This document contains an Infection Control Risk Assessment (ICRA) form and related materials for a federal contract opportunity to rebalance the HVAC system at a Veterans Affairs medical center.

The ICRA form provides instructions for evaluating the construction project risks and requirements for protecting patient safety. It involves recommissioning and rebalancing air handling units, VAV boxes, and ceiling grilles across the entire campus. Ancillary work includes temperature controls programming. As the project is classified as Type A and poses low patient risk, precautionary measures are limited to controlling dust and maintaining air quality during work within mechanical and service areas. The construction safety team must review and approve the completed ICRA form prior to the July 1, 2020 start date.

The related federal contract opportunity is solicitation number REBALANCE for rebalancing the HVAC system at the Center for Medicine located within Veterans Integrated Service Network 16. The purpose is to attach ninety-one documents to the solicitation. No further details are provided on response dates, pricing, or other contractual requirements.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--CFM - Rebalance HVAC System, newest first.
File Type Posted
VAV DNT 02303-2MH628.pdf PDF
P12-AMS CEP 115-7MH608.pdf PDF
S02-XHIBIT B PAST AND PRESENT PERFORMANCE QUESTIONNAIRE v2.pdf PDF
VAV DNT 02305-2MH630.pdf PDF
DNT L05 G.pdf PDF
RESEARCH 4th mech plan.pdf PDF
CEP L03.pdf PDF
P12-000110 Table of Contents 4-7-20.pdf PDF
AMS TLR 03470-6MH604.pdf PDF
013526 Safety Requirements.pdf PDF
VAV DNT 02302-2MH627.pdf PDF
OUT L08.pdf PDF
S02-EXHIBIT A PERFORMANCE RELEVANCY SURVEY v2.pdf PDF
PANAM 104.pdf PDF
03503-6EP103-M3.pdf PDF
OUT L06.pdf PDF
OUT L04.pdf PDF
OUT L03.pdf PDF
S02-EXHIBIT E SURETY FORM.pdf PDF
P15-M-2 DNT Building Existing AHU sequence.pdf PDF
AMS Research 348-8MH609.pdf PDF
P14-M-4 OP Building Existing AHU sequence.pdf PDF
P15-M-5 OP Building Existing DOAS sequence.pdf PDF
OUT L02.pdf PDF
VAV Research 352-8MH613.pdf PDF
RESEARCH 5 dixie penthouse.pdf PDF
INP L03.pdf PDF
DNT L02i F-G.pdf PDF
PANAM 101.pdf PDF
DNT L06 D.pdf PDF
P12-230593 Testing Adjusting and Balancing for HVAC 4-7-20.pdf PDF
DNT L01i F-G.pdf PDF
VAV Research 353-8MH614.pdf PDF
AMS DNT 02288-2MH613.pdf PDF
014219 Reference Standards.pdf PDF
RESEARCH 3rd mech plan.pdf PDF
AMS DNT 02289-2MH614.pdf PDF
PANAM 102.pdf PDF
INP L04.pdf PDF
S05- AMENDMENT- 0001.pdf PDF
S02-EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT v2.pdf PDF
CEP L02.pdf PDF
DNT L02i D-E.pdf PDF
AMS IP 01414-1MH604.pdf PDF
P12-VAV PANAM 0252-9MH610.pdf PDF
INP L05.pdf PDF
VAV CON -00MH602.pdf PDF
CEP L01.pdf PDF
382-8EL105-P.pdf PDF
VAV Research 351-8MH612.pdf PDF
Show all 50

Z2DA--CFM - Rebalance HVAC System has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Directions

Instructions
1. On tab 1 fill in information for Project Title or Type of Work, Project No., COTR., and Start and Completion Date.
2. Input a brief Description of work.
3. On tab 8 Give a detailed step by step description of work, and all risks/hazards associated with each step of the work, and the step being taken to reduce/ eliminate the risks/ hazards..
4. review tab 7 and determine what type of work is being done and the level of risk to patients and staff. Once the type and risk level have been determind return to tab1 and input those into the ICRA form just below the Brief Description, then take those findings and locate them on the chart just below that to determine the overall project class.
5. After determining the over all project class go to tab 2. Depending on the over all project class it will tell what precautions that need to be put into place prior to construction starting and remain in place throughout construction, and what steps that need to be done after construction is complete to ensure the work area is completely clean.
6.Review tab 3 and answer the questions Yes/No in the top chart, any yes answers will give you measures in the lower chart that need to be put into place prior to construction and remain in place throughout construction.
7. Once the form has been completed it needs to be sent to the Construction Safety Committee for review and approval. If anyone has any question about the ICRA they will contact the person submitting the form for clarification prior to approval.
8. Please try to submit ICRA's to the committee the week prior to the start date.
9. The committee will be reviewing ICRA's for all current projects and any new ICRA's that have been submitted for approval on Friday's prior to Construction Safety Rounds.
The committee consists of
Safety Management/ Construction/ GEMS Coordinator/ Industrial Hygiene- Send to VHANOL Safety Management mail group.
Facilities Management/ Project Engineering- Naclyn Lombard, Angela McKensie, Kenneth Ward
Police Services- Robert Kenyon, Connie Washington, Joshua Anderson
Infection Control- Jennifer Frisch, Deborah Lepre
Quality Management- Nana Coggin
Patient Safety- Ayesha Callaway, Randy Decuir
Contracting- Shrylin Lewis, Travis Sippel
AFGE/ NFFE Representatives- Eric Alexander, Vickie Charles
Clinical Engneering- Christopher Cain, Conner Walsh, Mariel Paciera, Jennifer Boudreaux

1-ICRA

Infection Control Risk Assessment (ICRA) Checksheet
Project Title or Type of Work:Retro Commission and Rebalance HVAC SystemProject No.629-20-106
COTR:Edwin ChinStart Date:7/1/20
Completion Date:6/30/21
Brief description of the construction or maintenance project:
Recommission and rebalance entire Campus Air Handling Units, VAV terminal boxes, ceiling grilles. Correction of temperature controls programming.
Type of construction project--choose from drop-down box (see "Types & Risk" tab):A
Patient Risk Group--choose from drop-down box (see "Types & Risk" tab):LowALowI
BMediumII
Class of Infection Control Precautions (select from grid)CHighIII
Construction Project TypeDHighestIV
Patient Risk GroupTYPE ATYPE BTYPE CTYPE DProject Class
LowIIIIIIII/IVI
MediumIIIIIIIV
HighIIIIII/IVIV
HighestIIIII/IVIII/IVIV
Other ConsiderationsComments
Air QualityWork will take place in the Mechanical Rooms and Service bays. There will not be air quaility issues.
NoiseMinimal noise. Similar to existing equipment within space.
VibrationsNone.
UtilitiesNone
Emergency proceduresCall Police at 911
SecurityContractors will be working after hours and weekends with VA personnel.
Construction Safety Assessment Team Concurrence
MemberPositionMemberPosition

Other Comments

2-ICRA2

Infection Control Risk Assessment (ICRA) Checksheet (check appropriate requirements)

Retro Commission and Rebalance HVAC System
July 1, 2020
ClassDuring Construction ProjectUpon Completion of Project
IExecute work by methods to minimize raising dust from construction operations.Immediately replace ceiling tile displaced for visual inspection.
IIProvide active means to prevent airborne dust from dispersing into atmosphere.Wipe work surfaces with disinfectant.
Water mist work surfaces to control dust while cutting.Wet mop and/or vacuum with HEPA-filtered vacuum before leaving work area.
Seal unused doors with duct tape.Remove isolation of HVAC system in areas where work is being performed.
Block off and seal air vents.Contain construction waste before transport in tightly covered containers.
Place dust mat at entrance and exit of work area.
Remove or isolate HVAC system in areas where work is being performed to prevent contamination of duct system.
IIIClass II (those checked) plus:Do not remove barriers from work area until completed project is inspected by Safety and Infection Control and thoroughly cleaned by Environmental Management.
Complete all critical barriers i.e. sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method (cart with plastic covering and sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.
Maintain negative air pressure within work site utilizing HEPA equipped air filtration units.Vacuum work area with HEPA filtered vacuums.
Cover transport receptacles or carts. Tape covering unless solid lid.Wet mop area with disinfectant.
IVClass III (those checked) plus:See other Classes.
Seal holes, pipes, conduits, and punctures appropriately.
Construct anteroom and require all personnel to pass through this room so they can be vacuumed using a HEPA vacuum cleaner before leaving work site or they can wear cloth or paper coveralls that are removed each time the worker leaves the worksite.
All personnel entering work site are required to wear shoe covers. Shoe covers must be changed each time the worker exits the work area.

3-ILSM Const

Interim Life Safety Measures (ILSM) Assessment for Construction and Maintenance
Project Title or Type of Work:Retro Commission and Rebalance HVAC System
Project No.629-20-106
Evaluate the project using the criteria below to determine which ILSM are applicable.
DeficiencyY or N?DeficiencyY or N?
Blocking off an approved exitNInstalling sprinkler system (out of service)NY
Rerouting of primary egress pathNSignificantly modifying smoke or fire barrier wallsNN
Rerouting of secondary egress pathNAdding an addition to an existing structureN
Rerouting of traffic to emergency care centerNTaking fire alarm / sprinkler system out of service >4 hoursN
Major renovation of an occupied floorNDisconnecting 4 or more alarm devices >4 hoursN
Replacing the fire alarm system (out of service)NAll / part of medical gas alarm panels out of serviceN
1Notify the fire department and initiate a fire watch.
2Post signage identifying the location of alternative exits to everyone affected.
3Inspect exits in affected areas on a daily basis.
4Provide temporary but equivalent fire alarm and detection systems for use when a fire system is impaired.
5Provide additional firefighting equipment.
6Use temporary construction partitions that are smoke-tight, or made of noncombustible or limited-combustible material that will not contribute to the development or spread of fire.
7Increase surveillance of buildings, grounds, and equipment, giving special attention to construction areas and storage, excavation, and field offices.
8Enforce storage, housekeeping, and debris-removal practices that reduce the building’s flammable and combustible fire load to the lowest feasible level.
9Provide additional training to those who work in the hospital on the use of firefighting equipment.
10Conduct one additional fire drill per shift per quarter. All areas.
11Conduct one additional fire drill per shift per quarter. Local area.
12Inspect and test temporary systems monthly.
13Conduct education to promote awareness of building deficiencies, construction hazards, and temporary measures implemented to maintain fire safety.
14Train those who work in the hospital to compensate for impaired structural or compartmental fire safety features.

4-ILSM Defic

Interim Life Safety Measures (ILSM) Assessment for Life Safety Code Deficiency
Deficiency:Retro Commission and Rebalance HVAC System
Evaluate the deficiency using the criteria below to determine which ILSM are applicable.
DeficiencyY or N?DeficiencyY or N?
Corridor door latching / gap / rating problemsNNonconforming building construction typeNY
Fire door latching / gap / rating problemsNImproperly protected vertical openingsNN
Smoke door latching / gap / rating problemsNLarge penetration in fire / smoke barriersN
Lacking a code-compliant barrierNCorridor walls do not extend to the structureN
Fire exit stairs discharge improperlyNFire protection systems* failure <4 hoursN*alarm, detection or

suppression

Excessive travel distance to approved exitNFire protection systems* failure >4 hoursN
Lacking two remote exitsNHazardous area not properly protectedN
1Notify the fire department and initiate a fire watch.
2Post signage identifying the location of alternative exits to everyone affected.
3Inspect exits in affected areas on a daily basis.
4Provide temporary but equivalent fire alarm and detection systems for use when a fire system is impaired.
5Provide additional firefighting equipment.
6Use temporary construction partitions that are smoke-tight, or made of noncombustible or limited-combustible material that will not contribute to the development or spread of fire.
7Increase surveillance of buildings, grounds, and equipment, giving special attention to construction areas and storage, excavation, and field offices.
8Enforce storage, housekeeping, and debris-removal practices that reduce the building’s flammable and combustible fire load to the lowest feasible level.
9Provide additional training to those who work in the hospital on the use of firefighting equipment.
10Conduct one additional fire drill per shift per quarter. All areas.
11Conduct one additional fire drill per shift per quarter. Local area.
12Inspect and test temporary systems monthly.
13Conduct education to promote awareness of building deficiencies, construction hazards, and temporary measures implemented to maintain fire safety.
14Train those who work in the hospital to compensate for impaired structural or compartmental fire safety features.

5-ILSM Contract ILSM Formal Contract

Project Title / Deficiency:Retro Commission and Rebalance HVAC SystemProject No.:629-20-106
COTR:Edwin ChinContractor:

Location and Description of Work:

Recommission and rebalance entire Campus Air Handling Units, VAV terminal boxes, ceiling grilles. Correction of temperature controls programming.

Date of this Formal Contract:July 1, 2020
Mandatory ILSMYesNo
1Notify the fire department and initiate a fire watch.
2Post signage identifying the location of alternative exits to everyone affected.
3Inspect exits in affected areas on a daily basis.
4Provide temporary but equivalent fire alarm and detection systems for use when a fire system is impaired.
5Provide additional fire-fighting equipment.
6Use temporary construction partitions that are smoke-tight, or made of noncombustible or limited-combustible material that will not contribute to the development or spread of fire.
7Increase surveillance of buildings, grounds, and equipment, giving special attention to construction areas and storage, excavation, and field offices.
8Enforce storage, housekeeping, and debris-removal practices that reduce the building’s flammable and combustible fire load to the lowest feasible level.
9Provide additional training to those who work in the hospital on the use of firefighting equipment.
10Conduct one additional fire drill per shift per quarter. All areas.
11Conduct one additional fire drill per shift per quarter. Local area.
12Inspect and test temporary systems monthly.
13Conduct education to promote awareness of building deficiencies, construction hazards, and temporary measures implemented to maintain fire safety.
14Train those who work in the hospital to compensate for impaired structural or compartmental fire safety features.
Staff Training
Subject(s)
(use above numbers)Names/Groups TrainedDate
Dates of Fire Drills
AreaDateTimeAreaDateTime

6-Inspection

MEDVAMC CONSTRUCTION SAFETY INSPECTION FORM

Project Title: Retro Commission and Rebalance HVAC System Project Number: 629-20-106

Inspector:Inspection Date:
Possible ILSMs from the Construction Safety AssessmentRequired?In Place?Comments
YesNo
1Notify the fire department and initiate a fire watch.
2Post signage identifying the location of alternative exits to everyone affected.
3Inspect exits in affected areas on a daily basis.
4Provide temporary but equivalent fire alarm and detection systems for use when a fire system is impaired.
5Provide additional firefighting equipment.
6Use temporary construction partitions that are smoke-tight, or made of noncombustible or limited-combustible material that will not contribute to the development or spread of fire.
7Increase surveillance of buildings, grounds, and equipment, giving special attention to construction areas and storage, excavation, and field offices.
8Enforce storage, housekeeping, and debris-removal practices that reduce the building’s flammable and combustible fire load to the lowest feasible level.
9Provide additional training to those who work in the hospital on the use of firefighting equipment.
10Conduct one additional fire drill per shift per quarter. All areas.
11Conduct one additional fire drill per shift per quarter. Local area.
12Inspect and test temporary systems monthly.
13Conduct education to promote awareness of building deficiencies, construction hazards, and temporary measures implemented to maintain fire safety.
14Train those who work in the hospital to compensate for impaired structural or compartmental fire safety features.
Other Construction Issues
YNN/AYNN/AComments
Construction area warning sign posted?Adequate lighting provided in all work areas?
All construction doors (including interstitial) closed and locked?Hand held and mounted equipment properly guarded?
Evidence of dust and debris tracked to outside of barrier?Aisles and passageways in good repair, kept clear and properly marked?
Mat/carpet at entrance?Egress to and from work site unobstructed?
Floor, wall, ceiling penetrations sealed properly?Fire extinguisher on site?
Ladders in good condition?
Hot Work or Confined Space Permits posted?MSDS available on site?
Area free of insects and rodents?Gas cylinders secured?
Area under negative pressure?Evidence of smoking?
Ventilation system adequately removes toxic dust and gases from work environment?Electrical power cords in good condition?
Workers wearing or have available appropriate PPE?Guardrails and toe boards provided for scaffolding that is open at all sides?
Safety harnesses being worn for work >6’ off the ground?Additional Comments:

7-Types & Risk TYPE A Inspection and Non-Invasive Activities Includes, but is not limited to:

Removal of ceiling tiles for visual inspection limited to 1 tile per 50 square feet Painting (but not sanding) Wall covering, electrical trim work, minor plumbing, and activities which do not generate dust or require cutting of walls or access to ceilings other than for visual inspection.

TYPE B Small scale, short duration activities which create minimal dust Includes, but is not limited to:

Installation of telephone and computer cabling Access to chase spaces Cutting of walls or ceiling where dust migration can be controlled TYPE C Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies Includes, but is not limited to:

Sanding of walls for painting or wall covering Removal of floor coverings, ceiling tiles and casework New wall construction Minor duct work or electrical work above ceilings Major cabling activities Any activity which cannot be completed within single work shift TYPE D Major demolition and construction projects Includes, but is not limited to:

Activities which require consecutive work shifts Requires heavy demolition or removal of complete cabling systems New Construction

Low RiskMedium RiskHigh RiskHighest Risk
Office areas

Medical records Non-patient care areas Cafeteria Cardiology clinic Echocardiography Endoscopy Nuclear Medicine Physical Therapy Radiology/MRI Respiratory Therapy CCU Emergency Room Laboratories (specimen) Admissions Outpatient Surgery Pharmacy Post Anesthesia Care Unit (PACU) Surgical Units Any area caring for immunocompromised patients Cardiac Cath Lab

SPS

Intensive Care Units Medical Units Negative pressure isolation rooms Oncology Operating rooms Invasive procedure rooms

8-Detailed Description of Work

Detailed Description of Work
Majority of new work wil be done in Mechanical Rooms and service bays.
TAB firm will be in hospital floor spaces after hours to measure ceiling grille air volumes and above ceiling work.
Temperature controls programming work.
Recommission and verification of entrie Campus Air Handling Units.