About this file
WI 0802 REV-1
View the file
Other files for this federal contract opportunity
Show all 43
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USS MT WHITNEY
(LCC 20)
HEATING, VENTILATION & AIR CONDITIONING N00033-11-R-7501
AMEND 0003 MAY 31 2016
ITEM NO. 0802 Category "B" MSC/N74/RHA
MISCELLANEOUS DUCT REPLACEMENT
0802-1
1.0 ABSTRACT
This work item requires the contractor to submit a
Category ‘‘B’’ unitized price list for the replacement of various sizes of ductwork and elbows.
2.0 REFERENCES:
2.1 NAVSEA 501-8386912, HVAC Diagram
3.0 ITEM LOCATION AND DESCRIPTION
3.1 Location/Quantity:
3.1.1Location: Various areas throughout the ship
3.1.2See Tables 802-1 and 802-2
3.1.3 Evaluation will be based on the total price.
Each unit may be exercised, in part or multiple quantities.
3.1.4 Prices provided in these unit prices will be
reasonably similar to the prices negotiated and proposed throughout the duration of this contract.
4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIALS/SERVICES: None
5.0 NOTES
5.1 The contractor and subcontractors must consult Military
Sealift Command’s General Technical Requirements, (GTR’s), to determine applicability to this work item.
The contractor and all subcontractors must comply with all applicable GTR requirements.
5.2 The contractor and subcontractors shall review other
work items under this contract, to determine their effect on the work required by this item. Based on this review the contractor shall plan and schedule work to minimize conflicts between work items.
0802-2
5.3 The definitions of many terms used in this work item
are found in Work Item 001.
5.4 The USS Mount Whitney is known to have a considerable
amount of asbestos. Additionally, it is known that the coating systems may contain lead. The contractor should expect this condition and factor in removal and remediation time requirements into his overall planning schedule. Costs associated with unexpected hazardous waste remediation and removal shall be attributed to
Work Item 023, rather than to the individual work items. Wastes removed in the course of work package accomplishment shall be removed from the ship, handled and disposed of in accordance with Work Item 023 of this work package. Contractor shall be responsible to follow all international, national and US Federal regulations in the containment and removal of these wastes as encountered.
5.5 The contractor is expected to use best management
practice to identify and dispose of all hazardous waste. Every effort shall be made to minimize the disturbance, removal and handling of hazardous wastes in the accomplishment of the work package
6.0 QUALITY ASSURANCE REQUIREMENTS: None additional
7.0 STATEMENT OF WORK
7.1 Submit a Condition Found Report (CFR) to MSCREP
identifying each designated duct replaced. CFR shall include the following:
a. Location of repair
b. Length of ducting
c. Size of duct to be replaced
d. Number/type/size of fittings to be replaced
e. Interferences
0802-3
7.2 Provide all labor, material, and services required to
remove and replace ducting as designated by the MSCREP.
For bidding purposes:
a. See Table 802-1 and 802-2 for sizes and length of ducting to be replaced.
b. Contractor shall provide four (4) duct hangers, per (3) meter straight section of ducting.
Contractor shall provide two (2) duct hangers for each elbow section of ducting.
c. Contractor shall provide for removal and renewal of ducting insulation with new insulation to match existing.
d. Contractor shall assume the newly installed insulation shall be painted to match existing.
e. Contractor shall perform an operational test prior to application of insulation to the satisfaction of the MSCREP. No leakage allowed.
f. Contractor shall mark/stencil ducting as required to designate ducting and flow.
8.0 GENERAL REQUIREMENTS: None additional
0802-4
Table 802-1, AMEND 0003
Square Metal Duct
(THICKNESS)
Length
Unit Bid
Price
200 mm X 300 mm, straight
(.8mm) 3 Meters
200 mm X 300 mm, elbow
(.8mm)
300 mm X 300 mm, straight
(.8mm) 3 Meters
300 mm X 300 mm, elbow
(.8mm)
300 mm X 450 mm, straight
(.9mm) 3 Meters
300 mm X 450 mm, elbow
(.9mm)
450 mm X 450 mm, straight
(.9mm) 3 Meters
450 mm X 450 mm, elbow
(.9mm)
600 mm X 600 mm, straight
(1.2mm) 3 Meters
600 mm X 600 mm, elbow
(1.2mm)
0802-5
Table 802-2 AMEND 0003
Round Metal Duct
(THICKNESS)
UNIT
SIZE
UNIT BID
PRICE
200 mm diameter (.8mm) 3 Meters
200 mm diameter, elbow
(.8mm)
250 mm diameter (.8mm) 3 Meters
250 mm diameter, elbow
300 mm diameter (.8mm) 3 Meters
300 mm diameter, elbow
450 mm diameter (.9mm) 3 meters
450 mm diameter, elbow
(.9mm)
600 mm diameter (1.2mm) 3 Meters
600 mm diameter, elbow
(1.2mm)
File details come from the government source that posted it. Updated .