About this file

This Contract Data Requirements List (CDRL) outlines reporting requirements for the Research and Development Integrated Space Experiments (RISE) contract. Task orders over $20 million will require a Progress Curve Report submitted within 17 working days of the first full month after award, with interim reports due every 12 months and a final report due 60 days after 95% of costs are incurred. Reports shall be marked and distributed according to the instructions, and contractor formats are acceptable if submitted via encrypted email.

The related federal contract opportunity notice announces an industry day on August 18, 2017 to provide information on the upcoming RISE acquisition and allow feedback on draft documents. Attendees are limited to two people per company and must complete visit and pass requests by August 4. Questions on requirements documents are due by August 23. The RISE contract will support research at the Air Force Research Laboratory Space Vehicles Directorate through the issuance of multiple task orders.

CDRL

View the file

Other files for this federal contract opportunity

Other files attached to Research and Development Integrated Space Experiments (RISE), newest first.
File Type Posted
Government_Response_to_Industry_Comments_-_DRFP.xlsx XLSX spreadsheet
RISE_Questions_and_Answers_Final.pdf PDF
KAFB_Visitor_Pass_Form_18_August_17.pdf PDF
Map_-_KAFB_West_Side.pdf PDF
CDRL 3 v1.pdf PDF
CDRL 20 v1.pdf PDF
RISE_TO_0002_SSP.pdf PDF
DD254_RISE_20170724.pdf PDF
Kirtland_AFB_Visitor_Pass_Request_-_Attach_2.pdf PDF
CDRL 4 v1.pdf PDF
RISE_TO_0004_NTS3.pdf PDF
CDRL 17 v2.pdf PDF
CDRL 9 v2.pdf PDF
CDRL 18 v2.pdf PDF
RISE_TO_0005_AGT.pdf PDF
CDRL 21 v1.pdf PDF
CDRL 15 v1.pdf PDF
RISE_TO_0003_UNP.pdf PDF
CDRL 16 v1.pdf PDF
CDRL 7 v1.pdf PDF
CDRL 14 v1.pdf PDF
CDRL 2 v2.pdf PDF
CDRL 8 v1.pdf PDF
CDRL 5 v1.pdf PDF
CDRL 19 v2.pdf PDF
CDRL 12 v1.pdf PDF
CDRL 11 v1.pdf PDF
RISE_Basic_SOW_v3.pdf PDF
CDRL 1 v1.pdf PDF
AFRL_VISIT_REQUEST_JAN_2016_-_Attach_1.pdf PDF
RISE_TO_0001_AIT.pdf PDF
CDRL 10 v1.pdf PDF
Map_-_KAFB_West_Side.pdf PDF
CDRL 6 v1.pdf PDF
Show all 34

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit A: FA9453-11-R-0285

CONTRACT DATA REQUIREMENTS LIST (1 Data Item) Form Approval OMB No. 0704-0188 Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.: 0002

B. EXHIBIT....................................:

C. CATEGORY..............................: OTHER IDIQ Contract

D. SYSTEM/ITEM........: R&D Integrated Space Experiments (RISE) E.

CONTRACT/PR NO.:

F. CONTRACTOR.........:

1. DATA ITEM NO........................: A013

2. TITLE OF DATA ITEM............: Progress Curve Report

3. SUBTITLE..................................: DD Form 1921-2

4. AUTHORITY.............................: DI-FNCL-81567C

5. CONTRACT REFERENCE......: Task Order Specific

6. REQUIRING OFFICE..............: AFRL/RVE

7. DD250 REQ................................: LT

8. APP CODE.................................: No

9. DIST. STATEMENT REQUIRED......: (See 16)

10. FREQUENCY......................................: (See 16)

11. AS OF DATE........................................: (See 16)

12. DATE OF FIRST SUBMISSION: (See Block 16)

13. DATE OF SUBSEQUENT SUBM.: (See Block 16)

14. DISTRIBUTION

A. ADDRESSEES

B. COPIES

Refer to Block 16 and Task Orders of the RISE contract for additional distribution instructions. Instructions vary per Task Order and provide additional guidance in regard to the requirements for Blocks 14A and 14B of this

CDRL

DRAFT FINAL

AFRL/RVKI LT

AFRLRVE COR/ 1

15. TOTAL: 1

16. REMARKS

Blk 4: Initial reports are submitted at the discretion of the task order manager.

Blk 9: All documentation shall be marked IAW DoDD 5230.24 with the following distribution statement: “DISTRIBUTION STATEMENT E. Distribution authorized to DoD Components only; Critical Technology and Contractor Performance Evaluation, 2Aug11. Other requests for this document shall be referred to the Air Force Research Laboratory/ RVK, RISE Contracting Officer Representative (COR), 3550 Aberdeen Ave SE, Kirtland AFB, NM 87117-5776.” EXPORT CONTROL WARNING: All technical data shall be marked as follows: “WARNING — This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C. Sec. 2751, et seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C. App 2401 et seq. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25.”

Blk 10-13: If required, the initial report is submitted within 17 working days after completion of the first full month following contract award of the task order.

An Interim Report is any report other than the Initial Report that is prepared before submission of the Final Report. The first Interim Report is required only after contract definitization. The as-of date for the first Interim Report is the last day of the 12th month following contract award, or the last day of the third month following contract definitization, whichever is later. The due date is 60 days following the as-of date. A Final Report is required as of the last day of the month when 95% or more of total contract costs have been incurred. The final due date is 60 days following this as-of date.

Contractor formats are acceptable and can be submitted via DoD encrypted email via the Kirtland AFB local area network.

This CDRL applies to Task Orders over $20M.

17. PRICE GROUP: 18. ESTIMATED TOTAL PRICE :

G. PREPARED BY: Stephen L. Lucero, AFRL/RVEI I. APPROVED BY: K. Kinifick

H. DATE: 18 Jan 2017 J. DATE:

DD Form 1423-1, SEP 97 (EG) (Computer Generated) PREVIOUS EDITIONS ARE OBSOLETE Page 1 of 1 Pages