010000 General Requirements.pdf

PDF 203 KB Posted

Attached to
Z2DA--CFM - Rebalance HVAC System Federal contract opportunity
Solicitation number
Not on record
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16

About this file

This document outlines general requirements for a federal construction contract to rebalance the HVAC system at a Department of Veterans Affairs medical facility. Key specifications include developing a project safety plan, securing the construction site, controlling access to sensitive documents, and implementing motor vehicle restrictions. Warranty requirements encompass creating a management plan, conducting inspections, and maintaining a performance bond throughout construction and during the one-year overall warranty period. The contractor must also participate in a pre-warranty conference to establish communication procedures for addressing issues once the project is complete.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--CFM - Rebalance HVAC System, newest first.
File Type Posted
OUT L08.pdf PDF
S02-EXHIBIT A PERFORMANCE RELEVANCY SURVEY v2.pdf PDF
PANAM 104.pdf PDF
03503-6EP103-M3.pdf PDF
OUT L06.pdf PDF
OUT L04.pdf PDF
OUT L03.pdf PDF
S02-EXHIBIT E SURETY FORM.pdf PDF
P15-M-2 DNT Building Existing AHU sequence.pdf PDF
AMS Research 348-8MH609.pdf PDF
P14-M-4 OP Building Existing AHU sequence.pdf PDF
P15-M-5 OP Building Existing DOAS sequence.pdf PDF
OUT L02.pdf PDF
VAV Research 352-8MH613.pdf PDF
RESEARCH 5 dixie penthouse.pdf PDF
INP L03.pdf PDF
DNT L02i F-G.pdf PDF
VAV DNT 02303-2MH628.pdf PDF
P12-AMS CEP 115-7MH608.pdf PDF
S02-XHIBIT B PAST AND PRESENT PERFORMANCE QUESTIONNAIRE v2.pdf PDF
VAV DNT 02305-2MH630.pdf PDF
DNT L05 G.pdf PDF
RESEARCH 4th mech plan.pdf PDF
CEP L03.pdf PDF
P12-000110 Table of Contents 4-7-20.pdf PDF
AMS TLR 03470-6MH604.pdf PDF
ICRA ILSM for CFM - Rebalance HVAC System.xlsx XLSX spreadsheet
013526 Safety Requirements.pdf PDF
VAV DNT 02302-2MH627.pdf PDF
PANAM 101.pdf PDF
DNT L06 D.pdf PDF
P12-230593 Testing Adjusting and Balancing for HVAC 4-7-20.pdf PDF
DNT L01i F-G.pdf PDF
VAV Research 353-8MH614.pdf PDF
AMS DNT 02288-2MH613.pdf PDF
014219 Reference Standards.pdf PDF
RESEARCH 3rd mech plan.pdf PDF
AMS DNT 02289-2MH614.pdf PDF
PANAM 102.pdf PDF
INP L04.pdf PDF
S05- AMENDMENT- 0001.pdf PDF
S02-EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT v2.pdf PDF
CEP L02.pdf PDF
DNT L02i D-E.pdf PDF
AMS IP 01414-1MH604.pdf PDF
P12-VAV PANAM 0252-9MH610.pdf PDF
INP L05.pdf PDF
VAV CON -00MH602.pdf PDF
CEP L01.pdf PDF
382-8EL105-P.pdf PDF
Show all 50

Z2DA--CFM - Rebalance HVAC System has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

12-01-18

01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for safety control requirements.

1.2 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security escort arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the

01 00 00 -2 approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting

Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

D. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

01 00 00 -3

2. A limited number of (2 to 5) permits shall be issued for General

Contractor and its employees for parking in designated areas only.

1.3 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

1.4 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by the

COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

1.5 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a

01 00 00 -4 binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer.

Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to continue the warranty in force.

j. Cross-reference to specific pertinent Operation and Maintenance manuals.

01 00 00 -5

k. Organizations, names and phone numbers of persons to call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

4. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

B. Performance Bond: The Performance Bond must remain effective throughout the construction period.

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for

Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for

Contractor response, and other details deemed necessary by the

Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and

01 00 00 -6 pursue construction warranty work action on behalf of the Contractor.

This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.

1.6 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract.

- - - E N D - - -