Exhibit_A_to_N00024-18-R-5200_DD_Form_1423s_CDRLs_20_June_2018.pdf

DoD Form Jun 20, 2018 PDF 2 MB Posted

Attached to
FY 20-24 Cooperative Engagement Capability Design Agent and Engineering Services
Solicitation number
N0002418R5200
Issued by

About this file

Exhibit A CDRLs for Solicitation N00024-18-R-5200-0005

View the file

Other versions and copies of DD Form 1423S

File Revision Posted Attached to
EXHIBIT A - CDRLs A001-A015 DD 1423s_Rev001.pdf Rev. 001 Mobile Aircraft Arresting System (MAAS)
FMS F4 Repairs DD1423s - 22 Nov 23.pdf Nov 22, 2023 F-4 Spare Parts
RFP Attachment 13 - Sensor Beam 2024 CDRL A013-A014 DD 1423s 29 Aug 2022.pdf Aug 29, 2022 Sensor Beam 2024 - DRAFT RFP
RFP Attachment 13 - Sensor Beam 2024 CDRL A009-A012 DD 1423s 29 Aug 2022.pdf Aug 29, 2022 Sensor Beam 2024 - DRAFT RFP
RFP Attachment 13 - Sensor Beam 2024 CDRL A005-A008 DD 1423s 29 Aug 2022.pdf Aug 29, 2022 Sensor Beam 2024 - DRAFT RFP
RFP Attachment 13 - Sensor Beam 2024 CDRL A001-A004 DD 1423s 29 Aug 2022.pdf Aug 29, 2022 Sensor Beam 2024 - DRAFT RFP
Attach 16 - Consolidated DD1423s_28 Feb 22.pdf Feb 28, 2022 SOLICITATION NOTICE/ Request for Proposals (RFP) for Keesler Air Force Base (KAFB) Base Operations Support (BOS)
Attach 16 - DD1423s Consolidated 2-32_8 Dec 21.pdf Dec 8, 2021 SOLICITATION NOTICE/ Request for Proposals (RFP) for Keesler Air Force Base (KAFB) Base Operations Support (BOS)
Attach 16 - DD1423s Consolidated Section 2-32_ 17 Nov 21.pdf Nov 17, 2021 SOLICITATION NOTICE/ Request for Proposals (RFP) for Keesler Air Force Base (KAFB) Base Operations Support (BOS)
Attachment 6 - CDRL DD1423s.pdf Revision not stated Amendment 1 - Solicitation - Kleine Brogel AB, Belgium Installation Warning System (IWS)
EXHIBIT B - CDRLs B001-B003 - DD 1423s.pdf Revision not stated Mobile Aircraft Arresting System (MAAS)
EXHIBIT A - CDRLs A001-A015 - DD 1423s.pdf Revision not stated Mobile Aircraft Arresting System (MAAS)
EXHIBIT F - CDRLs F001-F003 - DD 1423s.pdf Revision not stated Mobile Aircraft Arresting System (MAAS)
EXHIBIT E - CDRLs E001-E003 - DD 1423s.pdf Revision not stated Mobile Aircraft Arresting System (MAAS)
EXHIBIT C - CDRLs C001-C003 - DD 1423s.pdf Revision not stated Mobile Aircraft Arresting System (MAAS)
EXHIBIT D - CDRLs D001-D003 - DD 1423s.pdf Revision not stated Mobile Aircraft Arresting System (MAAS)
EXHIBIT G - CDRLs G001-G003 - DD 1423s.pdf Revision not stated Mobile Aircraft Arresting System (MAAS)
DD1423s F-4 Repair and Overhaul.pdf Revision not stated FA822024R3002 F-4 Repair and Overhaul
DD1423s.pdf Revision not stated Repair of ALQ-131, ALQ-161, and ALQ-172
Attachment 6 - T1 OandI CDRLs (DD1423s).pdf Revision not stated SDA Tranche 1 Operations & Integration (O&I)
Show all 20

Who attaches DD Form 1423S

Other files

File Type Posted
N00024-18-R-5200_Bidder's_Question_Responses_6.27.18.pdf PDF
N00024-18-R-5200_Bidder's_Question_Responses_6.26.18.pdf PDF
N00024-18-R-5200-0006_Conformed.docx DOCX document
Attachment_18_SLOC_Worksheet_Rev1.zip ZIP file
N00024-18-R-5200-0006.docx DOCX document
N00024-18-R-5200_Bidder's_Question_Responses_6.22.18.pdf PDF
Attachment_18_SLOC_Worksheet.zip ZIP file
N00024-18-R-5200-0005_Conformed.docx DOCX document
Attachment_3_Government_Furnished_Property_List_13-Jun-2018.xlsx XLSX spreadsheet
N00024-18-R-5200-0005.docx DOCX document
N00024-18-R-5200_Bidder's_Question_Responses_6.20.18.pdf PDF
N00024-18-R-5200_Bidder's_Question_Responses_6.18.18.pdf PDF
N00024-18-R-5200_Bidder's_Question_Responses_5.25.18.pdf PDF
N00024-18-R-5200-0004_Conformed.docx DOCX document
N00024-18-R-5200-0004.docx DOCX document
N00024-18-R-5200_Bidder's_Question_Responses_5.17.18.pdf PDF
N00024-18-R-5200-0003.docx DOCX document
Attachment_2_Government_Furnished_Information_(GFI)_List.pdf PDF
N00024-18-R-5200-0003_Conformed.docx DOCX document
N00024-18-R-5200_Bidder's_Question_Responses_5.11.18.pdf PDF
N00024-18-R-5200-0002.docx DOCX document
N00024-18-R-5200-0001_Conformed.docx DOCX document
N00024-18-R-5200-0001.docx DOCX document
Attachment_21_Bidder's_Library_Access_Instructions_rev1.pdf PDF
N00024-18-R-5200_Bidder's_Question_Responses_5.1.18.pdf PDF
N00024-18-R-5200_CDRLs.zip ZIP file
N00024-18-R-5200_Solicitation.docx DOCX document
N00024-18-R-5200_Public_Attachments.zip ZIP file
N00024-18-R-5200_Question-Comments_4.18.18.xlsx XLSX spreadsheet
N00024-18-R-5200_Question-Comments_3.6.18.xlsx XLSX spreadsheet
N00024-18-R-5200_Question-Comments_12.22.17.xlsx XLSX spreadsheet
N00024-18-R-5200_Question-Comments_12.13.17.xlsx XLSX spreadsheet
N00024-18-R-5200_CEC_DA-ES_Draft_Sections_L.docx DOCX document
N00024-18-R-5200 CEC DA-ES Draft Sections B-C-F.docx DOCX document
N00024-18-R-5200_Question-Comment_Template.xlsx XLSX spreadsheet
N00024-18-R-5200_DD_Form_254.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

CLIN 0600

B. EXH/ATCH NO.

A

C. CATEGORY

TDP TM OTHER MGMT 1

D. SYSTEM/ITEM

COOPERATIVE ENGAGEMENT

CAPABILITY

E. CONTRACT/PR NO.

N00024-18-R-5200

F. CONTRACTOR

TBD

1. DATA ITEM NO

A001

2. TITLE OF DATA ITEM

DATA ACCESSION LIST (DAL)

3. SUBTITLE

4. AUTHORITY (Data Acquisition Doc. No)

DI-MGMT-81453B

5. CONTRACT REFERENCE

SOW 3.1.1, 3.3.1.1, 3.3.2.1

6. REQUIRING OFFICE

PEO IWS 6.0

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

F

10. FREQUENCY

ANNUAL

12. DATE OF 1st SUBMISSION

30 DAC

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

SEE BLK 16

11. AS OF DATE

N/A

13. DATE OF SUBSEQUENT

SUBMISSION

SEE BLK 16

Draft

Final

Reg Repro

16. REMARKS

BLK 8: APPROVAL IS FOR FORMAT, TECHNICAL CONTENT AND

ACCURACY. GOVERNMENT RESPONSE TIME IS 30 CALENDAR DAYS. ANY

REJECTED SUBMISSION SHALL BE CORRECTED AND RESUBMITTED

WITHIN 30 CALENDAR DAYS OF THE REJECTION. IF NO RESPONSE

RECEIVED FROM GOVERNMENT AFTER 45 CALENDAR DAYS, THE

CONTRACTOR SHOULD CONSIDER THE SUBMITTAL APPROVED.

APPROVAL IS REQUIRED ONLY ON THE FIRST SUBMISSION. SUBSEQUENT

SUBMISSIONS DO NOT REQUIRE APPROVAL.

BLK 9: DISTRIBUTION STATEMENT F: FURTHER DISSEMINATION ONLY AS

DIRECTED BY THE PROGRAM EXECUTIVE OFFICE, INTEGRATED WARFARE

SYSTEMS (IWS 6.0), (26 JAN 2017) OR HIGHER AUTHORITY.

BLK 13: 15 DARP. NEGATIVE REPORTS ARE NOT REQUIRED.

BLK 14: CONTRACTOR SHALL DELIVER IN DIGITAL FORMAT TO THE

GOVERNMENT INTEGRATED DIGITAL ENVIRONMENT (IDE) PER

SUPPLEMENT A8 TO EXHIBIT.

UNLESS OTHERWISE DIRECTED, DELIVERABLES SHALL BE SUPPLIED IN

THEIR NATIVE FORMAT. NATIVE MEANS THE FILES SHALL BE DELIVERED

AS THEY COME OFF THEIR TOOL.

FOR LOE TASKS, ALTERNATIVE DELIVERY MAY BE SPECIFIED VIA TI.

SEE

ADDRESSEE

LIST

15. TOTAL

G. PREPARED BY

CHRISTOPHER M. BROWN

H. DATE

11 JAN 2018

I. APPROVED BY J. DATE

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 1 of 104 Pages

17. PRICE

GROUP

18.

ESTIMATE

D TOTAL

PRICE

richard.skillman Typewritten Text 20 June 2018

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

CLIN 0600

B. EXH/ATCH NO.

A

C. CATEGORY

TDP TM OTHER MGMT 1

D. SYSTEM/ITEM

COOPERATIVE ENGAGEMENT

CAPABILITY

E. CONTRACT/PR NO.

N00024-18-R-5200

F. CONTRACTOR

TBD

1. DATA ITEM NO

A002

2. TITLE OF DATA ITEM

CONTRACT WORK BREAKDOWN STRUCTURE

3. SUBTITLE

4. AUTHORITY (Data Acquisition Doc. No)

DI-MGMT-81334D

5. CONTRACT REFERENCE

SOW 3.1.1, 3.3.1.1, 3.3.2.1

6. REQUIRING OFFICE

PEO IWS 6.0

7. DD 250 REQ

LT

SEE BLK 16

12. DATE OF 1st SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

A

SUBMISSION

SEE BLK 16

Draft

Final

REJECTED SUBMISSION SHALL BE CORRECTED AND RESUBMITTED

WITHIN 30 CALENDAR DAYS OF THE REJECTION. IF NO RESPONSE

RECEIVED FROM GOVERNMENT AFTER 45 CALENDAR DAYS, THE

CONTRACTOR SHOULD CONSIDER THE SUBMITTAL APPROVED.

BLK 9: DISTRIBUTION STATEMENT F: FURTHER DISSEMINATION ONLY AS

DIRECTED BY THE PROGRAM EXECUTIVE OFFICE, INTEGRATED WARFARE

SYSTEMS (IWS 6.0), (26 JAN 2017) OR HIGHER AUTHORITY.

BLK 10/12/13/14: THE CONTRACTOR SHALL SUBMIT THE CWBS IN

ACCORDANCE WITH DI-MGMT-81334D (OR THE MOST RECENTLY

APPROVED VERSION) AND THE OSD DEPUTY DIRECTOR, COST

ASSESSMENT (DDCA) AND OSD ACQUISITION, TECHNOLOGY AND

LOGISTICS (AT&L) PERFORMANCE ASSESSMENTS AND ROOT CAUSE

ANALYSES (PARCA) DIRECTOR-APPROVED CONTRACT CSDR/EVM CO-

PLAN. THE DID, DI-MGMT-81334D, IS AVAILABLE FROM THE DEFENSE

COST AND RESOURCE CENTER (DCARC) WEBSITE AT

HTTP://CADE.OSD.MIL/CSDR/FORMSREPORTING.ASPX#DIDS. THE

CSDR/EVM CO-PLAN IS INCLUDED AS A CONTRACT ATTACHMENT.

CONTRACTORS SHALL BE REQUIRED TO SUBMIT THE CWBS DICTIONARY

AT FREQUENCIES SPECIFIED IN THE CA AND PARCA-APPROVED

CSDR/EVM CO-PLAN AND IN THE CONTRACT. THE CONTRACT CSDR/EVM

CO-PLAN USES THE EVENT FIELD AS THE DRIVER FOR THE SUBMISSION

OF THE REPORTS, NOT THE "AS OF DATE." IF THE EVENT SLIPS, THE

CONTRACTOR MUST NOTIFY THE GOVERNMENT PROGRAM OFFICE THAT

A DATE CHANGE IS NEEDED. IT IS THE RESPONSIBILITY OF THE

GOVERNMENT PROGRAM OFFICE TO SUBMIT A REQUEST FOR CHANGE IN

THE EVENT-DRIVEN DATE FOR REPORTING THROUGH THE CSDR SUBMIT-

REVIEW SYSTEM FOR DCARC APPROVAL BEFORE THE DATE REFLECTED

IN THE CA AND PARCA-APPROVED CSDR/EVM CO-PLAN.

THE CWBS DICTIONARY SHALL BE SUBMITTED ELECTRONICALLY USING

THE CSDR SUBMIT-REVIEW SYSTEM. DATA SUBMITTERS MUST REGISTER

THROUGH THE DCARC WEBSITE AND POSSESS A DOD-APPROVED ECA

DIGITAL CERTIFICATE OR A DOD-ISSUED CAC TO OBTAIN A DCARC

PORTAL ACCOUNT AND BE AUTHORIZED TO UPLOAD CSDR CONTENT.

CHRISTOPHER M. BROWN

H. DATE

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 2 of 104 Pages

18.

ESTIMATE

D TOTAL

PRICE

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

CLIN 0600

B. EXH/ATCH NO.

A

C. CATEGORY

TDP TM OTHER MGMT 1

D. SYSTEM/ITEM

COOPERATIVE ENGAGEMENT

CAPABILITY

E. CONTRACT/PR NO.

N00024-18-R-5200

F. CONTRACTOR

TBD

1. DATA ITEM NO

A002

2. TITLE OF DATA ITEM

CONTINUED

3. SUBTITLE

4. AUTHORITY (Data Acquisition Doc. No)

DI-MGMT-81334D

5. CONTRACT REFERENCE

SOW 3.1.1, 3.3.1.1, 3.3.2.1

6. REQUIRING OFFICE

PEO IWS 6.0

7. DD 250 REQ

LT

SEE BLK 16

12. DATE OF 1st SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

SUBMISSION

SEE BLK 16

Draft

Final

BLK 10/12/13/14: DELIVERY SHALL BE TO BOTH THE DCARC PORTAL AND

THE GOVERNMENT'S SPECIFIED INTEGRATED DIGITAL ENVIRONMENT

(IDE).

USERS CAN OBTAIN ACCESS BY SUBMITTING USER INFORMATION ABOUT

THEMSELVES AND THEIR ORGANIZATIONS TO THE DCARC PORTAL AND

REQUESTING A CSDR SUBMITTER USER ROLE. AFTER THE

REGISTRATION INFORMATION HAS BEEN VERIFIED, THE DCARC SHALL

AUTHORIZE THE USER ACCOUNT AND REQUESTED ROLE. ALL DCARC

PORTAL ACCOUNTS NEED TO BE RENEWED AT LEAST ANNUALLY.

SUBCONTRACTOR REPORTING. PRIME CONTRACTORS ARE

RESPONSIBLE FOR FLOWING DOWN CSDR REQUIREMENTS CONTAINED

IN THEIR PRIME CONTRACTS TO ALL SUBCONTRACTORS WHO MEET THE

REPORTING THRESHOLDS SPECIFIED IN THE DODI 5000.02, OR AS

REQUIRED BY THE CWIPT. THIS INCLUDES REQUIRING

SUBCONTRACTORS TO ELECTRONICALLY REPORT DIRECTLY TO THE

DCARC USING THE CSDR SUBMIT-REVIEW SYSTEM.

THE PRIME CONTRACTOR SHALL BE REQUIRED TO WORK WITH THE

CWIPT AND ALL APPROPRIATE SUBCONTRACTORS TO PREPARE

SEPARATE SUBCONTRACT CSDR PLANS FOR SUBMISSION TO THE DCARC

FOR DDCA APPROVAL.

BLK 14: CONTRACTOR SHALL DELIVER IN DIGITAL FORMAT TO THE

GOVERNMENT INTEGRATED DIGITAL ENVIRONMENT (IDE) PER

SUPPLEMENT A8 TO EXHIBIT.

UNLESS OTHERWISE DIRECTED, DELIVERABLES SHALL BE SUPPLIED IN

THEIR NATIVE FORMAT. NATIVE MEANS THE FILES SHALL BE DELIVERED

CHRISTOPHER M. BROWN

H. DATE

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 3 of 104 Pages

18.

ESTIMATE

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

CLIN 0600

B. EXH/ATCH NO.

A

C. CATEGORY

TDP TM OTHER MGMT 1

D. SYSTEM/ITEM

COOPERATIVE ENGAGEMENT

CAPABILITY

E. CONTRACT/PR NO.

N00024-18-R-5200

F. CONTRACTOR

TBD

1. DATA ITEM NO

A003

2. TITLE OF DATA ITEM

CONTRACTOR'S PROGRESS AND STATUS REPORT

3. SUBTITLE

MONTHLY PROGRESS AND STATUS REPORT

4. AUTHORITY (Data Acquisition Doc. No)

DI-MGMT-81928

5. CONTRACT REFERENCE

SOW 3.1.1, 3.1.1.4.1, 3.1.1.4.2, 3.1.1.11.1.3,

3.3.1.1, 3.3.1.2, 3.3.2.1

6. REQUIRING OFFICE

PEO IWS 6.0

7. DD 250 REQ

LT

MTHLY

12. DATE OF 1st SUBMISSION

30 DAC

14. DISTRIBUTION

a. ADDRESSEE

SUBMISSION

15 DARP

Draft

Final

BLK 4: 2.5C: PERIOD TO BE DEFINED AS FY

BLK 10: ONE REPORT SHALL BE DELIVERED. THAT REPORT SHALL

PROVIDE INFORMATION FOR EACH TASK.

BLK 14: CONTRACTOR SHALL DELIVER IN DIGITAL FORMAT TO THE

GOVERNMENT INTEGRATED DIGITAL ENVIRONMENT (IDE) PER

SUPPLEMENT A8 TO EXHIBIT.

UNLESS OTHERWISE DIRECTED, DELIVERABLES SHALL BE SUPPLIED IN

THEIR NATIVE FORMAT. NATIVE MEANS THE FILES SHALL BE DELIVERED

CHRISTOPHER M. BROWN

H. DATE

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 4 of 104 Pages

18.

ESTIMATE

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

CLIN 0600

B. EXH/ATCH NO.

A

C. CATEGORY

TDP TM OTHER MGMT 1

D. SYSTEM/ITEM

COOPERATIVE ENGAGEMENT

CAPABILITY

E. CONTRACT/PR NO.

N00024-18-R-5200

F. CONTRACTOR

TBD

1. DATA ITEM NO

A004

2. TITLE OF DATA ITEM

GOVERNMENT FURNISHED INFORMATION

DEFICIENCY REPORT

3. SUBTITLE

4. AUTHORITY (Data Acquisition Doc. No)

DI-MGMT-80596

5. CONTRACT REFERENCE

SOW 3.1.1, 3.3.2.1

6. REQUIRING OFFICE

PEO IWS 6.0

7. DD 250 REQ

LT

ANNLY

12. DATE OF 1st SUBMISSION

30 DAC

14. DISTRIBUTION

a. ADDRESSEE

SUBMISSION

SEE BLK 16

Draft

Final

BLK 9: DISTRIBUTION STATEMENT F: FURTHER DISSEMINATION ONLY AS

DIRECTED BY THE PROGRAM EXECUTIVE OFFICE, INTEGRATED WARFARE

SYSTEMS (IWS 6.0), (26 JAN 2017) OR HIGHER AUTHORITY.

BLK 13: UPDATES DUE ANNUALLY. REVISIONS DUE NLT 14 CALENDAR

DAYS AFTER A CHANGE AFFECTING THIS ITEM HAS BEEN IDENTIFIED.

BLK 14: CONTRACTOR SHALL DELIVER IN DIGITAL FORMAT TO THE

GOVERNMENT INTEGRATED DIGITAL ENVIRONMENT (IDE) PER

SUPPLEMENT A8 TO EXHIBIT.

UNLESS OTHERWISE DIRECTED, DELIVERABLES SHALL BE SUPPLIED IN

THEIR NATIVE FORMAT. NATIVE MEANS THE FILES SHALL BE DELIVERED

CHRISTOPHER M. BROWN

H. DATE

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 5 of 104 Pages

18.

ESTIMATE

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

CLIN 0600

B. EXH/ATCH NO.

A

C. CATEGORY

TDP TM OTHER MISC 1

D. SYSTEM/ITEM

COOPERATIVE ENGAGEMENT

CAPABILITY

E. CONTRACT/PR NO.

N00024-18-R-5200

F. CONTRACTOR

TBD

1. DATA ITEM NO

A005

2. TITLE OF DATA ITEM

TECHNICAL REPORT - STUDY/SERVICES

3. SUBTITLE

SOFTWARE METRICS REPORT

4. AUTHORITY (Data Acquisition Doc. No)

DI-MISC-80508B

5. CONTRACT REFERENCE

SOW 3.1.1.4.1, 3.1.1.4.2, 3.1.3.5, 3.1.3.6,

3.1.3.7, 3.1.3.8, 3.1.3.19, 3.1.3.20, 3.1.6.3, 3.1.6.4, 3.3.1.5, 3.3.1.6, 3.3.1.8

6. REQUIRING OFFICE

PEO IWS 6.0

7. DD 250 REQ

LT

ASREQ

12. DATE OF 1st SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

SUBMISSION

SEE BLK 16

Draft

Final

Reg Repro

16. REMARKS

BLK 4: CONTENT SHALL BE IN THE CONTRACTOR’S FORMAT AND SHALL

INCLUDE THE METRICS DESCRIBED IN THE SOW AND THE APPROVED

SDP. DELIVERY SHALL BE IN DIGITAL FORMAT.

BLK 8: APPROVAL IS FOR TECHNICAL CONTENT AND ACCURACY.

GOVERNMENT RESPONSE TIME IS 30 CALENDAR DAYS. ANY REJECTED

SUBMISSION SHALL BE CORRECTED AND RESUBMITTED WITHIN 30

CALENDAR DAYS OF THE REJECTION. IF NO RESPONSE RECEIVED FROM

GOVERNMENT AFTER 45 CALENDAR DAYS, THE CONTRACTOR SHOULD

CONSIDER THE SUBMITTAL APPROVED.

BLK 9: DISTRIBUTION STATEMENT F: FURTHER DISSEMINATION ONLY AS

DIRECTED BY THE PROGRAM EXECUTIVE OFFICE, INTEGRATED WARFARE

SYSTEMS (IWS 6.0), (26 JAN 2017) OR HIGHER AUTHORITY.

BLK 12: DRAFT DUE NLT 60 CALENDAR DAYS PRIOR TO ANY TIM, SETR

EVENT, OR BASELINE REVIEW INVOLVING SOFTWARE AND AS DIRECTED

BY THE TECHNICAL REVIEW ACTION PLAN (TRAP), A PART OF THE

SYSTEM ENGINEERING PLAN (SEP), PROVIDED AS GFI. FOR LOE TASKS,

ALTERNATIVE DELIVERY MAY BE SPECIFIED VIA TI.

BLK 13: FINAL DUE NLT 30 CALENDAR DAYS AFTER TO ANY TIM, SETR

EVENT, OR BASELINE REVIEW INVOLVING SOFTWARE AND AS DIRECTED

BY THE TRAP, A PART OF THE SEP, PROVIDED AS GFI. FOR LOE TASKS,

ALTERNATIVE DELIVERY MAY BE SPECIFIED VIA TI.

BLK 14: CONTRACTOR SHALL DELIVER IN DIGITAL FORMAT TO THE

GOVERNMENT INTEGRATED DIGITAL ENVIRONMENT (IDE) PER

SUPPLEMENT A8 TO EXHIBIT.UNLESS OTHERWISE DIRECTED,

DELIVERABLES SHALL BE SUPPLIED IN THEIR NATIVE FORMAT. NATIVE

MEANS THE FILES SHALL BE DELIVERED AS THEY COME OFF THEIR TOOL.

CHRISTOPHER M. BROWN

H. DATE

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 6 of 104 Pages

18.

ESTIMATE

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

CLIN 0600

B. EXH/ATCH NO.

A

C. CATEGORY

TDP TM OTHER MGMT 1

D. SYSTEM/ITEM

COOPERATIVE ENGAGEMENT

CAPABILITY

E. CONTRACT/PR NO.

N00024-18-R-5200

F. CONTRACTOR

TBD

1. DATA ITEM NO

A006

2. TITLE OF DATA ITEM

INTEGRATED PROGRAM MANAGEMENT REPORT

(IPMR)

3. SUBTITLE

4. AUTHORITY (Data Acquisition Doc. No)

DI-MGMT-81861A

5. CONTRACT REFERENCE

SOW 3.1.1.5.1, 3.1.1.5.2, 3.1.1.6.1, 3.1.1.6.2,

3.1.1.7, 3.3.1.1, 3.3.2.1

6. REQUIRING OFFICE

PEO IWS 6.0

7. DD 250 REQ

LT

MTHLY

12. DATE OF 1st SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

SUBMISSION

SEE BLK 16

Draft

Final

BLK 4:

ALL FORMATS SHALL BE SUBMITTED ELECTRONICALLY IN ACCORDANCE

WITH THE DOD-APPROVED XML SCHEMAS AND GUIDELINES LOCATED IN

THE EVM CENTRAL REPOSITORY (EVMCR) http://cade.osd.mil/tools/evm-tools.

FORMATS 1-4 SHALL BE SUBMITTED USING THE DOD-APPROVED XML

SCHEMA AND COST GUIDELINE.

FORMAT 5 SHALL BE SUBMITTED IN CONTRACTOR FORMAT.

FORMAT 6 SHALL BE SUBMITTED USING THE DOD-APPROVED XML

SCHEMA AND SCHEDULE GUIDELINE. A COPY OF THE IMS IN

CONTRACTOR NATIVE SOFTWARE FORMAT SHALL ALSO BE SUBMITTED.

FORMAT 7 SHALL BE SUBMITTED USING THE DOD-APPROVED XML

SCHEMA AND TIME-PHASED COST GUIDELINE.

FORMAT 1 INSTRUCTIONS: WORK BREAKDOWN STRUCTURE (WBS)

ELEMENTS SHALL BE REPORTED IN ACCORDANCE WITH THE APPROVED

MIL-STD-881 APPENDIX (LATEST VERSION AT TIME OF AWARD) AS

TAILORED TO MEET THE NEEDS OF THE PMO. THIS IS ALSO KNOWN AS

THE "REPORTING LEVEL."

FORMAT 2 INSTRUCTIONS: PROVIDE THE CONTRACTOR’S FUNCTIONAL

BREAKDOWN STRUCTURE (E.G. ENGINEERING, MANUFACTURING,

PROGRAM MANAGEMENT, QUALITY, TEST, ETC.) OR OTHER

ORGANIZATIONAL BREAKDOWN SUCH AS BY INTEGRATED PRODUCT

TEAMS (IPTS). MATERIAL AND MAJOR SUBCONTRACTORS WITH EVM

SYSTEM FLOW-DOWN REQUIREMENTS SHALL BE INCLUDED AS

SEPARATE ELEMENTS. NO FORMAL MONTHLY VARIANCE ANALYSIS IS

REQUIRED FOR FORMAT 2, HOWEVER, THE CONTRACTOR SHOULD

CORRELATE THE VARIANCES IN FORMAT 1 TO FORMAT 2, AS NEEDED.

CHRISTOPHER M. BROWN

H. DATE

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 7 of 104 Pages

18.

ESTIMATE

D TOTAL

http://cade.osd.mil/tools/evm-tools

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

CLIN 0600

B. EXH/ATCH NO.

A

C. CATEGORY

TDP TM OTHER MGMT 1

D. SYSTEM/ITEM

COOPERATIVE ENGAGEMENT

CAPABILITY

E. CONTRACT/PR NO.

N00024-18-R-5200

F. CONTRACTOR

TBD

1. DATA ITEM NO

A006

2. TITLE OF DATA ITEM

CONTINUED

3. SUBTITLE

4. AUTHORITY (Data Acquisition Doc. No)

DI-MGMT-81861A

5. CONTRACT REFERENCE

SOW 3.1.1.5.1, 3.1.1.5.2, 3.1.1.6.1, 3.1.1.6.2,

3.1.1.7, 3.3.1.1, 3.3.2.1

6. REQUIRING OFFICE

PEO IWS 6.0

7. DD 250 REQ

LT

MTHLY

12. DATE OF 1st SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

SUBMISSION

SEE BLK 16

Draft

Final

Reg Repro

16. REMARKS

FORMAT 3 INSTRUCTIONS:

SIGNIFICANT DIFFERENCES, THOSE THAT ARE ABSOLUTE VALUES

EXCEEDING +/- 5%5, BETWEEN THE PERFORMANCE MEASUREMENT

BASELINE (PMB) AT THE BEGINNING AND END OF EACH SPECIFIED

PERIOD BY MONTH AND IN TOTAL SHALL BE EXPLAINED IN FORMAT 5.

BASELINE CHANGE BREAKOUT SHOULD BE BY MONTH FOR THE NEXT SIX

MONTHS AND BY QUARTER THEREAFTER.

FORMAT 4 INSTRUCTIONS:

SIGNIFICANT CHANGES THAT REQUIRE EXPLANATIONS IN FORMAT 5 ARE

THOSE THAT CHANGE THE ABSOLUTE VALUE OF THE PROJECTED TOTAL

STAFF-MONTHS AT COMPLETION OF ANY ORGANIZATIONAL OR

FUNCTIONAL CATEGORY BY MORE THAN +/-5%7. STAFFING FORECAST

SHOULD BE BY MONTH FOR THE NEXT SIX MONTHS AND BY QUARTER

THEREAFTER.

FORMAT 5 INSTRUCTIONS:

THE CONTRACTOR SHALL APPLY THRESHOLDS CONSISTENT WITH THE

COMPANY-DOCUMENTED ANSI/EIA-748 COMPLIANT PROCESS, AS

APPLICABLE. THRESHOLDS SHALL BE BASED ON BOTH COST AND

SCHEDULE, INCLUDING AT COMPLETION. VARIANCE ANALYSIS

THRESHOLDS SHALL BE REVIEWED PERIODICALLY AND ADJUSTED AS

NECESSARY TO ENSURE THEY CONTINUE TO PROVIDE APPROPRIATE

INSIGHT AND VISIBILITY TO THE GOVERNMENT. THRESHOLDS SHALL NOT

BE CHANGED WITHOUT GOVERNMENT APPROVAL.

NARRATIVE EXPLANATIONS REQUIRED AND VARIANCE THRESHOLDS

WILL BE REVIEWED PERIODICALLY AND MAY BE ADJUSTED BY CONTRACT

MODIFICATION WITH NO CHANGE IN CONTRACT PRICE.

THE CONTRACTOR WILL NOTIFY THE GOVERNMENT MONTHLY ON WHICH

REPORTABLE WBSS EXCEEDED THE THRESHOLD NO LATER THAN THE

7TH WORKING DAY AFTER THE ACCOUNTING CLOSE. THE GOVERNMENT

MAY NOTIFY THE CONTRACTOR WHICH 15 VARIANCES ARE REPORTABLE

IN THE CURRENT PERIOD NO LATER THAN THE 10TH WORKING DAY AFTER

ACCOUNTING CLOSE. WITHOUT GOVERNMENT DIRECTION, THE

CONTRACTOR SHALL REPORT THE TOP THREE CURRENT PERIOD,

CUMULATIVE, AND AT COMPLETE VARIANCES. A TOTAL OF 15 WBS

ELEMENTS ARE REPORTED, AS APPLICABLE.

CHRISTOPHER M. BROWN

H. DATE

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 8 of 104 Pages

18.

ESTIMATE

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

CLIN 0600

B. EXH/ATCH NO.

A

C. CATEGORY

TDP TM OTHER MGMT 1

D. SYSTEM/ITEM

COOPERATIVE ENGAGEMENT

CAPABILITY

E. CONTRACT/PR NO.

N00024-18-R-5200

F. CONTRACTOR

TBD

1. DATA ITEM NO

A006

2. TITLE OF DATA ITEM

CONTINUED

3. SUBTITLE

4. AUTHORITY (Data Acquisition Doc. No)

DI-MGMT-81861A

5. CONTRACT REFERENCE

SOW 3.1.1.5.1, 3.1.1.5.2, 3.1.1.6.1, 3.1.1.6.2,

3.1.1.7, 3.3.1.1, 3.3.2.1

6. REQUIRING OFFICE

PEO IWS 6.0

7. DD 250 REQ

LT

MTHLY

12. DATE OF 1st SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

SUBMISSION

SEE BLK 16

Draft

Final

Reg Repro

16. REMARKS

FORMAT 5 INSTRUCTIONS (CONT):

THE CONTRACTOR OR THE GOVERNMENT MAY IDENTIFY ADDITIONAL

VARIANCES TO REPORT OVER THE 15 WBS ELEMENTS TO COVER

EMERGING TRENDS. ITEMS SHALL BE REVIEWED MONTHLY TO SEE IF

STILL REQUIRED; THE INTENT OF THE REQUIREMENT IS TEMPORARY.

VARIANCE ANALYSIS NARRATIVES SHALL BE REPORTED AT THE

REPORTING LEVEL AS DETERMINED BY THE WBS LEVEL ON FORMAT 1.

THE NARRATIVES ALSO SHALL:

1) QUANTIFY AND EXPLAIN THE ROOT CAUSE OF THE VARIANCE AND

ACCOUNT FOR THE MAJORITY OF THE VARIANCE AMOUNT

EXCEEDING THE THRESHOLD.

2) DISCUSS ANY SCHEDULE VARIANCE IN TERMS OF FLOAT AND THE

IMPACT TO THE PROGRAM CRITICAL PATH, IF ANY, AND IDENTIFY

SIGNIFICANT MISSED MILESTONES, IMPACT TO MAJOR MILESTONES,

AND EXPECTED RECOVERY DATES.

3) SPECIFIC CORRECTIVE ACTIONS, FORECASTED CLOSURE DATE, AND

IMPACT TO THE ESTIMATE AT COMPLETION (EAC) SHALL BE

INCLUDED IN EACH VARIANCE NARRATIVE.

4) IF THERE ARE NO CHANGES TO THE REPORTABLE ELEMENT ISSUE

DESCRIPTION, THE EXPECTED IMPACTS, OR CORRECTIVE ACTION

PLANS, THEN SPECIFY, “NO CHANGES SINCE THE LAST REPORTED

ANALYSIS” AND REFERENCE THE IPMR DATE WHEN THE ORIGINAL

NARRATIVE WAS REPORTED.

IPMRS, WHEN REQUIRED FROM SUBCONTRACTORS, WILL BE PROVIDED

ELECTRONICALLY USING THE DOD-APPROVED XML FORMATS.

FORMAT 6 INSTRUCTIONS

THE IMS WILL INCLUDE THE APPLICABLE CALENDAR(S). THE IMS SHALL

INCLUDE ALL DISCRETE WORK; SUBCONTRACTORS WITH EVM FLOW-

DOWN SHALL BE INCORPORATED WITH SUFFICIENT DETAIL TO DEVELOP

A REALISTIC CRITICAL PATH AND PROVIDE INSIGHT INTO THE SCOPE OF

WORK BEING ACCOMPLISHED. THE SCHEDULE RISK ASSESSMENT (SRA)

SHALL BE SUBMITTED IN FORMAT 5 AND DELIVERED 60 DAYS PRIOR TO

ANY IBR.

CHRISTOPHER M. BROWN

H. DATE

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 9 of 104 Pages

18.

ESTIMATE

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

CLIN 0600

B. EXH/ATCH NO.

A

C. CATEGORY

TDP TM OTHER MGMT 1

D. SYSTEM/ITEM

COOPERATIVE ENGAGEMENT

CAPABILITY

E. CONTRACT/PR NO.

N00024-18-R-5200

F. CONTRACTOR

TBD

1. DATA ITEM NO

A006

2. TITLE OF DATA ITEM

CONTINUED

3. SUBTITLE

4. AUTHORITY (Data Acquisition Doc. No)

DI-MGMT-81861A

5. CONTRACT REFERENCE

SOW 3.1.1.5.1, 3.1.1.5.2, 3.1.1.6.1, 3.1.1.6.2,

3.1.1.7, 3.3.1.1, 3.3.2.1

6. REQUIRING OFFICE

PEO IWS 6.0

7. DD 250 REQ

LT

MTHLY

12. DATE OF 1st SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

SUBMISSION

SEE BLK 16

Draft

Final

FORMAT 7 INSTRUCTIONS:

THE FOLLOWING ITEMS WILL BE PROVIDED AT THE SAME LEVEL AS THE

FORMAT 1 WBS LEVEL12: BCWS, BCWP, ACWP, AND ETC BY MONTH, FOR

THE PERIOD, FROM CONTRACT START TO COMPLETE, AS APPLICABLE.

BLK 9: DISTRIBUTION STATEMENT F: FURTHER DISSEMINATION ONLY AS

DIRECTED BY THE PROGRAM EXECUTIVE OFFICE, INTEGRATED WARFARE

SYSTEMS (IWS 6.0), (26 JAN 2017) OR HIGHER AUTHORITY.

BLK 12: THE FIRST SUBMISSION OF FORMATS 1-6 IS DUE 12 WORKING

DAYS AFTER THE END OF THE SECOND FULL ACCOUNTING PERIOD

FOLLOWING AUTHORIZATION TO PROCEED (ATP).

BLK 13: SUBSEQUENT SUBMISSIONS CONTAINING FORMATS 1 THROUGH

6 SHALL BE PROVIDED WITHIN 12 WORKING DAYS AFTER THE CLOSE OF

THE CONTRACTOR’S MONTHLY OR PERIODIC ACCOUNTING CYCLE.

FORMAT 7 IS DUE ANNUALLY ON 30 JANUARY. FINAL SUBMISSIONS ARE

DUE WHEN THE LAST SIGNIFICANT MILESTONE/DELIVERABLE AS DEFINED

BY THE CONTRACT HAS BEEN ACHIEVED AND REMAINING RISK AREAS

HAVE BEEN MITIGATED.

BLK 14: ALL IPMR FILES MUST BE ELECTRONICALLY FORWARDED TO THE

EVM-CR AT THE DCARC WEB SITE AT

https://service.cade.osd.mil/DCARCPortal AND DELIVERED TO THE

GOVERNMENT IDE PER SUPPLEMENT A8 TO EXHIBIT.

UNLESS OTHERWISE DIRECTED, DELIVERABLES SHALL BE SUPPLIED IN

THEIR NATIVE FORMAT. NATIVE MEANS THE FILES SHALL BE DELIVERED

AS THEY COME OFF THEIR TOOL.

FOR LOE TASKS, ALTERNATIVE DELIVERY MAY BE SPECIFIED VIA TI.

AN IDE POSTING NOTICE SHALL BE EMAILED TO THE COR, IWS 6.0 DATA

MANAGER, PROJECT MANAGER, LOGISTICIAN, AND CONTRACTING

OFFICER.

CHRISTOPHER M. BROWN

H. DATE

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 10 of 104 Pages

18.

ESTIMATE

https://service.cade.osd.mil/DCARCPortal

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

CLIN 0600

B. EXH/ATCH NO.

A

C. CATEGORY

TDP TM OTHER FNCL 1

D. SYSTEM/ITEM

COOPERATIVE ENGAGEMENT

CAPABILITY

E. CONTRACT/PR NO.

N00024-18-R-5200

F. CONTRACTOR

TBD

1. DATA ITEM NO

A007

2. TITLE OF DATA ITEM

COST DATA SUMMARY REPORT (DD FORM 1921)

3. SUBTITLE

4. AUTHORITY (Data Acquisition Doc. No)

DI-FNCL-81565C

5. CONTRACT REFERENCE

SOW 3.1.1.9.1, 3.1.1.9.2, 3.3.1.1, 3.3.2.1

6. REQUIRING OFFICE

PEO IWS 6.0

7. DD 250 REQ

LT

SEE BLK 16

12. DATE OF 1st SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

SUBMISSION

SEE BLK 16

Draft

Final

SYSTEMS (IWS 6.0), (26 JAN 2017) OR HIGHER AUTHORITY.

BLK 12/13/14: THE CONTRACTOR SHALL SUBMIT THE COST DATA

SUMMARY REPORT (CDSR) IN ACCORDANCE WITH DI-FNCL-81565C (OR

THE MOST RECENTLY APPROVED VERSION) AND THE OSD DEPUTY

DIRECTOR, COST ASSESSMENT (DDCA) AND OSD ACQUISITION,

TECHNOLOGY AND LOGISTICS (AT&L) PERFORMANCE ASSESSMENTS

AND ROOT CAUSE ANALYSES (PARCA) DIRECTOR-APPROVED CONTRACT

CSDR/EVM CO-PLAN. THE DID, DI-FNCL-81565C, IS AVAILABLE FROM THE

DEFENSE COST AND RESOURCE CENTER (DCARC) WEBSITE AT

HTTP://CADE.OSD.MIL/CSDR/FORMSREPORTING.ASPX#DIDS. THE CSDR

PLAN IS INCLUDED AS A CONTRACT ATTACHMENT.

CONTRACTORS SHALL BE REQUIRED TO SUBMIT THE CONTRACTOR

COST DATA REPORTS (CCDRS) AT FREQUENCIES SPECIFIED IN THE CA

AND PARCA-APPROVED CSDR/EVM CO-PLAN AND IN THE CONTRACT. THE

CONTRACT CSDR PLAN USES THE EVENT FIELD AS THE DRIVER FOR THE

SUBMISSION OF THE REPORTS, NOT THE "AS OF DATE." IF THE EVENT

SLIPS, THE CONTRACTOR MUST NOTIFY THE GOVERNMENT PROGRAM

OFFICE THAT A DATE CHANGE IS NEEDED. IT IS THE RESPONSIBILITY OF

THE GOVERNMENT PROGRAM OFFICE TO SUBMIT A REQUEST FOR

CHANGE IN THE EVENT-DRIVEN DATE FOR REPORTING THROUGH THE

CSDR SUBMIT-REVIEW SYSTEM FOR DCARC APPROVAL BEFORE THE

DATE REFLECTED IN THE CA AND PARCA-APPROVED CSDR/EVM CO-

PLAN.

ALL CCDRS SHALL BE SUBMITTED ELECTRONICALLY USING THE CSDR

SUBMIT-REVIEW SYSTEM. THE REQUIRED FORM AND FILE TYPE FOR

EACH CCDR IS SPECIFIED IN ITS DATA ITEM DESCRIPTION (DID). DATA

SUBMITTERS MUST REGISTER THROUGH THE DCARC WEBSITE AND

POSSESS A DOD-APPROVED ECA DIGITAL CERTIFICATE OR DOD-ISSUED

CAC TO OBTAIN A DCARC PORTAL ACCOUNT AND BE AUTHORIZED TO

UPLOAD CSDR CONTENT.

CHRISTOPHER M. BROWN

H. DATE

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 11 of 104 Pages

18.

ESTIMATE

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

CLIN 0600

B. EXH/ATCH NO.

A

C. CATEGORY

TDP TM OTHER FNCL 1

D. SYSTEM/ITEM

COOPERATIVE ENGAGEMENT

CAPABILITY

E. CONTRACT/PR NO.

N00024-18-R-5200

F. CONTRACTOR

TBD

1. DATA ITEM NO

A007

2. TITLE OF DATA ITEM

CONTINUED

3. SUBTITLE

4. AUTHORITY (Data Acquisition Doc. No)

DI-FNCL-81565C

5. CONTRACT REFERENCE

SOW 3.1.1.9.1, 3.1.1.9.2, 3.3.1.1, 3.3.2.1

6. REQUIRING OFFICE

PEO IWS 6.0

7. DD 250 REQ

LT

SEE BLK 16

12. DATE OF 1st SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

SUBMISSION

SEE BLK 16

Draft

Final

BLK 12/13/14: DELIVERY SHALL BE TO BOTH THE DCARC PORTAL AND

(IDE).

USERS CAN OBTAIN ACCESS BY SUBMITTING USER INFORMATION ABOUT

THEMSELVES AND THEIR ORGANIZATIONS TO THE DCARC PORTAL AND

REQUESTING A CSDR SUBMITTER USER ROLE. AFTER THE

REGISTRATION INFORMATION HAS BEEN VERIFIED, THE DCARC SHALL

AUTHORIZE THE USER ACCOUNT AND REQUESTED ROLES. ALL DCARC

PORTAL ACCOUNTS NEED TO BE RENEWED AT LEAST ANNUALLY.

SUBCONTRACTOR REPORTING: PRIME CONTRACTORS ARE

RESPONSIBLE FOR FLOWING DOWN CSDR REQUIREMENTS CONTAINED

IN THEIR PRIME CONTRACTS TO ALL SUBCONTRACTORS WHO MEET THE

REPORTING THRESHOLDS SPECIFIED IN THE DODI 5000.02, OR AS

REQUIRED BY THE CWIPT. THIS INCLUDES REQUIRING

SUBCONTRACTORS TO ELECTRONICALLY REPORT DIRECTLY TO THE

DCARC USING THE CSDR SUBMIT-REVIEW SYSTEM.

THE PRIME CONTRACTOR SHALL BE REQUIRED TO WORK WITH THE

CWIPT AND ALL APPROPRIATE SUBCONTRACTORS TO PREPARE

SEPARATE SUBCONTRACT CSDR PLANS FOR SUBMISSION TO THE DCARC

FOR DDCA APPROVAL.

CONTRACTOR SHALL DELIVER IN DIGITAL FORMAT TO THE GOVERNMENT

INTEGRATED DIGITAL ENVIRONMENT (IDE) PER SUPPLEMENT A8 TO

EXHIBIT.UNLESS OTHERWISE DIRECTED, DELIVERABLES SHALL BE

SUPPLIED IN THEIR NATIVE FORMAT. NATIVE MEANS THE FILES SHALL BE

DELIVERED AS THEY COME OFF THEIR TOOL.

CHRISTOPHER M. BROWN

H. DATE

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 12 of 104 Pages

18.

ESTIMATE

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

CLIN 0600

B. EXH/ATCH NO.

A

C. CATEGORY

TDP TM OTHER FNCL 1

D. SYSTEM/ITEM

COOPERATIVE ENGAGEMENT

CAPABILITY

E. CONTRACT/PR NO.

N00024-18-R-5200

F. CONTRACTOR

TBD

1. DATA ITEM NO

A008

2. TITLE OF DATA ITEM

FUNCTIONAL COST HOUR REPORT (DD FORM 1921-1)

3. SUBTITLE

4. AUTHORITY (Data Acquisition Doc. No)

DI-FNCL-81566C

5. CONTRACT REFERENCE

SOW 3.1.1.9.1, 3.1.1.9.2, 3.3.1.1, 3.3.2.1

6. REQUIRING OFFICE

PEO IWS 6.0

7. DD 250 REQ

LT

SEE BLK 16

12. DATE OF 1st SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

SUBMISSION

SEE BLK 16

Draft

Final

SYSTEMS (IWS 6.0), (26 JAN 2017) OR HIGHER AUTHORITY.

BLK 10/12/13: CONTRACTORS SHALL SUBMIT THE FUNCTIONAL COST

HOUR REPORT (FCHR) IN ACCORDANCE WITH DI-FNCL-81566C (OR THE

MOST RECENTLY APPROVED VERSION) AND THE OSD DEPUTY

DIRECTOR, COST ASSESSMENT (DDCA) AND OSD ACQUISITION,

TECHNOLOGY AND LOGISTICS (AT&L) PERFORMANCE ASSESSMENTS

AND ROOT CAUSE ANALYSES (PARCA) DIRECTOR-APPROVED CONTRACT

CSDR/EVM CO-PLAN. THE DID, DI-FNCL-81566C, IS AVAILABLE FROM THE

DEFENSE COST AND RESOURCE CENTER (DCARC) WEBSITE AT

HTTP://CADE.OSD.MIL/CSDR/FORMSREPORTING.ASPX#DIDS. THE

CSDR/EVM CO-PLAN IS INCLUDED AS A CONTRACT ATTACHMENT.

CONTRACTORS SHALL BE REQUIRED TO SUBMIT THE CONTRACTOR

COST DATA REPORTS (CCDRS) AT FREQUENCIES SPECIFIED IN THE CA

AND PARCA-APPROVED CSDR/EVM CO-PLAN AND IN THE CONTRACT. THE

CONTRACT CSDR/EVM CO-PLAN USES THE EVENT FIELD AS THE DRIVER

FOR THE SUBMISSION OF THE REPORTS, NOT THE "AS OF DATE." IF THE

EVENT SLIPS, THE CONTRACTOR MUST NOTIFY THE GOVERNMENT

PROGRAM OFFICE THAT A DATE CHANGE IS NEEDED. IT IS THE

RESPONSIBILITY OF THE GOVERNMENT PROGRAM OFFICE TO SUBMIT A

REQUEST FOR CHANGE IN THE EVENT-DRIVEN DATE FOR REPORTING

THROUGH THE CSDR SUBMIT-REVIEW SYSTEM FOR DCARC APPROVAL

BEFORE THE DATE REFLECTED IN THE CA AND PARCA-APPROVED

CSDR/EVM CO-PLAN. ALL CCDRS SHALL BE SUBMITTED ELECTRONICALLY

USING THE CSDR SUBMIT-REVIEW SYSTEM. THE REQUIRED FORM AND

FILE TYPE FOR EACH CCDR IS SPECIFIED IN ITS DATA ITEM DESCRIPTION

(DID). DATA SUBMITTERS MUST REGISTER THROUGH THE DCARC

WEBSITE AND POSSESS A DOD-APPROVED ECA DIGITAL CERTIFICATE OR

DOD-ISSUED CAC TO OBTAIN A DCARC PORTAL ACCOUNT AND BE

AUTHORIZED TO UPLOAD CSDR CONTENT.

CHRISTOPHER M. BROWN

H. DATE

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 13 of 104 Pages

18.

ESTIMATE

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

CLIN 0600

B. EXH/ATCH NO.

A

C. CATEGORY

TDP TM OTHER FNCL 1

D. SYSTEM/ITEM

COOPERATIVE ENGAGEMENT

CAPABILITY

E. CONTRACT/PR NO.

N00024-18-R-5200

F. CONTRACTOR

TBD

1. DATA ITEM NO

A008

2. TITLE OF DATA ITEM

CONTINUED

3. SUBTITLE

4. AUTHORITY (Data Acquisition Doc. No)

DI-FNCL-81566C

5. CONTRACT REFERENCE

SOW 3.1.1.9.1, 3.1.1.9.2, 3.3.1.1, 3.3.2.1

6. REQUIRING OFFICE

PEO IWS 6.0

7. DD 250 REQ

LT

SEE BLK 16

12. DATE OF 1st SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

SUBMISSION

SEE BLK 16

Draft

Final

(IDE).

USERS CAN OBTAIN ACCESS BY SUBMITTING USER INFORMATION ABOUT

THEMSELVES AND THEIR ORGANIZATIONS TO THE DCARC PORTAL AND

REQUESTING A CSDR SUBMITTER USER ROLE. AFTER THE

REGISTRATION INFORMATION HAS BEEN VERIFIED, THE DCARC SHALL

AUTHORIZE THE USER ACCOUNT AND REQUESTED ROLES. ALL DCARC

PORTAL ACCOUNTS NEED TO BE RENEWED AT LEAST ANNUALLY.

SUBCONTRACTOR REPORTING: PRIME CONTRACTORS ARE

RESPONSIBLE FOR FLOWING DOWN CSDR REQUIREMENTS CONTAINED

IN THEIR PRIME CONTRACTS TO ALL SUBCONTRACTORS WHO MEET THE

REPORTING THRESHOLDS SPECIFIED IN THE DODI 5000.02, OR AS

REQUIRED BY THE CWIPT. THIS INCLUDES REQUIRING

SUBCONTRACTORS TO ELECTRONICALLY REPORT DIRECTLY TO THE

DCARC USING THE CSDR SUBMIT-REVIEW SYSTEM.

THE PRIME CONTRACTOR SHALL BE REQUIRED TO WORK WITH THE

CWIPT AND ALL APPROPRIATE SUBCONTRACTORS TO PREPARE

SEPARATE SUBCONTRACT CSDR PLANS FOR SUBMISSION TO THE DCARC

FOR DDCA APPROVAL.

CONTRACTOR SHALL DELIVER IN DIGITAL FORMAT TO THE GOVERNMENT

INTEGRATED DIGITAL ENVIRONMENT (IDE) PER SUPPLEMENT A8 TO

EXHIBIT.

UNLESS OTHERWISE DIRECTED, DELIVERABLES SHALL BE SUPPLIED IN

THEIR NATIVE FORMAT. NATIVE MEANS THE FILES SHALL BE DELIVERED

CHRISTOPHER M. BROWN

H. DATE

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 14 of 104 Pages

18.

ESTIMATE

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

CLIN 0600

B. EXH/ATCH NO.

A

C. CATEGORY

TDP TM OTHER FNCL 1

D. SYSTEM/ITEM

COOPERATIVE ENGAGEMENT

CAPABILITY

E. CONTRACT/PR NO.

N00024-18-R-5200

F. CONTRACTOR

TBD

1. DATA ITEM NO

A009

2. TITLE OF DATA ITEM

SUSTAINMENT FUNCTIONAL COST-HOUR REPORT

(DD FORM 1921-5)

3. SUBTITLE

4. AUTHORITY (Data Acquisition Doc. No)

DI-FNCL-81992

5. CONTRACT REFERENCE

SOW 3.1.1.9.1, 3.1.1.9.2, 3.3.1.1, 3.3.2.1

6. REQUIRING OFFICE

PEO IWS 6.0

7. DD 250 REQ

LT

SEE BLK 16

12. DATE OF 1st SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

SUBMISSION

SEE BLK 16

Draft

Final

SYSTEMS (IWS 6.0), (26 JAN 2017) OR HIGHER AUTHORITY.

BLK 10/12/13: THE CONTRACTOR SHALL SUBMIT THE SUSTAINMENT

FUNCTIONAL COST-HOUR REPORT (CSR) IN ACCORDANCE WITH DI-FNCL-

81992 (OR MOST RECENTLY APPROVED VERSION) AND THE OSD DEPUTY

DIRECTOR, COST ASSESSMENT (DDCA) AND OSD ACQUISITION,

TECHNOLOGY AND LOGISTICS (AT&L) PERFORMANCE ASSESSMENTS

AND ROOT CAUSE ANALYSES (PARCA) DIRECTOR-APPROVED CONTRACT

CSDR/EVM CO-PLAN. THE DID, DI-FNCL-81992, IS AVAILABLE FROM THE

DEFENSE COST AND RESOURCE CENTER (DCARC) WEBSITE AT

HTTP://CADE.OSD.MIL/CSDR/FORMSREPORTING.ASPX#DIDS. THE

CSDR/EVM CO-PLAN IS INCLUDED AS A CONTRACT ATTACHMENT.

CONTRACTORS SHALL BE REQUIRED TO SUBMIT THE CONTRACTOR

COST DATA REPORTS (CCDRS) AT FREQUENCIES SPECIFIED IN THE CA

AND PARCA-APPROVED CSDR/EVM CO-PLAN AND IN THE CONTRACT. THE

CONTRACT CSDR/EVM CO-PLAN USES THE EVENT FIELD AS THE DRIVER

FOR THE SUBMISSION OF THE REPORTS, NOT THE "AS OF DATE." IF THE

EVENT SLIPS, THE CONTRACTOR MUST NOTIFY THE GOVERNMENT

PROGRAM OFFICE THAT A DATE CHANGE IS NEEDED. IT IS THE

RESPONSIBILITY OF THE GOVERNMENT PROGRAM OFFICE TO SUBMIT A

REQUEST FOR CHANGE IN THE EVENT-DRIVEN DATE FOR REPORTING

THROUGH THE CSDR SUBMIT-REVIEW SYSTEM FOR DCARC APPROVAL

BEFORE THE DATE REFLECTED IN THE CA AND PARCA-APPROVED

CSDR/EVM CO-PLAN. ALL CCDRS SHALL BE SUBMITTED ELECTRONICALLY

USING THE CSDR SUBMIT-REVIEW SYSTEM. THE REQUIRED FORM AND

FILE TYPE FOR EACH CCDR IS SPECIFIED IN ITS DATA ITEM DESCRIPTION

(DID). DATA SUBMITTERS MUST REGISTER THROUGH THE DCARC

WEBSITE AND POSSESS A DOD-APPROVED ECA DIGITAL CERTIFICATE OR

DOD-ISSUED CAC TO OBTAIN A DCARC PORTAL ACCOUNT AND BE

AUTHORIZED TO UPLOAD CSDR CONTENT.

CHRISTOPHER M. BROWN

H. DATE

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 15 of 104 Pages

18.

ESTIMATE

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

CLIN 0600

B. EXH/ATCH NO.

A

C. CATEGORY

TDP TM OTHER FNCL 1

D. SYSTEM/ITEM

COOPERATIVE ENGAGEMENT

CAPABILITY

E. CONTRACT/PR NO.

N00024-18-R-5200

F. CONTRACTOR

TBD

1. DATA ITEM NO

A009

2. TITLE OF DATA ITEM

CONTINUED

3. SUBTITLE

4. AUTHORITY (Data Acquisition Doc. No)

DI-FNCL-81992

5. CONTRACT REFERENCE

SOW 3.1.1.9.1, 3.1.1.9.2, 3.3.1.1, 3.3.2.1

6. REQUIRING OFFICE

PEO IWS 6.0

7. DD 250 REQ

LT

SEE BLK 16

12. DATE OF 1st SUBMISSION

SEE BLK 16

14. DISTRIBUTION

a. ADDRESSEE

SUBMISSION

SEE BLK 16

Draft

Final

(IDE).

USERS CAN OBTAIN ACCESS BY SUBMITTING USER INFORMATION ABOUT

THEMSELVES AND THEIR ORGANIZATIONS TO THE DCARC PORTAL AND

REQUESTING A CSDR SUBMITTER USER ROLE. AFTER THE

REGISTRATION INFORMATION HAS BEEN VERIFIED, THE DCARC SHALL

AUTHORIZE THE USER ACCOUNT AND REQUESTED ROLES. ALL DCARC

PORTAL ACCOUNTS NEED TO BE RENEWED AT LEAST ANNUALLY.

SUBCONTRACTOR REPORTING: PRIME CONTRACTORS ARE

RESPONSIBLE FOR FLOWING DOWN CSDR REQUIREMENTS CONTAINED

IN THEIR PRIME CONTRACTS TO ALL SUBCONTRACTORS WHO MEET THE

REPORTING THRESHOLDS SPECIFIED IN THE DODI 5000.02, OR AS

REQUIRED BY THE CWIPT. THIS INCLUDES REQUIRING

SUBCONTRACTORS TO ELECTRONICALLY REPORT DIRECTLY TO THE

DCARC USING THE CSDR SUBMIT-REVIEW SYSTEM.

THE PRIME CONTRACTOR SHALL BE REQUIRED TO WORK WITH THE

CWIPT AND ALL APPROPRIATE SUBCONTRACTORS TO PREPARE

SEPARATE SUBCONTRACT CSDR PLANS FOR SUBMISSION TO THE DCARC

FOR DDCA APPROVAL.

CONTRACTOR SHALL DELIVER IN DIGITAL FORMAT TO THE GOVERNMENT

INTEGRATED DIGITAL ENVIRONMENT (IDE) PER SUPPLEMENT A8 TO

EXHIBIT.

UNLESS OTHERWISE DIRECTED, DELIVERABLES SHALL BE SUPPLIED IN

THEIR NATIVE FORMAT. NATIVE MEANS THE FILES SHALL BE DELIVERED

CHRISTOPHER M. BROWN

H. DATE

DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 16 of 104 Pages

18.

ESTIMATE

Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

CLIN 0600

B. EXH/ATCH NO.

A

C. CATEGORY

TDP TM OTHER FNCL 1

D. SYSTEM/ITEM

COOPERATIVE ENGAGEMENT

CAPABILITY

E. CONTRACT/PR NO.

N00024-18-R-5200

F. CONTRACTOR

TBD

1. DATA ITEM NO

A010

2. TITLE OF DATA ITEM

LIFE CYCLE COST (LCC) AND INDEPENDENT

SCHEDULE ASSESSMENT (ISA) REPORT