Amendment 0009 - 01 31 23.13 20 - ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM.pdf
PDF 37 KB Posted
- Attached to
- DESIGN-BUILD, P-1458 2ND RADIO BATTALION COMPLEX, PHASE 2 MARINE CORPS BASE, CAMP LEJEUNE, NORTH CAROLINA
- Solicitation number
- N4008523R2557
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2ND RADIO BATTALION COMPLEX PHASE II 19P1458
MCB CAMP LEJEUNE, NC ePROJECTS W.O. NO.: 1397586
SECTION 01 31 23.13 20
ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM
05/ 17, CHG 7: 11/ 21
PART 1 GENERAL
1.1 CONTRACT ADMINISTRATION
Utilize the Naval Facilities Engineering Command's (NAVFAC's) Electronic Construction and Facility Support Contract Management System (eCMS) for the transfer, sharing, and management of electronic technical submittals and documents. The web-based eCMS is the designated means of transferring technical documents between the Contractor and the Government. Paper media or e-mail submission, including originals or copies, of the documents identified in Table 1 are not permitted, except where eCMS is unavailable, non-functional, or specifically requested in addition to electronic submission.
1.1.1 Format Naming Convention for Files Uploaded Into eCMS
Include the identification number of the document, the type of document, the name/subject or title, and for daily reports, the date (day of work) with format YYYY/MM/DD in the filename. For example, for RFI's, 0011_RFI_Roof_Leaking.doc; for submittals, 0032a_Submittals_Light_Fixture.pdf; for Daily Reports, 0132_Daily_Report_20190504.xls. Contact the Contracting Officer's Representative (COR) regarding availability of eCMS training and reference materials.
1.1.2 Uploading Documents Processed Outside of eCMS
When specifically requested to provide documents outside of eCMS, upload all final project documentation (e.g., documents that are signed and/or adjudicated by the Government) mentioned in Table 1 into eCMS by creating a record in the module associated with that document type and uploading the document(s). Subject/title of the record should include the type of record i.e., RFI/Submittal/Other, the identification number(s), and the statement "Processed Outside of eCMS". For example, "RFI 001-012 Processed Outside of eCMS".
1.2 USER PRIVILEGES
The Contractor will be provided access to eCMS. All technical submittals and documents must be transmitted to the Government via the COR. Project roles and system roles will be established to control each user's menu, application, and software privileges, including the ability to create, edit, or delete objects.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
SECTION 01 31 23.13 20 Page 1
List of Contractor's Personnel ; G
1.4 SYSTEM REQUIREMENTS AND CONNECTIVITY
1.4.1 General
The eCMS requires a web-browser (platform-neutral) and Internet connection. Obtain from an approved vendor an External Certification Authority (ECA), Primary Key Infrastructure (PKI) certificate, or other similar digital identification to support two-factor authentication and access to eCMS. Provide and maintain computer hardware and software for the eCMS access throughout the duration of the contract for all Contractor-designated users. Provide connectivity, speed, bandwidth, and access to the Internet to ensure adequate functionality. 70 mbps download speed recommended, 40 mbps minimum for loading large files. Neither upgrading of the Contractor's computer system nor delays associated from the usage of the eCMS will be justification or grounds for a time extension or cost adjustment to the Contract.
1.4.2 Contractor Personnel List
Within 20 calendar days of contract award, provide to the Contracting Officer a list of Contractor's personnel who will have the responsibility for the transfer, sharing and management of electronic design, technical submittals and documents and will require access to the eCMS. Project personnel roles to be filled in the eCMS include the Contractor's Project Manager, Designer of Record, Superintendent, Quality Control (QC) Manager, and Site Safety and Health Officer (SSHO). Personnel must be capable of electronic document management. Notify the COR immediately of any personnel changes to the project. The Contracting Officer reserves the right to perform a security check on all potential users. Provide the following information:
First Name Last Name E-mail Address Office Address Project Role (e.g. Project Manager, QC Manager, Superintendent)
1.4.3 Field Administration
Within 30 days of Contract Award, provide a tablet computer with a Common Access Card (CAC) reader at the job site for Government use only. The tablet computer must have a minimum 10-inch (measured diagonally) screen size, Windows or Apple Operating System, 16 GB Internal Memory (RAM), 256GB Hard Drive, GPS, WIFI, web-browser, built-in camera, and cellular data connectivity. Manufacturer date on the tablet should be within 2 years of contract award. Provide tablet computer with a rugged case suitable for use in a construction environment. The tablet computer must be fully charged and made available at all times for Government use to facilitate the input of construction data at the job site. The tablet will be given back to the contractor prior to leaving the jobsite for charging, maintaining and securing. After completion of the work, reset the tablet computer to factory default settings. The tablet computer remains the property of the Contractor and must be removed from the site.
There are restrictions on use of WIFI on military bases. Cellular data connectivity and availability, and use of WIFI requires coordination with and approval by the Contracting Officer.
SECTION 01 31 23.13 20 Page 2
1.5 SECURITY CLASSIFICATION
In accordance with Department of Navy guidance, all military construction contract data are unclassified, unless specified otherwise by a properly designated Original Classification Authority (OCA) and in accordance with an established Security Classification Guide (SCG). Refer to the project's OCA when questions arise about the proper classification of information.
The eCMS and tablet computer must only be used for the transaction of unclassified information associated with construction projects. In conformance with the Freedom of Information Act (FOIA), DoD INSTRUCTION
5200.48 CONTROLLED UNCLASSIFIED INFORMATION (CUI), and DoD requirements, any unclassified project documentation uploaded into the eCMS must be designated either "U - UNCLASSIFIED" (U) or "CUI - CONTROLLED UNCLASSIFIED
INFORMATION"
(CUI).
1.6 ECMS UTILIZATION
Establish, maintain, and update data and documentation in the eCMS throughout the duration of the contract.
Personally Identifiable Information (PII) transmittal is not permitted in the eCMS.
1.6.1 Information Security Classification/Identification
The eCMS must be used for the transmittal of the following documents.
This requirement supersedes conflicting requirements in other sections, however, submittal review times in Section 01 33 00 SUBMITTAL PROCEDURES remain applicable. Table 1 - Project Documentation Types provides the appropriate U and CUI designations for various types of project documents. Construction documents requiring CUI status must be marked accordingly. Apply the appropriate markings before any document is uploaded into eCMS. Markings are not required on U documents.
Table 1 also identifies which eCMS application is to be used in the transmittal of data (these are subject to change based on the latest software configuration). If a designated application is not functional within 4 hours of initial attempt, defer to the Submittal application and submit the required data as an uploaded portable document (e.g. PDF), word processor, spreadsheet, drawing, or other appropriate format. Hard copy or e-mail submission of these items is acceptable only if eCMS is documented to be not available or not functional or specifically requested in addition to electronic submission. After uploading documents to the Submittal application, transmit the submittals and attachments to the COR via the Transmittal application. For Submittals, select the following:
Preparation by = Contractor personnel assigned to prepare the submittal Approval by = Contracting Officer Representative (COR) Returned by = Design Lead/Manager Forwarded to = Contractor project manager
Table 1 - Project Documentation Types
SECTION 01 31 23.13 20 Page 3
SUBJECT/NAME DESIG REMARKS ECMS APPLI CATI ON
As-Built Drawings U Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
Submittals and Transmittals
Building Information Modeling (BIM)
U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Submittals and Transmittals
Construction Permits U Refer to rules of the issuing activity, state or jurisdiction
Submittals and Transmittals
Construction Schedules (Activities and Milestones)
U After the schedule submittal is approved by the COR, import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Submittals, Transmittals and Scheduling App
Construction Schedules (Cost-Loaded)
CUI After the schedule submittal is approved by the COR, import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Submittals, Transmittals and Scheduling App
Construction Schedules (3-Week Lookahead)
U Import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Scheduling App
DD 1354 Transfer of Real Property
U Submittals and Transmittals
Daily Production Reports
CUI Provide weather conditions, crew size, man-hours, equipment, and materials information
Daily Report
Daily Quality Control (QC) Reports
CUI Provide QC Phase, Definable Features of Work Identify visitors
Daily Report
SECTION 01 31 23.13 20 Page 4
SUBJECT/NAME DESIG REMARKS ECMS APPLI CATI ON
Designs and Specifications
U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Submittals and Transmittals
Environmental Notice of Violation (NOV), Corrective Action Plan
U Refer to rules of the issuing activity, state or jurisdiction
Submittals and Transmittals
Environmental Protection Plan (EPP)
CUI Submittals and Transmittals
Invoice (Supporting Documentation)
CUI Applies to supporting documentation only. Invoices are submitted in Wide-Area Workflow (WAWF)
Submittals and Transmittals
Jobsite Documentation, Bulletin Board, Labor Laws, SDS
U Submittals and Transmittals
Meeting Minutes CUI Meeting Minutes
Modification Documents
CUI Provide final modification documents for the project. Upload into "Modifications - RFPs
Document Management
Operations & Maintenance Support Information (OMSI/eOMSI), Facility Data Worksheet
U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Submittals and Transmittals
Photographs U Subject to base/installation restrictions
Submittals and Transmittals
QCM Initial Phase Checklists
CUI Checklists (Site Management)
SECTION 01 31 23.13 20 Page 5
SUBJECT/NAME DESIG REMARKS ECMS APPLI CATI ON
QCM Preparatory Phase Checklists
CUI Checklists (Site Management)
Quality Control Plans CUI Submittals and Transmittals
QC Certifications U Submittals and Transmittals
QC Punch List U Punch Lists (Testing Logs)
Red-Zone Checklist U Checklists (Site Management)
Rework Items List CUI Punch Lists (Testing Logs)
Request for Information (RFI) Post-Award
CUI RFIs
Safety Plan CUI Daily Report
Safety - Activity Hazard Analyses (AHA)
CUI Daily Report
Safety - Mishap Reports
CUI Daily Report
SCIF/SAPF
Accreditation Support Documents
CUI Note: Some Construction Security plans may be classified as Secret.
Classified information must not be uploaded into eCMS. Refer to the Site Security Manager, as applicable.
Submittals and Transmittals
Shop Drawings U Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
Submittals and Transmittals
Storm Water Pollution Prevention (Notice of Intent - Notice of Termination)
U Refer to rules of the issuing activity, state or jurisdiction
Submittals and Transmittals
SECTION 01 31 23.13 20 Page 6
SUBJECT/NAME DESIG REMARKS ECMS APPLI CATI ON
Submittals and Submittal Log
U Submittals and Transmittals
Testing Plans, Logs, and Reports
CUI Submittals and Transmittals
Training/Reference Materials
U Submittals and Transmittals
Training Records (Personnel)
CUI Submittals and Transmittals
Utility Outage/Tie-In Request/Approval
CUI Submittals and Transmittals
Warranties/BOD Letter CUI Submittals and Transmittals
Quality Assurance Reports
CUI Checklists (Government initiated)
Non-Compliance Notices
CUI Non-Compliance Notices (Government initiated)
Other Government-prepared documents
CUI GOV ONLY
All Othere Documents CUI Refer to FOIA guidelines and contact the FOIA official to determine whether exemptions exist
As applicable
1.6.2 Markings on CUI documents
a. Only CUI documents being electronically uploaded into the eCMS (.docx, .xlsx, .pptx, .pdf, .jpg, .zip, and others as appropriate), and associated paper documents described in the paragraph CONTRACT ADMINISTRATION require CUI markings as indicated in the subparagraphs below.
b. CUI documents that are originally created within the eCMS application using the web-based forms (RFIs, Daily Reports, and others as appropriate) will be automatically watermarked by the eCMS software, and these do not require additional markings.
c. CUI documents must be marked "CONTROLLED UNCLASSIFIED INFORMATION" at the bottom of the outside of the front cover (if there is one), the title page, the first page, and the outside of the back cover (if there is one).
SECTION 01 31 23.13 20 Page 7
d. CUI documents must be marked on the internal pages of the document as "CONTROLLED UNCLASSIFIED INFORMATION" at top and bottom.
e. Where Installations require digital photographs to be designated CUI, place the markings on the face of the photograph.
f. For visual documentation, other than photographs and audio documentation, mark with either visual or audio statements as appropriate at both the beginning and end of the file.
1.7 QUALITY ASSURANCE
Requested Government response dates on Transmittals and Submittals must be in accordance with the terms and conditions of the Contract. Requesting response dates earlier than the required review and response time, without concurrence by the Government COR, may be cause for rejection.
Incomplete submittals will be rejected without further review and must be resubmitted. Required Government response dates for resubmittals must reflect the date of resubmittal, not the original submittal date.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
-- End of Section --
SECTION 01 31 23.13 20 Page 8