This is a Continuation Sheet documenting revisions to the construction drawings and specifications for the P-1550 SOF Marine Raider Battalion/Company/Team Facilities project at Marine Corps Base Camp Lejeune, North Carolina. The revisions, dated June 22, 2026, include modifications to drawings A1-S-512 and A2-S-512, where dimension references have been updated to "see schedule" to eliminate confusion and improve clarity. Additionally, Section 13 34 19 of the specifications has been revised to incorporate warranty provisions for the project.
The revisions support the overall Design-Bid-Build solicitation (N4008526R0138) for construction of approximately 73,400 square feet of SOF Marine Battalion Operations, Supply, Communications, and Intel facilities; 127,200 square feet of Company Headquarters and Team Facilities; and 17,600 square feet of Company Storage Buildings, along with supporting infrastructure including utilities, parking, roadways, and site work. The structures will feature single-story steel frame construction with brick veneer, standing seam metal roofs, and pile foundations to address site-specific conditions including surcharged sites, wetlands mitigation, and stormwater management.
View the file
Other files
Show all 46
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P-1550 SOF MARINE RAIDER BATTALION /COMPANY / TEAM FACILITIES
Continuation Sheet for Revisions June 22, 2026
Drawings
1. A1-S-512: Changed dimension reference to be “see schedule” to avoid confusion.
2. A2-S-512: Changed dimension reference to be “see schedule” to avoid confusion.
Specifications Section 13 34 19 revised to include warranty provisions.