1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. PROJECT NO. (If applicable) 0009 02/13/2023
6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code
NAVFACSYSCOM MID-ATLANTIC
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK, VA 23511
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.
N40085-23-R-2557
9B. DATED (SEE ITEM 11)
12/05/2022
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning _1 _ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER: (specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
N40085-23-R-2557, DESIGN-BUILD, P-1458, 2nd RADIO BATTALION COMPLEX, PHASE 2, MARINE CORPS BASE, CAMP LEJEUNE, NORTH CAROLINA
SEE SF 30 BLOCK 14 CONTINUATION PAGE
Contract POC: Brittany Cristelli; Email: brittany.n.cristelli.civ@us.navy.mil; Phone: 757-341-1978
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR (Same as Item 8)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)
PREVIOUS EDITION UNUSABLE Prescribed by GSA mailto:brittany.n.cristelli.civ@us.navy.mil
N40085-23-R-2557
SF 30 BLOCK 14 CONTINUATION PAGE
The purpose of this amendment is to provide the following:
1. Remaining Pre-Proposal Inquiry (PPI) Responses
2. Revised Attachment B - Price Proposal Form – REV 2
ATTACHMENTS
1. Amendment 0009 – Attachment B – Price Proposal Form –REV 2
2. Amendment 0009 – 01 31 23.13 20 - ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT
MANAGEMENT SYSTEM
3. Amendment 0009 – 01 78 00 - CLOSEOUT SUBMITTALS
4. Amendment 0009 – 01 78 23 - OPERATION AND MAINTENANCE DATA
5. Amendment 0009 – 01 78 30.00 22 - GIS DATA DELIVERABLES
6. Amendment 0009 - 6_ESR_E20 – Furnishings
7. Amendment 0009 - 23 09 23.13 - BACNET DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC
8. Amendment 0009 - 25 05 11.00 - CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS - ISOLATED
SYSTEMS
9. Amendment 0009 – PPI 393 2015-2020_MCBCL_INRMP_(MASTER)
The following has been revised (in red):
PROJECT TABLE OF CONTENTS
PART 2 General Requirements
Section 01 78 00, CLOSEOUT SUBMITALS, is added to the Table of Contents and accompanies this amendment.
Delete section 01 78 30.00 22 GIS DATA DELIVERABLES and 01 31 23.13 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM and replace with 01 78 30.00 22 GIS DATA DELIVERABLES dated March
2022 and 01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM dated November 2021 accompany this amendment.
PART 3 – PROJECT PROGRAM
Delete section ESR E20 Furnishings and replace with ESR E20 Furnishings accompany this amendment
PART 5 – PRESCRIPTIVE SPECIFICATIONS
Section 23 09 23.13 - BACnet Direct Digital Control Systems for HVAC and Section 25 05 11.00 - Cybersecurity for Facility-Related
Control Systems - Isolated Systems are added to the Table of Contents and accompanies this amendment.
Question
Reference Question Government Response
Page Section Paragraph
Part 2, Spec
Section 01 30
00 1.8, 1.9 and
01 31 19.05
PLEASE CONFIRM THAT BOTH THE DP/D
AND THE CDW ARE REQUIRED AS
SEPARATE MEETINGS/DELIVERABLES OR
clarify if the intent is to be only (1) DESIGN
MEETING as IDENTIFIED BY THE
FOLLOWING:
01 30 00 1.8 POST AWARD KICKOFF (PAK)
MEETING: STATES THAT THE PAK MUST BE
HELD WITHIN 35 CALANDER DAYS AFTER
CONTRACT AWARD AND MAY BE HELD
CONCURRENTLY WITH THE DESIGNED
PRESENTATION/DESIGN DEVELOPMENT
The PAK shall be held within the first 35 days after award, with the
CDW starting either after the
PAK on the same or following day. Partnering shall be its own one day meeting, within 45 days after award. A separate Design
Presentation/Design Development
MEETING OR THE CONCEPT DESIGN
WORKSHOP (CDW) WHICHEVER IS
REQUIRED.
INDICATING THAT ONLY ONE WOULD BE
APPLICABLE, HOWEVER BOTH ARE
INDICATED AS FOLLOWS:
01 30 00 1.9 DESIGN
PRESENTATION/DEVELOPMENT (DP/D) IS
REQUIRED
01 31 19.05 20 CONCEPT DESIGN WORKSHOP
(CDW) IS REQUIRED WITH A 14 DAY
REVIEW OF ALL DOCUMENTS
ESR
D30 page 2;
ESR
E10
& 4
Part 3, Chapter 6;
Part 3, Chapter 5
D30
General
System
Requireme nts;
The RFP requires that the Supply Warehouse building be conditioned with a VAV AHU with chilled water and hot water and also a
DOAS. The RFP also states that the warehouse area of this facility is heated and ventilated only. The warehouse is the majority of the building, leaving less than 3K SF of conditioned area. An RTU is a more appropriate system type for this scale application. Shall a pad-mounted VAV RTU with electric reheat be used in lieu of the
VAV AHU, chillers, boilers, and DOAS?
REVISED RESPONSE: A heat pump DX unit with hot gas reheat
(no electric reheat) and supplemental hot water coil is acceptable for the warehouse building. It can be a packaged unit, but cannot be a RTU. If the duct is outdoors, must use phenolic duct.
Part 2, 01 30
1.7
01 30 00 states the the PAK may be held concurrently with the Design Presentation/Design
Devleopment Meeting or Concept Design
Workshop whichever is required. Paragraph 1.9 identfies a Design Presentation/Development. 01
31 19.05 20 identifies the Concept Dewign Work
Shop.
Confirm only the Concept Design Workshop is required and the DP/D requirements are not applicable.
Confirm the PAK and Concept Design Workshop can be held concurrently as a multiday meeting.
See Response to PPI #143
Attachment B -
Rev 1 Price
Proposal Form
Note "f." for CLINS 5 & 6, Planned Mods for
FF&E and AV , states "No schedule extensions will be granted if the modification is awarded at least six months prior to the contract completion date."
With current market conditions and suppply chain issues especially for electronics, 12 months is required to procure and install FF&E and AV.
Please revise this from 6 months to 12 for award of these options in order to meet the schedule requirements.
For FF&E: Provide a Final FF&E
Package twelve months prior to contract completion date, rather than the original six months requirement.
Electrical or the CTS-D must still approve this change for AV.
Part 2, 01 30
1.11
1.11 notes partnering session must be schedule within 45 calendar days of the contract award.
1.11.1 notes within 35 calendar days after award and prior to the start of work a formal Partnering session is required.
Please confirm which time frame is required and confirm this can be coordinated concurrently with a multi-day PAK and CDW meetings.
The PAK shall be held within the first 35 days after award, with the
CDW starting either after the
PAK on the same or following day. Partnering shall be its own one day meeting, within 45 days after award. A separate Design
Presentation/Design Development
Meeting is not required.
Attachment B -
Rev 1 Price
Proposal Form
CLIN 1G states sampling shall be performed in accordance with Specification 01 57 19 01.20, however, 01 57 19 01.20 does not list any sampling requirements.
Please identify the sampling requirements.
PENDING RESPONSE
268 3
Part 3 / D4010
Fire
Alarm/Detectio
D4010 states "BID OPTION: Provide a factory trained instructor to teach a five-day technical training classroom instruction for at least five
Yes, include the training of Fire
Alarm System in the base bid.
n and Mass
Notification
Systems
Government personnel at Camp Lejeune."
However, there is no Bid Option for this training on the bid form. Please confirm this training should be included in the Base Bid.
272 11 01 35 26 1.7.1.4
Section 01 35 26 1.7.1.4 provides safety requirements for workers with a H-1B or H-2B visa. However, no where else in the specifications does it mention H-1B or H-2B workers. Please clarify if H-1B and H-2B visa workers are allowed on this project.
Information on installation access and Phone number for questions may be found at the Contractor
Vetting Office website at https://www.mcieast.marines.mil/ cvo/)
392 1 ESR G11
Last
Paragraph
Part 3, Chapter 6, ESR G10, Page 1, Last
Paragraph - Wetland Impacts - Has there been any presence/absence surveys for Northern long-eared bat (NLEB) completed in the area within the past 5 years?
Surveys for NLEB have been conducted on base but no individuals have been identified.
Portions of this site have been clearcut so there should be minimal NLEB habitat within the limits of disturbance.
393 1 ESR G12
Last
Paragraph
Part 3, Chapter 6, ESR G10, Page 1, Last
Paragraph - Wetland Impacts - Would NAVFAC provide the most recent version of the facility
INRMP to help determine any potential T&E impacts or constraints?
See Attachement PPI 393 2015-
2020_MCBCL_INRMP_(MAST
ER)
394 1 ESR G13
Last
Paragraph
Part 3, Chapter 6, ESR G10, Page 1, Last
Paragraph - Wetland Impacts - Is there an existing
EA/EIS or is one being developed for the Project
(is there a NEPA component to this project with
NAVFAC as the lead federal agency?)
NEPA analysis for this project was documented in the 2009
Grow the Force EIS. Because design will limit impacts to less than ½ acre and 300lf of stream, there will be no additional NEPA analysis required to wetland/stream impacts. Any communication with agencies regarding 401/404 permitting must be coordinated with
Environmental Planning section
414 page 56 BEAP
Please confirm if CLIN 1 is to include sodding of the CLIN 2 & 3 sites (inside the security fence) if
CLIN 2 & 3 are not awarded.
If CLIN 2 and 3 are not awarded, sod disturbed areas only. Note that security fences for CLIN 2 and 3 areas are not installed if the associated CLIN is not awarded.
PPI #218
Response
The response to PPI 218 did not provide clear direction. The response appears to be directed to the government from HDR to provide the final response. Please clarify if the HVAC system for the Supply Warehouse should be as required per the results of the LCCA performed by the government. If the intent is to change the system, please provide clear direction as to what the revised HVAC shall be in order for a complete bid to be provided.
A heat pump DX unit with hot gas reheat (no electric reheat) and supplemental hot water coil is acceptable for the warehouse building. It can be a packaged unit, but cannot be a RTU. If the duct is outdoors, must use phenolic duct.
(End of Summary Changes)