Questions_Answers_FPS3_RFP_10_Jan_2014.docx
DOCX document 44 KB Posted
- Attached to
- FPS3 SolicitationFA8730-14-R-0004 Federal contract opportunity
- Solicitation number
- FA8730-14-R-0004
About this file
Questions Answers
View the file
Other files for this federal contract opportunity
Show all 40
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFIED
Questions and Answers FPS3 RFP
| # |
| Artifact |
| Pg |
| Para |
| Question |
| Government Response |
| 1 |
| Attachment 8 |
Section L Sample Problem #1
| For sample problem 1, where is the BDOC located? Para 2.1.2.b indicates it is 1200 meters from ECP1. Building 135 is considerably less than this distance and no other facilities are indicated on the provided drawing. |
| The BDOC is not depicted on the drawing, but is in the indicated position in Section L paragraph 2.1.2.b. Building 135 is not the BDOC. |
| 2 |
| Attachment 8 |
Section L Sample Problem #1; Table 4-5
| The approved equipment list for sample problem 1 has items indicated which the vendors indicate are no longer available (obsolete). Recommended replacements (whether approved or not) are not on the approved item list. For the purposes of the sample problem, shall we/may we use the items identified on the approved equipment list regardless of availability? |
| The FPS3 Fixed Site Approved Equipment List has been updated. The changes are detailed below: |
The following items have been removed:
- Vivotek Version-Fixed
- Short Range Thermal Imager; Fixed/Mounted (SRTI F/M) Version Fixed Mounted
- DiOP Thermal Imager Version PTZ Complete 180/60mm
- P&L E-Communications, Video Motion Detection (VMD) Version AVT234
- SightLogix Enterprise VMD Version SightSensor Video Motion Detection (VMD)
The following items have been updated to include additional information (new language is underlined):
- Advantor Annunciator Advantor Integrated Command, Control, and Access Control Version 4.0; Version 5.0; Version 5.0 (SP 6)
- Vindicator Annunciator Vindicator Command and Control (VCC) with Access Control System Version 2.40; Version 2.43; V5 - Version 5.0; V5 - Version 6.0; V5 – Version 6.5 (SP11)
- Video Management System (VMS)/Broadware 5.1.1(Approved with Predator Elite only)
- General Dynamics - LRTI with CCTV – PTZ Thermal Imager (GD-GIT VZ-250 Thermal Camera System/CCTV )
- FLIR T-2000 LRTI w/CCTV Version-PTZ Thermal Imager
- FLIR Wide-Area Surveillance Thermal Imager (WSTI) - Sentry II Version- PTZ Thermal Imager Protech PIRAMID Version SDI-77XL2-EX (Explosion Proof)
- General Electric Sentrol, BMS Version Model 2807T BMS (Explosion Proof)
- Banner Engineering Series Active Infrared (AIR) Sensor Version SMI30 (Intrinsically Safe)
- Visonic & Xtralis PIR Combination: Version Visonic CH 1000 PIR & Version Xtalis ADPRO 18 WH PIR
- DeTekion Vertical Taut Wire Sensor, (VTWS) Version VTW-400 (Full Fence & Outrigger configuration)
- FLIR/ICx PSRS STS-350 Ground Based Radar, Wide Area Detection/Approach Zone Sensors (WAD/AZS) Version ICX application software version 2.4.41.12 (350 meters)
- FLIR/ICx STS-1400 Ground Based Radar, WAD/AZS Version ICX application
The following items have been added:
- Bosch Allegiant Matrix/Control System, LTC 8600 & 8800 Series
- Bosch Auto Dome 600 Series Analog, PTZ (Version VG5-6xx-xxxx)
- Protech PIRAMID Version SDI-76M-HS1-H
- Inertia-Guard Fence Sensor – Version IG Fence Sensor
Obsolete items that cannot be procured should not be proposed by offerors.
| 3 |
| Attachment 8 |
Section L Sample Problem #1; Table 4-4
| Requirement entries paragraph numbers in Table 4-4 do not match paragraph numbers in the RFP. Will a correct table be provided, or is RFP response meant to correct this table to reflect current RFP? (Para 4.4.1). |
| The Government understands that the paragraphs listed in the sample Test Verification Matrix (Table 4-4) do not match the Sample Problem requirements. Offerors should update the sample Test Verification Matrix from Table 4-4 with the requirements from the Sample Problems as part of their proposal. |
| 4 |
| Attachment 8 |
Section L Sample Problem #1; Table 4-4
| Should the Requirement Entries in Table 4-4 which correspond to references driven by approved equipment list be marked as “not applicable” (N/A)? The same question applies to Probability of Detection (para 4.2.1.2) which has notes stipulating conditions as responsibility of Government Test representatives. |
| These items may be marked as N/A. |
| 5 |
| Attachment 8 |
Section L Sample Problem #1; Table 4-4
| Should the numbering in the ‘Requirement’ column of Table 4-4 align with paragraph numbering in section 4.2? For example, table 4-4 indicates 4.2.4 as ‘Self Test’ while paragraph 4.2.4 (Attachment 8, Page 41) is titled ‘Command Control and Display Equipment’ and ‘Self Test’ requirements are addressed in paragraph 4.2.6. |
| Yes. Offerors should update the sample Test Verification Matrix from Table 4-4 with the requirements from Sample Problems as part of their proposal. |
| 6 |
| Attachment 8 |
Section L Sample Task #1 and Sample Task #2; Tables 4-5, and 4-6 53-57
| If a specified approved equipment requires non-listed equipment to function in its intended manner, does non-specified support equipment inherit acceptance? |
| If ancillary items are required they may be proposed. IDS items not listed on the solicitation’s approved equipment list should be proposed. |
| 7 |
| Sample Task #1 |
| Can we cut the pavement inside the Restricted Area, i.e. trench and replace in kind? |
| The solicitation does not restrict offerors from cutting, trenching, and replacing pavement. |
| 8 |
| Sample Task #1 |
| Is there an area available for equipment and materials laydown and staging? |
| Yes. This assumption has been added to Section L, Attachment L-2, Table 2-1 |
| 9 |
| Sample Task #1 |
| Is there government provided office space for the Construction Team? If not is there an area for a trailer? |
| Government provided office space will not be provided. However, space is available for a trailer. Offerors should assume that power and internet connectivity is available and will be provided. This information has been included in Section L, Attachment L-2 para 2.2.1.l. |
| 10 |
| Sample Task #2 |
| Is the area within the inner perimeter paved? |
| The area depicted as grey is steel reinforced concrete. This information has been added to Section L, Attachment L-8, Table 3-1. |
| 11 |
| Sample Task #2 |
| Can we cut the pavement inside the Restricted Area, i.e. trench and replace in kind? |
| The solicitation does not restrict offerors from cutting, trenching, and replacing pavement. |
| 12 |
| Attachment 8 Sample Problem #1 |
| 44 |
| 4.2.7.d |
| Can there be simultaneous (more than one intruder) events at the RA? |
| Yes. |
| 13 |
| Attachment 8 |
Sample Task #2
| Is internet service provided by USG for Construction Mgmt team? |
| For Sample Problem #2, offerors should assume that internet access will be provided by the Government. This information has been added to Section L, Attachment L-8, Table 3-1. |
| 14 |
| Attachment 8 |
| Is major medical (danger to life or limb) provided by USAF? |
| Emergency medical treatment will be provided in the AOR IAW 5152.225-5902 FITNESS FOR DUTY AND MEDICAL/DENTAL CARE LIMITATIONS (DEC 2011) |
| 15 |
| Attachment 8 |
| Is on-site transportation provided for construction personnel? Any vehicles available for use? |
| The offeror should assume that any required vehicles and specialized vehicles (i.e., forklifts, JLG lifts, etc) will be provided on-site by the government. Fueling of these vehicles and of any proposed generators will be furnished by the Government. This information has been added to Section L, Attachment L-8, Table 3-1. |
| 16 |
| Attachment 8 |
| Is fuel for vehicles and equipment provided by US Government? |
| Offerors should assume that fuel for vehicles and fueling for generators will be provided by the Government. |
| 17 |
| Attachment 8 Sample Problem #1 |
| 41 |
| 4.2.1.1.2 |
| Is the hanger considered the resource? Does penetration detection of the RA constitute ‘before reaching the resource’? |
| In the context of this paragraph, the resource would be an aircraft within the hangar. This requirement applies specifically to the interior IDS, so detection at the RA boundary does not apply. |
| 18 |
| Attachment 8 Sample Problem #1 |
| 44 |
| 4.2.9 |
| What are the archival storage requirements for video? |
| The VMS shall be equipped with a storage capacity to accommodate no less than 48 hours of video storage. This information has been added to Section L, Attachment L-2 as a new paragraph 4.2.9.l. |
| 19 |
| Attachment 8 |
| Will the US Government provide shipping container(s), packing and shipping materials for GFE at debarkation point? |
| The shipping containers listed in the Sample Problem #2 Equipment list will be provided as GFE for shipping. Offerors should assume that packing and shipping materials associated with these containers will be provided by the Government. |
| 20 |
| Attachment 8 |
Section L Table 2-1
| Do the turnstiles currently have biometrics or other security devices (PIN Pads) installed already, or will we have to provide additional access controls for these ECPs? |
| No. The turnstiles do not currently have biometrics, PIN Pads, or other security devices installed. Offerors must propose all equipment to meet the solicitation requirements. |
| 21 |
| Attachment 8 |
Section L Table 2-1
| Are there existing spare conduits running from Hanger 1 to Hanger 2? |
| Per Section L, Attachment L-2 Table 2-1, (Hangar #2 Interior and Exterior), there is existing empty communication conveyance space (conduit) available between Hangar 1 and Hangar 2. |
| 22 |
| Attachment 8, Sample Problem 1, Drawing |
| Can we tap into existing airfield pole lighting for power feeds to equipment around the perimeter of the parking apron? |
| No. Offerors may not tap into existing lighting for power feeds. |
| 23 |
| Exhibit B FPS3 B Tables T&M Rates |
| Table asks for Contractor Fiscal Year and starts with FY15. Assuming a start date in 2014, if the contractor’s FY is the calendar year, assume we add a column for FY14 to cover the initial period. Please confirm. |
| Section L para 6.2.2, 6.3.5.2 and 7.1.10 have been updated to indicate that all T&M labor rates shall be based on Government Fiscal Year. Exhibit B template has also been updated. |
Paragraph 6.2.2 now reads as follows, “Proposals for T&M labor rates shall be based on the Government fiscal year (GFY). Assume for pricing purposes a Period of Performance commencing 1 October 2014 for the T&M tables and the sample problems.”
| 24 |
| Attachment 8 Section L |
| 14, 15 |
| 4.4.2, 4.5.2 |
| Requirement in Section L: The plan and procedures shall also include a description of proposed test procedures that will verify the functionality of proposed subsystems, and shall include a proposed test verification matrix in the format described in Attachment L-2, Table 4.3. |
Can the test verification matrix be included as an attachment to the basic response to the sample problem?
To clarify, Table 4-4 is the test verification matrix. Section L has been updated to include the Test Verification Matrix as an attachment to each of the Sample Problems. This attachment does not have a page limit.
| 25 |
| Attachment 8 Section L |
| 27 |
| 7.1.10 |
| Requirement in Section L: Veteran Owned Small Business is a listed small business category however VOSB is not listed in Table 7-1. |
Is there a separate work percentage for VOSB or is it included in the overall small business goal?
“Veteran-owned small business” was removed from para 7.1.10 attachment 4 instructions since there is not a separate work percentage for VOSB.
| 26 |
| Industry_Update_Q&A Cover_Letter_20_Dec_2013 |
| 1 |
| 3 & 2 |
| The Government indicated that Amendment 1 is forthcoming and will implement the changes identified in the questions and answers. The Government also instructed industry to submit Final RFP questions NLT 5:00PM (ET) on 6 Jan 14 to give the Government sufficient time to respond before the proposal due date. |
The Government has not released Amendment 1. There may be additional amendments resulting from questions due on 6 Jan 14. The contractor is required to incorporate requirements from all amendments into the proposal. To enable the prime and the primes subcontractors to be responsive to all Government requirements, would the Government extend the proposal due date to 24 Jan 14.
The Government anticipates releasing Amendment 1 on or about 13 January 2014. The Government anticipates extending the deadline for proposal submission to 31 January 2014.
| 27 |
| Questions_Answers_FPS3_RFP_20_Dec_2013 |
| 7 |
| Q. 26 |
| In Q&A 26, the Government directed contractors to use Contractor Fiscal Year (CFY) in tabs 5, 7 & 9 of Attachment 8 (L-7) – FPS3 Cost Formats. However, the RFP (Section L, page 19) says to use 1 October 2014 as a start date for sample problem pricing purposes and this requirement is consistent with Government Fiscal Year (GFY). |
Should contractors still price the 2 sample problems based on Government Fiscal Year starting from 1 October 2014 without identifying Contracting Fiscal Year (CFY) in the Attachment 8 Cost Formats? Our fiscal year runs on the calendar year, so pricing with Contractor Fiscal Year (CFY) may cause potential confusion.
The 1 Oct 14 is the given start date for the Sample Problems and was not selected for the purpose of starting the Government Fiscal Year.
Tabs 5, 7 & 9 of the Cost Formats (Section L para 6.3.5.5, 6.3.5.7 and 6.3.5.9) shall use Contractor Fiscal Year (CFY). Offerors shall identify their FY.
Section L para 6.2.2, 6.3.5.2 and 7.1.10 have been updated to indicate that all T&M labor rates shall be based on Government Fiscal Year. Exhibit B template has also been updated.
Paragraph 6.2.2 now reads as follows, “Proposals for T&M labor rates shall be based on the Government fiscal year (GFY). Assume for pricing purposes a Period of Performance commencing 1 October 2014 for the T&M tables and the sample problems.”
| 28 |
| Attachment L-1 |
| 30 |
| Solicitation Cross Reference Matrix |
para M002, para c.1
| Please confirm that the references to Table 4.3 and Table 4.4 should be Table 4-3 and Table 4-4. |
| This is correct. All table references have been changed to reflect the “X-Y” numbering convention. |
| 29 |
| Attachment L-1 |
| 30 |
| Solicitation Cross Reference Matrix |
para M002, para c.1
| Please clarify the reference to “including Table 4.3 and Table 4.4 2, 4, 4.1, 4.2”. The references to “2”, “4”, and “4.1” are not clear since there are no tables numbered in this fashion. |
| All table references in this section have been changed to reflect the “X-Y” numbering convention and extraneous paragraph references removed. |
| 30 |
| Attachment L-1 |
| 30 |
| Solicitation Cross Reference Matrix |
para M002, para c.2
| Please clarify the reference to Para 3-3.2.5. The paragraph could not be located in the solicitation. |
| This refers to paragraphs 3 through 3.2.5. This refers to paragraphs 3 through 3.2.5. A space has been added to assist with legibility. |
| 31 |
| Attachment L-1 |
| 30 |
| Solicitation Cross Reference Matrix |
para M002, para c.2
| Please clarify the reference to Para 4.3-4.3.4.5. The paragraph could not be located in the solicitation. |
| This refers to paragraphs 4.3 through 4.3.4.5. A space has been added to assist with legibility. |
| 32 |
| Attachment L-2 |
| 34 |
| Section 2.2.1 General Assumptions for Fixed Site Sample Problem # 1 |
| 2.2.1 c. States that the period of performance will begin on 1 October 2014. The pricing formats allow information for 3 contractor years of pricing information. |
Is it the intent to limit the POP for the entire project to a maximum of 27 months (15 months for design, install, test, and acceptance followed by a 12 month ICS)?
If not, will the Government provide an update to its pricing formats to include presentation of pricing information beyond the third contractor year?
Per Section L para 6.3.5, offerors may make adjustments to the cost model if needed.
| 33 |
| Attachment 8, Section L |
| 13 |
| 4.4 |
| In order to fully address the requirements specified for Sample Problem #1 (to include the multiple subsystems and complexity of the required IDS System), in-depth explanations are required throughout Volume II, Section 4.4. Would the Government consider increasing the page limit for Section 4.4 an additional five (5) pages to a total of twenty (20) pages? |
| The Government will not increase the page limits specified. However, the Government has moved the Quality Control Checklist and the Test Verification Matrices from the page-limited portion of the proposal to the attachments section (no page limit). |
| 34 |
| Section I |
| 37 |
Topic: Wage Determinations, 52.222-06 Davis-Bacon Act (JUL 2005) Question: The RFP contains the Davis Bacon Act, but does not include any Wage Determinations or instructions for what to price, nor do the labor categories contain any indication if any of them pertain to Davis Bacon (although they appear not to be Davis Bacon categories). Is it the Government’s intention to indicate only at the task level whether Davis Bacon specifically applies and provide the appropriate Wage Determination at that time?
Recommendation: Please clarify.
Correct. Davis Bacon applicability and appropriate determinations will be made at the delivery order level.
| 35. |
| Section I and Section K |
RFP Reference: Section I – Contract Clauses; Section K 52.222-52 Topic: Service Contract Act Question: The RFP does not include the Service Contract Act, but Section K contains 52.222-52. Is it the Government’s intention to exclude SCA?
Recommendation: Please clarify.
Clause 52.222-41 Service Contract Act has been added to Section I.
| 36. |
| Attachment 5 |
Topic: T&M Labor rates Question: Please confirm that the RFP labor categories and the associated rates to be proposed pertain to Time and Materials CLINs only, and are not to be used for pricing of tasks of any other type.
Recommendation: Please clarify.
Correct. The T&M Labor Categories and Labor Rates are to be used for T&M CLINs only. Offerors may propose the labor mix and rates for non T&M work as part of the proposal.
| 37. |
| Attachment 8, Section L |
| 6.2.2 |
| Topic: Contract Start Date |
Question: RFP Section L 6.2.2 states that offerors should assume a start date of October 2014, but the Exhibit B tables indicate Year 1 as 2015. Can the Government please confirm the start date of October 2014, and revise the Exhibit B tables accordingly?
Recommendation: Please clarify.
Paragraph 6.2.2 now reads as follows, “Proposals for T&M labor rates shall be based on the Government fiscal year (GFY). Assume for pricing purposes a Period of Performance commencing 1 October 2014 for the T&M tables and the sample problems.”
Section L para 6.2.2, 6.3.5.2 and 7.1.10 have been updated to indicate that all T&M labor rates shall be based on Government Fiscal Year. Exhibit B template has also been updated.
| 38. |
| Part I - The Schedule; Section B - Supplies Or Services And Prices/Costs |
Topic: Exhibit B Pricing of CLINS Question: Please confirm that the offeror is not expected to complete Section B of the model contract in its proposal response.
Recommendation: Please clarify.
Please complete Section B with the amounts for CLIN 0001 Post Award Conference only ($5,000).Section L para 7.1.2 has been updated to clarify this.
| 39. |
| Attachment 8, Section L |
| 24 |
Topic: Exhibit B - CLINS Question: Various CLINS in Section B identify fee as TBD. Is it the Government’s intent that the successful contractor submitting a task proposal will propose its fee and fee percentage at that time?
Recommendation: Please clarify.
Correct. Fees would be determined at the delivery order level, as applicable.
| 40. |
| RFP Section A through I and other Attachments |
Topic: TDB (To Be Determined) Question: Throughout the RFP, the term TBD is referenced in various “fill-in” sections. It is our assumption that these TBD fill-ins will be completed at contract award and/or at the Task Order/Delivery Order level. Is this correct?
Recommendation: Please clarify That is correct.
| 41. |
| Cost Model GFE List; Section L Sample Problem 2 Approved Equipment List |
Topic: Discrepancy of Approved Equipment Lists Question: There are discrepancies between the Sample Problem 2 Section L Approved Equipment List requirements and the Government’s cost model GFE list. Additionally the cost model GFE list does not include SCD/part numbers that clearly define the equipment/configuration. This prohibits Offerors from accurately pricing a solution according to the requirements for CLIN 0006AB. Will the government clarify the inconsistencies?
Recommendation: Revise the Cost Model to match Section L.
The GFE Summary tab of the Cost Formats has been updated to match the exact item descriptions, order in which items are listed, and SCD # specified in the Sample Problem #2 Equipment List.
| 42. |
| Attachment 1, SOW |
| 4.2.6.4 |
| Operations Security (OPSEC): OPSEC guidelines are required in an effort to reduce a program’s vulnerability to an adversary’s collection and exploitation of critical information. The Contractor shall apply OPSEC IAW AFI 10-701, Operations Security. The Government will provide the Contractor with a copy of the Critical Information List (CIL) as part of solicitations for FPS3 orders. |
Question: Does the Government have its own OPSEC plan and program? Is the OPSEC manager going to be the contractor or the Government?
The government has its own OPSEC program in place. More detailed OPSEC information and requirements for the contractor will be provided in the solicitations for future orders.
| 43 |
| Attachment 8, Section L |
| The offeror respectfully requests that the Government permit a summary quality assurance checklist within the Sample Task 1 page constraints and the addition of a full quality assurance checklist as an attachment and outside of page count. |
| Section L has been updated to include the Quality Control Checklists as an attachment to Sample Problem #1. This attachment does not have a page limit. |
| 44. |
| Attachment 8, Section L |
| Table 4-6 |
| Table 4-6 of Section L of the RFP includes Diesel Generator (5.0 KVA to 7.5 KVA) with extended fuel tanks and desert kits. Tab 4. GFE Summary of the Cost Formats do not include that item. How are we to price this GFE? |
This description is provided to inform the basic requirements for the proposed generator; this item should be selected, priced, and proposed by the offeror and will not be available as GFE. A note has been added to this item description in Section L, Attachment L-2 Table 4-6 to reflect this.
| 45. |
| Attachment 8, Section L |
What is the “resource code” that is referred to in Attachment 8 of the Cost Formats Excel document? “Each line item, shall identify the applicable source (i.e. prime, division, or subcontractor), applicable CLIN, resource code, WBS, and the basis of estimate…”
The resource code is a code associated with each separate element of cost. For example, a Senior Engineer at Company X that works at location Z may be coded SE1W. The resource code is an internal code unique to each individual offeror. If an offeror does not utilize resource codes, the offeror is not required to create one.
| 46. |
| Attachment 8, Section L |
Are we restricted to the 100 meter or less sector distance for Problem #2?
The Government believes the question refers to Section L, Attachment L-2 para 4.2.3, which states that for the Fixed Site Sample Problem the sensor detection/alarm section shall be configured not to exceed 100-meter intervals. There is no such requirement for the Tactical Site Sample Problem.