Attachment A - 1397586rfp01of03.pdf

PDF 31 MB Posted

Attached to
DESIGN-BUILD, P-1458 2ND RADIO BATTALION COMPLEX, PHASE 2 MARINE CORPS BASE, CAMP LEJEUNE, NORTH CAROLINA
Solicitation number
N4008523R2557
Issued by

View the file

Other files

File Type Posted
AMENDMENT 0010.pdf PDF
Amendment 0010 - Attachment B - Price Proposal Form - REV 3.docx DOCX document
Amendment 0009 - 23 09 23.13 - BACNET DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC.pdf PDF
Amendment 0009 - PPI 393 2015-2020_MCBCL_INRMP_MASTER.pdf PDF
Amendment 0009 - 25 05 11.00 - CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS - ISOLATED SYSTEMS.pdf PDF
Amendment 0009 - 01 78 23 - OPERATION AND MAINTENANCE DATA.pdf PDF
Amendment 0009 - 01 78 30.00 22 - GIS DATA DELIVERABLES.pdf PDF
AMENDMENT 0009.pdf PDF
Amendment 0009 - Attachment B - Price Proposal Form - REV 2.docx DOCX document
Amendment 0009 - 01 31 23.13 20 - ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM.pdf PDF
Amendment 0009 - 6_ESR_E20 - Furnishings.pdf PDF
Amendment 0009 - 01 78 00 - CLOSEOUT SUBMITTALS.pdf PDF
Amendment 0008.pdf PDF
Amendment 0007.pdf PDF
Amendment 0006 - PPI 129 - Supply Warehouse Space Tabulation.pdf PDF
Amendment 0006 - Attachment F - DFARS 252.225-7059 AND 7060.pdf PDF
Amendment 0006 - PPI 129 - Estimated Electrical Loads - Combined Facility.pdf PDF
Amendment 0006 - PPI 129 - Supply Warehouse Affinity Diagram.pdf PDF
Amendment 0006.pdf PDF
Amendment 0005.pdf PDF
Amendment 0004.pdf PDF
Amendment 0003.pdf PDF
Amendment 0003 - Attachment 1 - Combined Vehicle Maintenace Facility and Boat Operations Facility.pdf PDF
Amendment 0003 - P1458 MACC General Requirements - Rev 1.pdf PDF
Amendment 0002.pdf PDF
Amendment 0002 - Site Visit Roster P-1458.pdf PDF
Amendment 0001 - Attachment 1 - 01 78 00 PPI 3.pdf PDF
Amendment 0001 - Attachment 2 - REGISTER.pdf PDF
Amendment 0001.pdf PDF
Amendment 0001 - Attachment 3 - Table of Contents.pdf PDF
P1458 MACC General Requirements.pdf PDF
Attachment E - PIEE Vendor Access Instructions.pdf PDF
Attachment C - Pre-Proposal Inquiry (PPI) Form.xlsx XLSX spreadsheet
Attachment A - 1397586rfp02of03.pdf PDF
Attachment A - 1397586rfp03of03.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WORK ORDER NO. 1397586

CONSTRUCTION CONTRACT

No.: XXXXX-XX-X-XXXX

APPROPRIATION: MILCON

2ND Radio Battalion Complex, Phase II

At

Camp Lejeune, NC

(P-1458)

SUBMITTED BY:

HDR

440 S. Church St, Suite 00

Charlotte, NC 28202

DB RFP Submission

PREPARED BY:

Civil:

Landscape:

Architectural:

Interior Design:

Structural:

Mechanical:

Electrical:

Cyber Security:

Fire Protection:

Submitted By:

Date:

, P.E.;

David West, LA.; HDR Zachary Kane, R.A.; HDR Kevin Lynch, NCIDQ; HDR Randy Maccaferri, P.E.; HDR

P.E.; HDR

P.E.; HDR

HDR

Adam Senk, P.E.; HDR

Nicholas Nash R.A. HDR 29 Novem 20

APPROVED BY:

For Commander, NAVFAC Mid-Atlantic:

Date:

James E. Donahue, RA

04:10:07 PM 12-01-2022 (-05'00' GMT)

This page intentionally left blank.

RFP

Table of Contents

2ND RADIO BATTALION COMPLEX PHASE II 19P1458

MCB CAMP LEJEUNE, NC ePROJECTS W.O. NO.: 1397586

RFP Table of Contents

PART 1 - PROPOSAL FORMS AND DOCUMENTS (BY NAVFAC)

PART 2 - GENERAL REQUIREMENTS

01 14 00 Work Restrictions

01 20 00 Price And Payment Procedures

01 30 00 Administrative Requirements

01 31 19.05 20 Concept Design Workshop (CDW)

01 31 23.13 20 Electronic Construction And Facility Support Contract Management System

01 32 17.05 20 Cost-Loaded Network Analysis Schedules (NAS)For Design-Build

01 33 00.05 20 Construction Submittal Procedures

01 33 10.05 20 Design Submittal Procedures

01 33 29 Sustainability Requirements And Reporting

01 35 26 Governmental Safety Requirements

01 45 00.05 20 Design And Construction Quality Control

01 45 35 Special Inspections

01 50 00 Temporary Construction Facilities And Controls

01 50 00.05 20 Temporary Facilities And Controls For Design-Build

01 57 19 Temporary Environmental Controls

01 57 19.01 20 Supplemental Temporary Environmental Controls

01 60 00.00 22 Requirements For Pesticide And Herbicide Coordination

01 74 19 Construction Waste Management And Disposal

01 78 23 Operation And Maintenance Data

01 78 24.00 20 Facility Electronic Operation and Maintenance Support Information (eOMSI)

01 78 30.00 22 GIS Data Deliverables 01 91 00.15 22 Total Building Commissioning

PART 3 - PROJECT PROGRAM

Chapter 1 - Project Description

Chapter 2 - Project Objectives

2.1 Mission Statement

2.2 Facility Function

2.3 Project Specific Priorities

2.4 Appropriate Design

2.5 Workflow Process

2.6 Special Design Challenges

2.7 Haul Route

2.8 Adaptability and Flexibility

Chapter 3 - Site Analysis

3.1 Para loft Facility, Supply Warehouse and Electronics / Communications Maintenance- Vehicle

Maintenance-Boat Operations Facility, Hazardous Material Storage Facility

3.2 Site Photos

Chapter 4 - Space Tabulation

Paraloft

Supply Warehouse

Hazardous Material Storage Facility

Combined Spaces

Chapter 5 - Room Requirements

Paraloft

Supply Warehouse

HazMat Storage Facility Hazmat Building Combined Elec-Comm-Auto-Boat

Chapter 6 - Engineering Systems Requirements - ESR

ESR_A10_Foundations

ESR_B10 - Super Structure

ESR_B20 - Exterior Enclosure

ESR_B30 - Roofing

ESR_C10 - Interior Construction

ESR_C20 - Stairs

ESR_C30 - Interior Finishes

ESR_D10 - Crane

ESR_D20 - Plumbing

ESR_D30 - Mechanical

ESR_D40 - Fire Protection

ESR_D50 - Electrical

ESR_E10 - Equipment

ESR_E20 - Furnishings

ESR_F10 - Special Construction

ESR_F20 - Selective Site Demolition

ESR_G10 - Site Preparation

ESR_G20 - Site Improvements

ESR_G30 - Site Civil Mechanical Utilities

ESR_G40 - Site Electrical Utilities

PART 4 – PERFORMANCE TECHNICAL SPECIFICATIONS

A10 Foundations

A20 Not Used

B10 Superstructure

B20 Exterior Enclosure

B30 Roofing

C10 Interior Construction

C20 Stairs

C30 Interior Finishes

D10 Conveying

D20 Plumbing

D30 HVAC

D40 Fire Protection

D50 Electrical

E10 Equipment

E20 Furnishings

F10 Special Construction

F20 Selective Site Demolition

G10 Site Preparations

G20 Site Improvements

G30 Site Mechanical Utilities

G40 Site Electrical Utilities

Z10 General Performance Technical Specification

PART 5 – PRESCRIPTIVE SPECIFICATIONS

23 05 93.00 22 Testing, Adjusting, And Balancing for Mechanical Systems

23 09 00.00 22 Instrumentation and Control for HVAC

23 09 13.00 22 Instrumentation and Control Devices for HVAC

23 09 23.02 22 BACNET Direct Digital Control for HVAC and Other Building

Control Systems

25 05 11.00 Cybersecurity for Facility-Related Control Systems -

Isolated Systems

26 27 14.20 Electric Meter Specification MCB Camp Lejeune

27 10 00 Building Telecommunications Cabling System (MCBCL)

28 31 76.22 Interior Combination Emergency Communications Systems

33 12 33.00 Water Meter Specification MCB Camp Lejeune

33 82 00 Telecommunications Outside Plant (OSP)

PART 6 – ATTACHMENTS

Chapter A - Miscellaneous Documents

• Camp Lejeune Base Exterior Architectural Plan (BEAP)

• Determining Compliance with the Guiding Principles for Sustainable Federal Buildings

• NAVFAC Sustainability and Energy Building Requirements

• Executive Order 13834 - Efficient Federal Operations

• Guiding Principles for Sustainable Federal Buildings and Associated Instructions

• Determining Compliance with the Guiding Principles for Sustainable Federal Buildings

• ESOP 10.1 - Vapor Intrusion Evaluation Program for Marine Corps Base Camp Lejeune and

Marine Corps Air Station New River

• Environmental Standard Operating Procedure (ESOP) 5090.21

• Per and Polyfluoroalkyl Substances Guidance for Construction

• NCDEQ Express Application Fee Chart 2022

Chapter B – Drawings

• Overall Site Plan

• Topographic Survey

• Partial Survey

Chapter C - Affinity Diagrams

• Parachute Maintenance and Paraloft

• Supply Warehouse

• Combined Electrical / Communications / Vehicle Maintenance, and Boat Operations Facility

• Hazardous Material Storage Facility

• Wash Rack and Pad

• Overall Site Plan

• Southwest Site – Parachute Maintenance with Paraloft and Supply Warehouse Site Plan

• Southeast Site – Vehicle Maintenance/Boat Operations Facility, and Hazardous Material Storage

Facility Site Plan

Chapter D - Low Impact Development

• Department of Navy Policy November 2007 Memorandum

• Low Impact Development Data – January 2017, Version 3.0

• Report Documentation Page – Standard Form 298 (Rev. 8-98)

• Low Impact Development Waiver Form

• LID Waiver Form Instructions

Chapter E - Mechanical and Fire Protection

• Fire Hydrant Flow Test

• IWD-MILCON FACP MNS 28 JAN 2015 Typical (US Version - Alkurdi)

• MNS Riser

• Baseline Energy Cost Data

• 22 14 00.00 22 - Rainwater Harvesting

• 22 33 30.05 22 - Solar Water Heating Equipment (Integrated Solar Hot Water)

• 22 33 31.05 22 - Integrated PV-Thermal System (Integrated Solar Hot Water & PV)

• 22 81 28.10 22 - Variable Refrigerant Flow (VRF) Multi-Split Air Conditioning and Heat Pump

• Equipment

• Camp Lejeune Mechanical Design Guidance Rev. July 2017

• 28 31 76 - Interior Fire Alarm and Mass Notification System, Addressable

Chapter F – Electrical

• Estimated Electrical Load – Paraloft and Supply Warehouse

• Estimated Electrical Load - Combined Electrical / Communications / Vehicle Maintenance, and

Boat Operations Facility and Hazardous Material Storage Facility

• Estimated Electrical Load – Wash Rack and Pad

• Lightning Risk Assessment – Parachute Maintenance with Paraloft

• Lightning Risk Assessment – Supply Warehouse

• Lightning Risk Assessment – Hazardous Materials Storage Facility

• 28 31 76.22 - Interior Combination Emergency Communications Systems

• MCB Camp Lejeune Electrical Policies and Criteria

• 26 31 00.00 22 – Solar Energy Electrical Power Generation Systems

Chapter G – FF&E

• Estimated Furnishings, Fixture and Equipment FF&E) Cost Summary

• Estimated Audio / Visual Cost Summary

Chapter H – Elevator Guide (Not Used - Refer to UFC 3-490-06 ELEVATORS)

Chapter I – Forms

• ATFP UFC 4-010-01 Checklist, Updated 19 August 2020

• NAVFAC MIDLANT Permits Record of Decision (PROD)

Chapter J – Reference Drawings and Documents

• SW8 110906 Permit Renewal 08.27.20 – Project Limits

• State Stormwater Management Permit No. SW8 110906 2D - Anglico and 2N BN OPS Complexes

- Overall Low Density Project With Areas Of Higher Density - Onslow County

Chapter K – Subsurface Soil Information

• Geotechnical Site Characterization Report 2nd Radio Battalion Complex Phase (P1458)

• Report of Geotechnical Exploration 2nd Radio Battalion Complex (P1280) Report of Geo-technical

Exploration 2nd Radio Battalion Complex (P1280)

PART 1 – PROPOSAL FORMS AND DOCUMENTS

PART 2 – GENERAL REQUIREMENTS

PROJECT TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 14 00 WORK RESTRICTIONS

01 20 00 PRICE AND PAYMENT PROCEDURES

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 31 19.05 20 CONCEPT DESIGN WORKSHOP (CDW)

01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT

MANAGEMENT SYSTEM

01 32 17.05 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)FOR

DESIGN-BUILD

01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES

01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REQUIREMENTS AND REPORTING

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 45 00.05 20 DESIGN AND CONSTRUCTION QUALITY CONTROL

01 45 35 SPECIAL INSPECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 50 00.05 20 TEMPORARY FACILITIES AND CONTROLS FOR DESIGN-BUILD

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS

01 60 00.00 22 REQUIREMENTS FOR PESTICIDE AND HERBICIDE COORDINATION

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 78 23 OPERATION AND MAINTENANCE DATA

01 78 24.00 20 FACILITY ELECTRONIC OPERATION AND MAINTENANCE SUPPORT

INFORMATION (eOMSI)

01 78 30.00 22 GIS DATA DELIVERABLES

01 91 00.15 22 TOTAL BUILDING COMMISSIONING

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION 01 14 00

WORK RESTRICTIONS

11/ 11, CHG 14: 02/ 22

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 .05 20 CONSTRUCTION SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Meal Signature Record Book (MSRB)

Dining And Lodging Requirements

Housing Plan

Medical Plan

Contractor Regulations

Transportation of Personnel, Materials, and Equipment

Purchase Orders

List of Contact Personnel

Personnel List

Entry Approval for Employees ; G

1.2 CONTRACTOR ACCESS AND USE OF PREMISES

1.2.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. To minimize traffic congestion, delivery of materials must be outside of peak traffic hours (6:30 to 8:00 a.m. and 3:30 to 5:00 p.m.) unless otherwise approved by the Contracting Officer. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.

1.2.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

SECTION 01 14 00 Page 1

1.2.1.2 Installation Access

Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/om/dbids.html . No fees are associated with obtaining a DBIDS credential.

Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.

1.2.1.2.1 Registration for DBIDS

Registration for DBIDS is available at https://www.cnic.navy.mil/om/dbids.html . Procedure includes:

a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.

b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.

c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/om/dbids.html .

d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, fingerprints, base restriction and several other assessments.

e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.

1.2.1.2.2 DBIDS Eligibility Requirements

Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.

An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification.

The Government is the final authority.

1.2.1.2.3 DBIDS Notification Requirements

a. Immediately report instances of lost or stolen badges to the Contracting Officer.

b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:

SECTION 01 14 00 Page 2

(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.

(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.

1.2.1.2.4 One-Day Passes

Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.

1.2.1.3 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer must identify designated smoking areas.

1.2.2 Working Hours

Regular working hours will consist of an 8 1/2 hour period, between 7 a.m.

and 3:30 p.m., Monday through Friday , and 7 a.m. to 3:30 p.m. on Saturday, excluding Government holidays.

1.2.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.2.4 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and are considered utility cutovers pursuant to the paragraph

WORK OUTSIDE REGULAR HOURS.

d. Operation of Station Utilities: The Contractor must not operate nor

SECTION 01 14 00 Page 3 disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.

e. Connection to Existing Sanitary Sewer Line: Provide positive verification that the existing line conveys sanitary sewer; verify line is not incorrectly connected to a storm drain. Obtain Installation's Sanitary Sewer Connection Permit 2 weeks prior to connection and in accordance with Section 33 30 00 SANITARY SEWERAGE.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 14 00 Page 4

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

11/ 20, CHG 2: 08/ 21

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EP 1110-1-8 (2021) Engineering and Design -- Construction Equipment Ownership and Operating Expense Schedule

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 .05 20 CONSTRUCTION SUBMITTAL PROCEDURES and

01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Earned Value Report ; G

1.3 EARNED VALUE REPORT

1.3.1 Data Required

This Contract requires the use of a cost-loaded Network Analysis Schedule (NAS). Schedule of Prices must not be used with cost-loaded Network Analysis Schedule (NAS). Use Earned Value Report derived from cost-loaded NAS. Within 15 calendar days of notice of award, prepare and deliver to the Contracting Officer a Earned Value Report (construction Contract) as directed by the Contracting Officer. Provide a detailed breakdown of the Contract price, giving quantities for each of the various kinds of work, unit prices and extended prices. Contractor overhead and profit including salaries for field office personnel, if applicable, must be proportionately spread over all pay items and not included as individual pay items.

1.3.2 Payment Schedule Instructions

Payments will not be made until the Earned Value Report from the cost-loaded NAS has been submitted to and accepted by the Contracting Officer. For design phase progress payment(s), the Schedule of Prices or Earned Value Report from the Cost Loaded CPM must include detailed design activities and general (summarized) approach for the construction phase(s) of the project. The Schedule of Prices or Earned Value Report must be fully developed with detailed construction line items as design progresses. The complete design and construction Schedule of Prices or Earned Value Report must be submitted and accepted prior to starting

SECTION 01 20 00 Page 1 construction work.

For Fast-Tracked or Critical Path Submittals of construction projects, the Earned Value Report must include detailed design and construction line items for each fast-tracked/ critical path phase(s), submitted to and accepted by the Contracting Officer during the Post Award Kickoff Meetings and confirmed prior to starting construction work in that phase.

Additionally, the Earned Value Report must be separated as follows:

a. Primary Facilities Cost Breakdown:

Defined as work on the primary facilities out to the 5 foot line.

Work out to the 5 foot line includes construction encompassed within a theoretical line 5 foot from the face of exterior walls and includes attendant construction, such as pad mounted HVAC cooling equipment, cooling towers, and transformers placed beyond the 5 foot line.

b. Supporting Facilities Cost Breakdown:

Defined as site work, including incidental work, outside the 5 foot line.

1.3.3 Schedule Requirements for HVAC TAB

The field work requirements in Section 23 05 93 .00 22 TESTING, ADJUSTING, AND BALANCING FOR MECHANICAL SYSTEMS must be broken down in the Earned Value Report from the cost-loaded NAS by separate line items which reflect measurable deliverables. The value for each pay item listed below must be established on a case by case basis for each Contract. The line items are as follows:

a. Approval of Design Review Report: The TABS Agency is required to conduct a review of the project plans and specifications to identify any feature, or the lack thereof, that would preclude successful testing and balancing of the project HVAC systems. Submit the resulting findings to the Government to allow correction of the design. The progress payment will not be issued until the report is reviewed and approved.

b. Approval of the pre-field engineering report: The TABS Agency submits a report which outlines the scope of field work. The report must contain details of what systems will be tested, procedures to be used, sample report forms for reporting test results and a quality control checklist of work items that must be completed before TABS field work commences.

c. Season I field work: Incremental payments are issued as the TABS field work progresses. The TABS Agency mobilizes to the project site and executes the field work as outlined in the pre-field engineering report. The HVAC water and air systems are balanced and operational data must be collected for one seasonal condition (either summer or winter depending on project timing).

d. Approval of Season I report: On completion of the Season I field work, the data is compiled into a report and submitted to the Government. The report is reviewed, and approved, after ensuring compliance with the pre-field engineering report scope of work.

e. Completion of Season I field QA check: Contract QC and Government

SECTION 01 20 00 Page 2 representatives meet the TABS Agency at the jobsite to retest portions of the systems reported in the Season I report. The purpose of these tests are to validate the accuracy and completeness of the previously submitted Season I report.

f. Approval of Season II report: The TABS Agency completes all Season II field work, which is normally comprised mainly of taking heat transfer temperature readings, in the season opposite of that under which Season I performance data was compiled. Compile this data into a report and submit to the Government. On completion of submittal review to ensure compliance with the pre-field engineering report scope, progress payment is issued. Progress payment is less than that issued for the Season I report since most of the water and air balancing work effort is completed under Season I.

1.4 CONTRACT MODIFICATIONS

In conjunction with the Contract Clause DFARS 252.236-7000 Modification Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, base equipment use rates upon the applicable provisions of the

EP 1110-1-8 .

1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT

1.5.1 Content of Invoice

Requests for payment must be processed in accordance with the Contract Clause FAR 52.232-27 Prompt Payment for Construction Contracts and FAR 52.232-5 Payments Under Fixed-Price Construction Contracts. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies. The requests for payment must include the documents listed below.

a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 must include certification by Quality Control (QC) Manager as required by the Contract.

b. The Earned Value Report from the cost-loaded NAS.

c. Contractor's Monthly Estimate for Voucher and Contractors Certification (NAVFAC Form 4330) with Subcontractor and supplier payment certification. Other documents, including but not limited to, that need to be received prior to processing payment include the following submittals as required. These items are still required monthly even when a pay voucher is not submitted.

d. Monthly Work-hour report.

e. Updated Construction Progress Schedule and tabular reports required by the contract.

f. Contractor Safety Self Evaluation Checklist.

g. Updated submittal register.

h. Solid Waste Disposal Report.

SECTION 01 20 00 Page 3

i. Certified payrolls.

j. Updated testing logs.

k. Other supporting documents as requested.

1.5.2 Submission of Invoices

If DFARS Clause 252.232-7006 Wide Area WorkFlow Payment Instructions is included in the Contract, provide the documents listed in above paragraph CONTENT OF INVOICE in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction, provide it as instructed by the Contracting Officer.

Monthly invoices and supporting forms for work performed through the anniversary award date of the Contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, if Contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.

1.5.3 Final Invoice

a. A final invoice must be accompanied by the certification required by DFARS 252.247.7023 Transportation of Supplies by Sea, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release.

b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor must then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.

c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.

1.6 PAYMENTS TO THE CONTRACTOR

Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.

1.6.1 Obligation of Government Payments

The obligation of the Government to make payments required under the provisions of this Contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR FAR

SECTION 01 20 00 Page 4

32.103 Progress Payments Under Construction Contracts:

a. Reasonable deductions due to defects in material or workmanship;

b. Claims which the Government may have against the Contractor under or in connection with this Contract;

c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and

d. Failure to maintain accurate "as-built" or record drawings in accordance with FAR 52.236.21.

1.6.2 Payment for Onsite and Offsite Materials

Progress payments may be made to the Contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:

a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.

b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment must be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.

c. Materials to be considered for progress payment prior to installation must be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Earned Value Report requirement of this Contract.

Requests for progress payment consideration for such items must be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 Payments Under Fixed-Price Construction Contracts have been met.

d. Materials are adequately insured and protected from theft and exposure.

e. Provide a written consent from the surety company with each payment request for offsite materials.

f. Materials to be considered for progress payments prior to installation must be stored either in the Continental United States. Other locations are subject to written approval by the Contracting Officer.

g. Materials in transit to the job site or storage site are not acceptable for payment.

SECTION 01 20 00 Page 5

1.7 SINGLE JOB PAYMENT ITEMS

1.7.1 Mobilization and Demobilization

1.7.1.1 Payment

Payment will be made for costs associated with mobilization and demobilization, as defined in Special Contract Clause PAYMENT FOR

MOBILIZATION AND DEMOBILIZATION.

1.7.1.2 Unit of Measure

Unit of measure: job.

1.7.2 Structure No. 1

1.7.2.1 Payment

Payment will be made for costs associated with operations necessary for construction of the structure at Station XX+XX.

1.7.2.2 Unit of Measure

Unit of measure: job.

1.7.3 Structure No. 2

1.7.3.1 Payment

Payment will be made for costs associated with operations necessary for construction of the structure at Station XX+XX.

1.7.3.2 Unit of Measure

Unit of measure: job.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 20 00 Page 6

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

11/ 20, CHG 1: 08/ 21

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES and

01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map

Progress and Completion Pictures

Design Submittal Packaging

Performance Assessment Plan (PAP)

1.3 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.4 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Include aerial photographs. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file. Include a date designator in file names.

SECTION 01 30 00 Page 1

Photographs provided are for unrestricted use by the Government.

1.5 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by North Carolina law.

1.6 SUPERVISION

1.6.1 Superintendent Qualifications

Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

1.6.2 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work.In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

1.6.3 Duties

The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.6.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.7 PRECONSTRUCTION MEETING

Immediately after award , upon completion of design and design acceptance by the government , prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Meeting . The meeting must take place within 35 calendar

SECTION 01 30 00 Page 2 days after award of the contract, but prior to commencement of any work at the site. The purpose of this meeting is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.

1.7.1 Attendees

Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.

1.8 POST AWARD KICKOFF (PAK) MEETING

Immediately after award, coordinate with the Contracting Officer a time and place for the PAK Meeting. The PAK meeting must be held within 35 calendar days after contract award and prior to commencing work. If mutually agreed upon by the Contractor and the Government, the PAK Meeting may be held concurrently with the Design Presentation/Design Development Meeting or Concept Design Workshop (CDW) whichever is required.

1.8.1 PAK Meeting Outcomes

a. Integrate the Contractor and all client representatives into the project team.

b. Achieve consensus from the project team on any issues and concerns with the Contractor's technical proposal and the User's functional requirements. Confirm the design is within the project budget.

c. Review the administrative requirements of the contract that are critical during the design phase.

d. Establish clear lines of communication and points of contact for Government and Contractor team members.

e. Obtain an acceptable conceptual design including floor and site plans, signed by the client, Contractor and other key team members.

f. Review the project design schedule and design package requirement, design submittal packaging , and preliminary construction schedule in accordance with Section 01 32 17.0 5 20 COST-LOADED NETWORK ANALYSIS SCHEDULE (NAS). Discuss design milestones and events that must be included in the Quality Control Communication Plan.

g. Establish clear expectations and schedules for facility turnover, providing DD Form 1354 asset management records, eOMSI submittals, Guiding Principle Validation, Third Party Certification (if applicable), and training of Government maintenance personnel.

h. Establish procedure for design packages reviews, Contractor's resolution to comments, and Government's role in review of packages.

i. Establish clear expectations for the Concept Design Workshop as

SECTION 01 30 00 Page 3 established in UFGS 01 31 19.05 20 CONCEPT DESIGN WORKSHOP (CDW).

j. Establish clear expectations for Design Model presentations for projects implementing Building Information Management/Modeling (BIM).

1.8.2 PAK Meeting Contractor Attendees

The following Contractor personnel must attend the PAK meeting; Project Manager, Project Scheduler, Lead Designer-of-Record (DOR), Design Staff responsible for each architectural/engineering discipline when facility design is discussed, Environmental Design/Permitting Specialist, Superintendent, QC Manager, and the DQC Manager and the Commissioning Authority (CA). Optional attendees include: Principal, Assistant Project Manager, major subcontractors and specialized supplemental QC personnel.

1.9 DESIGN PRESENTATION/DEVELOPMENT (DP/D)

The Contractor must lead discussions to develop an understanding of the facility design that the accepted technical proposal represents with the Government users and maintainers of the facility. Develop site plans, floor plans, exterior finish materials, and building elevations to conduct working sessions with the Government meeting attendees. The purpose of the DP/D Meeting is to confirm the appropriateness of the facility design and develop acceptable alternatives if changes are needed. The Contractor must anticipate that Government Facility Users represented at the DP/D Meeting will provide additional functional information. Incorporate functional design changes into the facility design as required to meet the needs of the Users. At the end of the DP/D Meeting the Contractor must provide either assurance that the updated design can be built within the budget or identify potential cost modification items and establish a follow-on DP/D Meeting to finalize a design that will include trade-offs to bring the project within the budget. The following Contractor key personnel must attend the Design Presentation: Project Manager, Project Scheduler, Cost Estimator, Lead Designer of Record, Design Staff responsible for each architectural/engineering discipline when facility design is discussed, Environmental Design/Permitting Specialist, Major Subcontractors, and DQC.

Demonstrate ability to achieve identified Guiding Principle sustainability goals and also Third-Party Certification sustainability goals, if applicable. Provide Preliminary Sustainability Notebook, refer to Section 01 33 29 SUSTAINABILITY REQUIREMENTS AND REPORTING for requirements.

1.10 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)

Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled NRZ Meetings beginning at approximately 75 percent of project completion.

Include the following in the facility Turnover effort:

1.10.1 Red Zone Checklist

a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the Red Zone Checklist template.

b. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project

SECTION 01 30 00 Page 4 and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.

1.10.2 Meetings

a. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.

b. The Contracting Officer will establish the frequency of the meetings, which is expected to increase as the project completion draws nearer.

At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.

c. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.

d. During the Red Zone Meetings discuss with the COTR any upcoming activities that require Government involvement.

e. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress.

Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.

1.11 PARTNERING

Contractor must host the partnering session within 45 calendar days of contract award. To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, NAVFAC, PWD, FEAD/ROICC, Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.

1.11.1 Facilitated (Formal) Partnering

a. Within 35 calendar days after award and prior to the start of work, host a Formal Partnering session with key personnel from the project team including both Contractor and Government personnel. All costs associated with the Partnering session including the third-party independent Facilitator Consultant, meeting room and other incidental items are the responsibility of the Contractor.

b. Before the Facilitated (Formal) Partnering session, coordinate with the Facilitator all requirements for incidental items (such as audio-visual equipment, easels, flipchart paper, colored markers, note pads, pens/pencils, colored flash cards) and have these items available at the Partnering session. Provide copies of any documents required for distribution to all attendees. Participants must bear their own costs for meals, lodging and transportation associated with

SECTION 01 30 00 Page 5

Partnering .

c. The Initial Partnering Session must be a duration of one day and be held at a location off base as agreed to by the Contracting Officer.

Partnering session may take place concurrently with the Pre-Construction Post-Award Kickoff Meeting.

d. Facilitator must be experienced in conducting corporate Partnering sessions and must be a third-party independent facilitating consultant

- not an employee of the Contractor. The Facilitator is responsible for leading all aspects of the Partnering session necessary to achieve the Partnering goal.

e. An outcome of the Partnering session must be an escalation matrix agreed upon by both the Government and Contractor, which identifies key Government and Contractor decision makers by name and anticipated decision durations.

f. Host follow-on Partnering Sessions at three- to six-month intervals or more frequently if needed and lasting generally a half day or less.

Attendees need only be those required to resolve current issues. The same Facilitator used in the Initial Partnering session must lead the follow-on sessions unless an alternative is permitted by the Contractor Officer. All costs associated with follow-on Partnering sessions are the responsibility of the Contractor.

1.12 PERFORMANCE ASSESSMENT PLAN (PAP)

The Performance Assessment Plan (PAP) must be used to document design innovation and budget management, provide performance feedback to the Contractor, and as a basis for interim and final evaluations in the Contractor Performance Appraisal Reporting System (CPARS) on-line database.

It is the intent of the Government to establish the PAP based on tangible, measurable indicators of outstanding contractor performance, and on commitments made in the Contractor's proposal. The initial PAP may be found on the NAVFAC Design-Build Request for Proposal Website in RFP PART 6 Attachments. Review and finalize the initial PAP during the Partnering Session. During the initial Partnering Session, the Government, the Contractor, the Designer-of-Record, and the Client must establish the PAP.

Following the establishment of the PAP, the Contractor must present it, with his input, for update and discussion at projects meetings which discuss project performance. Submit an updated PAP on a monthly basis with the invoice for that period as a minimum.

1.13 MOBILIZATION

Contractor must mobilize to the jobsite within 30 calendar days of final site or building design approval. Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 30 00 Page 6

SECTION 01 30 00 Page 7

SECTION 01 31 19.05 20

CONCEPT DESIGN WORKSHOP (CDW)

02/21

PART 1 GENERAL

1.1 SUMMARY

This document includes post-award requirements for the concept design workshop.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REQUIREMENTS AND REPORTING. Submit the following in accordance with Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES and 01 33 10.05 20

DESIGN SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

CDW Facilitator Experience Resume ; G

CDW Preliminary Concept Design ; G

CDW Report ; G

1.3 CONCEPT DESIGN WORKSHOP (CDW)

Provide a CONCEPT DESIGN WORKSHOP that meets the following requirements:

1.3.1 CDW General Requirements

a. Methodology. Conduct a CDW for this project. This effort must examine programmatic functions, review project requirements, ensure life and operational safety requirements are met, analyze alternate design concepts, expose and resolve project issues, and develop the final conceptual design.

b. Facilitator. Provide a Facilitator who is experienced in conducting Concept Design Workshops. Submit a CDW Facilitator Experience Resume to the Contracting Officer describing experience with facilitation including a minimum of three examples. He or she must be responsible for leading the team in a timely manner, making sure issues are addressed and resolved during the CDW, documenting meetings held throughout the CDW, organizing concept design documents for on-site presentations and endorsement, and providing the Concept Design Workshop Report.

c. Contractor's Design Team. The primary functions of the Design Team will be to investigate, develop and present alternate design solutions. The entire Design Team must participate in all phases of the Concept Design Workshop and assist the Facilitator in developing the Concept Design Workshop Report.

SECTION 01 31 19.05 20 Page 1

d. Concept Design Workshop Report. Summarize the workshop including the various concepts developed and presented. Include a copy of the signature/endorsement sheet prepared and signed at the end of the on-site CDW.

e. Award Amount. Confirm the final concept is within the contract award amount.

1.3.2 CDW Procedures

a. Preliminary Work.

Complete the following prior to the on-site workshop:

(1) Review the contract documents and references explaining the project scope and history.

(2) Prepare and submit, at least 14 days in advance of the CDW, electronic copies and an agreed upon number of hard copies of a CDW Preliminary Concept Design (Concept #1) , Preliminary Permit Record of Discussion form, and a Basis…