This invitation for bid solicits sealed bids for the reconstruction and rehabilitation of approximately 75 miles of the Blue Ridge Parkway located in North Carolina. Work includes pavement reconstruction, drainage improvements, signage, markings, guardrail installation, and other miscellaneous activities. The project is split into multiple schedules that will be awarded separately or together. The total cost of the project is estimated between $75 million to $100 million. Bids are due by the date specified on the SF1442. Interested vendors must register on SAM.gov to receive notifications and download solicitation documents. Annual representations and certifications must be completed on SAM.gov. VETS-4212 reporting must also be filed electronically. Subcontracting plans are required from businesses other than small businesses if subcontracts will exceed $750,000.
View the file
Other files for this federal contract opportunity
Show all 45
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION
IFB No. 693C73- 22-B-000004
This Contract Cites
STANDARD SPECIFICATIONS (FP-14)
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
NP-BLRI 2B13, 2H17, ETC
BLUE RIDGE PARKWAY - NATIONAL PARK SERVICE
RECONSTRUCTION AND REHABILITATION OF BLUE RIDGE PARKWAY,
2B-2H FROM MP 229.6 TO MP 305.1
Contract No.
PMIS# 258063, NPS# 601/175165
ADDRESS:
CONTRACTOR:
STATE
COUNTY
PARK
North Carolina
Alleghany, Ashe, Avery, Burke, Caldwell, Watauga, Wilkes
Blue Ridge Parkway
TYPE OF IMPROVEMENT
Work will include pavement reconstruction/rehabilitation, drainage improvements, signage, pavement markings, guardrail and other miscellaneous work.
Project Length Totals For Parking Areas, Lane Miles is calculated as SQFT/11ft (nominal) lane
78.16 167.10
Schedule Parking Area Roadway / Parking Area / Other Mileposts / SQFT Linear
Feet Route Miles
Lane Miles
A BLRI-0001CA - Blue Ridge Parkway 229.6 To 237.0 39,072 7.40 14.80
B BLRI-0001CA - Blue Ridge Parkway 237.0 To 247.9 57,552 10.90 21.80
C BLRI-0001CA - Blue Ridge Parkway 247.9 To 261.1 69,696 13.20 26.40
D BLRI-0001CA - Blue Ridge Parkway 261.1 To 261.4 1,584 0.30 0.60
D BLRI-0001CB - Blue Ridge Parkway 261.4 To 276.2 78,144 14.80 29.60
E BLRI-0001CB - Blue Ridge Parkway 276.2 To 282.0 30,624 5.80 11.60
F BLRI-0001CB - Blue Ridge Parkway 291.7 To 299.3 40,128 7.60 15.20
G BLRI-0001CB - Blue Ridge Parkway 299.3 To 305.1 30,624 5.80 11.60
J BLRI-0001CB - Blue Ridge Parkway 282.0 To 291.7 51,216 9.70 19.40
A BLRI-0127ZZ - Access Ramp to US-21 North
0 To 0.07 370 0.07 0.14
A BLRI-0126ZZ - Access Ramp to US-21 South
0 To 0.06 317 0.06 0.12
B BLRI-0413 - Bluff Maintenance Road 0 To 0.27 1,426 0.27 0.54
C BLRI-0125ZZ - Access Ramp to NC-18 North
0 To 0.14 739 0.14 0.28
C BLRI-0124ZZ - Access Ramp to NC-18 South
0 To 0.15 792 0.15 0.30
D BLRI-0154 - Access Ramp to NC-16 North
0 To 0.05 264 0.05 0.10
D BLRI-0123 - Access Ramp to NC-16 South
0 To 0.07 370 0.07 0.14
E BLRI-0122 - Access Ramp to US-421 0 To 0.14 739 0.14 0.28
E BLRI-0121 - Access Ramp to US-421 0 To 0.05 264 0.05 0.10
J BLRI-0235 - Access Ramp to Bamboo Road
0 To 0.04 211 0.04 0.08
F BLRI-0120ZZ North - Access Ramp to US-221 North & US-321 North
0 To 0.14 739 0.14 0.28
F BLRI-0120ZZ South - Access Ramp to US-221 South & US-321 South
0 To 0.15 792 0.15 0.30
F BLRI-0443 - Male Servant Quarters Road
0 To 0.05 264 0.05 0.05
F BLRI-0119 - Access Ramp to US-221 0 To 0.09 475 0.09 0.18
F BLRI-0236 - Trout Lake Road 0 To 0.63 3,326 0.63 0.63
F BLRI-0158 - Access Ramp to Holloway Mountain Road
0 To 0.07 370 0.07 0.14
G BLRI-0118 - Access Ramp to US-221 West
0 To 0.13 686 0.13 0.26
A ■ BLRI-1002 - Little Glade Mill Pond Overlook
4,242 0 0.00 0.07
A ■ BLRI-1003 - Stone Mountain Overlook 18,018 0 0.00 0.31
A ■ BLRI-1004 - Bullhead Mountain Overlook
3,287 0 0.00 0.06
A ■ BLRI-1005 - Mahogany Rock Overlook 13,496 0 0.00 0.23
A ■ BLRI-1006 - Devils Garden Overlook 10,382 0 0.00 0.18
B ■ BLRI-1007 - Air Bellows Overlook 16,907 0 0.00 0.29
B ■ BLRI-1008 - Brinegar Cabin Spur Overlook
11,684 0 0.00 0.20
B ■ BLRI-1009 - Fodders Stack Parking Area 23,700 0 0.00 0.41
B ■ BLRI-1010 - Bluffs Restaurant Parking Area
49,955 0 0.00 0.86
B ■ BLRI-1011C - Wildcat Bluffs Overlook 4,415 0 0.00 0.08
B ■ BLRI-1012 - Alligator Back Overlook 17,611 0 0.00 0.30
B ■ BLRI-1013 - Bluff Mountain Overlook 8,004 0 0.00 0.14
B ■ BLRI-1014 - Basins Cove Overlook 9,814 0 0.00 0.17
C ■ BLRI-1016 - Sheets Gap Overlook 19,001 0 0.00 0.33
C ■ BLRI-1017 - Northwest Trading Post Parking Area
15,122 0 0.00 0.26
C ■ BLRI-1018 - Jumpinoff Rock Overlook 8,374 0 0.00 0.14
D ■ BLRI-1019 - The Lump Overlook 17,171 0 0.00 0.30
D ■ BLRI-1020 - Mount Jefferson Overlook 4,142 0 0.00 0.07
D ■ BLRI-1021 - Betsey's Rock Falls Overlook
1,215 0 0.00 0.02
D ■ BLRI-1023 - Lewis Fork Overlook 7,813 0 0.00 0.13
D ■ BLRI-1024 - Jeffress Park / Cascades Picnic Area
23,300 0 0.00 0.40
D ■ BLRI-1025 - Tompkins Knob Overlook 8,376 0 0.00 0.14
D ■ BLRI-1026 - Elk Mountain Overlook 9,769 0 0.00 0.17
E ■ BLRI-1027 - Stony Fork Valley Overlook
5,581 0 0.00 0.10
E ■ BLRI-1028 - Osborne Mountain Overlook
12,659 0 0.00 0.22
E ■ BLRI-1029 - Carroll Gap Overlook 5,886 0 0.00 0.10
E ■ BLRI-1030 - Grandview Overlook 15,112 0 0.00 0.26
J ■ BLRI-1031 - Boone's Trace Overlook 2,135 0 0.00 0.04
J ■ BLRI-1032 - Ravens Rock Overlook 11,169 0 0.00 0.19
J ■ BLRI-1033 - Yadkin Valley Overlook 5,476 0 0.00 0.09
J ■ BLRI-1034 - Thunder Hill Overlook 10,053 0 0.00 0.17
F ■ BLRI-1035 - Moses Cone Overlook 18,264 0 0.00 0.31
F ■ BLRI-1036ZZ - Trout Lake Parking Areas
21,360 0 0.00 0.37
F ■ BLRI-1038 - Sims Creek Overlook 4,024 0 0.00 0.07
F ■ BLRI-1039 - Sims Pond Overlook 10,659 0 0.00 0.18
F ■ BLRI-1203 - Sandy Flat Maintanace Area
64,612 0 0.00 1.11
F ■ BLRI-1040 - Price Lake Overlook 14,725 0 0.00 0.25
F ■ BLRI-1041 - Cold Prong Overlook 11,921 0 0.00 0.21
G ■ BLRI-1042 - Calloway Peak Overlook 6,412 0 0.00 0.11
G ■ BLRI-1043 - Boone Fork Overlook 13,288 0 0.00 0.23
G ■ BLRI-1044 - Green Mountain Overlook 10,602 0 0.00 0.18
G ■ BLRI-1045 - Pilot Ridge Overlook 6,133 0 0.00 0.11
G ■ BLRI-1046 - Wilson Creek Valley Overlook
11,184 0 0.00 0.19
G ■ BLRI-1047 - Boulder Field Overlook 5,201 0 0.00 0.09
G ■ BLRI-1048 - Rough Ridge Overlook 7,301 0 0.00 0.13
G ■ BLRI-1049 - Wilson Creek Overlook 4,938 0 0.00 0.09
G ■ BLRI-1050 - Yonahlossee Overlook 6,236 0 0.00 0.11
G ■ BLRI-1051 - Linn Cove Visitor Center Parking Area
39,417 0 0.00 0.68
G ■ BLRI-1052 - Stack Rock Parking Area 11,227 0 0.00 0.19
B BLRI-0216 - Bluffs Park Lodge Road 0 To 0.36 1,901 0.36 0.72
B ■ BLRI-1011AZ - Bluffs Lodge Parking Area A
19,324 0 0.00 0.33
B ■ BLRI-1011BZ - Bluffs Lodge Parking Area B
5,089 0 0.00 0.09
TABLE OF CONTENTS
Page
Notice to Bidders 1 through 3
Checklist for Bid Submission 1 through 2
*SF-1442 Solicitation, Offer, and Award 1 through 7
Statement of Work 1 page
Bid Schedule Instructions 1 through 4
*Bid Schedule B-1 through B-55
*SF-24 Bid Bond C-1 through C-2
FEDERAL ACQUISITION REGULATION & TRANSPORTATION ACQUISITION
REGULATION SOLICITATION PROVISIONS & CONTRACT CLAUSES
Index to Federal and Transportation Acquisition Regulations 1 through 7
Representations and Certifications (SAMs online) D-1 through D-3
Instructions to Bidders E-1
*Socioeconomic Program Requirements F-1 through F-8
Minimum Wage Schedule F-9 through F-24
*General Contract Requirements G-1 through G-7
Construction Contract Requirements H-1 through H-6
Special Contract Requirements J-1 through J-100
Section K K-1 through K-3
Permits Obtained for this Project 1 page
SPECIFICATIONS via File Sharing Email
Plans 1 through 181
Categorical Exclusion Form (NEPA) 1 through 10
CADD_File_Disclaimer_Letter_2B13 1 page
BLRI_C4_MaintenanceFeatures 1 through 507
BLRI_C5_RipReport 1 through 496
BLRI_C5_RouteID 1 through 75
Bridge Inspection Reports (28) See Documents/SAM.gov
CulvertData See Document/SAM.gov
EnvironmentalData See Document/SAM.gov
GeotechData See Document/SAM.gov
*Subcontracting Plan 1 through 5
* Bidder’s Qualifications Form 1 through 7
* Federal Contractor Veterans’ Employment Report VETS-4212 1 through 5
*BOLD FACED ITEMS ARE TO BE INCLUDED WITH THE BID SUBMITTAL PACKAGE
NOTICE TO BIDDERS
CONTRACT FORMAT:
Bidders should note that the format of this contract is in accordance with Federal Acquisition
Regulations (FAR), promulgated by the General Services Administration (GSA), effective April 1, 1984, including all applicable revisions. Applicable FAR provisions and clauses are incorporated in this contract by reference or full text as indicated in the INDEX before the D-pages in this booklet.
FAR provisions and clauses incorporated by reference can be accessed on the Internet website at https://www.acquisition.gov/. Bidders are encouraged to review the documents thoroughly before submitting a bid.
PROPOSAL BOOKLET AND OFFER SUBMITTAL:
It is the responsibility of the Bidder to verify that this bid is complete as listed in the Table of Contents. The Bidder is responsible for submitting all required forms and documents with the bid.
Bidders should use the Checklist for Bid Submission included in this booklet to check that their bids are complete.
CONSTRUCTION CONTRACTS:
As stated in FAR Clause 52.236-1, the Contractor shall perform on the site, and with its own organization, work equivalent to at least 50%. Additional guidance is given in FAR Subpart 35.005 where the majority of the project work is complex and specialized such as restoration work, bridge painting, and proprietary construction techniques (i.e. proprietary Cintec arch strengthening.) There are exceptions and they will be reviewed on a case-by-case basis.
HAZARDOUS MATERIALS IDENTIFICATION AND MATERIAL SAFETY DATA:
As required by FAR Clause 52.223-3, Hazardous Materials Identification and Safety Data, the apparent low Bidder must submit prior to award a Material Safety Data Sheet (MSDSs) for all hazardous materials that the Bidder identifies in paragraph (b) of this clause in Section G of this booklet. Failure to submit MSDSs may render the Bidder ineligible for award of contract. The apparent low Bidder should submit their MSDSs within two weeks after bid opening.
ATTENTION LARGE BUSINESSES - UTILIZATION OF SMALL BUSINESS CONCERNS:
All bidders that are large businesses should note their responsibilities in the awarding of subcontracts in accordance with FAR Clause 52.219-8, Utilization of Small Business Concerns. An awardee, if a large business concern, should note its responsibility to establish and conduct a subcontracting plan in accordance with FAR Clause 52.219-9, Alternate I, Small Business Subcontracting Plan. If the apparently successful bidder selected for award is a LARGE BUSINESS, then that bidder is required to submit a subcontracting plan prior to contract award. If the apparently successful bidder fails to submit a subcontracting plan within the time limit prescribed by the Contracting Officer, the bidder will be ineligible for award. PLEASE NOTE: A blank subcontracting plan is included in this solicitation package as a separate document for your use.
INTERNET BASED DATA BASES - REQUIRED INPUT:
According to FAR Subpart 4.1102 contractors are required to be registered in the System for
Award Management (SAM) at the time a bid is submitted. Access the following web site to register: https://www.sam.gov/.
According to FAR Subpart 4.1201 contractors are required to complete electronic annual representations and certifications in SAM accessed via https://www.sam.gov/ as a part of required registration.
According to FAR Subpart 22.1302 (b) federal contractors and sub-contractors MUST complete the required annual Vets-4212 Form in order to be eligible for a contract award. It can be completed on-line at http://www.dol.gov/vets/vets4212.htm. The annual filing period for Form VETS-4212 is
August 1 through September 30. Reports filed before August 1 will be treated as part of the previous year's filing cycle. Federal contractors and subcontractors who are required to file a form VETS-4212 can submit their forms electronically by using either the VETS-4212 Reporting Application or batch https://www.sam.gov/ https://www.sam.gov/ http://www.dol.gov/vets/vets4212.htm filing process, or by using the paper form by email or U.S. mail. It is recommended that you file your form electronically at https://vets4212.dol.gov/vets4212. Please visit http://www.dol.gov/vets/vets4212.htm for more information on the reporting process.
PAYMENT:
Bidders are advised to review the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP), subsection 109.05, concerning direct and indirect payment included under a pay item in the bid schedule.
PROGRESS PAYMENTS:
ALL payments will be made via Electronic Funds Transfer (EFT) as such; the payment information in SAM must be accurate in order for contractors' invoices to be considered proper invoices for the purpose of prompt payment under DOT contracts. Contractors must input and maintain (update as necessary) their EFT information in the SAM database. Bidders are advised that under FAR Clause 52.232-5, Payments Under Fixed Price Construction Contracts, upon request, progress payments will include premiums paid by the Contractor to obtain performance and payment bonds as required under this contract. These payments shall not be made in addition to the contract price. As specified in the FP, “Section 151 - MOBILIZATION", payments for performance and payment bond premiums shall be included in mobilization.
WELFARE-TO-WORK INITIATIVE:
The President’s Welfare Reform Bill was initiated to assist welfare recipients and hopefully aid welfare recipients to find gainful employment. In support of this bill, Contractors are encouraged to hire welfare recipients whenever possible and to use welfare recipients in performance of duties on Government contracts.
INCREASING SEAT BELT USE IN THE UNITED STATES:
The President’s Executive Order 13043 dated April 16, 1997, was issued to increase the use of seat belts in the United States. In support of this Order, contractors and subcontractors are encouraged to adopt and enforce on-the-job seat belt policies for their employees when operating company-owned, rented, or personally owned vehicles.
OBTAINING BID DOCUMENTS:
Invitation For Bid (IFB) documents will not be mailed. All solicitation documents are available for direct download from the Contract Opportunities website: https://sam.gov/. Contractors are encouraged to register on the website (for this specific project) in order to receive automatic notifications when a document is added or updated for this specific project. All questions about this construction project must be emailed to the following address:
eflhd.contracts@dot.gov.
THE CONTRACTOR IS SOLELY RESPONSIBLE FOR MONITORING THE WEB PAGES
NOTED ABOVE FOR ALL CHANGES TO THE SOLICITATION AND ACTING ON
THOSE CHANGES.
PLEASE NOTE: For security reasons, individuals requiring access to all government buildings must present a valid photo ID and be escorted to their destination by a Government employee. All visitors attending bid openings are urged to arrive at least 1 hour prior to a scheduled bid opening. All visitors must sign in at the main entrance of the Quantum Park facility and wait to be escorted by a
Government employee to Eastern Federal Lands Highway Division (EFLHD) in Suite 200. Visitors must then register with the EFLHD Receptionist. A Government employee will collect all bids. Prior to the bid opening, a Government employee will escort all bidders to the bid opening. Unescorted visitors will be denied entry and no exceptions will be made.
https://vets4212.dol.gov/vets4212 https://sam.gov/ mailto:eflhd.contracts@dot.gov
PLEASE NOTE ELECTRONIC BIDS WILL BE ACCEPTED VIA EMAIL
ONLY AT EFLHD.CONTRACTS@DOT.GOV. Bids sent to any other email address besides EFLHD.Contracts@DOT.GOV will not be accepted. Bids will not be accepted via facsmile. Hand-delivered bids are not recommended unless the contractor is also attending the bid opening.
mailto:EFLHD.CONTRACTS@DOT.GOV mailto:EFLHD.Contracts@DOT.GOV
CHECKLIST FOR BID SUBMISSION
The following is a checklist of items included in the proposal/bid package that are required to be completed and returned (or filled in on-line) to the address in Block 7 of the Standard Form 1442, Solicitation, Offer, and Award (page 1). This checklist is for informational purposes only and is not required to be filled out by the bidder. Failure to submit a complete bid may be cause to reject your bid.
PLEASE NOTE ELECTRONIC BIDS WILL BE ACCEPTED VIA EMAIL ONLY
AT EFLHD.CONTRACTS@DOT.GOV. Bids sent to any other email address besides
EFLHD.Contracts@DOT.GOV will not be accepted. Bids will not be accepted via facsmile. Hand-delivered bids are not recommended.
1. Bid Envelope (If the contractor elects not to send the bid electronically via email to
EFLHD.Contracts@dot.gov):
a. Addressed as shown in Block 7 of SF-1442
b. In the lower left corner, indicate the following: Solicitation No., Project Name & Number, and mail to Suite E2-3-300, ATTENTION: ACQUISITIONS. If bids are hand-delivered, bring them to the main entrance of Quantum Park, and ask for the Federal Highway Administration (EFLHD)
Receptionist to be contacted and an EFLHD representative will come to collect the bid. HAND-
DELIVERED BIDS ARE NOT RECOMMENDED.
2. Standard Form 1442: Solicitation, Offer and Award
a. Block 14: Name and Address of Bidder.
b. Block 15: Telephone Number of Bidder.
c. Block 16: Remittance Address if different from Block 14.
d. Block 19: All Amendments Acknowledged, with dates of Amendments.
e. Block 20: Bid is signed and dated.
3. Bid Schedule - (Pages B-1 through B-55)
a. Unit bid price and bid amount provided for each pay item in numbers.
b. Corrections initialed.
c. Price Evaluation eligibility is indicated on the Bid Summary page.
4. Standard Form 24, Bid Bond (Pages C-1 through C-2) (Required if bid guarantee is bid bond)
a. Date executed
b. Legal name and address of bidder.
c. Type of organization.
d. State of incorporation (if applicable).
e. Name and business address of Treasury approved surety.
f. Penal sum of bond (not less than 20% of bid total).
g. Bid identification.
h. Signature of Bidder
i. Seal, if corporation
j. Signature of Surety
k. Seal, if corporation
BIDS RECEIVED WITHOUT A VALID BID BOND WILL BE REJECTED.
mailto:EFLHD.CONTRACTS@DOT.GOV mailto:EFLHD.Contracts@DOT.GOV mailto:EFLHD.Contracts@dot.gov
CHECKLIST FOR BID SUBMISSION
5. Power of Attorney.
a. Dated on or before execution date of bond
b. Power has original signature of surety, or is embossed with surety's seal in the certification section
BIDS RECEIVED WITHOUT A VALID POWER OF ATTORNEY WILL BE REJECTED.
6. Fill-ins. The following full text Clauses and/or Provision numbers shall be checked or filled in and returned with the bid package:
a. 52.219-4 – HubZone ONLY - See Section F, Clause 52-219-4, paragraph "C", check block if wavier is applicable.
7. Bidder's Qualifications form (provided separately as part of the Bid Documents Package).
Form completed, signed and submitted with bid
8. Subcontracting Plan - Large Businesses Only: Submittal with the bid is not mandatory, but it is encouraged, as it will speed up the award process should your firm be the apparent low bidder.
Legislated subcontracting goals: (15 USC 644 (g)(1)
• 45.25% - Small Businesses (SB)
• 5% - Small Disadvantaged Businesses (SDB)
• 3% - HUBZone
• 5% - Woman Owned Small Business (WOSB)
• 3% - Service-Disabled Veteran-Owned Small Businesses (SDVOSB)
9. System for Award Management (SAM): The contractor is currently registered in the System For Award Management (SAM) database at https://www.sam.gov/ at the time the bid is submitted. If the contractor elects to not have its active SAM registration viewable by the public, then the contractor must submit a copy with the bid.
10. Online Representations and Certifications Application: The contractor's Representations and Certifications have been input online via the electronic database at https://www.sam.gov/.
11. VETS – 4212 Reporting: The contractor has completed the annual reporting requirement online at http://www.dol.gov/vets/vets4212.htm.
The annual filing period for Form VETS-4212 is August 1 through September 30. Reports filed before
August 1 will be treated as part of the previous year's filing cycle. Federal contractors and subcontractors who are required to file a form VETS-4212 can submit their forms electronically by using either the VETS-
4212 Reporting Application or batch filing process, or by using the paper form by email or U.S. mail. It is recommended that you file your form electronically at https://vets4212.dol.gov/vets4212. Please visit http://www.dol.gov/vets/vets4212.htm for more information on the reporting process.
NOTE: THE CONTRACTOR IS FULLY RESPONSIBLE TO VERIFY THAT ALL
DATA IN THE ABOVE DATABASES IS CORRECT EACH TIME A BID PACKAGE
IS SUBMITTED. FAILURE TO PROPERLY INPUT AND/OR UPDATE YOUR DATA
PRIOR TO BID SUBMISSION MAY CAUSE THE BID TO BE REJECTED.
https://www.sam.gov/ https://www.sam.gov/SAM/ http://www.dol.gov/vets/vets4212.htm https://vets4212.dol.gov/vets4212
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
SUITE E2-3-300
693C73
ATTN: ACQUISITIONS
ASHBURN VA 20147
See Block 7
EMILY MCCLEARY
b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
EFLHD.Contracts@dot.gov
See Block 10 x
12/16/2021
693C7322B000004
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
This Invitation for Bids is for the Blue Ridge Parkway, Project No. NP-BLRI 2B13, 2H17, ETC, located in Alleghany, Ashe, Avery, Burke, Caldwell, Watauga, and Wilkes
Counties, North Carolina in strict accordance with the Solicitation/Contract instructions, notices, clauses, provisions, items listed below, and for the quantities of work actually performed at the unit prices as bid in the Bid Schedule, including all applicable Federal, State, and local taxes.
FP - Standard Specification for Construction of Roads & Bridges on Federal Highway
Projects.
Bid Schedule, Section B - pages B-1 through B-55.
Special Contract Requirements, Section J - pages J-1 through J-100.
Plans, Sheets 1 through 181.
Categorical Exclusion Form (NEPA), pages 1 through 10.
CADD_File_Disclaimer_Letter_2B13, 1 page.
BLRI_C4_MaintenanceFeatures, pages 1 through 507.
BLRI_C5_RipReport, pages 1 through 496.
BLRI_C5_RouteID, pages 1 through 75.
Bridge Inspection Reports (28), See Documents/SAM.gov.
CulvertData, See Document/SAM.gov.
Continued ...
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 calendar days and complete it within ________________ ________________ calendar days after receiving
Continuation Sheet, Block 11
01/18/2022
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
September 30, 2025
�����./�0::/303�#73//5�20�9/3:03;�2./�=03D�3/AB83/>�#2�2./�9384/5�59/48:8/>�$/60=�81�523842�#4403>#14/�=82.�2./�2/3;5�0:�2.85�5068482#2801?�8:�2.85�0::/3�85�#44/92/>
$@�2./��0E/31;/12�81�=382817�=82.81�--------------------�4#6/1>#3�>#@5�#:2/3�2./�>#2/�0::/35�#3/�>B/����������
| � | %(�� |
| �) | �� |
| �� | ����� |
| � | �� |
| ����� ���������� | ���� | ����� |
| � | �� |
�����./�0::/303�#73//5�20�:B3185.�#1@�3/AB83/>�9/3:03;#14/�#1>�9#@;/12�$01>5�
0��#������ ��2�
| ����� | ������ | � |
| H���� | �� |
������� �)4��
3�2���%����
| �����" | ��� � ����� | ��� |
| ����������� | �� |
| ��" ���� | ���������� | |
| �������� | ����� | "��� |
����������3 4��� '5 '6 �--����7��
3�2���%���
| �� | ������ | �� | ������ | ������ | � |
| H���� | �� |
������� )4������ �$���� �� �4������
���� 2 OF 7
����2�� #��0 ��2�����
�)��������� )�&4'��������������� ������������ &4'���������������
�"������&��*���G��'����, Block 26
Federal Highway Administration Eastern Federal Lands Highway Division ATTN: Construction Branch Quantum Park 22001 Loudoun County Parkway Suite E2-2-200 Ashburn, VA 20147
Federal Highway Administration Eastern Federal Lands Highway Division A/P Branch, AMZ-150 P.O. Box 25710 or E-MAIL
9-AMC-AMZ-EFLINVOICES@FAA.GOV
Oklahoma City, OK 73125
EFLHD-CO
peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text peggy.schaad Typewritten Text
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 7
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
693C7322B000004
EnvironmentalData, See Document/SAM.gov.
GeotechData, See Document/SAM.gov.
Permits, 1 page.
The project consists of the reconstruction and rehabilitation of the Blue Ridge Parkway in North Carolina from Milepost 229.6 to MP 305.1, including overlooks, parking areas and ramps.
Work also includes drainage assessments and improvements, signage, pavement markings, guardrail, and slope stabilization and other miscellaneous work.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
CONTINUATION OF SF 1442
Block 2:
This project is UN-RESTRICTED - Bids will be accepted from ALL eligible business concerns.
This procurement falls under North American Industry Classification System (NAICS) code
237310 - Highway, Street, and Bridge Construction (see FAR Subpart 19.10)
The award of this project is subject to a 10% price evaluation preference for eligible HubZone
Small Business Concerns (must be on the SBA listing) (see FAR Clause 52.219-4).
Electronic bids will be accepted via email sent to EFLHD.Contracts@dot.gov. Please be sure to indicate the solicitation number, project number, and ATTN: Emily McCleary on the subject line of your email. Please note you must include a scanned copy of your official bid bond along with your bid documents if you submit your bid electronically.
PHYSICAL DATA AVAILABLE FOR REVIEW
1. Manual on Uniform Traffic Control Devices for Streets and Highways, 2009 Edition, published by the Federal Highway Administration. http://mutcd.fhwa.dot.gov.
2. National Park Service Sign Manual, revised - January 1988, United States Department of the Interior. http://flh.fhwa.dot.gov/resources/design/library.
3. Categorical Exclusion Form (NEPA)
4. CADD_File_Disclaimer_Letter_2B13
5. BLRI_C4_MaintenanceFeatures
6. BLRI_C5_RipReport
7. BLRI_C5_RouteID
8. Bridge Inspection Reports (28)
9. CulvertData
10. EnvironmentalData
11. GeotechData
12. Permits
Block 9:
In accordance with FAR Provision 52.236-27, Site Visit, a Government representative can be available to show the project to prospective bidders. All requests for site visits see Section
E of the solicitation and e-mail all questions concerning this construction project to the following e-mail address eflhd.contracts@dot.gov. Interested parties must provide the Solicitation Number and the relevant project name with all requests and questions.
Block 11:
Maximum Time Allowed for the Contract if Schedules are Awarded at the Same Time
If the Government awards the contract as Schedules A+B+C+D+E+F+G+H+J or +K, the performance period to complete all contract work will be as stated in Subsection 108.01 of the
Special Contract Requirements (J Pages), all construction activities at the project site must be completed by no later than September 30, 2025.
mailto:EFLHD.Contracts@dot.gov http://flh.fhwa.dot.gov/resources/design/library mailto:eflhd.contracts@dot.gov
Maximum Time Allowed for Each Schedule of Work if Awarded Separately
If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 247 calendar days and will start on the effective date of
Schedule A’s Notice to Proceed.
If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 231 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.
If Schedule C (Government Option 2) is exercised after the award of the original contract, the performance period to complete all Schedule C work will be 243 calendar days and will start on the effective date of Schedule C’s Notice to Proceed.
If Schedule D (Government Option 3) is exercised after the award of the original contract, the performance period to complete all Schedule D work will be 204 calendar days and will start on the effective date of Schedule D’s Notice to Proceed.
If Schedule E (Government Option 4) is exercised after the award of the original contract, the performance period to complete all Schedule E work will be 168 calendar days and will start on the effective date of Schedule E’s Notice to Proceed.
If Schedule F (Government Option 5) is exercised after the award of the original contract, the performance period to complete all Schedule F work will be 215 calendar days and will start on the effective date of Schedule F’s Notice to Proceed.
If Schedule G (Government Option 6) is exercised after the award of the original contract, the performance period to complete all Schedule G work will be 124 calendar days and will start on the effective date of Schedule G’s Notice to Proceed.
If Schedule H (Government Option 7) is exercised after the award of the original contract, the performance period to complete all Schedule H work will be 392 calendar days and will start on the effective date of Schedule H’s Notice to Proceed.
If Schedule J (Government Option 8) is exercised after the award of the original contract, the performance period to complete all Schedule J work will be 144 calendar days and will start on the effective date of Schedule J’s Notice to Proceed.
If Schedule K (Government Option 9) is exercised after the award of the original contract, the performance period to complete all Schedule K work will be 91 calendar days and will start on the effective date of Schedule K’s Notice to Proceed.
See Completion of Work section of the B-Pages – Bid Schedule Instructions for further information. The completion time for the contract is not to exceed the maximum time above.
Work restrictions can be found in SCR Sections 108 and 156
Notice to Proceed will be issued within 30 days following receipt of acceptable performance and payment bonds. (Actual Notice to Proceed date will be 10 days from issuance or the date specified in the Notice.)
Bidders are to assume that the award of the contract and approval of the Contractor’s
Performance and Payment Bonds (see Block 12a of the SF-1442 and FAR Clause 52.228-
15) may result in the start of construction activities to be no earlier than April 2022. See
Subsection 108.01 of the SCR’s for additional details.
Block 12A:
Furnish performance and payment bonds in accordance with FAR Clause 52.228-15.
Block 13:
A bid guarantee in the amount of not less than 20 percent of the bid price or $3 million, whichever is less, is required with this bid. If the bidder fails to provide the required bid guarantee, such failure may require rejection of the bid. Reference FAR Provision
52.228-1, Bid Guarantee. Please note you must include a scanned copy of your official bid bond along with your bid documents if you submit your bid electronically.
Block 17:
Amounts should be completed as follows:
Schedule A - $
Schedule B (Option 1) - $
Schedule C (Option 2) - $
Schedule D (Option 3) - $
Schedule E (Option 4) - $
Schedule F (Option 4) - $
Schedule G (Option 6) - $
Schedule H (Option 7) - $
Schedule J (Option 8) - $
Schedule K (Option 9) - $
Other:
The estimated price is expected to fall within the price range of $75,000,000 to $100,000,000.
Responsibility of bidders shall be evaluated in accordance with the information provided on the Bidder's Qualification Form, which can be downloaded from the Contract Opportunities website located at http://SAM.gov. FP-14 versions can be downloaded at the FHWA web site located at http://flh.fhwa.dot.gov/resources/specs/.
Electronic bids must contain the required signatures (electronic or by hand).
http://sam.gov/ http://flh.fhwa.dot.gov/resources/specs/
Subcontracting Goals
Required from all other than Small business when the requirement is expected to exceed
$750,000 ($1,500,000 for Construction) [FAR 19.702]. The Contracting Officer, along with review and advisory comments from the Office of Small Disadvantaged Business Utilization
(OSDBU), is responsible for approving a reasonable and realistic plan [FAR 19.705-4] [TAM
1219.201(e)(6)]. The legislated subcontracting goals are as shown below. A copy of each subcontracting plan (or contractor statement that no subcontracts are to be awarded) must be provided to OSDBU prior to close of negotiations [TAM 1219.705-5 and - 6].
Legislated subcontracting goals: (15 USC 644 (g)(1)
• 45.25% - Small Businesses (SB)
• 5% - Small Disadvantaged Businesses (SDB)
• 3% - HUBZones
• 5% - Women-Owned Small Businesses (WOSB)
• 3% - Service-Disabled Veteran-Owned Small Businesses (SDVOSB)
STATEMENT OF WORK
Sealed bids from all business concerns will be accepted for the Blue Ridge Parkway, Project
NP-BLRI 2B13, 2H17, ETC, Solicitation Number 693C73-22-B-000004, located in Alleghany, Ashe, Avery, Burke, Caldwell, Watauga, and Wilkes Counties, North Carolina. The project consists of the reconstruction and rehabilitation of the Blue Ridge Parkway in North Carolina from Milepost 229.6 to MP 305.1, including overlooks, parking areas and ramps. Work also includes drainage assessments and improvements, signage, pavement markings, guardrail, and slope stabilization and other miscellaneous work.
The project will be split into multiple work schedules/contract options, with the cost of the entire project expected to fall within the price range of $75,000,000 to $100,000,000.
The performance period to complete all contract work will be September 30, 2025 after the issuance of the Notice to Proceed.
BID SCHEDULE INSTRUCTIONS
PROJECT: NP BLRI 2B13, 2H17, ETC
BIDDERS PLEASE NOTE: Before preparing the bid, carefully read the Instructions to
Bidders. While preparing the bid, comply with the following:
COMPLETING THE BID SCHEDULE
Complete the Bid Schedule(s) by handwriting in ink or typing. Specify a Unit Bid Price, in figures with cents to only two decimal places, for each pay item in the Unit Bid Price column for which a quantity is given. Do not enter or tender a Unit Bid Price for any pay item for which no estimated quantity appears in the Bid Schedule. Determine the products of the respective unit prices and quantities, and show them, in figures, in the Amount Bid column. If a Unit Bid Price and Amount Bid have been inserted by the Government for a pay item, do not change the Unit Bid Price and Amount Bid for the pay item. Determine the Bid Total for each specific individual Schedule of Work by adding the amounts of the listed items and show in the block provided for that individual Schedule of Work. In case of multiplication errors, the Amount Bid for the item will be based on the Unit Bid Price.
To be eligible for award, bidders must submit prices for each pay item.
Review Subsection 109.05 of the FP (standard specifications book) regarding scope of payment for direct and indirect payment work.
Fill in the Bid Total(s) for each individual Schedule of Work as directed on the Bid Summary pages. Fill in the Evaluation Total Price of Project in the space provided on the B-54 Bid Summary page.
The amount in Block 17 of the SF 1442 should be completed as follows:
Schedule A - $ .
Schedule B - $ .
Schedule C - $ .
Schedule D - $ .
Schedule E - $ .
Schedule F - $ .
Schedule G - $ .
Schedule H - $ .
Schedule J - $ .
Schedule K - $ .
SCHEDULES OF WORK
The Bid Schedule is comprised of the following separate schedules and options of work:
Schedule A (Base Contract) - Pages B-1 thru B- 5 Schedule B (Government Option 1) - Pages B- 6 thru B-11
Schedule C (Government Option 2) - Pages B-12 thru B-16 Schedule D (Government Option 3) - Pages B-17 thru B-22 Schedule E (Government Option 4) - Pages B-23 thru B-27 Schedule F (Government Option 5) - Pages B-28 thru B-33 Schedule G (Government Option 6) - Pages B-34 thru B-39 Schedule H (Government Option 7) - Pages B-40 thru B-42 Schedule J (Government Option 8) - Pages B-43 thru B-48 Schedule K (Government Option 9) - Pages B-49 thru B-53
The Government will award the project as a Base Contract (Schedule A) with the option to award Schedules B, C, D, E, F, G, H, and either J or K (Government Options 1, 2, 3, 4, 5, 6, 7, and either 8 or 9). The Schedule J (Government Option 8) and Schedule K (Government Option 9) cover the same milepost limits, but with different treatment options, and the Government will evaluate price per FAR Clause 52.217-4.
The purpose of the multiple schedules and options is to give the Government maximum flexibility in completing the project in a timely manner and at a cost-effective price, by proper utilization of programmed funds and upon receipt of any additional funds required to award the contract. If complete funding is in place at the time of award of Schedule A (Base Contract), the Government may award Schedules B, C, D, E, F, G, H, and either J or K (Government Options 1 2, 3, 4, 5, 6, 7, and either 8 or 9) at that time. If additional funding is required for the award of Schedules B, C, D, E, F, G, H, and either J or K (Government Options 1, 2, 3, 4, 5, 6, 7, and either 8 or 9), and is received after the award of Schedule A (Base Contract), the Government has the right to exercise Schedules B, C, D, E, F, G, H, and either J or K (Government Options 1, 2, 3, 4, 5, 6, 7, and either 8 or 9) at the unit prices bid according to the following schedule:
Schedules B, C, D, E, F, G, H, and either J or K (Government Option 1, 2, 4, 5, 6, 7, and either 8 or 9): No later than the contract completion date for Schedule A (Base Contract).
COMPLETION OF WORK
The Government has estimated the number of calendar days necessary to complete all contract work from the effective date of the Notice to Proceed to contract completion for the various contract award scenarios. The maximum number of calendar days allowed (i.e., the contact performance period) is shown in Block 11 of the SF-1442 and described below.
If the Government awards the contract as Schedules A+B+C+D+E+F+G+H+J or +K, the performance period to complete all contract work will be as stated in Subsection 108.01 of the Special Contract Requirements (J Pages), all construction activities at the project site must be completed by no later than September 30, 2025.
If the Government awards the contract as Schedule A only, the performance period to complete all Schedule A work will be 247 calendar days and will start on the effective date of Schedule A’s Notice to Proceed.
If Schedule B (Government Option 1) is exercised after the award of the original contract, the performance period to complete all Schedule B work will be 231 calendar days and will start on the effective date of Schedule B’s Notice to Proceed.
If Schedule C (Government Option 2) is exercised after the award of the original contract, the performance period to complete all Schedule C work will be 243 calendar days and will start on the effective date of Schedule C’s Notice to Proceed.
If Schedule D (Government Option 3) is exercised after the award of the original contract, the performance period to complete all Schedule D work will be 204 calendar days and will start on the effective date of Schedule D’s Notice to Proceed.
If Schedule E (Government Option 4) is exercised after the award of the original contract, the performance period to complete all Schedule E work will be 168 calendar days and will start on the effective date of Schedule E’s Notice to Proceed.
If Schedule F (Government Option 5) is exercised after the award of the original contract, the performance period to complete all Schedule F work will be 215 calendar days and will start on the effective date of Schedule F’s Notice to Proceed.
If Schedule G (Government Option 6) is exercised after the award of the original contract, the performance period to complete all Schedule G work will be 124 calendar days and will start on the effective date of Schedule G’s Notice to Proceed.
If Schedule H (Government Option 7) is exercised after the award of the original contract, the performance period to complete all Schedule H work will be 392 calendar days and will start on the effective date of Schedule H’s Notice to Proceed.
If Schedule J (Government Option 8) is exercised after the award of the original contract, the performance period to complete all Schedule J work will be 144 calendar days and will start on the effective date of Schedule J’s Notice to Proceed.
If Schedule K (Government Option 9) is exercised after the award of the original contract, the performance period to complete all Schedule K work will be 91 calendar days and will start on the effective date of Schedule K’s Notice to Proceed.
In developing a construction schedule to determine the number of calendar days, the Government considered and included the work limitations shown in Sections 108 and 156 of the FP and Special Contract Requirements (SCR’s). Specific work limitations may be (but are not limited to): National legal holidays, weekends, rush hours, night work, specified no work periods, work or traffic control phasing, etc. The Government also considered those work items that are weather sensitive and when those work items will be performed. Specific work items are (but not limited to): those that require a minimum ambient air temperature (asphalt paving and surface treatment, pavement striping, stone masonry, etc.); those that require maintaining a minimum surface temperature (concrete pavement, structural concrete, painting, etc.); and those that have specific planting seasons (turf establishment, sod, trees, plants, etc.). The Government also considered time required for preparing material and drawing submittals, and the allowable Government review times for those submittals (Subsection 104.03 of the FP and SCR’s).
Bidders are to assume that the award of the contract and approval of the Contractor’s Performance and Payment Bonds (see Block 12a of the SF-1442 and FAR Clause 52.228-
15) may result in the start of construction activities to be no earlier than April 2022. See Subsection 108.01 of the SCR’s for additional details.
BASIS FOR AWARD
The contract will be awarded to the responsive, responsible bidder with the lowest Evaluation Total Price of Project, which is defined as:
Schedule A (Base Contract) Bid Total + Schedule B (Government Option 1) Bid Total + Schedule C (Government Option 2) Bid Total+ Schedule D (Government Option 3) Bid Total+ Schedule E (Government Option 4) Bid Total+ Schedule F (Government Option 5) Bid Total+ Schedule G (Government Option 6) Bid Total+ Schedule H (Government Option 7) Bid Total+ Schedule J (Government Option 8) Bid Total+ Schedule K (Government Option 9) Bid Total.
B - 1
Item No. Pay Item No. Description Quantity Unit Unit Price Amount
A0010 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
A0020 15201-0000 CONSTRUCTION SURVEY AND STAKING
ALL LPSM $___LPSM_____ $____________
A0030 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
A0040 15702-5000 SOIL EROSION CONTROL, TEMPORARY DIVERSION BERM (BYPASS
PUMPING)
ALL LPSM $___LPSM_____ $____________
A0050 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
88,000 LNFT $____________ $____________
A0060 15706-1000 SOIL EROSION CONTROL, INLET PROTECTION (FIBER ROLL)
147 EACH $____________ $____________
A0070 15720-0000 STORM WATER POLLUTION PREVENTION PLAN (AND PERMITTING DESIGN
AND SERVICES)
ALL LPSM $___LPSM_____ $____________
A0080 20301-2400 REMOVAL OF SIGN
8 EACH $____________ $____________
A0090 20302-0400 REMOVAL OF CURB, ASPHALT
400 LNFT $____________ $____________
A0100 20302-0600 REMOVAL OF CURB, STONE
1,350 LNFT $____________ $____________
A0110 20302-2000 REMOVAL OF PAVED WATERWAY, STONE
1,000 LNFT $____________ $____________
A0120 20302-2600 REMOVAL OF PAVEMENT MARKINGS
165 LNFT $____________ $____________
A0130 20303-1600 REMOVAL OF PAVEMENT, ASPHALT
5,700 SQYD $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:NP-BLRI 2B13, 2H17, ETC
Project Name:Reconstruct and rehabilitate 75.5 miles of the Blue Ridge Parkway, 2B-2H from MP 229.6 to MP 305.1
B - 2
A0140 20303-3000 REMOVAL OF SIDEWALK, ASPHALT
410 SQYD $____________ $____________
A0150 20401-0000 ROADWAY EXCAVATION
1,300 CUYD $____________ $____________
A0160 20701-0200 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE B
1,500 SQYD $____________ $____________
A0170 20703-0000 GEOGRID (TRIAXIAL)
5,500 SQYD $____________ $____________
A0180 25102-0200 PLACED RIPRAP, METHOD A, CLASS 2
5 TON $____________ $____________
A0190 25510-0000 SELECT GRANULAR BACKFILL (#57 STONE)
1,300 CUYD $____________ $____________
A0200 30101-4000 AGGREGATE BASE GRADING C OR D
430 TON $____________ $____________
A0210 30302-1000 DITCH RECONDITIONING
21,500 LNFT $____________ $____________
A0220 30303-1000 ROADBED RECONDITIONING
5,600 SQYD $____________ $____________
A0230 30303-4000 SHOULDER RECONDITIONING
28,500 SQYD $____________ $____________
A0240 30502-0800 FULL DEPTH RECLAMATION WITH CEMENT, 8-INCH DEPTH
97,000 SQYD $____________ $____________
A0250 40101-0100 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/8-INCH NOMINAL
MAXIMUM SIZE AGGREGATE, <0.3 MILLION ESAL (PG 64-22)
8,700 TON $____________ $____________
A0270 40101-0500 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH NOMINAL
MAXIMUM SIZE AGGREGATE, <0.3 MILLION ESAL (PG 64-22)
12,000 TON $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project Name:Reconstruct and rehabilitate 75.5 miles of the Blue Ridge Parkway, 2B-2H from MP 229.6 to MP 305.1
B - 3
A0320 41202-0000 TACK COAT
15,500 GAL $____________ $____________
A0330 55220-0000 REPAIR CONCRETE
45 SQYD $____________ $____________
A0340 55223-0000 REPAIR CONCRETE (CLEAN AND EPOXY COAT REINFORCEMENT)
1 LNFT $____________ $____________
A0350 55225-0000 CLEAN AND RESEAL JOINTS (POURABLE JOINT)
105 LNFT $____________ $____________
A0360 55226-0000 CLEAN CONCRETE SURFACE (GRAFFITI REMOVAL)
1 SQYD $____________ $____________
A0370 60702-1000 REMOVING, CLEANING, AND RELAYING CULVERT
90 LNFT $____________ $____________
A0380 60704-0000 CLEANING CULVERT IN PLACE
27 EACH $____________ $____________
A0390 60706-0000 CLEANING DRAINAGE STRUCTURE
25 EACH $____________ $____________
A0400 60707-0300 LINING 18-INCH PIPE CULVERT
240 LNFT $____________ $____________
A0410 60707-0500 LINING 24-INCH PIPE CULVERT
220 LNFT $____________ $____________
A0420 60802-0300 PAVED WATERWAY, TYPE 3
1,000 LNFT $____________ $____________
A0430 60815-0300 RECONDITION PAVED WATERWAY, TYPE 3
3,400 SQYD $____________ $____________
A0440 60901-2300 CURB, ASPHALT, 6-INCH DEPTH
400 LNFT $____________ $____________
A0450 60910-0000 RESET CURB (STONE)
1,350 LNFT $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project Name:Reconstruct and rehabilitate 75.5 miles of the Blue Ridge Parkway, 2B-2H from MP 229.6 to MP 305.1
B - 4
A0460 61501-1100 SIDEWALK, ASPHALT
410 SQYD $____________ $____________
A0470 61502-1000 DRIVE PAD, CONCRETE (CONCRETE GRID PAVING UNIT)
75 SQYD $____________ $____________
A0480 62011-0300 STONE MASONRY HEADWALL FOR 18-INCH PIPE CULVERT
3 EACH $____________ $____________
A0490 62011-0500 STONE MASONRY HEADWALL FOR 24-INCH PIPE CULVERT
1 EACH $____________ $____________
A0500 62028-1000 REMOVE AND RESET STONE MASONRY HEADWALL
10 EACH $____________ $____________
A0510 62030-0000 REPOINT STONE MASONRY
1,350 LNFT $____________ $____________
A0520 62031-0000 REPOINT STONE MASONRY (BRIDGE)
465 SQFT $____________ $____________
A0530 62303-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES (BIOLOGICAL MONITORING)
ALL LPSM $___LPSM_____ $____________
A0540 62502-0000 TURF ESTABLISHMENT
355 SQYD $____________ $____________
A0550 63304-0900 SIGNS, ALUMINUM PANELS, TYPE 3 SHEETING
55 SQFT $____________ $____________
A0560 63305-0400 POSTS, STEEL, 2-INCH X 2-INCH
160 LNFT $____________ $____________
A0570 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID
430 LNFT $____________ $____________
A0580 63401-2300 PAVEMENT MARKINGS, TYPE L, SOLID
87,500 LNFT $____________ $____________
A0590 63401-2400 PAVEMENT MARKINGS, TYPE L, BROKEN
11,000 LNFT $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project Name:Reconstruct and rehabilitate 75.5 miles of the Blue Ridge Parkway, 2B-2H from MP 229.6 to MP 305.1
B - 5
A0600 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
280 EACH $____________ $____________
A0610 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
280 EACH $____________ $____________
A0620 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
6 EACH $____________ $____________
A0630 63503-0300 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
200 LNFT $____________ $____________
A0640 63503-0700 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
43,000 LNFT $____________ $____________
A0650 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
5,500 SQFT $____________ $____________
A0660 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
1,000 HOUR $____________ $____________
A067…