This is a Continuation Sheet for Revisions to the P-1550 SOF Marine Raider Battalion/Company/Team Facilities specification document, dated October 28, 2026. The revision addresses Section 01 57 19 Temporary Environmental Controls, specifically revising Part 1.5.1.2 for Camp Lejeune to align with requirements outlined in the MCB Camp Lejeune Environmental Standard Operating Procedure ESOP 5090.10.1, effective January 21, 2026. The document is associated with the Design-Bid-Build solicitation (N4008526R0138) for construction of SOF Marine Raider facilities at Marine Corps Base Camp Lejeune, North Carolina, issued by the Department of the Navy Naval Facilities Engineering Command.
The underlying construction project encompasses approximately 20,262 square meters (218,200 square feet) of facilities, including a SOF Marine Battalion Operations, Supply, Communications, and Intel facility; Company HQ and Team Facilities; and Company Storage Buildings, along with supporting infrastructure such as utilities, parking, roadways, and site work at Stone Bay. The structures will feature single-story steel frame construction with brick veneer over metal studs, standing seam metal roofs, metal soffits, and translucent wall panels, with special construction features including pile foundations, surcharged sites, wetlands mitigation, and storm water best management practices. This continuation sheet ensures contractor compliance with the specified environmental control standards applicable to temporary construction measures at the Camp Lejeune location.
View the file
Other files
Show 40 more
Latest 50 of 56 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P-1550 SOF MARINE RAIDER BATTALION /COMPANY / TEAM FACILITIES
Continuation Sheet for Revisions October 28, 2026
Specifications
1. Section 01 57 19 Temporary Environmental Controls: Revised Part 1.5.1.2 Camp Lejeune to align with the requirements on the MCB Camp Lejeune Environmental Standard Operating Procedure ESOP 5090.10.1 January 21, 2026 image1.jpeg