to the previously submitted PPI:

13 47 00, 1.5.3 Work Plan calls for an independent, third party testing consultant for assembly testing. 1.1 References refers to IEEE 299 & MIL-STD-202 Methods for Measuring the Effectiveness of EM Shielding Enclosures. From several past experiences and consulting with numerous RF Shielding contractors, testing a 6-

Submit proposals in accordance with RFP, sided box, that utilizes the metal roof deck and floor slab as the fifth and sixth side of the box will yield many local failure points in the IEEE 299 testing tables. What has been acceptable on other projects with an “Open Storage” level of classification is to perform the testing, and provide the results confidentially to the Gov’t. This will show and identify the isolated points of weakness for information only.

However, to build a shielded space that would pass all of the tables in IEEE 299, on all six sides is an extremely expensive, and incredibly sensitive and time consuming endeavor (if not impossible). We just want to verify that the Gov’t is aware of and acceptable to the fact that the 4 sided box will yield local shielding failure points, and those will be tested and pointed out in the reports, but those won’t be able to be remedied in the field. Please confirm the Gov’t acknowledges and is acceptable to this.

6/25/2026 Amendment #3 PPI Responses

The PPI responses stating "The shielding test parameters must be stipulated by the AO. We asked this question during design but never received an answer", does not provide clarity to the scope of work and could risk major impact to the cost and schedule of the project. Please review and provide response to the previously submitted PPI:

Section 1.5.3 says "The Accrediting Officer performs a final series of tests to determine work acceptance for accreditation purposes". 1. Please confirm what the actual testing procedures are for the secured space. 2. Please confirm if the government owns testing of the secured space.

Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

6/25/2026 Amendment #3 PPI Responses

Section 3.2.2 Floor and Wall Surfaces says "Sandwich radiant barrier foil between concrete slabs and finish flooring". Details provided for RF shielding at floors only show RF foil and conductive taping at seams above the concrete slab. As per Amendment #3 PPI response, including rFoil in-between a concrete slabs. This is not recommended. This comes with multiple risks of damage to the concrete and foil.

The secured area will fail due the specified testing requirements. Please consider removing any RF shielding between concrete slab and revise testing requirements to be compatible with the current level of design for RF shielding.

The RF shielding is on top of the floor slab not " in-between a concrete slabs". Submit proposals in accordance with RFP, Specifications, Drawings and all amendments.

6/25/2026 C530 Detail A1 on Sheets C-530, C-532, and C-533 includes a note calling for 12 inches of topsoil above a clay liner; however, the thickness of the clay liner is not indicated.

Please…