AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
DESIGN-BUILD/DESIGN-BID-BUILD, INDEFINITE DELIVERY/INDEFINITE QUANTITY (IDIQ) FIRM FIXED PRICE (FFP) MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) FOR GENERAL CONSTRUCTION OF FACILITIES LOCATED AT MCAS BEAUFORT, MCRD PARRIS
ISLAND, AND NAVAL HOSPITAL BEAUFORT
See Continuation Page(s)
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 21-Mar-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008523R2575
X 9B. DATED (SEE ITEM 11)
16-Feb-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
21-Mar-2023
CODE
NAVFACSYSCOM MID-ATLANTIC
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008523R2575
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0006
CONTINUATION SHEET
The purpose of this amendment is to provide the following:
1. Extend proposal due date from 30 March 2023 to 06 April 2023.
2. Provide Revised Pre-Proposal Inquiry (PPI) Response to PPI #50 & 51
3. Provide updates to the Drawings and Specifications
4. Revised Attachment E - Price Proposal Form – REV 2
ATTACHMENTS
1. Amendment 0006 – Attachment E – Price Proposal Form –REV 2
2. Amendment 0006 - BLDG-P485-1362850-AE531 - MISCELLANEOUS DETAILS_REV3
DOCUMENT 00 01 15 LIST OF DRAWINGS
1.2 CONTRACT DRAWINGS
NAVFAC Dwg. No. 12854102 (AE531) is revised as of March 20, 2023 and accompanies this amendment.
On NAVFAC Dwg. No. 12854051 (CG501)
Trench Drain Detail B4, Section A, Notes: ADD to Note 1 related to trench grate: Provide ductile cast iron grating and frames conforming to ASTM A536-80 grade 65-45-12. All castings must be of uniform quality, free from blow holes, shrinkage defects, swells, cracks or other defects. Castings must be free of fins, burrs and slag.
SECTION 05 12 100 STRUCTURAL STEEL
1.4.3.2 Overhead, Top Running Crane Rail Beam
Delete this Paragraph in its entirety and replace with the following:
“1.4.3.2 NOT USED.”
SECTION 05 50 13 MISCELLANEOUS METAL FABRICATIONS
1.2 SUMMARY
1.2.1 Section Includes:
Delete paragraph d for Floor gratings.
Delete paragraph f for Guy cables and safety chains.
1.3 SUBMITTALS
SD-02 Shop Drawings
N4008523R2575
Delete “Floor Gratings, Installation Drawings” in its entirety.
SD-03 Product Data Delete “Floor Gratings” in its entirety.
2.2 MATERIALS
2.2.5 Gratings
Delete this Paragraph in its entirety.
2.5 FLOOR GRATINGS
Delete this Paragraph in its entirety.
2.8 SAFETY CHAINS
Delete this Paragraph in its entirety.
2.9 GUY CABLES
Delete this Paragraph in its entirety.
3.10 MOUNTING OF SAFETY CHAINS
Delete this Paragraph in its entirety.
Question
Reference Question Government Response
Page Section Paragraph
CS101 05 50 13 2.5 Please confirm the floor gratings mentioned in spec section 05 50 13 only refer to the trench drain shown on CS101 and CG501.
No other floor gratings were found in the building.
Delete Grating reference from Specification Section 05 50
13. Trench Drain Grating requirements indicated on
CG501. Frame material must match Grate material. Ductile Iron Frames and Grates shall conform to ASTM A536-80 grade 65-45-12.
CS101 05 50 13 2.5 Regarding the trench drain on CS101, please confirm the 100,000 pound single wheel load with 250 PSI tire pressure supercedes the requirements in spec paragraph 2.5 within spec section 05 50 13.
See response to PPI #50.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 30-Mar-2023 02:00 PM to 06-Apr-2023 02:00 PM.
(End of Summary of Changes)