FMS F4 Repairs DD1423s - 22 Nov 23.pdf
DoD Form Nov 22, 2023 PDF 436 KB Posted
- Attached to
- F-4 Spare Parts
- Solicitation number
- FA822024R3000
About this file
This document contains five Contract Data Requirements Lists (CDRLs) for a federal contract to provide spare parts and services for F-4 aircraft. The CDRLs require the following deliverables: monthly status reports, meeting minutes within five days of meetings, test inspection reports within 20 days of testing, aftermarket inspection reports within 10 days of part delivery, and traceability documentation with inspection reports. The Air Force Materiel Command Lifecycle Management Center at Hill Air Force Base is the requiring agency. Delivery due dates and distribution requirements are specified for each data item. The likely purpose of this procurement is to maintain F-4 aircraft used for foreign military sales training purposes.
View the file
Other versions and copies of DD Form 1423S
Show all 20
Who attaches DD Form 1423S
Other files
| File | Type | Posted |
|---|---|---|
| FA822024R3000_______0001.pdf | ||
| F-4 Parts Section M.docx | DOCX document | |
| L-1 F-4 Parts Cross Reference Matrix.xlsx | XLSX spreadsheet | |
| F-4 Parts PWS.docx | DOCX document | |
| F-4 Parts Section L.docx | DOCX document | |
| FA822024R3000.pdf | ||
| L-2 F-4 Parts Price Matrix.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11/22/2023 12:34:59 PM CST CDRL Table of Contents
CONTRACT #:
CONTRACTOR:
SET NAME: FMS - FMS F-4 SYSTEM ITEM: FMS F-4
PROGRAM: Training Aircraft
DATA ITEM REQUIRING OFFICE AUTHORITY/TITLE/SUBTITLE SOW PARAGRAPH
A001 AFLCMC/WLDI DI-MGMT-81928 PWS Para. 2.3
Contractor’s Status and Progress Report
A002 AFLCMC/WLDI DI-ADMN-81250C PWS Para. 2.3
Meeting Minutes
A003 AFLCMC/WLDI DI-NDTI-80809B PWS Para. 1.3.1.4
Test Inspection Report
First Article Inspection/First Article Test (FAI/FAT)
A004 AFLCMC/WLDI DI-MGMT-80508B PWS Para. 1.3.3; 1.3.3.2
Technical Report-Studies/Services
Aftermarket Inspection Report
A005 AFLCMC/WLDI DI-MGMT-80508B PWS Para. 1.3.3.1
Technical Report-Studies/Services
Traceability Documentation
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP TM OTHER MGMT
D. SYSTEM/ITEM
FMS F-4
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A001
2. TITLE OF DATA ITEM
Contractor’s Status and Progress Report
3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-81928
5. CONTRACT REFERENCE
PWS Para. 2.3
6. REQUIRING OFFICE
AFLCMC/WLDI
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
D
10. FREQUENCY
MTHLY
12. DATE OF FIRST SUBMISSION
30DAC
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
A
11. AS OF DATE
Contract Award
13. DATE OF SUBSEQUENT
SUBMISSION
BLK16
Draft
Final
Reg Repro
16. REMARKS
Block 4: DID DI-MGMT-81928 is tailored as follows:
Delete: Paras. 2.4 thru 2.7. Status of the progress of work report contents should follow the topics outlined in PWS paragraph 2.3.
Block 9: See CDRL General Instructions for detailed requirements.
Blocks 10, 12 and 13: The Contractor shall submit the first delivery NLT than 30 days after contract award. Subsequent deliverables shall be submitted NLT than 5 calendar days of each month.
AFLCMC/WLDI 1
15. TOTAL 0 1 0
G. PREPARED BY
Laura A. Ivey, GS-12, Config Mgr AFLCMC/WLDI, Wright-Patt AFB, OH
H. DATE I. APPROVED BY
Maxine Christensen, GS-12, Prog Mgr AFLCMC/WLDI, Hill AFB, UT
J. DATE
18. ESTIMATED
TOTAL PRICE
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 1 of 1 Pages
17. PRICE GROUP
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP TM OTHER ADMN
D. SYSTEM/ITEM
FMS F-4
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A002
2. TITLE OF DATA ITEM
Meeting Minutes
3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.)
DI-ADMN-81250C
5. CONTRACT REFERENCE
PWS Para. 2.3
6. REQUIRING OFFICE
AFLCMC/WLDI
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
D
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
ASREQ
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
BLK16
11. AS OF DATE
Contract Award
13. DATE OF SUBSEQUENT
SUBMISSION
ASREQ
Draft
Final
Reg Repro
16. REMARKS
Block 9: See CDRL General Instructions for detailed requirements.
Block 8: Approval required for first submission only. All subsequent deliveries do not require approval provided content is accurate.
Blocks 10, 12 and 13: The Contractor shall submit no later than 5-calendar days after the conclusion of each meeting/review. The Contractor shall collaborate with PMO for any corrections and shall resubmit updates as required.
AFLCMC/WLDI 1
15. TOTAL 0 1 0
G. PREPARED BY
Laura A. Ivey, GS-12, Config Mgr AFLCMC/WLDI, Wright-Patt AFB OH
H. DATE I. APPROVED BY
Maxine Christensen, GS-12, Prog Mgr AFLCMC/WLDI, Hill AFB UT
J. DATE
18. ESTIMATED
TOTAL PRICE
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP TM OTHER NDTI
D. SYSTEM/ITEM
FMS F-4
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A003
2. TITLE OF DATA ITEM
Test Inspection Report
3. SUBTITLE
First Article Inspection/First Article Test
(FAI/FAT)
4. AUTHORITY (Data Acquisition Document No.)
DI-NDTI-80809B
5. CONTRACT REFERENCE
PWS Para. 1.3.1.4
6. REQUIRING OFFICE
AFLCMC/WLDI
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
D
10. FREQUENCY
BLK16
12. DATE OF FIRST SUBMISSION
BLK16
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
A
11. AS OF DATE
Contract Award
13. DATE OF SUBSEQUENT
SUBMISSION
ASREQ
Draft
Final
Reg Repro
16. REMARKS
Block 9: See CDRL General Instructions for detailed requirements.
Blocks 10, 12 and 13: The Contractor shall submit deliverable and subsequent submissions 20-days after completion of every FAI/FAT.
AFLCMC/WLDI 1
15. TOTAL 0 1 0
G. PREPARED BY
Laura A. Ivey, GS-12, Config Mgr AFLCMC/WLDI, Wright-Patt AFB, OH
H. DATE I. APPROVED BY
Maxine Christensen, GS-12, Prog Mgr AFLCMC/WLDI, Hill AFB, UT
J. DATE
18. ESTIMATED
TOTAL PRICE
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP TM OTHER MGMT
D. SYSTEM/ITEM
FMS F-4
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A004
2. TITLE OF DATA ITEM
Technical Report-Studies/Services
3. SUBTITLE
Aftermarket Inspection Report
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-80508B
5. CONTRACT REFERENCE
PWS Para. 1.3.3; 1.3.3.2
6. REQUIRING OFFICE
AFLCMC/WLDI
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
D
10. FREQUENCY
BLK16
12. DATE OF FIRST SUBMISSION
BLK16
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
A
11. AS OF DATE
Contract Award
13. DATE OF SUBSEQUENT
SUBMISSION
ASREQ
Draft
Final
Reg Repro
16. REMARKS
Block 9: See CDRL General Instructions for detailed requirements.
Blocks 10, 12 and 13: The Contractor shall submit deliverable and subsequent submissions 10-calendar days after visual inspection delivery of parts, as required per the applicable PWS paragraphs in Block 5.
AFLCMC/WLDI 1 1
15. TOTAL 1 1 0
G. PREPARED BY
Laura A. Ivey, GS-12, Config Mgr AFLCMC/WLDI, Wright-Patt AFB, OH
H. DATE I. APPROVED BY
Maxine Christensen, GS-12, Prog Mgr AFLCMC/WLDI, Hill AFB, UT
J. DATE
18. ESTIMATED
TOTAL PRICE
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP TM OTHER MGMT
D. SYSTEM/ITEM
FMS F-4
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A005
2. TITLE OF DATA ITEM
Technical Report-Studies/Services
3. SUBTITLE
Traceability Documentation
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-80508B
5. CONTRACT REFERENCE
PWS Para. 1.3.3.1
6. REQUIRING OFFICE
AFLCMC/WLDI
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
D
10. FREQUENCY
BLK16
12. DATE OF FIRST SUBMISSION
BLK16
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
A
11. AS OF DATE
Contract Award
13. DATE OF SUBSEQUENT
SUBMISSION
ASREQ
Draft
Final
Reg Repro
16. REMARKS
Block 9: See CDRL General Instructions for detailed requirements.
Blocks 10, 12 and 13: The Contractor shall submit deliverable and subsequent submissions concurrently with CDRL A004 and as required per the applicable PWS paragraphs in Block 5.
AFLCMC/WLDI 1
15. TOTAL 0 1 0
G. PREPARED BY
Laura A. Ivey, GS-12, Config Mgr AFLCMC/WLDI, Wright-Patt AFB, OH
H. DATE I. APPROVED BY
Maxine Christensen, GS-12, Prog Mgr AFLCMC/WLDI, Hill AFB, UT
J. DATE
18. ESTIMATED
TOTAL PRICE
File details come from the government source that posted it. Updated .