WWYK200051_SWITCHGEAR_IFC_DRAWINGS.pdf

PDF 3 MB Posted

Attached to
TINKER AFB MAC BOA WWYK200051 Replace Switchgear, Bldg 1
Solicitation number
FA813726R0025
Issued by

About this file

This is a construction document set for a federal contract to replace switchgear in Building 1 at Tinker Air Force Base, Oklahoma, issued by the Air Force Materiel Command's 72nd Air Base Wing Civil Engineer Directorate. The project (WWYK200051) involves demolishing existing electrical distribution infrastructure and installing new 480V and 208V switchgear equipment with associated structural, electrical, and life safety improvements.

The scope of work requires removal of existing 480V and 208V unit substations, associated electrical devices, power meters, and grounding systems, with conductors and conduits retained for reuse where applicable. New work includes installation of a 480V switchgear enclosure (2500A, 480Y/277V, 3-phase, NEMA 3RX, 65KAIC rating), a 500KVA step-down transformer (480V-208Y/120V), a 208V switchgear enclosure (1600A, 208Y/120V, NEMA 3RX, 65KAIC rating), two 600A replacement panelboards with new circuit breakers, remote operational breaker enclosures, grounding systems, and conduit routing both underground and overhead along the building exterior. The contractor is responsible for phased demolition and installation work coordinated with OG&E utility and facility operations to minimize production impact, field verification of existing conditions against as-builts, special inspections per IBC requirements, fire stopping at penetrations, and comprehensive testing to restore all existing loads to original operation. The project location is in the electrical closet, elevator room, and dock areas within the 1,130 square-foot equipment/mechanical space, with an occupant load of three persons and required compliance with UFC and NFPA standards.

View the file

Other files

File Type Posted
Solicitation Amendment FA813726R00250005 SF 30.pdf PDF
WWYK160073 REPAIR FIRE RISER AS-RECORDED 3.18.24.pdf PDF
Att1_200051_SWITCHGEAR_IFC_REV_1_6-17-26_DRAWINGS.pdf PDF
Att2_200051_IFC Rev1_Design_Analysis.pdf PDF
Solicitation Amendment FA813726R00250004 SF 30.pdf PDF
PreBid Govt Revised Response for WWYK200051 Replace Switchgear Bldg 1 ( 06.22.2026).pdf PDF
Solicitation Amendment FA813726R00250003 SF 30.pdf PDF
Pre-Bid RFI Govt Response Att2_Pictures for Electrical Closet.pdf PDF
Solicitation Amendment FA813726R00250002 SF 30.pdf PDF
Pre-Bid RFIs Govt Response for WWYK200051 Replace Switchgear Bldg 1 (06.08.2026).pdf PDF
Pre-Bid RFI Govt Response Att1_Inspection Report - WWYK090044F.pdf PDF
WWYK200051_TAFB IFC_FINAL_SPECIFICATIONS.pdf PDF
841018.pdf PDF
830009.pdf PDF
Solicitation Amendment FA813726R00250001 SF 30.pdf PDF
Bldg 1 - Electrical.pdf PDF
770142.pdf PDF
730072.pdf PDF
870148.pdf PDF
WWYK200051_SWITCHGEAR_IFC_CAD (2).zip ZIP file
B-1MEP.pdf PDF
950213.pdf PDF
710216.pdf PDF
00 80 00.pdf PDF
01 45 00.00 10.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
00 71 00.pdf PDF
00 80 05.pdf PDF
01 32 16.00 20.pdf PDF
01 78 00.pdf PDF
00 70 00.pdf PDF
00 72 00.pdf PDF
01 78 23.pdf PDF
01 33 00.pdf PDF
01 33 16.00 10.pdf PDF
01 42 00.pdf PDF
01 50 00.pdf PDF
WWYK200051 Initial Site Visit Sign In Sheet.pdf PDF
Section M - Evaluation Factors for Award.pdf PDF
Solicitation FA813726R0025_WWYK200051_Replace_Switchgear .pdf PDF
Section L - Instructions to Offerors.pdf PDF
WWYK200051 WAGE Determinations.pdf PDF
WWYK200051 Initial Site Visit Location.pdf PDF
EAL List.xlsx XLSX spreadsheet
STATEMENT OF WORK (SOW).pdf PDF
DRAWINGS.pdf PDF
Submittal Register.pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5th Ave

"C " A ve

Arnold St.

"E "A ve

"D " A ve

"C " A ve

3rd Ave.

"D

" D riv e

6th St.

RU

NW

AY

/36

RUNWAY 13/31

TA

XI

W

AY

G

TAXIW

AY H

TAXIWAY B

TAXIWAY C

TAXIWAY M

TA

XI

W

AY

K

TAXIWAY E

TAXIWAY A

TA

XIW

AY EE

TAXIWAY F

TAXIWAY D

TAXIWAY E

TAXIWAY J

TA

XI

W

AY

G

TAXIWAY A

TAXIW

AY H

TAXIWAY C

TAXIWAY D

TAXIWAY EE

TAXIWAY F

Elm Creek

Crutcho Creek

Kuhlman Creek

Kuhlman Creek

Elm Creek

East Crutcho Creek

Elm Creek

El m

Cr ee k

Elm Creek

Elm Creek

Elm Creek

Elm Creek

Ku hlm an Cr ee k

Ea st

Cr utc ho C ree k

Elm Cree k

West Crutcho Creek W es t C ru tch o C re ek

Elm Creek

Soldier Creek

Elm Creek

Soldier CreekSoldier Creek

Ea st

Cr utc ho C re ek

Elm Creek

Ea st

Cr utc ho C re ek

East Crutcho Creek

Soldier Creek

So ldi er Cr ee k

East C rutcho Creek

Soldier Creek

Soldier Creek

So ldi er C re ek

East Crutcho Creek

416506

11401128

59035909

838837

62509

62512

62525

99999

62543

71086

53902

50414

55300

56601

61019

62501

45134

62503

61289

62542

15904

15908

15904

15908

62502

41046

62501

62514

62501

41157

45815

40592

62522

15930

11824

3 10

62540

61089

62528

62523

62501X

43774

62516

3592135916

32101

930G

948-E

911-E

948-W

911-W

33001

35913

65672

930S

43609

42116

62517

62515

62526

62527

62513

62501OK

11289

62501

15930

15908

15904

15908

15904

61018

71089

45134

96022

43120

44045

43610

41163

15930

Ea st

Dr

SE 59th St.

St aff

D r.

5th Ave

W ar eh ou se R d.

7th St.

Mc Na rn ey

A ve

Mitchell Ave

Co ok

A ve

W es t D r.

Extender Dr.

5th Ave.

Globemaster Dr.

Ai r D ep ot

Mercury Rd.

Po nd

R d.

"C " A ve

Hi llto p R d.

"M " A ve

Doolittle Ave

W hit e D r.

Ba ll P ar k R d.

6th St.

Po we rh ou se D r.

Int ru de r D r.

Holden Dr.

Vanaman Rd.

1st St.

Arnold St.

SE 74th St

Ai r D ep ot

Patrol Rd.

Reserve Rd.

"A " A ve

Mu nit ion s R d.

"B " A ve

"H " A ve

Al er t R d.

"E "A ve

Sentry Rd.

34th St.

Twining Dr.

Jo ne s

To we r R d.

Vanaman Rd.

Ind us tria l B lvd

So uth

S t.

1st St.

Do oli ttle A ve

Pi cn ic Rd

Ja me s D r.

Wo lfe

D r.

Ai r D ep ot

"D " A ve

Perimeter Rd.

Rapcon Rd.

Reserve Rd

"L " A ve

"F " A ve

1st St.

Br ow n D r.

Ol d A ir D ep ot

Airey Dr.

General Motors Dr

Bradley Dr.

Entrance Road "C"

Entrance Road "A"

"C " A ve

Vandenberg Dr.

Do rm ito ry

Rd

Dormitory Rd.

Chennault Dr.

Mi tch ell A ve

Spaatz Dr.

En gin e T es t D r.

3rd Ave.

"D " D riv e

Joint STARS Dr.

Ai r D ep ot

Bl vd

Turbine Dr. Turbine Dr.

Central Plant Dr.

6th St.

Falcon Dr.

Blac kbi rd D r.

W ey lan d L oo p

Pegasus Dr.

Thunderbolt D r.

Munitions Rd. Ext.

Codding Rd.

Starlifter Dr.

Chidlaw Ct.

Co rsa ir D r.

Rap tor

Ct.

Ni gh t H aw k C t.

Ph an tom D r.

Fr an kli n

Sk ym as ter

D r.

Spaatz Ct.

La wr en ce

Mu nd ell

Nabors Dr.

Mc Ni ck le

Mi lle r D r.

Ta il F ea the r D r.

Air ey

Ci r.

Smith Ct. Raven Ct.

Air Dep ot Ai r D ep ot

1st St.

TAXIWAY F

Ra w li ng s A ve

Mitc he ll Av e.

Mercury Rd.

Ra ily ar d R d.

He rcu les R d.

TINKER AFB, OK

VICINITY MAP

BASE OPERATIONS B240

CONTRACTING B3

GOTT GATE

TINKER GATE

PASS & ID

B6611

HRUSKOCY GATE

EAKER

GATE

FIRE DEPARTMENT B117

VANCE GATE

LIBERATOR GATE

HOPE

GATE

LEGEND

CONTRACTOR

HAUL ROUTE

LANCER GATE

TRUCK GATE

PIAZZA GATE

BASE CIVIL

ENGINEER

B400

PROJECT

LOCATION

G-001

GE

NE

RA

L N

OT

ES

VI

CI

NI

TY

M

AP

A

ND

SH

EE

T

IN

DE

X

REVIEWED BY:

REVIEWED BY:

USING AGENCY:

ASBESTOS EVALUATION:

SAFETY:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

DATE:

INDUSTRIAL HYGIENE:

DATE:

PROJECT DRAWING INDEX SIGNATURES

CORROSION ENGINEER: (CECE)

CE OPERATIONS: (CECO)

COMMUNICATIONS: (COMM)

CHIEF ENGINEER DIR: (CECE)

CHIEF DESIGN BRANCH: (CECE)

DESIGN MANAGER: (CECE)

ZONE MANAGER:

CONSTRUCTION MANAGEMENT: (CECE)

ENVIRONMENTAL:

BASE CIVIL ENGINEER: (CE)

FIRE DEPARTMENT: (CEFT)

GENERAL1. BRAND NAMES: REFERENCE TO SPECIFIC BRAND NAMES

OR COMPANIES IS FOR THE PURPOSE OF ESTABLISHING

MINIMUM QUALITY STANDARDS, IDENTIFICATION AND

GUIDANCE AND IS NOT INTENDED TO LIMIT SELECTION OF

OTHER MANUFACTURERS THAT ARE EQUAL OR EXCEED

THE SPECIFIED ITEMS IN TERMS OF PHYSICAL

PROPERTIES, INCLUDING, COLOR RANGE, FINISH,

DURABILITY, APPEARANCE, PERFORMANCE

CHARACTERISTICS, AND OTHER FACTORS. OTHER

PRODUCTS, MATERIALS, COLORS AND SYSTEMS, MAY BE

SUBMITTED FOR EVALUATION AND

APPROVAL/DISAPPROVAL BY THE CONTRACTING OFFICER.

2. THIS SET OF CONSTRUCTION DOCUMENTS SHALL BE

CONSIDERED AS A WHOLE IN THAT THE GENERAL

CONTRACTOR AND ALL THE SUB-CONTRACTORS ARE

RESPONSIBLE FOR THE INFORMATION PRESENTED ON ALL

SHEETS ON THE SET OF DRAWINGS AND ALL SECTIONS OF

THE SPECIFICATIONS.

3. THE CONTRACTOR IS RESPONSIBLE FOR ERECTING ALL

CONSTRUCTION FENCING AND BARRICADES AS REQUIRED

TO PROTECT CONSTRUCTION MATERIAL AND TO PREVENT

ANY UNAUTHORIZED PERSONNEL FROM ENTERING THE

CONSTRUCTION SITE.

4. ANY DAMAGE TO THE EXISTING GROUNDS OR FACILITIES

CAUSED BY CONSTRUCTION TRAFFIC OR ANY

CONSTRUCTION OPERATION SHALL BE REPAIRED OR

REPLACED BY THE CONTRACTOR TO MATCH OR EXCEED

EXISTING CONDITIONS AT NO ADDITIONAL COST TO THE

GOVERNMENT.

5. ALL WORK NOTED & LOCATED IN THESE DOCS SHALL BE

UNDERSTOOD BY THE CONTRACTOR TO REQUIRE ALL NEW

LABOR & MATERIALS UNLESS SPECIFICALLY NOTED TO BE

"EXISTING" OR "BY OTHERS".

GENERAL NOTES:

G-001 GENERAL NOTES, VICINITY MAP AND SHEET INDEX

SHT. SHEET TITLE

WWYK200051

REPLACE SWITCHGEAR,

BLDG 1

TI

N

KE

R

A

IR

F O

R C

E

BA

SE

, O

KL

AH

O M

A

PR

O

JE

C

T

IN

FO

R

M

AT

IO

N

D

ES

IG

N

F

IL

E

LO

C

AT

IO

N

R

EV

IS

IO

N S

M

AR

K

D

ES

IG

N

G R

O U

P:

H

D R

B

ES

D R

AW

N

B Y:

C H

EC

KE

D B

Y:

D

ES

IG

N

ED

B

Y:

D

AT

E D

ES

C

R

IP

TI

O

N

1 2 3 4 5

E

D

C

B

A

M

AN

AG

EM

EN

T

IN

FO

R M

AT

IO

N

1 2 3 4 5

E

D

C

B

A

IS

SU

E D

AT

E:

SHEET NUMBER

SH

EE

T

TI

TL

E

AIR FORCE MATERIEL COMMAND

72 ABW CIVIL ENGINEER DIRECTORATE

TINKER AFB, OK

W W

YK

RE

PL

AC

E

SW

IT

CH

GE

AR

BL

DG

PROJECT

LOCATION

G-101 LIFE SAFETY PLAN

STRUCTURAL

S-001 STRUCTURAL NOTES

S-002 TYPICAL CONCRETE DETAILS

SD101 EXISTING FIRST FLOOR FRAMING PLAN - DEMOLITION

S-101 EXISTING FIRST FLOOR FRAMING PLAN - NEW WORK

ELECTRICAL

E-001 LEGEND AND ABBREVIATIONS

E-100 OVERALL PLAN

ED401 ENLARGED PLANS - DEMOLITION

ED601 ONE-LINE - DEMOLITION

E-401 ENLARGED PLANS - NEW WORK

E-501 480V AND 280V SWITCHGEAR RISER

E-601 ONE-LINE - NEW WORK

E-701 SCHEDULES JW

KH

JW17

A

PR

IL

JGARAFOLA

Snapshot

L

J

J

J

J

J

J

J

J

J

J

J

J

T D

-1 T

D -1

TD-1 TD-1TD-1 TD-1 TD-1

T D

-1 T

D -1

TD-1 TD-1TD-1 TD-1 TD-1

7 8 9 10 11 12 13 14 15 16 17 18

J

K

L

M

EQUIPMENT

ROOM

MECH/ELEC

1130 SF / 500 / 3 PER

32" 0.2

4'

/4

CORRIDOR

RAMP

CHILLER ON

MEZZANINE

DOCK

DOCK

A CLEAR DOOR WIDTH [FEET - INCHES]

C EXIT CAPACITY [OCCUPANTS]

EXIT DOOR TAG

NEW FIRE EXTINGUISHER

OTHERS

LIFE SAFETY NOTES:

1. FOR EXIT LIGHTS AND EMERGENCY LIGHTING, SEE ELECTRICAL

LIGHTING DRAWINGS (E SERIES).

LINE TYPES FOR MEANS OF EGRESS:

TRAVEL DISTANCE

SYMBOLCOMPONENT

LIFE SAFETY SYMBOLS:

TD

EXIT DISCHARGE ARROW

EXIT DISCHARGE

B CAPACITY FACTOR [INCHES PER OCCUPANT]

COMMON PATH CP

T

IN

K E

R A

IR

F

O R

C E

B A

S E

O

K L A

H O

M A

P R

O J E

C T

I N

F O

R M

A T

IO

N

D E

S

IG

N F

IL

E

L O

C A

T

IO

N

R E

V

IS

IO

N

S

M A

R K

D E

S

IG

N G

R O

U P

D R

A W

N B

Y

C H

E C

K E

D B

Y

D E

S

IG

N E

D B

Y

D A

T E

D E

S C

R

IP

T

IO

N

1 2 3 4 5

E

D

C

B

A

M A

N A

G E

M E

N T

I N

F O

R M

A T

IO

N

1 2 3 4 5

E

D

C

B

A

IS

S

U E

D A

T E

SHEET NUMBER

S H

E E

T T

IT

L E

AIR FORCE MATERIEL COMMAND

72 ABW CIVIL ENGINEER DIRECTORATE

TINKER AFB, OK

W W

Y K

R

E P

L A

C E

S W

IT

C

H G

E A

R

B L

D G

KEY PLAN

/1

/2

H D

R B

E S

D E

J R

M

J M

G-101

L

IF

E S

A F

E T

Y P

L A

N

1/8" = 1'-0"

LIFE SAFETY PLAN1

PROJECT AREA CODE SUMMARY

UFC 1-200-01 (12 JUNE 2023) WITH CHANGE 2

2024 NFPA 101 LIFE SAFETY CODE

UFC 3-600-01 (6 MAY 2021) WITH CHANGE 6

2021 IBC AS AMENDED BY UFC 1-200-01

2021 IEBC AS AMENDED BY UFC 1-200-01

PROJECT AREA BUILDING AREA

FLOOR

1ST FLOOR STORAGE (GROSS)

PROJECT AREA OCCUPANT LOAD

FLOOR

1ST FLOOR

AREA TYPE LOAD FACTOR LOAD REFERENCE

MECH/ELEC 500 SF/ OCC. 3 UFC 3-600-01 TABLE 10-1

EXISTING AREA (GSF)

TOTAL

1,130

1,130

TOTAL 3

G-101

PROJECT EGRESS TRAVEL DISTANCE

STORAGE USE

ALLOWED ACTUAL NFPA 101 REF.

COMMON PATH N/A100 FEET (WITH SPRINLKERS) TABLE 42.2.5

TRAVEL DISTANCE 120 FT400 FEET (WITH SPRINLKERS) TABLE 42.2.6

DEAD-END CORRIDOR N/A100 FEET (WITH SPRINLKERS) TABLE 42.2.5

KEYED NOTES:

EXISTING DIMENSIONS FOR FIRE RISER ROOM TO

BE FIELD VERIFIED BY CONTRACTOR.

04/10/2026

GENERAL STRUCTURAL NOTES (GSN)

GENERAL

G1. SCOPE

THE NOTES ON THIS SHEET AND THE STANDARD STRUCTURAL DETAILS ARE GENERAL AND

APPLY TO THE ENTIRE PROJECT WHETHER SPECIFICALLY CALLED OUT OR NOT, EXCEPT

WHERE THERE ARE SPECIFIC INDICATIONS TO THE CONTRARY ON STRUCTURAL SHEETS. IF

THERE ARE QUESTIONS, THEY SHALL BE SUBMITTED TO THE STRUCTURAL ENGINEER AND

ANSWERED IN WRITING PRIOR TO CONSTRUCTION.

G2. APPLICABLE SPECIFICATIONS AND CODES

A. INTERNATIONAL BUILDING CODE, IBC 2024 WITH APPLICABLE EDITIONS OF THE CODE

REFERENCED STANDARDS.

B. ACI 318-19

C. TAFB FACILITY STANDARDS

D. UFC 1-200-01 (WITH CHANGE 4, DATED 17 DEC 2024)

E. UFC 3-301-01 (WITH CHANGE 6, DATED 30 JAN 2026)

F. AISC 360-22

G3. DESIGN CRITERIA

1. APPLIES TO ALL STRUCTURES (UNO)

A. DEAD LOAD:

1. ACTUAL TRIBUTARY STRUCTURE WEIGHT

B. LIVE LOAD:

1. ELECTRICAL YARD: 150 PSF

C. WIND:

1. RISK CATEGORY: III

2. ULTIMATE WIND SPEED; VULT: 116 MPH

3. ALLOWABLE STRESS WIND SPEED; VASD: 90 MPH

4. EXPOSURE: C

D. SEISMIC:

1. RISK CATEGORY: III

2. IMPORTANCE FACTOR: 1.25

3. SPECTRAL RESPONSE ACCELERATION, SS: 0.298g

4. SPECTRAL RESPONSE ACCELERATION, S1: 0.081g

5. SITE CLASS: D

6. SEISMIC DESIGN CATEGORY: B

7. SPECTRAL RESPONSE COEFFICIENT, SDS: 0.31g

8. SPECTRAL RESPONSE COEFFICIENT, SD1: 0.129g

9. BASIC SEISMIC FORCE RESISTING SYSTEM: ASCE 7 SECTION 13.3

10. ANALYSIS PROCEDURE: EQUIVALENT LATERAL FORCE PROCEDURE

11. DESIGN BASE SHEAR (MAX): 1.6*SDSIPWP

E. SNOW LOAD:

1. STRUCTURE INTERIOR TO EXISTING BUILDING; THEREFORE, SNOW LOADING HAS NOT

BEEN CONSIDERED.

F. ICE LOADS:

1. STRUCTURE INTERIOR TO EXISTING BUILDING; THEREFORE, ICE LOADING HAS NOT BEEN

CONSIDERED.

G4. SAFETY

SAFETY AND STRUCTURE STABILITY DURING CONSTRUCTION ARE THE SOLE RESPONSIBILITY

OF THE CONTRACTOR. STRUCTURES HAVE BEEN DESIGNED TO RESIST THE DESIGN LOADS

ONLY AS A COMPLETED STRUCTURE.

G5. OPENINGS

OPENINGS FOR PIPES, DUCTS, CONDUITS, ETC. ARE NOT ALL SHOWN ON THE STRUCTURAL

DRAWINGS. COORDINATE AND PROVIDE OPENINGS AS REQUIRED TO ACCOMMODATE ALL

WORK SHOWN OR SPECIFIED IN THE CONTRACT DOCUMENTS AND OTHERWISE REQUIRED FOR

THE FURNISHING OF A FUNCTIONALLY COMPLETE PROJECT. REINFORCE AROUND OPENINGS

PER STANDARD STRUCTURAL DETAILS UNLESS OTHERWISE SHOWN.

G6. STANDARD DETAILS

THE STANDARD DETAILS DEPICT TYPICAL DETAILING TO BE USED ON THIS PROJECT. IF

CONDITIONS ARE NOT EXPLICITLY SHOWN ON THE DRAWINGS THEY SHALL BE MADE SIMILAR

TO THE STANDARD DETAILS. OBTAIN APPROVAL OF ENGINEER IN WRITING FOR SIMILAR

CONDITIONS PRIOR TO CONSTRUCTION.

G7. THE CONTRACTOR SHALL FIELD VERIFY ALL DIMENSIONS AND ELEVATIONS OF EXISTING

CONSTRUCTION AS REQUIRED TO COORDINATE NEW CONSTRUCTION. SUBMIT REQUIRED

CHANGES FOR APPROVAL.

G8. CONTRACTOR TO SUBMIT FOR REVIEW ALL EQUIPMENT SIZES, OPERATING WEIGHTS,

VIBRATION FORCES, SUPPORT LOCATIONS, ALONG WITH ANY FLOOR OPENINGS, NOTCHES,

AND RECESSES REQUIRED BY SUCH EQUIPMENT. CONCRETE SUPPORT PADS AND/OR

FRAMING REQUIRED TO SUPPORT SAID EQUIPMENT SHALL NOT BE FABRICATED AND PLACED

UNTIL THE CONCRETE SUPPORT PADS AND/OR FRAMING IS APPROVED TO SUPPORT THE

EQUIPMENT.

CONCRETE

C1. DESIGN STRENGTHS:

F'c = 4,000 PSI Fy = 60,000 PSI

C2. CONCRETE COVER

UNLESS OTHERWISE NOTED, PROVIDE CONCRETE COVER FOR REINFORCING AS FOLLOWS:

CONCRETE DEPOSITED AGAINST EARTH: 3"

ALL OTHER: 2"

SEE DRAWINGS FOR EXCEPTIONS

C3. SEE SPECIFICATIONS FOR REINFORCING PLACEMENT REQUIREMENTS.

C4. REFER TO OTHER DISCIPLINE DRAWINGS PRIOR TO CONSTRUCTION FOR EMBEDDED ITEMS

AND PENETRATIONS NOT SHOWN ON STRUCTURAL DRAWINGS. AS REQUIRED TO

ACCOMMODATE ALL WORK SHOWN OR SPECIFIED IN THE CONTRACT DOCUMENTS AND

OTHERWISE REQUIRED FOR THE FURNISHING OF A FUNCTIONALLY COMPLETE PROJECT.

REINFORCE AROUND OPENINGS PER STANDARD STRUCTURAL DETAILS UNLESS OTHERWISE

SHOWN.

C5. PROVIDE 3/4" CHAMFERS AT ALL EXPOSED EDGES. NOT ALL CHAMFERS MAY BE SHOWN ON

DRAWINGS.

C6. FIELD ADJUST REINFORCING AT OPENINGS AND EMBEDDED ITEMS AS INDICATED.

C7. ANCHOR BOLTS NOT SPECIFIED BY ENGINEER SHALL BE DESIGNED AND CERTIFIED BY A

REGISTERED PROFESSIONAL ENGINEER LICENSED IN THE STATE OF OKLAHOMA, RETAINED

BY THE CONTRACTOR, IN ACCORDANCE WITH APPLICABLE PROJECT AND CODE

REQUIREMENTS. SUBMIT AS A SHOP DRAWING FOR REVIEW AND APPROVAL BY THE ENGINEER.

COORDINATE LOCATION, SIZE AND EMBEDMENT PRIOR TO CASTING CONCRETE.

C8. ABSOLUTELY NO WELDING OF REINFORCING BARS OR TORCHING TO BEND REINFORCING

BARS SHALL BE ALLOWED WITHOUT SPECIFIC APPROVAL FROM THE STRUCTURAL

ENGINEER.

C9. ALL CAST IN PLACE AND POST-INSTALLED ANCHORS INDICATED IN THE STRUCTURAL

DOCUMENTS SHALL COMPLY WITH CHAPTER 17 OF ACI 318 AND CHAPTER 19 OF THE

IBC. ALL EXPANSION AND ADHESIVE ANCHORS SHALL HAVE THE ICC REPORT SHOWING

EQUIVALENT LOAD CAPACITY. SUBMIT AND INSTALL PER THE ICC EVALUATION REPORT.

DEFERRED SUBMITTALS

1. DEFINITION:

DELEGATED DESIGN SUBMITTALS ARE ITEMS FOR WHICH THE FINAL DESIGN OF A SPECIFIC ELEMENT OF THE PERMANENT CONSTRUCTION WORK EXPRESSLY DELEGATED TO A PROPERLY LICENSED AND

REGISTERED DESIGN PROFESSIONAL LICENSED IN THE STATE OF OKLAHOMA RETAINED OR

EMPLOYED BY THE CONTRACTOR, SUBCONTRACTOR, SUPPLIER OF ANY TIER. "DELEGATED DESIGN"

APPLIES ONLY TO PERMANENT WORK THAT WILL BE PART OF THE COMPLETED PROJECT AS A

FUCTIONING WHOLE.

2. DELEGATED DESIGN LIST:

THE FOLLOWING IS A LIST OF DELEGATED SUBMITTALS THAT ARE EXPECTED TO CONTAIN SEALED

STRUCTURAL CALCULATIONS OF SAFETY-RELATED SYSTEM INFORMATION FOR REVIEW. THESE

SUBMITTALS APPLY TO DELEGATED DESIGNED SYSTEMS PRIOR TO INSTALLATION OF THE INDICATED STRUCTURAL ELEMENT, EQUIPMENT, DISTRIBUTION SYSTEM, COMPONENT, OR ITS ANCHORAGE. THE CONTRACTOR SHALL SUBMIT THE REQUIRED ENGINEER CERTIFICATION, SUPPORTING DATA, AND

SEALED DRAWINGS FOR REVIEW AND ACCEPTANCE BY THE CONTRACTING OFFICER.

DEFERRED SUBMITTALS

SPEC SECTIONS/

COMPONENTS

SWITCHGEAR

ANY EQUIPMENT OR COMPONENT IN WHICH A

TECHNICAL SPECIFICATION REQUIRES SUBMITTAL

OF EQUIPMENT OR ANCHORAGE SYSTEM

CALCULATIONS

CONSTRUCTION AT EXISTING STRUCTURES

E1. SEE DEMOLITION SHEETS.

E2. WHERE DRILL AND EPOXY REINFORCING OR ANCHORS ARE INSTALLED CONTRACTOR SHALL NOT DAMAGE EXISTING REINFORCING. IF REQUIRED, CONTRACTOR SHALL HAVE EXISTING CONCRETE

INVESTIGATED USING GROUND PENETRATING RADAR TO LOCATE EXISTING REINFORCING.

E3. EXISTING CONCRETE SURFACES TO BE JOINED WITH NEW CONCRETE SHALL BE ROUGHENED

TO 1/4" AMPLITUDE, THROUGHLY CLEANED BY SAND BLASTING, AND APPLY BONDING AGENT

JUST PRIOR TO PLACEMENT OF NEW CONCRETE.

E4. WHERE EXISTING REINFORCING IS TO BE PRESERVED, CONTRACTOR SHALL STRAIGHTEN AND

SAND BLAST REINFORCING JUST PRIOR TO PLACEMENT OF NEW CONCRETE.

E5. PRIOR TO DRILL AND EPOXY BOLTS OR REBAR, LOCATE ALL EXISTING REINFORCEMENT. CARE

SHALL BE TAKEN NOT TO DISTURB THE EXISTING REINFORCEMENT.

STATEMENT OF SPECIAL INSPECTIONS (IBC 1705):

UNLESS NOTED OTHERWISE

SI1. SHOP FABRICATED ITEMS BY APPROVED FABRICATOR ARE EXEMPT FROM SPECIAL INSPECTION. UPON COMPLETION, APPROVED FABRICATOR SHALL SUBMIT A CERTIFICATE OF COMPLIANCE STATING WORK WAS PERFORMED IN ACCORDANCE WITH APPROVED CONSTRUCTION DOCUMENTS.

SI2. CONTRACTOR SHALL SUBMIT A WRITTEN STATEMENT OF RESPONSIBILITY PRIOR TO CONSTRUCTION, INCLUDING:

A. ACKNOWLEDGEMENT OF SPECIAL INSPECTION REQUIREMENTS.

B. ACKNOWLEDGE THAT CONTROL WILL BE EXERCISED TO CONFORM WITH APPROVED CONSTRUCTION DOCUMENTS.

C. PROCEDURES FOR EXERCISING CONTROL, INCLUDING METHOD AND FREQUENCY OF REPORTING, AND DISTRIBUTION OF REPORTS.

D. IDENTIFICATION AND QUALIFICATION OF PERSON(S) EXERCISING SUCH CONTROL.

SI3. STRUCTURAL OBSERVATIONS ARE REQUIRED IN ACCORDANCE WITH IBC SECTION 1704.6.1 STRUCTURAL OBSERVATIONS SHALL BE PERFORMED BY THE ENGINEER OF RECORD (EOR) OR A LICENSED PROFESSIONAL ENGINEER (PE) DESIGNATED BY THE EOR. FOR GENERAL COMPLIANCE WITH DESIGN DOCUMENTS AND INTENT, OBSERVATION SCHEDULE SHALL BE SUBMITTED PRIOR TO OBSERVATION COMMENCEMENT. REGISTERED DESIGN PROFESSIONAL SHALL PREPARE A REPORT INDICATING SITE VISITS MADE AND IDENTIFYING ANY STRUCTURAL DEFICIENCIES THAT HAVE NOT BEEN CORRECTED. OBSERVATIONS ARE REQUIRED DURING INSTALLATION OF SMALL EQUIPMENT PADS.

SI4. THE FOLLOWING CONSTRUCTION IS SUBJECT TO SPECIAL INSPECTION:

SCHEDULE OF SPECIAL INSPECTION SERVICES

FREQUENCY

CONTINUOUS PERIODIC

CODE

REFERENCE REMARKSINSPECTION ITEM REQUIRED

GENERAL STRUCTURAL OBSERVATIONS

CONDUCT DAILY VISUAL OBSERVATION OF THE

STRUCTURAL SYSTEMS FOR GENERAL

CONFORMANCE TO THE CONSTRUCTION

DOCUMENTS. PREPARE WEEKLY REPORT OF

OBSERVATIONS DESCRIBING WORK PROGRESS

AND NON-CONFORMING ITEMS.

- X

CONCRETE AND REINFORCING STEEL

INSPECTION OF REINFORCING STEEL SIZE

AND PLACEMENT. - X ACI 318: CH 20, 25.2,

25.3, 26.6.1-26.6.3

IBC TABLE 1705.3

INSPECTION OF BOLTS TO BE INSTALLED IN

CONCRETE PRIOR TO AND DURING PLACEMENT

OF CONCRETE WHERE ALLOWABLE LOADS HAVE

BEEN INCREASED OR WHERE STRENGTH DESIGN

IS USED.

- X ACI 318: 17.8.2.4,

ACI 318: 17.8.2

INSPECTION OF ANCHORS INSTALLED IN

HARDENED CONCRETE MEMBERS.

A. ADHESIVE ANCHORS INSTALLED IN

HORIZONTALLY OR UPWARDLY

ORIENTATIONS TO RESIST SUSTAINED

TENSION LOADS.

B. MECHANICAL ANCHORS AND ADHESIVE

ANCHORS NOT DEFINED IN ITEM A ABOVE

X - ACI 318: 17.8.2.4

VERIFYING USE OF REQUIRED DESIGN MIX. - X ACI 318: CH. 19,

26.4.3-26.4.4

PRIOR TO CONCRETE PLACEMENT, FABRICATE

SPECIMENS FOR STRENGTH TESTS,

PERFORM SLUMP AND AIR CONTENT TESTS, AND

DETERMINE TEMPERATURE OF THE CONCRETE.

X -

ASTM C172

ASTM C31

ACI 318: 5.6, 5.8

INSPECTION OF CONCRETE PLACEMENT FOR

PROPER APPLICATION TECHNIQUES. X - ACI 318: 26.5

INSPECTION FOR MAINTENANCE OF SPECIFIED

CURING TEMPERATURE AND TECHNIQUES. - X ACI 318:

26.5.3-26.5.5

ACI 318: 26.12VERIFYING CONCRETE STRENGTH. X-

ACI 318: CH. 26.8ERECTION OF PRECAST CONCRETE MEMBERS. X-

INSPECT FORMWORK FOR SHAPE, LOCATION

AND DIMENSIONS OF THE CONCRETE MEMBER

BEING FORMED.

X- ACI 318: 26.11.1.2(b)

INSPECTION OF ANCHORS CAST IN CONCRETE X- ACI 318: 17.8.2

- X ACI 318: 17.8.2

05 05 20 POST-INSTALLED CONCRETE ANCHORS

TI

N

KE

R

A

IR

F O

R C

E

BA

SE

, O

KL

AH

O M

A

PR

O

JE

C

T

IN

FO

R

M

AT

IO

N

D

ES

IG

N

F

IL

E

LO

C

AT

IO

N

R

EV

IS

IO

N S

M

AR

K

D

ES

IG

N

G R

O U

P:

D R

AW

N

B Y:

C H

EC

KE

D B

Y:

D

ES

IG

N

ED

B

Y:

D

AT

E D

ES

C

R

IP

TI

O

N

1 2 3 4 5

E

D

C

B

A

M

AN

AG

EM

EN

T

IN

FO

R M

AT

IO

N

1 2 3 4 5

E

D

C

B

A

IS

SU

E D

AT

E:

SHEET NUMBER

SH

EE

T

TI

TL

E

AIR FORCE MATERIEL COMMAND

72 ABW CIVIL ENGINEER DIRECTORATE

TINKER AFB, OK

W W

YK

R

EP

LA

C

E

SW

IT

C

H G

EA

R

BL

D G

A

PR

IL

H D

R B

ES

C M

R

N JC

S-001

G

EN

ER

AL

ST

R

U C

TU

R

AL

N

O

TE

S

AN

D S

TA

TE

M

EN

T O

F

SP

EC

IA

L

IN

SP

EC

TI

O

N S

04/10/2026

1 1/2"

CLR.

6" MIN. CONTRACTOR

COORDINATE PAD

THICKNESS WITH REQUIRED

EQUIP ANCHOR BOLT

EMBEDMENT

6"

MIN.

12"

#4@12" E.W.

MIN.#4 CLOSED TIE ADDL

CONT. @ PERIMETER

CONCRETE SURFACE SHALL BE CLEAN,

FREE OF LATENCE, ROUGHENED TO A 1/4"

AMPLITUDE, & COATED W/ BONDING AGENT

3/4" CHAMFER (TYP.)

EXISTING SLAB

EQUIP.

BASE

#4@12"W/ STD HOOKS @

TOP PERIM, 3" EMBEDMENT

AND EPOXY

8" LEG (TYP.)

PAD NOTES:

1.

2.

3.

PAD DETAILS APPLY FOR SUPPORT OF ALL EQUIPMENT UNLESS INDICATED

OTHERWISE ON THE DRAWINGS.

BEFORE EQUIPMENT SUPPORT PADS ARE CAST, THE PAD SIZES AND

REINFORCING SHALL BE APPROVED BY THE ENGINEER AS BEING CAPABLE

OF SUPPORTING EQUIPMENT TO BE PLACED THEREON. EQUIPMENT BASE

DIMENSIONS SHALL BE THE LARGER OF AS DETERMINED BY THE

EQUIPMENT MANUFACTURER OR AS INDICATED ON THE DRAWINGS.

SUBMIT ALL EQUIPMENT DIMENSIONS AND LOADS TO ENGINEER. THE SIZE,

NUMBER, TYPE, LOCATION AND THREAD PROJECTION OF THE ANCHOR

BOLTS (A.B.) SHALL BE AS DETERMINED BY THE EQUIPMENT

MANUFACTURER AND SHALL BE AS APPROVED BY THE ENGINEER. A.B.

SHALL BE HELD IN POSITION WITH A TEMPLATE WHILE EQUIPMENT PAD IS

CAST.

REFERENCE ELECTRICAL DRAWINGS FOR DIMENSIONS & LOCATIONS OF

PADS. FINAL PAD DIMENSIONS ARE TO BE ADJUSTED AS NEEDED TO FIT

FINAL EQUIPMENT SELECTED.

EQUIP. A.B.

TI

N

KE

R

A

IR

F O

R C

E

BA

SE

, O

KL

AH

O M

A

PR

O

JE

C

T

IN

FO

R

M

AT

IO

N

D

ES

IG

N

F

IL

E

LO

C

AT

IO

N

R

EV

IS

IO

N S

M

AR

K

D

ES

IG

N

G R

O U

P:

D R

AW

N

B Y:

C H

EC

KE

D B

Y:

D

ES

IG

N

ED

B

Y:

D

AT

E D

ES

C

R

IP

TI

O

N

1 2 3 4 5

E

D

C

B

A

M

AN

AG

EM

EN

T

IN

FO

R M

AT

IO

N

1 2 3 4 5

E

D

C

B

A

IS

SU

E D

AT

E:

SHEET NUMBER

SH

EE

T

TI

TL

E

AIR FORCE MATERIEL COMMAND

72 ABW CIVIL ENGINEER DIRECTORATE

TINKER AFB, OK

W W

YK

R

EP

LA

C

E

SW

IT

C

H G

EA

R

BL

D G

A

PR

IL

H D

R B

ES

C M

R

N JC

S-002

TY

PI

C

AL

C O

N C

R

ET

E D

ET

AI

LS

12" = 1'-0"

TYPICAL EQUIPMENT SUPPORT PAD1

04/10/2026

P

P

PP

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

Q

Q

QQ

Q

Q

Q

Q

Q

Q

Q

Q

Q

Q

Q

Q

Q

R

R

RR

R

R

R

R

R

R

R

R

2R

1R1

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R 3A

R1

S

SS

S

S

S

S

S

S

S

S 1A

S1

S1

S

S 3A

S1

T

T

TT

T

T

T

T

T

T

T

T

1A

T1

T1

T

T

3A

T1

U

U

UU

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

W

W

WW

W

W

W

W

W

W

W

W

1A

U1

U1

W

W

3A

U1

X

X

XX

X

X

X

X

X

X

X

X

1A

W1

W1 20

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

3A

W1

Y

Y

YY

Y

Y

Y

Y

Y

Y

Y

Y

1A

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

3A

Y

N

N

NN

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

3B

N

P

P

P

P

I

I

II

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

H

H

HH

H

H

H

H

H

H

H

H

H

H

H

H

H

H

H

G

G

GG

G

G

G

G

G

G

G4G

G1G

G

G

G

G

G

G

G

G

G

G

G

G

G

G

G

G

F

F

FF

F

F

F

F

F

F

F

E1

E1

E1

F

F

F

F

3A

E1

E

E

EE

E

E

E

E

E

E

E

E

1A

D1

D1

E

E

E

E

D1

D

D

DD

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

C

C

CC

C

C

C

C

C

C

C

C

C

C

C

C

B

B

BB

B

B

B

B

B

B

B

B1

1A

B1

B1

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B1

A

A

AA

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A 47

A1

A1

A

A

A

N

N

N

3B

R 1R

1AR1

Y

Y

M

M

M

K

K

K

L

I

H

5G

1F1 1F1

F

D1

1A

C1

C1

C1

C1

B

A

A

A

3AF1 4F1

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

BLOCKED

AHU-8

AHU-5

MO

AA

AHU-7

A A

M O

N

P

Q

R

S

T

T1

U

U1

W

W1

Y

X

S1

R1

M

L

K

J

I

H

G

F1

F

E1

E

D1

D

C1

C

B1

B

A1

A

1 1a 2 3 3a 3b 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53

1 1a 2 3 3a 4 5 6 7 8 9 10 11 12 13 14 15 16 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 5317

1 B-00001 FIRST FLOOR PLAN

0 30' 30' 60' 15'

WWYK140029

M

N

L

K

J

6 7 8 9 10 11 12 13 14 15 16 17 18

GENERAL NOTES:

1.

2.

3.

(*) INDICATES EXISTING DIMENSION TO BE

FIELD VERIFIED BY CONTRACTOR.

EXISTING BUILDING INFORMATION IS AS

INDICATED ON THE AS-BUILT DRAWINGS. THE

CONTRACTOR SHALL NOTIFY THE

CONTRACTING OFFICER OF ANY

DISCREPANCIES.

CONTRACTOR SHALL REVIEW AS-BUILT

DRAWINGS REPLACE TRANSFORMERS, BLDG 1

PROJECT NUMBER OC-216-1 DATED 17 JULY

1972, AND REPLACE POWER DISTRIBUTION

SYSTEM, LIGHTS AND AIR-CONDITIONING,

BUILDING 1 PROJECT NUMBER OC-9-9, DATED

19 MAY 1986 FOR EXISTING STRUCTURAL

INFORMATION. VERIFY ALL DIMENSIONS

SHOWN WITH EXISTING CONSTRUCTION AND

REPORT ANY DISCREPANCIES TO THE

CONTRACTING OFFICER.

KEYNOTES:

EXISTING POSTS, INCLUDING BASE PLATES AND

SCREENS, SHALL BE REMOVED.

COORDINATE REMOVAL OF EXISTING EQUIPMENT

AND CONCRETE PADS WITH ELECTRICAL SCOPE.

EXISTING EQUIPMENT AND SCREEN POST

ANCHORS SHALL BE GROUND OUT, BACKGOUGED,

AND COVERED WITH GROUT.

EXISTING FIRE RISER ROOM. SEE WWYK160073 FOR

OVERALL DIMENSIONS AND AS-BUILT LOCATION.

TRASH

COMPACTOR

DOCK

25-KW

GENERATOR

NINE

RAMP

CHILLER ON

MEZZANINE

EQUIPMENT

ROOM

CANOPY COLUMNS,

TYP

2' - 6" (*) 30' - 3" (*) 30' - 11" (*)

2'

1"

18' - 4 1/2" (*) 1' - 6" (*) 15' - 1 1/2" (*) 8' - 6 1/2" (*) 12' - 11" (*) 8' - 6 1/2" (*) 15' - 0" (*) 20' - 0" (*) 18' - 9" (*) 2' - 0" (*) 19' - 3" (*) 20' - 0" (*)

321' - 11" (*) 11' - 0 3/4" (*)

/2

9'

1/ 2"

9'

1/

2"

/2

TI

N

KE

R

A

IR

F O

R C

E

BA

SE

, O

KL

AH

O M

A

PR

O

JE

C

T

IN

FO

R

M

AT

IO

N

D

ES

IG

N

F

IL

E

LO

C

AT

IO

N

R

EV

IS

IO

N S

M

AR

K

D

ES

IG

N

G R

O U

P:

D R

AW

N

B Y:

C H

EC

KE

D B

Y:

D

ES

IG

N

ED

B

Y:

D

AT

E D

ES

C

R

IP

TI

O

N

1 2 3 4 5

E

D

C

B

A

M

AN

AG

EM

EN

T

IN

FO

R M

AT

IO

N

1 2 3 4 5

E

D

C

B

A

IS

SU

E D

AT

E:

SHEET NUMBER

SH

EE

T

TI

TL

E

AIR FORCE MATERIEL COMMAND

72 ABW CIVIL ENGINEER DIRECTORATE

TINKER AFB, OK

W W

YK

R

EP

LA

C

E

SW

IT

C

H G

EA

R

BL

D G

KEY PLAN

A

PR

IL

H D

R B

ES

C M

R

N JC

SD101

EX

IS

TI

N

G F

IR

ST

FL

O

O R

F R

AM

IN

G

PL

AN

D

EM

O

LI

TI

O

N

1/8" = 1'-0"

EXISTING FIRST FLOOR FRAMING PLAN - DEMOLITION1

SD101

04/10/2026

P

PP

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

Q

Q

QQ

Q

Q

Q

Q

Q

Q

Q

Q

Q

Q

Q

Q

Q

R

R

RR

R

R

R

R

R

R

R

R

2R

1R1

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R 3A

R1

S

SS

S

S

S

S

S

S

S

S 1A

S1

S1

S

S 3A

S1

T

T

TT

T

T

T

T

T

T

T

T

1A

T1

T1

T

T

3A

T1

U

U

UU

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

W

W

WW

W

W

W

W

W

W

W

W

1A

U1

U1

W

W

3A

U1

X

X

XX

X

X

X

X

X

X

X

X

1A

W1

W1 20

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

3A

W1

Y

Y

YY

Y

Y

Y

Y

Y

Y

Y

Y

1A

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

3A

Y

N

N

NN

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

3B

N

P

P

P

P

I

I

II

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

H

H

HH

H

H

H

H

H

H

H

H

H

H

H

H

H

H

H

G

G

GG

G

G

G

G

G

G

G4G

G1G

G

G

G

G

G

G

G

G

G

G

G

G

G

G

G

G

F

F

FF

F

F

F

F

F

F

F

E1

E1

E1

F

F

F

F

3A

E1

E

E

EE

E

E

E

E

E

E

E

E

1A

D1

D1

E

E

E

E

D1

D

D

DD

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

C

C

CC

C

C

C

C

C

C

C

C

C

C

C

C

B

B

BB

B

B

B

B

B

B

B

B1

1A

B1

B1

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B1

A

A

AA

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A 47

A1

A1

A

A

A

N

N

N

3B

R 1R

1AR1

Y

Y

M

M

M

K

K

K

L

I

H

5G

1F1 1F1

F

D1

1A

C1

C1

C1

C1

B

A

A

A

3AF1 4F1

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

BLOCKED

AHU-8

AHU-5

MO

AA

AHU-7

A A

M O

N

P

Q

R

S

T

T1

U

U1

W

W1

Y

X

S1

R1

M

L

K

J

I

H

G

F1

F

E1

E

D1

D

C1

C

B1

B

A1

A

1 1a 2 3 3a 3b 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53

1 1a 2 3 3a 4 5 6 7 8 9 10 11 12 13 14 15 16 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 5317

1 B-00001 FIRST FLOOR PLAN

0 30' 30' 60' 15'

WWYK140029

M

N

L

K

J

6 7 8 9 10 11 12 13 14 15 16 17 18

GENERAL NOTES:

1.

2.

3.

(*) INDICATES EXISTING DIMENSION TO BE

FIELD VERIFIED BY CONTRACTOR.

EXISTING BUILDING INFORMATION IS AS

INDICATED ON THE AS-BUILT DRAWINGS. THE

CONTRACTOR SHALL NOTIFY THE

CONTRACTING OFFICER OF ANY

DISCREPANCIES.

CONTRACTOR SHALL REVIEW AS-BUILT

DRAWINGS REPLACE TRANSFORMERS, BLDG 1

PROJECT NUMBER OC-216-1 DATED 17 JULY

1972, AND REPLACE POWER DISTRIBUTION

SYSTEM, LIGHTS AND AIR-CONDITIONING,

BUILDING 1 PROJECT NUMBER OC-9-9, DATED

19 MAY 1986 FOR EXISTING STRUCTURAL

INFORMATION. VERIFY ALL DIMENSIONS

SHOWN WITH EXISTING CONSTRUCTION AND

REPORT ANY DISCREPANCIES TO THE

CONTRACTING OFFICER.

KEYNOTES:

NEW EQUIPMENT PAD, SEE 1/S-002. COORDINATE

LOCATION WITH ELECTRICAL DRAWINGS.

EXISTING FIRE RISER ROOM. SEE WWYK160073 FOR

OVERALL DIMENSIONS AND AS-BUILT LOCATION.

x

TRASH

COMPACTOR

DOCK

25-KW

GENERATOR

NINE

RAMP

CHILLER ON

MEZZANINE

EQUIPMENT

ROOM

2' - 6" (*) 30' - 3" (*) 30' - 11" (*)

CANOPY COLUMNS,

TYP

2'

1"

TOP OF EXISTING

CONCRETE DOCK

EL. 0'-0"

18' - 4 1/2" (*) 1' - 6" (*) 15' - 1 1/2" (*) 8' - 6 1/2" (*) 12' - 11" (*) 8' - 6 1/2" (*) 15' - 0" (*) 20' - 0" (*) 18' - 9" (*) 2' - 0" (*) 19' - 3" (*) 20' - 0" (*)

21' - 11" (*) 11' - 0 3/4" (*)

/2

9'

1/ 2"

9'

1/

2"

/2

9'

5/

8"

6'

8"

12' - 1 1/4" (*)

/2

2'

1/ 4"

12' - 1 1/4" (*) 6' - 4 7/8" (*) 1'

6"

5'

2"

3'

9"

3' - 10" (*) 9 1/4" (*)

6' - 0" (*)

TI

N

KE

R

A

IR

F O

R C

E

BA

SE

, O

KL

AH

O M

A

PR

O

JE

C

T

IN

FO

R

M

AT

IO

N

D

ES

IG

N

F

IL

E

LO

C

AT

IO

N

R

EV

IS

IO

N S

M

AR

K

D

ES

IG

N

G R

O U

P:

D R

AW

N

B Y:

C H

EC

KE

D B

Y:

D

ES

IG

N

ED

B

Y:

D

AT

E D

ES

C

R

IP

TI

O

N

1 2 3 4 5

E

D

C

B

A

M

AN

AG

EM

EN

T

IN

FO

R M

AT

IO

N

1 2 3 4 5

E

D

C

B

A

IS

SU

E D

AT

E:

SHEET NUMBER

SH

EE

T

TI

TL

E

AIR FORCE MATERIEL COMMAND

72 ABW CIVIL ENGINEER DIRECTORATE

TINKER AFB, OK

W W

YK

R

EP

LA

C

E

SW

IT

C

H G

EA

R

BL

D G

KEY PLAN

A

PR

IL

H D

R B

ES

C M

R

N JC

S-101

EX

IS

TI

N

G F

IR

ST

FL

O

O R

F R

AM

IN

G

PL

AN

N

EW

W O

R K

1/8" = 1'-0"

EXISTING FIRST FLOOR FRAMING PLAN - NEW WORK1

S-101

04/10/2026

T

IN

K E

R A

IR

F

O R

C E

B A

S E

O

K L A

H O

M A

P R

O J E

C T

I N

F O

R M

A T

IO

N

D E

S

IG

N F

IL

E

L O

C A

T

IO

N

R E

V

IS

IO

N

S

M A

R K

D E

S

IG

N G

R O

U P

D R

A W

N B

Y

C H

E C

K E

D B

Y

D E

S

IG

N E

D B

Y

D A

T E

D E

S C

R

IP

T

IO

N

1 2 3 4 5

E

D

C

B

A

M A

N A

G E

M E

N T

I N

F O

R M

A T

IO

N

1 2 3 4 5

E

D

C

B

A

IS

S

U E

D A

T E

SHEET NUMBER

S H

E E

T T

IT

L E

AIR FORCE MATERIEL COMMAND

72 ABW CIVIL ENGINEER DIRECTORATE

TINKER AFB, OK

W W

Y K

R

E P

L A

C E

S W

IT

C

H G

E A

R

B L

D G

/1

/2

H D

R B

E S

K L E

G C

O R

N E

L L

G J A

G L O

W S

K I

E-001

E L E

C T

R

IC

A L

L E

G E

N D

A N

D A

B B

R E

V

IA

T

IO

N S

B

D

Y

T

C

F

C

J

C

J

S

S2

S3

S4P

SDM

SM

T

S

M

TV

M

VFD

3P

1200A

M

C

SPD

GFP

E

ES

E

E

E

ES

E

ES

E

ES

OS

SOS

IG

P

ELECTRICAL SYMBOLS LEGENDS AND ABBREVIATIONS

A AMPERES OR TRIP

AMPERES

AC ALTERNATING CURRENT

AFF ABOVE FINISHED FLOOR

AFG ABOVE FINISHED GRADE

AIC SYMMETRICAL AMPS

INTERRUPTING CAPACITY

AWG AMERICAN WIRE GAUGE

A/R AS REQUIRED

ARR. ARRESTOR

BLDG BUILDING

BRKT BRACKET

C CONDUIT

CB CIRCUIT BREAKER

CKT CIRCUIT

CL CURRENT LIMITING

CO CONDUIT ONLY

CTL CONTROL

DC DIRECT CURRENT

D.T.C. DATA TERMINAL CABINET

EMCS ENERGY MONITORING

AND CONTROL SYSTEM

FACP FIRE ALARM CONTROL

PANEL

FT FOOT, FEET

GFCI GROUND FAULT CIRCUIT

INTERRUPTER, 5MA

PERSONNEL PROTECTION

UNLESS OTHERWISE NOTED.

GRD GROUND

HZ HERTZ

IAW IN ACCORDANCE WITH

IG ISOLATED GROUND

IN INCH, INCHES

IR INFRARED

KV KILOVOLTS

KVA KILOVOLT AMPERES

KVAR KILOVOLT AMPS REACTIVE

KWH KILOWATT HOURS

L-L LINE TO LINE

L-N LINE TO NEUTRAL

MFR MANUFACTURER

MH MANHOLE

MIN MINIMUM

MTD MOUNTED

MTG MOUNTING

N.C. NORMALLY CLOSED

NEC NATIONAL ELECTRICAL

CODE

NEMA NATIONAL ELECTRICAL

MANUFACTURERS ASSOCIATION

NEUT NEUTRAL

N.O. NORMALLY OPEN

NLT NOT LESS THAN

NMT NOT MORE THAN

OH OVERHEAD

OV OVERRIDE SWITCH

PAS PUBLIC ADDRESS SYSTEM

PE PHOTOELECTRIC

PH PHASE

PLCS PLACES

PNL PANELBOARD

PVC POLYVINYL CHLORIDE

ELECTRICAL RACEWAY

USED ONLY U.G., CARLON

OR EQUIVALENT

RC RIGID STEEL CONDUIT

REF REFERENCE

REQ'D REQUIRED

RGC RIGID GALVANIZED STEEL

CONDUIT

RM ROOM

RMC RIGID METALIC CONDUIT

SHT SHEET

SOB STANDOFF BRACKET

SPACE SPACE(S) ONLY (NO

BREAKER DEVICE)

SPARE SPARE BREAKER OR DEVICE

SPDT SINGLE-POLE, DOUBLE-THROW

SPECS CONTRACT SPECIFICATIONS

SPST SINGLE-POLE, SINGLE-THROW

S/N SOLID NEUTRAL

TB TELEPHONE BACKBOARD

TYP TYPICAL

UG UNDERGROUND

UL LISTED BY UNDERWRITER'S

LABORATORIES

UON UNLESS OTHERWISE NOTED

V VOLTS

VA VOLT AMPERES

W WATT

WAP WIRELESS ACCESS POINT

WH WEATHERHEAD

W/ WITH

∅ PHASE

2W+G CIRCUIT TYPE

3W+G CIRCUIT TYPE

4W+G CIRCUIT TYPE

ABBREVIATIONS

POWER SYMBOLS LEGEND

DESCRIPTIONSYMBOL

RECEPTACLE, DUPLEX, 20A, 120V, GROUNDING 2W+G, NEMA

5-20R

RECEPTACLE, DUPLEX, FLOOR MOUNTED, FLUSH, 20A, 120V,

GROUNDING 2W+G NEMA 5-20R.

RECEPTACLE, DUPLEX, CEILING MOUNTED, 20A, 120V,

GROUNDING 2W+G, NEMA 5-20R

RECEPTACLE, QUADRAPLEX

RECEPTACLE/EQUIPMENT CONNECTION, SPECIAL PURPOSE

RECEPTACLE, CLOCK

JUNCTION BOX, ABOVE CEILING

JUNCTION BOX, WALL MOUNTED, SERVING COMPUTER LOAD.

RECEPTACLE, DUPLEX, SERVING COMPUTER LOAD. 20A, 120V,

GROUNDING 2W+G RECEPTACLE, NEMA 5-20R

SWITCH, TOGGLE, WALL MOUNTED, 20A., 120/277V RATED (AC

ONLY), SINGLE-POLE, MOUNT 54" AFF

SWITCH, TOGGLE, WALL MOUNTED, 20A., 120/277V RATED (AC

ONLY), THREE-WAY, SPDT. MOUNT 54" AFF

SWITCH, LOW VOLTAGE, WALL MOUNTED, 4-SCREEN PRESET.

MOUNT 54" AFF

SWITCH, DIMMER, LOW VOLTAGE 0-10V. MOUNT 54" AFF

BRANCH CIRCUIT HOME RUN WITH NEUTRAL, PHASE AND

EQUIPMENT GROUND RESPECTIVELY

RACEWAY, ABOVE FLOOR

COMBINATION STARTER/DISCONNECT WITH HOA

SWITCH-COORDINATE WITH MECH. CONTRACTOR.

SWITCH, DISCONNECT

PANELBOARD, SURFACE MOUNTED

PANELBOARD, RECESSED

DESCRIPTIONSYMBOL

TRANSFORMER, POWER, KVA RATING, WINDING VOLTAGES AND

CONNECTIONS ARE SHOWN NEXT TO SYMBOL

ONE-LINE & CONTROL SCHEMATIC LEGEND

TRANSFORMER, CURRENT, TURNS RATIO, SHOWN NEXT TO

SYMBOL

GROUNDING CONNECTION. WHEN USED WITH TRANSFORMER

WINDING SYMBOL IT INDICATES A NEUTRAL GROUNDING

CONNECTION (ON SECONDARY SIDE ONLY)

GROUNDED WYE WINDING CONNECTION

DELTA CONNECTED

RELAY OR CONTACTOR CONTACTS

SEPARABLE (PLUG-IN) CONNECTOR OR CONNECTION FOR

DRAWOUT ASSEMBLIES

SCHEMATIC, CIRCUIT CONNECTIONS

CIRCUIT BREAKER, MOLDED CASE, TRIP CURRENT [A] AND

QUANTITY OF POLES [P] SHOWN NEXT TO SYMBOL

SWITCH, DISCONNECT, NON-FUSED, LOAD BREAK. CONTINUOUS

CURRENT RATING [A] AND QUANTITY OF POLES [P] SHOWN

NEXT TO SYMBOL

SWITCH, DISCONNECT, FUSED, LOAD BREAK. FUSE AMPERE

RATING [A] AND FUSE TYPE SHOWN NEXT TO SYMBOL

FUSE, AMPERE RATING [A] AND FUSE TYPE SHOWN NEXT TO

SYMBOL

MOTOR THERMAL OVERLOAD PROTECTOR

INTEGRAL PHOTOELECTRIC CELL AND RELAY (PHOTOCONTROL)

WATTHOUR METER

CONTACTOR OR RELAY COIL. LETTER(S) INSIDE OF SYMBOL

MATCH CONTACTS CONTROLLED

SURGE ARRESTER, VALVE TYPE ARRESTER KV RATING SHOWN

NEXT TO SYMBOL

EQUIPMENT ENCLOSURE

SYMBOL MODIFIERS

DESCRIPTIONSYMBOL

AUDIBLE AND VISUALAV

EXISTINGE

FIXED TEMPERATUREF

GROUND FAULT CIRCUIT INTERRUPTERGFI

NEWN

ITEM OR DEVICE RECESSED INTO MOUNTING SURFACER

RADIO FREQUENCYRF

WEATHERPROOFWP

DEVICE MOUNTED ABOVE COUNTER TOPAC

RECEPTACLE SERVING COMPUTER LOAD.C

GROUNDING LEGEND

DESCRIPTIONSYMBOL

CONDUCTOR, BARE, UON

GROUNDING CONNECTION, COUNTERPOISE TO GROUND ROD.

SCHEMATIC CIRCUIT

ELECTRICAL BUSS

CABLE OR WIRE

WYE CONNECTED

LIGHTING SYMBOLS LEGEND

RACEWAY, RISER UP

RACEWAY, RISER DOWN

THERMOSTAT BY MECHANICAL CONTRACTOR

POWER SYMBOLS LEGEND (CONTINUED)

DESCRIPTIONSYMBOL

RECEPTACLE, DUPLEX, SPECIAL PURPOSE

TELEPHONE RECEPTACLE, WALL MOUNTED

BELL

SPEAKER, CEILING MOUNTED

MICROPHONE, CEILING MOUNTED

SPEAKER CONTROL

SOUND CABINET

AUDIO/VISUAL PROJECTOR

CEILING FAN

CABLE TV OUTLET

MOTOR

SWITCH, MOTOR

HORIZONTAL WIREMOLD

240 VOLT 20 AMP RECEPTACLE

SWITCH, TOGGLE, WALL MOUNTED, 20A., 120/277V RATED (AC

ONLY), DOUBLE-POLE, MOUNT 54" AFF

DESCRIPTIONSYMBOL

FLUORESCENT/LED, SURFACE OR PENDANT, RECESSED

CEILING MOUNTED

FLUORESCENT/LED, WALL MOUNTED

NIGHT LIGHT, FLUORESCENT/LED FIXTURE WITH INTERGAL

EMERGENCY BALLAST

CFL/HID/LED FIXTURE, RECESSED CEILING MOUNTED

CFL/HID/LED FIXTURE, WALL MOUNTED

EXIT SIGN, LIGHTED, SURFACE OR PENDANT, CEILING MOUNTED

W/LIGHTED FACE AND DIRECTIONAL ARROW.

EXIT SIGN, LIGHTED, WALL MOUNTED.

EMERGENCY LIGHT, 2 LAMPS, BATTERY POWERED

BRANCH CIRCUIT HOME RUN

CFL/HID/LED FIXTURE, SURFACE OR PENDANT

TRANSFORMER, DRY TYPE

NIGHT LIGHTNL

DATA RECEPTACLE, WALL MOUNTED

TELEPHONE/DATA RECEPTACLE, WALL MOUNTED

SURGE PROTECTION DEVICE

GROUND FAULT PROTECTION

VARIABLE FREQUENCY DRIVER

LIGHTING SWITCHLEG

SITE UTILITIES LEGEND

DESCRIPTIONSYMBOL

DUCT BANK, OVERHEAD PRIMARY

DUCT BANK, OVERHEAD SECONDARY

CFL/HID/LED FIXTURE, AREA LIGHT POLE

MANHOLE, ELECTRIC

HANDHOLE, ELECTRIC

POWER POLE, ELECTRIC

CCTV SECURITY CAMERA

DUCT BANK, UNDERGROUND PRIMARY

DUCT BANK, UNDERGROUND SECONDARY

SWITCH, OCCUPANCY SENSOR, 120V, 1500 WATT.

MOUNT 54" AFF

VERTICAL WIREMOLD

ISOLATED GROUND RECEPTACLE, DUPLEX, ORANGE TYPE. 20A,

120V, GROUNDING 2W+2G RECEPTACLE, NEMA 5-20R

OCCUPANCY SENSOR, CEILING MOUNTED.

MANUAL ON/INTEGRAL MANUAL DIMMING

PHOTOSENSOR, CEILING MOUNTED

GENERAL NOTES:

(APPLICABLE TO ALL ELECTRICAL SHEETS)

1. ALL WORKS SHALL BE PROVIDED AND INSTALLED IN ACCORDANCE WITH

TINKER AFB ELECTRICAL STANDARDS (JANUARY 2026)

2. EQUIPMENT INTERRUPTING CAPACITIES SPECIFIED IN THE CONTRACT

DOCUMENTS ARE BASED UPON EQUIPMENT CHARACTERISTICS AND

IMPEDANCES SHOWN ON THE DRAWINGS. IF ACTUAL INSTALLED EQUIPMENT

DEVIATES FROM THESE CHARACTERISTICS OR HAS LOWER IMPEDANCES. THE

CONTRACTOR SHALL INCREASE THE INTERRUPTING CAPACITIES OF ALL ITEMS

ON THE LOAD SIDE OF THE DEVIANT EQUIPMENT IN DIRECT PROPORTION TO

THE CHANGED CHARACTERISTICS. INTERRUPTING CAPACITIES SHALL NOT BE

REDUCED TO VALUES LESS THAN THOSE REQUIRED BY THE CONTRACT

DOCUMENTS.

3. FIRE STOP SHALL BE PROVIDED AT ALL LOCATIONS WHERE ELECTRICAL

EQUIPMENT OR SYSTEMS PENETRATE FIRE RATED WALLS. SEE

ARCHITECTURAL PLANS FOR RATED WALL LOCATIONS.

4. CONTROL WIRING P&ID'S FOR MECHANICAL EQUIPMENT ARE NOT SHOWN ON

THESE SHEETS.

5. RISER AND ONE-LINE DIAGRAMS ARE MEANT TO SHOW ELECTRICAL

RELATIONSHIPS FOR EQUIPMENT, AND THEREFORE MAY NOT INCLUDE ALL

REQUIRED EQUIPMENT DEVICES, AND ACCESSORIES.

SYMBOL NOTES

1. THESE SYMBOLS APPLY TO THE ENTIRE SET OF CONTRACT DRAWINGS.

2. ALL SYMBOLS ARE NOT NECESSARILY USED IN THE DRAWINGS FOR THIS PROJECT. LISTING OF

SYMBOLS DOES NOT IMPLY THAT ALL SYMBOLS ARE USED IN THE CONTRACT DRAWINGS.

3. COLORS FOR ALL OUTLETS AND SWITCHES SHALL BE AS SHOWN ON ARCHITECTURAL PLANS.

4. ALL MOUNTING HEIGHTS SHOWN IN SYMBOL LEGEND SHALL BE AS PER TAS/ADA REQUIREMENTS

UNLESS OTHERWISE NOTED ON THE ARCHITECTURAL DRAWINGS.

5. BRANCH CIRCUIT NUMBERS MAY BE SHOWN NEXT TO SYMBOLS IN MULTIWIRE CIRCUITS.

6. EQUIPMENT IDENTIFIERS, MATCHING EQUIPMENT SCHEDULES, ARE DISPLAYED ATTACHED TO

SYMBOLS BY LEADER ARROWS, UON.

7. SYMBOL ORIENTATION DOES NOT IMPLY DEVICE OR EQUIPMENT ORIENTATION, UNLESS NOTED

AS SUCH. SEE REFLECTED CEILING PLANS FOR LIGHT FIXTURE POSITIONS AND ORIENTATIONS.

8. SYMBOL SIZE DOES NOT IMPLY EQUIPMENT SIZE, UON.

9. LOWER CASE LETTER IN POSITION "X" INDICATES FIXTURES CONTROLLED BY SAME LETTER.

10. PLAN SYMBOLS USE THE FOLLOWING LINE TYPE CONVENTION AND ARE REPRESENTED AS

FOLLOWS:

LINETYPE, DENOTES EXISTING TO REMAIN

LINETYPE, DENOTES EXISTING TO BE DEMOLISHED

LINETYPE, DENOTES NEW U.G. OR CONCEALED CONSTRUCTION

LINETYPE, DENOTES NEW CONSTRUCTION

EPM ELECTRIC POWER METER

J

J

J

J

J

J

J

J

J

J

J

J

BREAK RM

COMM

CORRIDOR

BREAK RM

OPEN OFFICE

VENDING

OPEN

OFFICE

OPEN

OFFICE

MECH

ENTRY

--MOP SINK

1-PNL-33

F A

C P

RAMP

CHILLER ON

MEZZANINE

DOCK

DOCK

J

J

ELECT

OFFICE

A

ELEVATOR

M E

C H

ELEC

OFFICE

STORAGE

7 8 9 10 11 12 13 14 15 16 17 18

J

K

L

M

EXISTING OG&E XFMR

RE: E-601.

EXISTING 480V UNIT SUBSTATION

(UID-1-SWGSEC-5)

EXISTING 208V UNIT SUBSTATION B

(UID-B-1-SWGSEC-3)

T

M M

M

4 5

I

EXISTING

PANEL B-13

(UID #1-PNL-11)

T

1A 2

4 5

P

PANEL

HG1

EXISTING PANEL LPO

(UID #1-FA-801)

T

IN

K E

R A

IR

F

O R

C E

B A

S E

O

K L A

H O

M A

P R

O J E

C T

I N

F O

R M

A T

IO

N

D E

S

IG

N F

IL

E

L O

C A

T

IO

N

R E

V

IS

IO

N

S

M A

R K

D E

S

IG

N G

R O

U P

D R

A W

N B

Y

C H

E C

K E

D B

Y

D E

S

IG

N E

D B

Y

D A

T E

D E

S C

R

IP

T

IO

N

1 2 3 4 5

E

D

C

B

A

M A

N A

G E

M E

N T

I N

F O

R M

A T

IO

N

1 2 3 4 5

E

D

C

B

A

IS

S

U E

D A

T E

SHEET NUMBER

S H

E E

T T

IT

L E

AIR FORCE MATERIEL COMMAND

72 ABW CIVIL ENGINEER DIRECTORATE

TINKER AFB, OK

W W

Y K

R

E P

L A

C E

S W

IT

C

H G

E A

R

B L

D G

KEY PLAN

/1

/2

H D

R B

E S

K L E

G C

O R

N E

L L

G J A

G L O

W S

K I

ED401

E L E

C T

R

IC

A L

E N

L A

R G

E D

P L A

N S

D

E M

O L

IT

IO

N

1/8" = 1'-0" E-100

ELECTRICAL DEMO PLAN - ENLARGED DOCK4

1/8" = 1'-0" E-100

ELECTRICAL DEMO PLAN - ENLARGED ELECTRICAL CLOSET2

1/8" = 1'-0" E-100

ELECTRICAL DEMO PLAN - ENLARGED ELEVATOR ROOM1

GENERAL NOTES:

1. REFER TO ED-601 FOR DEMOLITION ONE-LINE

DIAGRAM FOR ADDITIONAL INFORMATION.

2. ALL DEMO WORK MUST BE PLANNED IN PHASES

TO MINIMIZE IMPACT TO PRODUCTION.

COORDINATE ALL WORK WITH OG&E AND THE

FACILITY USER GROUP. REFER TO E-100 FOR

PHASING PLAN.

3. THIS DRAWING WAS PREPARED FROM EXISTING

AS-BUILTS AND LIMITED ACCESS FOR FIELD

OBSERVATIONS AND VERIFICATIONS. FIELD VERIFY

EXISTING CONDITIONS AND UPDATE AS-BUILT

DRAWINGS FOR RECORD. SUBMIT RFIs TO

GOVERNMENT AND DOR IF THERE ARE ANY

DISCREPANCIES BETWEEN DRAWINGS AND

EXISTING SITE CONDITIONS FOR RESOLUTIONS.

4. UNLESS NOTED OTHERWISE, ALL EXISTING

EQUIPMENT TO REMAIN AND MAINTAIN NORMAL

OPERATION. REFER TO SPECIFICATION 26 20 00

FOR ADDITIONAL INFORMATION ON EXISTING TO

REMAIN EQUIPMENT

KEYED NOTES:

DISCONNECT POWER CONNECTION AND REMOVE

EXISTING 480V UNIT SUBSTATION WITH 480V

SWITCHGEAR ENCLOSURE, INCLUDING EXISTING

ASSOCIATED ELECTRICAL DEVICES, POWER

METERS, AND GROUNDING/BONDING TO

EXISTING BUILDING. REMOVE EXISTING MV

FEEDER BACK TO SOURCE.

DISCONNECT POWER CONNECTION AND REMOVE

EXISTING 208V UNIT SUBSTATION WITH 208V

SWITCHGEAR ENCLOSURE, INCLUDING EXISTING

ASSOCIATED ELECTRICAL DEVICES, POWER

METERS, AND GROUNDING/BONDING TO

EXISTING BUILDING. REMOVE EXISTING MV

FEEDER BACK TO SOURCE.

EXISTING 1500KVA OG&E TRANSFORMER TO

REMAIN IN PLACE FOR CONNECTION IN NEW

WORK.

EXISTING PANELBOARD MUST BE REPLACED IN

PLACE. DISCONNECT POWER CONNECTION AS

INDICATED ON DEMOLITION ONE-LINE DIAGRAM.

RETAIN ALL EXISTING BRANCH CIRCUITS BEING

FED FROM PANEL FOR RECONNECTION IN NEW

WORK.

DISCONNECT POWER CONNECTION TO EXISTING

TRANSFORMER AND REMOVE ALL PRIMARY AND

SECONDARY CONDUCTORS/CONDUITS TO

POWER SOURCE.

DISCONNECT POWER CONNECTION FROM

EXISTING 30KVA XFMR (UID #1XFMR-2). SEE

KEYED NOTE #5.

DISCONNECT EXISTING FEEDER. RETAIN FOR

RECONNECTION IN NEW WORK.

REMOVE CONDUCTORS AND RETAIN CONDUIT

CONNECTION. SEE DEMOLITION ONE-LINE, SHEET

ED601 FOR ADDITIONAL INFORMATION.

1/8" = 1'-0" E-100

ELECTRICAL DEMO PLAN - ELECTRICAL CLOSETS3

EXISTING 30KVA

TO ELEVATOR

D/S

(UID #1XFMR-2)

EXISTING PANEL

B-9

(UID #1-SWGSEC-2)

EXISTING 60A

DISCONNECT

SWITCH TO REMAIN

IN PLACE

EXISTING

30KVA XFMR

TO REMAIN IN

PLACE

8 (TYP)

(TYP)

NORTH BUS

UNDERGROUND PRIMARY FEEDER

SWITCHING STATION "A"

VAULT "A" #4

SOUTH BUS

UNDERGROUND PRIMARY FEEDER

4 POINT LOAD BREAK IN SUBSTATION "A"

200A

3 POINT LOAD BREAK IN SUBSTATION "A"

3 POINT LOAD BREAK

EXISTING 500 KVA XFMR

12.5 KV 208/120 V

LOCATED ON DOCK

AMMETER

WITH SELECTOR

SWITCH

D

Y

VOLTMETER

WITH SELECTOR

SWITCH

V

A

GFI

(EXISTING)

EXISTING 208V

UNIT SUBSTATION

(B-1-SWGSEC-3)

1200 AMP BUS

(EXISTING UNIT

SUBSTATION B)

S P

A R

E

S P

A R

E

PNL. LPO (EXISTING)

(UID #1-FA-801)

600A BUS

S P

A R

E

S P

A R

E

PANEL

"B3 & B3A"

PANEL

"B4 & B5"

T O

A C

U N

IT

S

PANEL

"B16"

PANEL

"B7"

T O

A C

U N

IT

S

T O

A C

U N

IT

S

PANEL

"B14"

PANEL

"B1"

PNL. B-9 (EXISTING)

(UID #1-SWGSEC-2)

600A BUS

EXISTING

30 KVA

XFMR

PANEL

"B4 & B5"

T O

A C

U N

IT

S

PANEL

"B16"

PANEL

"B7"

PANEL

"B8" S P

A R

E

PANEL

"B12"

PANEL

"B-13"

(UID #1-

PNL-11)

EXISTING 1000KVA

XFMR 12.5 KV 208/120 V

LOCATED ON DOCK

D

Y

VOLTMETER

WITH SELECTOR

SWITCH

V

AMMETER

WITH SELECTOR

SWITCH

A

GFI

(EXISTING)

EXISTING 480V

UNIT SUBSTATION

(UID-1-SWGSEC-5)

1600 AMP BUS

S P

A R

E

S P

A R

E

S P

A R

E

S P

A R

E

S P

A R

E

S P

A R

E

S P

A R

E

S P

A R

E

S P

A R

E

S P

A R

E

200 400 200

T-9 T-10 T-8 T-8

225 100

T-8

CHILLER

MOTOR CONTROL

CENTER MCC-1

T-6

225 100

T-8

EXISTING 60A

ELEVATOR D/S

T

IN

K E

R A

IR

F

O R

C E

B A

S E

O

K L A

H O

M A

P R

O J E

C T

I N

F O

R M

A T

IO

N

D E

S

IG

N F

IL

E

L O

C A

T

IO

N

R E

V

IS

IO

N

S

M A

R K

D E

S

IG

N G

R O

U P

D R

A W

N B

Y

C H

E C

K E

D B

Y

D E

S

IG

N E

D B

Y

D A

T E

D E

S C

R

IP

T

IO

N

1 2 3 4 5

E

D

C

B

A

M A

N A

G E

M E

N T

I N

F O

R M

A T

IO

N

1 2 3 4 5

E

D

C

B

A

IS

S

U E

D A

T E

SHEET NUMBER

S H

E E

T T

IT

L E

AIR FORCE MATERIEL COMMAND

72 ABW CIVIL ENGINEER DIRECTORATE

TINKER AFB, OK

W W

Y K

R E

P L A

C E

S W

IT

C

H G

E A

R

B L

D G

/1

/2

H D

R B

E S

K L E

G C

O R

N E

L L

G J A

G L O

W S

K I

ED601

E L

E C

T R

IC

A

L

O N

E -L

IN

E

D E

M O

L

IT

IO

N

NOT TO SCALE

ELECTRICAL ONE-LINE - DEMOLITION1

ED601

GENERAL NOTES:

1. UNLESS NOTED OTHERWISE, RETAIN EXISTING

DOWNSTREAM CONDUCTORS AND CONDUIT

FEEDING EXISTING-TO-REMAIN EQUIPMENT AS

SHOWN IN PLACE.

2. DISCONNECT AND REMOVE EXISTING MEDIUM

VOLTAGE FEEDER INCLUDING CABLES AND

CONDUITS BACK TO VAULT "A" AS SHOWN. CAP

AND ABANDON UNDERGROUND CONDUITS PER

TAFB ELECTRICAL STANDARDS.

3. TRACE AND VERIFY THE EXISTING BRANCH

CIRCUITS FEEDING FROM DEMOLISHED

PANELBOARDS AND EXISTING UNIT-SUBSTATIONS

AS SHOWN. CONFIRM AND PROVIDE CIRCUIT INDEX

DIRECTORIES PER SPECIFICATIONS.

4. ALL DEMO WORK MUST BE PLANNED IN PHASES

TO MINIMIZE IMPACT TO PRODUCTION.

COORDINATE ALL WORK WITH OG&E AND THE

FACILITY USER. REFER TO E-100 FOR PHASING

PLAN.

5. THIS DRAWING WAS PREPARED FROM EXISTING

AS-BUILTS AND LIMITED ACCESS FOR FIELD

OBSERVATIONS AND VERIFICATIONS. FIELD VERIFY

EXISTING CONDITIONS AND UPDATE AS-BUILT

DRAWINGS FOR RECORD.

6. UNLESS NOTED OTHERWISE, ALL EXISTING

EQUIPMENT AS SHOWN TO REMAIN. EXISTING

CIRCUIT BREAKERS AS INDICATED ARE 3-POLE.

KEYED NOTES:

REMOVE EXISTING CONDUCTORS AND CONDUITS.

REMOVE EXISTING CONDUCTORS. RETAIN

CONDUITS FOR RECONNECTION IN NEW WORK.

P

PP

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

P

Q

Q

QQ

Q

Q

Q

Q

Q

Q

Q

Q

Q

Q

Q

Q

Q

R

R

RR

R

R

R

R

R

R

R

R

2R

1R1

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

3A

R1

S

SS

S

S

S

S

S

S

S

S

1A

S1

S1

S

S

3A

S1

T

T

TT

T

T

T

T

T

T

T

T

1A

T1

T1

T

T

3A

T1

U

U

UU

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

U

W

W

WW

W

W

W

W

W

W

W

W

1A

U1

U1

W

W

3A

U1

X

X

XX

X

X

X

X

X

X

X

X

1A

W1

W1 20

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

3A

W1

Y

Y

YY

Y

Y

Y

Y

Y

Y

Y

Y

1A

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

Y

3A

Y

N

N

NN

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

3B

N

P

P

P

P

I

I

II

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

I

H

H

HH

H

H

H

H

H

H

H

H

H

H

H

H

H

H

H

G

G

GG

G

G

G

G

G

G

G4G

G1G

G

G

G

G

G

G

G

G

G

G

G

G

G

G

G

G

F

F

FF

F

F

F

F

F

F

F

E1

E1

E1

F

F

F

F

3A

E1

E

E

EE

E

E

E

E

E

E

E

E

1A

D1

D1

E

E

E

E

D1

D

D

DD

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

D

C

C

CC

C

C

C

C

C

C

C

C

C

C

C

C

B

B

BB

B

B

B

B

B

B

B

B1

1A

B1

B1

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B

B1

A

A

AA

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A

A 47

A1

A1

A

A

A

N

N

N

3B

R

1R

1AR1

Y

Y

M

M

M

K

K

K

L

I

H

5G

1F1 1F1

F

D1

1A

C1

C1

C1

C1

B

A

A

A

3AF1 4F1

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

J

SL I D I N G H AN GA R D OOR

BLOCKED

AHU-8

AHU-5

M

O

AA

AHU-7

A A

M O

STOCKROOM "E"STOCKROOM "D"

STOCKROOM "C"STOCKROOM "B"

EQU I P C AGE

EQU I P C AGE

OFFI C E

OFFI C E

OFFI C E

BRE AK AR EA

PRODUCTION

PRINTING

U

TI

L C

H

AS

E

STOR A GE

STOR A GE

STOCKROOM "A"

OFFI C E

SHEETMETAL TRAINING AREA

HOT AIR SOLDER TRAINING AREA

STOCKROOM "F"

STOCKROOM "G"

AB A N DON E D

EL E VA TOR

OFFICE

127 SF

OFFICE

124 SF

OFFICE

125 SF

C O

R R

S

F

VEST.

OFFICE

122 SF

OFFICE

122 SF

OFFICE

122 SFC

O

R R

S F

CONFERENCE

ROOM

151 SF

PSN

240 SF

OFFICE

100 SF

OFFICE

100 SF

OFFICE

100 SF

OFFICE

100 SF

OFFICE

79 SF

OFFICE

75 SF

OFFICE

107 SF

MEPS OPEN

OFFICE

1426 SF

CAC CARD OPEN

OFFICE

1702 SF

VEST.

61 SF

OFFICE

116 SF

OFFICE

120 SF

MPS OPEN

OFFICE

DLA ADMIN

OPEN OFFICE

OFFICE

CORRIDOR

OFFICE

105B

OFFICE

OFFICE

OFFICE

OFFICE

CORRIDOR

OFFICE

STORAGE

100A

CORRIDOR

PRINTING OFFICE

RECEPTION

OFFICE

OPEN

OFFICE

WOMANS

RESTRM

MENS

RESTRM

MENS

RESTRM

STORAGE

--ENTRY

OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

EM

LAB

WOMANS

RESTRM

MENS

RESTRM

CONFERENCE/

BREAK RM

CONFERENCE RM

OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

BREAK RM

C O

R R

ID

O

R

CORRIDOR

MEETING RM

IG WORKSPACE

CONFERENCE

STORAGE

STORAGE

STORAGE

CORRIDOR

EM

LAB

109A

EM

CONFERENCE

109B

EM

OPEN OFFICE

109C

EM

OPEN OFFICE

OPEN OFFICE

CLASS RM

EYE EXAM RM

113B

COMM

OFFICE

OFFICE

OFFICE

STORAGE

108X

ADC

WAITING RM

CORRIDOR

C O

R R

ID

O

R

420 SCM

OPEN OFFICE

OPEN OFFICE

EM

OPEN OFFICE

EM

OFFICE

CONFERENCE

OFFICE AREA

BREAK AREA

OFFICE

OFFICE

OFFICE

ELECT

OFFICE

OFFICE

72 ABW/XP

OPEN OFFICE

BREAK RM

COMM

CORRIDOR

BREAK RM

OPEN OFFICE

OPEN OFFICE

OPEN OFFICE

CORRIDOR

OFFICE

147A

OFFICE

147B

OPEN OFFICE

MECH

WOMAN

RESTRM

VACANT

STORAGE

WOMEN

RESTRM

147B

JANITOR

STG

STORAGE

WOMEN

RESTRM

BREAK

AREA

ELEC

MENS

RESTRM

JANITOR

CORRIDOR

ENTRY

PHONE

JANITOR

RECEPTION

ENTRY

COMM

CLOSET

115A

MEN

RESTRM

WOMENS

RESTRM

CORRIDOR

OFFICE

CONF

RM

CLOSET

OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

STORAGE

OPEN

OFFICE

OPEN

OFFICE

OFFICE

OPEN

OFFICE

BREAK

AREA

OPEN

OFFICE

OFFICE

CONF RM

OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

STORAGE

STORAGE

RECEPTION

CLOSET

ENTRY

MEN

RESTRM

WOMENS

RESTRM

STORAGE

VACANT

VACANT

BREAK RM

STORAGE

ICC

CONF RM

CORRIDOR

OPEN OFFICE

OFFICE

CORRIDOR

PARTS

STORAGE

VENDING

OPEN

OFFICE

OPEN

OFFICE

M E

C H

ELEC

MECH

W O

M E

N 'S

MEN'S

CORRIDOR

ENTRY

ENTRY

MECH

ENTRY

SERVER RM

OFFICE

MICROFICHE

LAB

MECHANICAL

VACANT

LAB

SERVER

ROOM

OFFICE

CONF RM

OFFICE

OFFICE

OFFICE

108 OFFICE

STORAGE

CORRIDOR

OFFICE

C O

F F

E E

4 OFFICE

OFFICE

COPY

AREA

101 ENTRANCE

OFFICE

OFFICE

OFFICE OFFICECOMM

OFFICE

OFFICE OFFICE

MECH

HALLWAY

VAULT

STORAGE

STORAGE

OFFICE

OFFICE

OFFICE

BREAK RM

CLASS RM

CLASS RM

OFFICE

OFFICE

OFFICE

CLASS RM

CLASS RM

CLASS RM

CLASS RM

CLASS RM

CLASS RM

OFFICE

STORAGE

MECH

OFFICE

CLASS RM

CLASS RM

OFFICE

F

IN

N A

N C

E C

U S

T O

M E

R S

V C

A R

E A

FINANCE

WAITING RM

OFFICE

QA

OFFICE

OFFICE

CLASS RM

CLASS RM

VAULT

OFFICE

-- OFFICE

OFFICE

OFFICE

OFFICE

OFFICE

OPEN

OFFICE

T.O LIBRARY

AREA

T.O LIBRARY

OFFICE

TRAINING

STORAGE

INSTRUCTORS

OPEN OFFICE

STORAGE

CLASS RM

D

CURRICULUM DEV

OPEN OFFICE

CONFERENCE RM

STORAGE

STORAGE

COMM

CLASS RM

E

CLASS RM

F

WOMEN

RESTRM

MEN

RESTRM

SINK

HALLWAY

OPEN

OFFICE

OFFICE

ENTRY

RECEPTION

OFFICE

OFFICE

STORAGE

CORRIDOR

OFFICE

MECH

OPEN

OFFICE

OFFICE

OFFICE

OFFICE

CLASS RM

BREAK AREA

OPEN

OFFICE

MECH

MOP SINK

VITA

OFFICE

OPEN

OFFICE

MEN

RESTRM

WOMEN

RESTRM

-- MEN

RESTRM

STORAGE

OFFICE

VACANT

STORAGE

ELEC

CLASS RM

G

CLASS RM

H

COMM

OPEN

OFFICE

JANITOR

C O

R R

ID

O

R

OPEN

OFFICE

RECORDS

STORAGE

W W YK140029

1-PNL-33

1-PNL-32

FACP

1-FA-2

F A

C P

-P

N L

-3

RAMP

CHILLER ON

MEZZANINE

DOCK

DOCK

1A 2

3A

6 7

13 14 15

17 18 19 20

B1

22 23 24 25 26 27

28 29 30 31

32 33 34 35

38 39

41 42

43 44 45 46

50 51 52 53

A

A1

B

C

C1

D

D1

E

E1

F

Q

G

H

I

J

K

L

M

N

P

O

R

R1

S

S1

T

T1

U

U1

W

W1

X

Y

ED401

E-401

ED401

E-401

ED401

E-401

E-401

ED401

T

IN

K E

R A

IR

F

O R

C E

B A

S E

O

K L A

H O

M A

P R

O J E

C T

I N

F O

R M

A T

IO

N

D E

S

IG

N F

IL

E

L O

C A

T

IO

N

R E

V

IS

IO

N

S

M A

R K

D E

S

IG

N G

R O

U P

D R

A W

N B

Y

C H

E C

K E

D B

Y

D E

S

IG

N E

D B

Y

D A

T E

D E

S C

R

IP

T

IO

N

1 2 3 4 5

E

D

C

B

A

M A

N A

G E

M E

N T

I N

F O

R M

A T

IO

N

1 2 3 4 5

E

D

C

B

A

IS

S

U E

D A

T E

SHEET NUMBER

S H

E E

T T

IT

L E

AIR FORCE MATERIEL COMMAND

72 ABW CIVIL ENGINEER DIRECTORATE

TINKER AFB, OK

W W

Y K

R

E P

L A

C E

S W

IT

C

H G

E A

R

B L

D G

KEY PLAN

/1

/2

H D

R B

E S

K L E

G C

O R

N E

L L

G J A

G L O

W S

K I

E-100

E L

E C

T R

IC

A

L O

V E

R A

L L P

L A

N

1" = 40'-0"

ELECTRICAL OVERALL PLAN1

E-100

PHASING NOTES:

THE FOLLOWING PHASING PLAN IS A GENERAL

SEQUENCING PLAN THAT IS NOT DEEMED TO BE FINAL.

THE CONTRACTOR AND THEIR SUBS MUST PREPARE

THEIR OWN OPERATIONS PLAN AND PHASING PLAN

VALIDATING AND CONFIRMING SEQUENCING AND

TIMELINES THAT WILL ALLOW THE WORK TO BE

COMPLETED IN A LIMITED AMOUNT OF TIME DURING

PLANNING OUTAGES. CONTRACTOR WILL BE

RESPONSIBLE TO PLAN AND COORDINATE WITH THE

CONTRACTING OFFICER, BASE CE, OG&E, AND ANY

OTHER PARTY AS NECESSARY TO ENSURE ALL WORK

IS ACCOMPLISHED IN A TIMELY FASHION AT A TIME

THAT WORKS FOR ALL PARTIES. PHASE NUMBER:

1. DISCONNECTING AND REMOVING EXISTING 480V

UNIT SUBSTATION, INCLUDING MV FEEDERS BACK

TO POWER SOURCE. DISCONNECTING ALL

EXISTING FEEDERS DISTRIBUTING POWER INTO

THE BUILDING AND BEING FED FROM THE EXISTING

UNIT SUBSTATION. RETAIN

CONDUCTORS/CONDUITS FOR RECONNECTION IN

NEW WORK. PROVIDE TEMPORARY POWER DURING

EQUIPMENT REPLACEMENT. PROVIDING,

INSTALLING AND CONNECTING NEW 480V

SWITCHGEAR (UID-1-SWGSEC-5) TO THE

SECONDARY SIDE OF NEWLY INSTALLED 1500KVA

OG&E TRANSFORMER. ALL POWER CONNECTIONS

TO THE SECONDARY SIDE OF THE TRANSFORMER

WILL BE COORDINATED WITH OG&E. CONTRACTOR

MUST ROUTE SECONDARY FEEDERS ABOVE

GROUND AND OVERHEAD TO CANOPY AND ALONG

THE SIDE OF THE BUILDING EXTERIOR WALL.

RECONNECTING ALL EXISTING DISTRIBUTION

FEEDERS TO NEW 480V SWITCHGEAR (UID-1-

SWGSEC-5). TEST AND ENSURE ALL EXISTING

LOADS RETURN TO ORIGINAL OPERATION.

2. DISCONNECTING AND REMOVING EXISTING 208V

UNIT SUBSTATION, INCLUDING MV FEEDERS BACK

TO PANEL SOURCE. DISCONNECTING ALL EXISTING

FEEDERS DISTRIBUTING POWER INTO THE

BUILDING AND BEING FED FROM THE EXISTING UNIT

SUBSTATION. RETAIN CONDUCTORS/CONDUITS

FOR RECONNECTION IN NEW WORK. PROVIDE

TEMPORARY POWER DURING EQUIPMENT

REPLACEMENT. PROVIDING AND INSTALLING

500KVA (480V-208V/120Y) STEP-DOWN

TRANSFORMER AND NEW 208V SWITCHGEAR (UID-

B-1-SWGSEC-3). CONNECTING TRANSFORMER TO

NEW 480V SWITCHGEAR (UID-1-SWGSEC-5) AND TO

NEW 208V SWITCHGEAR (UID-B-1-SWGSEC-3).

RECONNECTING EXISTING DISTRIBUTION FEEDERS

TO NEW 208V SWITCHGEAR. TEST AND ENSURE ALL

LOADS RETURN TO ORIGINAL OPERATION.

3. DISCONNECTING TWO (2) EXISTING 600A

PANELBOARDS , PANEL B-9 (UID #1-SWGSEC-2) AND

PANEL LPO (UID #1-FA-801), INCLUDING OUTDATED

SUB-FED PANELBOARD, PANEL B-13 (UID #1-PNL-11).

REMOVE CONDUCTORS BACK TO PANEL SOURCE.

RETAIN CONDUITS FOR RECONNECTION IN NEW

WORK. PROVIDING AND INSTALLING TWO (2) 600A

PANELBOARDS, PANEL B-9 (UID #1-SWGSEC-2) AND

PANEL LPO (UID #1-FA-801), INCLUDING PANEL B-13

(UID #1-PNL-11) AT THEIR ORIGINAL LOCATIONS.

RECONNECTING ALL EXISTING BRANCH CIRCUITS

TO NEW REPLACEMENT PANELBOARDS. PROVIDING

NEW CONDUCTORS FOR REPLACEMENT

PANELBOARDS AND ROUTED VIA EXISTING

CONDUITS. TEST AND ENSURE ALL NEW AND

EXISTING EQUIPMENT OPERATE PROPERLY.

4. DISCONNECTING AND REMOVING THE EXISTING

30KVA STEP-UP TRANSFORMER (UID #1XFMR-2).

THE STEP-UP TRANSFORMER IS CURRENTLY

FEEDING EXISTING 60A/480V DISCONNECT SWITCH

FOR ELEVATOR. REMOVE CONDUCTORS AND

CONDUITS BACK TO PANEL, PANEL B-9 (UID #1-

SWGSEC-2). RE-FEED EXISTING 60A DISCONNECT

SWITCH (480V) FROM ELEVATOR MACHINE ROOM

AND CONNECT TO NEW 480V SWITCHGEAR (UID-1-

SWGSEC-5). TEST AND ENSURE THE ELEVATOR

MACHINE RETURNS TO ORIGINAL OPERATION.

J

J

J

J

J

J

J

J

J

J

J

J

COMM

MECH

MEN'S

1-PNL-33

RAMP

CHILLER ON

MEZZANINE

DOCK

DOCK

4 5

ELECT

OFFICE

A

ELEVATOR

M E

C H

ELEC

OFFICE

STORAGE

7 8 9 10 11 12 13 14 15 16 17 18

J

K

L

M

E-501

E-501

F R

O N

T

B A

C K

F R

O N

T

B A

C K

EXISTING OG&E XFMR

RE: E-601.

3' - 0"

3' - 0"

208V-ROCP-1

480V-ROCP-2

480V-ROCP-1

/2

12' - 1 1/4"

4' - 10"

4'

/8

12' - 1 1/4"

9'

/8

3'

0"

UNISTRUT RACK-MOUNTED

EQUIPMENT

CONCRETE FOUNDATION,

REFER TO STRUCTURAL

DETAIL.

CONCRETE FOUNDATION,

REFER TO STRUCTURAL

DETAIL.

4' - 0"

ROUTE SECONDARY

UNDERGROUND SERVICE TO

EXTERIOR WALL-MOUNTED

PULL-BOX.

ROUTE SECONDARY ELECTRICAL

SERVICE OVERHEAD. 7 SETS OF 4"C.

SEE ONE-LINE E-601.

CONDUITS ROUTING ON SURFACE OF

EXTERIOR BUILDING WALL. SEE

TINKER AFB ELECTRICAL STANDARD

FOR ADDITIONAL REQUIREMENTS.

4 5

I

1A 2

EXISTING 60A

ELEVATOR

D/S

4 5

P

T

IN

K E

R A

IR

F

O R

C E

B A

S E

O

K L A

H O

M A

P R

O J E

C T

I N

F O

R M

A T

IO

N

D E

S

IG

N F

IL

E

L O

C A

T

IO

N

R E

V

IS

IO

N

S

M A

R K

D E

S

IG

N G

R O

U P

D R

A W

N B

Y

C H

E C

K E

D B

Y

D E

S

IG

N E

D B

Y

D A

T E

D E

S C

R

IP

T

IO

N

1 2 3 4 5

E

D

C

B

A

M A

N A

G E

M E

N T

I N

F O

R M

A T

IO

N

1 2 3 4 5

E

D

C

B

A

IS

S

U E

D A

T E

SHEET NUMBER

S H

E E

T T

IT

L E

AIR FORCE MATERIEL COMMAND

72 ABW CIVIL ENGINEER DIRECTORATE

TINKER AFB, OK

W W

Y K

R E

P L A

C E

S W

IT

C

H G

E A

R

B L

D G

KEY PLAN

/1

/2

H D

R B

E S

K L E

G C

O R

N E

L L

G J A

G L O

W S

K I

E-401

E L E

C T

R

IC

A L

E N

L A

R G

E D

P L A

N S

N E

W W

O R

K

1/8" = 1'-0" E-100

ELECTRICAL PLAN - ENLARGED DOCK4

1/8" = 1'-0" E-100

ELECTRICAL PLAN - ENLARGED ELECTRICAL CLOSET2

1/8" = 1'-0" E-100

ELECTRICAL PLAN - ENLARGED ELEVATOR ROOM1

GENERAL NOTES:

1. REFER TO E-601 FOR NEW WORK ONE-LINE

DIAGRAM FOR ADDITIONAL INFORMATION.

2. ALL NEW WORK MUST BE DONE IN PHASES

COORDINATED WITH THE FACILITY USER GROUP.

REFER TO E-100 FOR PHASING PLAN DETAILS.

3. COORDINATE PLACEMENT OF ELECTRICAL

EQUIPMENT WITH OTHER DISCIPLINES PRIOR TO

ROUGH-IN.

KEYED NOTES:

PROVIDE NEW 480V SWITCHGEAR ENCLOSURE.

RECONNECT EXISTING FEEDER-TO-REMAIN AND

LINE UP WITH THE SWITCHGEAR DISTRIBUTION

SECTION AS REQUIRED FOR RECONNECTION.

PROVIDE 480V-208Y/120V TRANSFORMER AND

MAKE CONNECTION TO 480V SWITCHGEAR AFTER

EQUIPMENT RUNNING.

PROVIDE 208V SWITCHGEAR ENCLOSURE AND

MAKE CONNECTION TO 500KVA TRANSFORMER

AFTER EQUIPMENT IS RUNNING. RECONNECT

EXISTING FEEDER-TO-REMAIN AND LINE UP WITH

THE SWITCHGEAR DISTRIBUTION SECTION AS

REQUIRED FOR RECONNECTION.

PROVIDE REMOTE OPERATIONAL BREAKER

ENCLOSURE FOR 480V AND 208V BREAKERS

HOUSED IN SWITCHGEAR ENCLOSURES.

COORDINATE WITH MANUFACTURER FOR EXACT

SIZE AND DIMENSION AND ADDITIONAL

REQUIREMENTS SUCH AS CLEARANCES AND

INSTALLATIONS. REFER TO SHEET E-501 FOR

REMOTE OPERATIONAL BREAKER ENCLOSURE

ELEVATIONS.

EXISTING 1500KVA OG&E 480V TRANSFORMER TO

FEED NEW 480V SWITCHGEAR ENCLOSURE TO

REMAIN.

CONNECT EXISTING ELEVATOR…