00 80 05.pdf

PDF 10 KB Posted

Attached to
TINKER AFB MAC BOA WWYK200051 Replace Switchgear, Bldg 1
Solicitation number
FA813726R0025
Issued by

About this file

This is a Special Provisions section of the Tinker General Requirements document for contractors performing work on or near the active airfield at Tinker Air Force Base.

The document establishes mandatory procedures and safety requirements for airfield operations. Runway and taxiway closures require written requests submitted to the Contracting Officer at least 45 calendar days in advance, including the location, requested date, estimated duration, detailed work description, required equipment, and personnel estimates. Base Operations coordinates closure scheduling, and contractors must be ready to commence work on the approved date without expectation of schedule extensions. Contractors are responsible for providing all personnel with ear plugs and/or ear muffs to protect against high-level noise from jet aircraft, in addition to all OSHA-required safety equipment. All work sites must remain clean with no Foreign Object Debris (FOD), and no unescorted contractor vehicles, equipment, or personnel may cross active runways or taxiways without clearance from the control tower. Vehicles operating on landing areas (first 1,000 feet of runway) must display approved low-intensity amber flashing lights. Temporary structures or equipment exceeding 12 feet within 1,000 feet of a runway or 50 feet elsewhere require written approval submitted 21 calendar days prior to use. Contractors must maintain on-site cleaning equipment and may be required to inspect entire runway and taxiway lengths with Government representatives to verify removal of all personnel, debris, materials, equipment, and tools. On the first workday, contractors must identify a designated evacuation area with Contracting Officer and Base Operations representatives for use during aircraft emergencies.

View the file

Other files

File Type Posted
Solicitation Amendment FA813726R00250005 SF 30.pdf PDF
WWYK160073 REPAIR FIRE RISER AS-RECORDED 3.18.24.pdf PDF
Solicitation Amendment FA813726R00250004 SF 30.pdf PDF
PreBid Govt Revised Response for WWYK200051 Replace Switchgear Bldg 1 ( 06.22.2026).pdf PDF
Att1_200051_SWITCHGEAR_IFC_REV_1_6-17-26_DRAWINGS.pdf PDF
Att2_200051_IFC Rev1_Design_Analysis.pdf PDF
WWYK200051_SWITCHGEAR_IFC_DRAWINGS.pdf PDF
Solicitation Amendment FA813726R00250003 SF 30.pdf PDF
Pre-Bid RFIs Govt Response for WWYK200051 Replace Switchgear Bldg 1 (06.08.2026).pdf PDF
Pre-Bid RFI Govt Response Att1_Inspection Report - WWYK090044F.pdf PDF
Solicitation Amendment FA813726R00250002 SF 30.pdf PDF
Pre-Bid RFI Govt Response Att2_Pictures for Electrical Closet.pdf PDF
WWYK200051_TAFB IFC_FINAL_SPECIFICATIONS.pdf PDF
841018.pdf PDF
830009.pdf PDF
WWYK200051_SWITCHGEAR_IFC_CAD (2).zip ZIP file
B-1MEP.pdf PDF
950213.pdf PDF
710216.pdf PDF
870148.pdf PDF
Solicitation Amendment FA813726R00250001 SF 30.pdf PDF
Bldg 1 - Electrical.pdf PDF
770142.pdf PDF
730072.pdf PDF
00 80 00.pdf PDF
01 45 00.00 10.pdf PDF
01 33 00.pdf PDF
01 33 16.00 10.pdf PDF
01 42 00.pdf PDF
01 50 00.pdf PDF
00 70 00.pdf PDF
00 72 00.pdf PDF
01 78 23.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
00 71 00.pdf PDF
01 32 16.00 20.pdf PDF
01 78 00.pdf PDF
WWYK200051 Initial Site Visit Sign In Sheet.pdf PDF
STATEMENT OF WORK (SOW).pdf PDF
DRAWINGS.pdf PDF
Submittal Register.pdf PDF
Solicitation FA813726R0025_WWYK200051_Replace_Switchgear .pdf PDF
Section L - Instructions to Offerors.pdf PDF
WWYK200051 WAGE Determinations.pdf PDF
WWYK200051 Initial Site Visit Location.pdf PDF
EAL List.xlsx XLSX spreadsheet
Section M - Evaluation Factors for Award.pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tinker AFB Tinker General Requirements

SECTION 00 80 05

SPECIAL PROVISIONS FOR WORKING ON OR NEAR THE AIRFIELD ON TINKER AFB

PART 1 GENERAL

The following provisions shall apply when work is required to take place on the active airfield, within the clear zones, or in the primary surfaces as defined by Unified Facilities Criteria 3- 260-1, Airfield and Heliport Planning and Design.

1.1 CLOSURES

a. All runway and taxiway closures require coordination and scheduling with Base Operations. Written requests for closures shall be submitted to the Contracting Officer no less than 45 calendar days prior to the requested date of closure. The request shall include:

1. The nomenclature of the runway/taxiway to be closed

2. The area of the runway/taxiway where the work is to take place

3. The requested date of closure

4. The estimated duration of closure

5. A detailed description of the work to be performed

6. A list of the equipment required to perform the work

7. An estimate of the personnel required to perform the work

b. The Contracting Officer shall coordinate with Base Ops to close the requested runway/taxiway on or as close as possible to the date requested and for the length of time requested. The Contracting Officer shall notify the contractor, in writing, of the date and length of time approved for closure.

c. It is the responsibility of the contractor to have the necessary personnel, materials, and equipment ready to start work on the approved date of closure and to complete the work in the time requested. Under most circumstances, Base Operations will be unable to adjust flight and runway/taxiway utilization schedules to accommodate extensions to closures.

d. The contractor shall notify the Contracting Officer, in writing, when the work on the closed runway/taxiway is complete.

1.2 SAFETY

1.2.1 Personnel

The contractor shall provide all of his personnel ear plugs and/or ear muffs to prevent injury to their auditory systems while working on the Airfield. Jet aircraft operating on the runways, taxiways, and aprons make these areas zones of high-level noise. The government will not be held liable for auditory system damage due to non or improper use of noise protection equipment.

This requirement is in addition to the contractor providing his personnel with safety equipment required by OSHA for the work to be performed.

January 2022 Page 1 Section 00 80 05

1.2.2 Aircraft

The contractor shall maintain a clean work site and shall implement all measures necessary to insure that material and equipment do not interfere with or damage aircraft operating or parked in areas of the airfield that are not closed. NO FOD.

1.3 ACCESS RESTRICTIONS

No unescorted contractor vehicles, equipment, or personnel shall be on or cross any active runway or taxiway unless clearance is requested from, and granted by, the control tower. All contractor vehicles and mechanized equipment operating on the landing areas (the first 1,000 feet from either end of the runway) will be identified by approved, mounted, low intensity, amber flashing lights. When contractor operations require repeated vehicle or personnel crossing of an active runway, taxiway, or other controlled area, a two-way radio, furnished by the Government, will be used to maintain contact with the control tower. Use of the radio for other purposes will be strictly prohibited. The radio will be returned to the Government at the end of each workday, and will be reacquired as necessary.

1.4 HEIGHT RESTRICTIONS

The construction of any temporary structure or the use of any equipment that extends more than 12 feet above the ground within 1000 feet of a runway or that extends 50 feet above the ground elsewhere on Tinker AFB shall be approved by the Government prior to installation or use. Written request for approval shall be submitted to the Contracting Officer no later than 21 calendar days prior to the date needed.

1.5 CLEANLINESS

The contractor shall maintain the cleanliness of his work site and all traversed runways, taxiways, aprons, and ramps at all times. He shall utilize methods and equipment to prevent spilling or dropping materials in these areas and shall utilize whatever method or equipment necessary to insure the removal of loose materials from these areas. The contractor shall remove all material and equipment to his staging area at the end of each work day. No material is to be stockpiled nor equipment stored within 1000 feet of the centerline of a runway.

1.6 EMERGENCIES

1.6.1 Evacuation Area

On the first day of work on the airfield, the contractor, a representative of the Contracting Officer, and a representative of Base Ops shall identify an area a safe distance from the runway where the contractor is to move his personnel and equipment during an aircraft emergency.

1.6.2 Evacuation

During an aircraft emergency, the contractor shall vacate the work site.

He shall move all personnel and equipment to the designated evacuation area. Evacuation orders will be given on short notice and will require expeditious action by the contractor.

January 2022 Page 2 Section 00 80 05

1.7 INSPECTION AND CLEANING

The contractor shall maintain, on site and in good working order, equipment capable of cleaning loose materials from the runway, taxiway, ramp, or apron. The contractor, accompanied by a Government representative, may be required to inspect the entire length of the runway and taxiway to insure that all personnel, debris, material, equipment, and tools have been removed from these areas.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --