Att12_230052_Submittal Register_r1.xlsx
XLSX spreadsheet 36 KB Posted
- Solicitation number
- FA813725R0033
About this file
The file is a Submittal Register for a Federal contract (Contract No. WWYK230052) at Tinker Air Force Base to replace a vault and fuel tank in Building 1032. The project requires removing existing concrete vault, fuel tank, underground fuel lines, conduit, and vent piping, and installing 4 new fuel tanks with associated accessories and fill stations. The contract is specifically for MAC BOA (Multiple Award Contract, Basis of Award) holders, and contractors must be licensed underground storage tank installers/removers with the Oklahoma Corporation Commission.
The detailed submittal register outlines over 200 specific submittal requirements across multiple specification sections, including preconstruction submittals (such as health and safety plans, entry access lists, and construction phasing plans), product data, certificates, test reports, shop drawings, and closeout documents. Key submission timelines include providing initial documents within 10 days of Notice to Proceed, monthly reporting, and specific documentation requirements for safety, environmental compliance, training, and equipment installation. The solicitation requires an mandatory initial site visit on 22 May 2025 from 9:00-10:00 AM, with RSVPs due by 19 May 2025 at 2:00 PM CT.
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal Register_General Requ
| TITLE: | Tinker AFB General Requirements Specification (Div 00-01) | SUBMITTAL REGISTER | ||||||||||||||||
| JOB NAME: | Replace Cault and Fuel Tank | |||||||||||||||||
| LOCATION: | B1032 | |||||||||||||||||
| CONTRACT NO: | WWYK230052 | |||||||||||||||||
| CONTRACTOR: | ||||||||||||||||||
| CONTRACTOR SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | ||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) |
| Line | Activity # | Transmittal # | Specification Section | SD # | Submittal Description | Item Submitted | Paragraph # | Classification: GOVT or A/E Reviewer | Submit | Approval Needed By | Material Needed By | Action Code | Date Of Action | Date FWD to APPR / Auth Date RCD From CONTR | Date FWD To Other Revwr | Date RCD From Other Reviewer | Action Code | Date Of Action | Mailed To CONTR/ Date RCD From APPR Authority | Remarks | |
| 1 | 00 70 00 | 01 | Preconstruction Submittals | Entry Access List | 1.6 | G | |||||||||||||||
| 2 | 00 70 00 | 01 | Preconstruction Submittals | Key Issue Receipt | 1.3.12.1 | ||||||||||||||||
| 3 | 00 70 00 | 06 | Test Reports | Pre-Construction Testing Record | 1.3.11 | G | |||||||||||||||
| 4 | 00 70 00 | 07 | Certificates | Welding, Cutting and Brazing Permit | 1.4 | G | |||||||||||||||
| 5 | 00 70 00 | 07 | Certificates | Framed Instructions | 1.8 | ||||||||||||||||
| 6 | 00 70 00 | 11 | Closeout Submittals | Key Return Receipt | 1.3.12.1 | ||||||||||||||||
| 7 | 00 71 00 | 01 | Preconstruction Submittals | Health and Safety Plan | 1.3 | G | |||||||||||||||
| 8 | 00 71 00 | 01 | Preconstruction Submittals | Internal Combustion Engines Plan | 1.3.5 | G | |||||||||||||||
| 9 | 00 71 00 | 01 | Preconstruction Submittals | Entry Authority List | 1.5.2 | ||||||||||||||||
| 10 | 00 71 00 | 01 | Preconstruction Submittals | Vehicle Entry Authority List | 1.5.2 | G | |||||||||||||||
| 11 | 00 71 00 | 01 | Preconstruction Submittals | Equipment and Material Storage | 1.5 | G | |||||||||||||||
| 12 | 00 71 00 | 01 | Preconstruction Submittals | Contractor Offices and Plants | 1.5 | G | |||||||||||||||
| 13 | 00 71 00 | 01 | Preconstruction Submittals | Designated Waste and Disposal Areas | 1.5 | G | |||||||||||||||
| 14 | 00 71 00 | 01 | Preconstruction Submittals | Construction Phasing Plan | 1.5 | G | |||||||||||||||
| 15 | 00 71 00 | 01 | Preconstruction Submittals | Airfield Construction Waiver | 1.5 | G | Must be turned in by the 5th day of the month to make that month Waiver Package. Provide editable form to the CO to be forwarded to Community Planning. Allow 45 days for processing. | ||||||||||||||
| 16 | 00 71 00 | 01 | Preconstruction Submittals | FAA Form 7460-1 | 1.5.3 | G | |||||||||||||||
| 17 | 00 71 00 | 07 | Certificates | Safety Meetings | 1.3 | ||||||||||||||||
| 18 | 00 71 00 | 07 | Certificates | FOD Awareness and Prevention Training | 1.4 | ||||||||||||||||
| 19 | 00 72 00 | 01 | Preconstruction Submittals | Restoration Plan | 1.3.2 | G | |||||||||||||||
| 20 | 00 72 00 | 01 | Preconstruction Submittals | Storm Water Pollution Prevention Plan | 1.3.3.2 | G | |||||||||||||||
| 21 | 00 72 00 | 01 | Preconstruction Submittals | Water System Construction Permit | 1.3.3.6 | G | |||||||||||||||
| 22 | 00 72 00 | 01 | Preconstruction Submittals | AF Form 3952 Chemical/Hazardous Material Request/Authorization | 1.4 | G | |||||||||||||||
| 23 | 00 72 00 | 01 | Preconstruction Submittals | Spray Painting Plan | 1.9 | G | |||||||||||||||
| 24 | 00 72 00 | 01 | Preconstruction Submittals | Environmental Management System Awareness Training | 1.1 | ||||||||||||||||
| 25 | 00 72 00 | 03 | Product Data | New Boiler Information Form | 1.3.8.2 | G | |||||||||||||||
| 26 | 00 72 00 | 03 | Product Data | Affirmative Procurement Documentation or Green Statement | 1.3.10 | G | Provide only one. Reference specification for additional information | ||||||||||||||
| 27 | 00 72 00 | 06 | Test Reports | AF Form 487 Generator Operating Log (Inspection and Testing) | 1.3.8.1 | G | |||||||||||||||
| 28 | 00 72 00 | 07 | Cerificates | Fire Ant Federal Compliance Agreement or state phyto-sanitary certificate | 1.3.4.1 | ||||||||||||||||
| 29 | 00 72 00 | 07 | Cerificates | Monthly Hazardous Material Usage Report | 1.4 | G | Provide 1st week of each month during construction | ||||||||||||||
| 30 | 00 72 00 | 07 | Cerificates | Refrigerant Technical Certifications | 1.5 | G | |||||||||||||||
| 31 | 00 72 00 | 07 | Cerificates | Refrigerant Installation | 1.5 | G | |||||||||||||||
| 32 | 00 72 00 | 08 | Manufacturer's Instructions | Safety Data Sheets/Material Safety Data Sheets | 1.4 | ||||||||||||||||
| 33 | 00 72 00 | 11 | Closeout Submittals | Notice of Termination | |||||||||||||||||
| (ODEQ Form 640-572) | 1.3.3.2 | G | |||||||||||||||||||
| 34 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Documentation of Training/ Experience | C.2 |
C.13 35 00 72 00 - Attch 2 01 Preconstruction Submittals Employee Physicals C.2 C.13
| 36 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Regulatory Agency Notification | C.3 | ||
| 37 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Security Documentation | C.4 | ||
| 38 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Communications | C.5 | ||
| 39 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Step-by-Step Abatement Procedures | C.6 | G | |
| 40 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Glovebag Procedures | C.7 | G | |
| 41 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Negative Pressure Enclosure Construction Procedures | C.8 | G | |
| 42 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Respirator Protection Program | C.9 | ||
| 43 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Encapsulation Procedures | C.11 | G | |
| 44 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Landfill Qualifications | C.14 | ||
| 45 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Work Schedule | C.16 | ||
| 46 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Emergency Plans and Fire Prevention Plans | C.17 | G | |
| 47 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Written Hazardous Communication Program | C.18 | ||
| 48 | 00 72 00 - Attch 2 | 01 | Preconstruction Submittals | Rental Equipment | C.19 | ||
| 49 | 00 72 00 - Attch 2 | 07 | Cerificates | Manufacturer’s Certifications | C.10 | ||
| 50 | 00 72 00 - Attch 2 | 07 | Cerificates | Laboratory and Monitoring Qualifications/Certifications | C.12 | ||
| 51 | 00 72 00 - Attch 2 | 07 | Cerificates | Asbestos Waste Transporter Certification of Insurance | C.13 | ||
| 52 | 00 72 00 - Attch 2 | 08 | Manufacturer's Instructions | Safety Data Sheets/Material Safety Data Sheets | C.15 | ||
| 53 | 00 72 00 - Attch 2 | 11 | Closeout Submittals | Waste Disposal Receipt | M.1(1) | G | |
| 54 | 00 72 00 - Attch 2 | 11 | Closeout Submittals | Air Sampling Results | M.1(2) | G | |
| 55 | 00 72 00 - Attch 3 | 01 | Preconstruction Submittals | Documentation of Training/ Experience | C.1 | ||
| 56 | 00 72 00 - Attch 3 | 01 | Preconstruction Submittals | Employee Physicals | C.2 | ||
| 57 | 00 72 00 - Attch 3 | 01 | Preconstruction Submittals | Security Documentation | C.3 | ||
| 58 | 00 72 00 - Attch 3 | 01 | Preconstruction Submittals | Step-by-Step Abatement Procedures Plan | C.4 | G | |
| 59 | 00 72 00 - Attch 3 | 01 | Preconstruction Submittals | Full Containment Construction Procedures/Drawings | C.5 | G | |
| 60 | 00 72 00 - Attch 3 | 01 | Preconstruction Submittals | Respirator Protection Program | C.6 | ||
| 61 | 00 72 00 - Attch 3 | 01 | Preconstruction Submittals | Work Schedule | C.11 | G | |
| 62 | 00 72 00 - Attch 3 | 03 | Product Data | Materials List | C.10 | ||
| 63 | 00 72 00 - Attch 3 | 07 | Cerificates | Manufacturer’s Certifications | C.7 | ||
| 64 | 00 72 00 - Attch 3 | 07 | Cerificates | Laboratory and Monitoring Qualifications | C.8 | ||
| 65 | 00 72 00 - Attch 3 | 07 | Cerificates | Lead Based Paint Waste Transporter’s Qualifications | C.9 | ||
| 66 | 00 72 00 - Attch 3 | 11 | Closeout Submittals | Waste Disposal Receipt | M.1.1 | G | |
| 67 | 00 72 00 - Attch 3 | 11 | Closeout Submittals | Air Sampling Results | M.1.2 | G | |
| 68 | 00 72 00 - Attch 3 | 11 | Closeout Submittals | Verification of Decontamination of Rental Equipment | M.1.3 | ||
| 69 | 00 72 00 - Attch 3a | 01 | Preconstruction Submittals | Removal Procedures | B.1 | G | |
| 70 | 00 72 00 - Attch 3a | 03 | Product Data | List of Material | B.2 | ||
| 71 | 00 72 00 - Attch 3a | 08 | Manufacturer's Instructions | Material Data Sheets | B.3 | ||
| 72 | 00 72 00 - Attch 5 | 01 | Preconstruction Submittals | Construction Debris Analysis Plan | 1.2.3 | G | |
| 73 | 00 72 00 - Attch 5 | 07 | Certificates | Monthly Debris Management Report | 2 | G | Provide 1st week of each month during construction |
| 74 | 00 72 00 - Attch 11 | 01 | Preconstruction Submittals | Tree Planting/Removal Permit | 1.1 | G | |
| 75 | 00 72 00 - Attch 11 | 01 | Preconstruction Submittals | Tree Protection Plan | 2.1 | G | |
| 76 | 01 32 16.00 20 | 01 | Preconstruction Submittals | Baseline Construction Schedule | 1.2 | G | Provide within 10 days of NTP. |
| 77 | 01 32 16.00 20 | 01 | Preconstruction Submittals | Baseline Design Schedule | 1.2 | G | Provide within 10 days of NTP. |
| 78 | 01 32 16.00 20 | 07 | Certificates | Monthly Updates | 1.4 | Provide 1st week of each month during construction, or as directed by CO | |
| 79 | 01 32 16.00 20 | 07 | Certificates | 3-Week Look Ahead Schedule | 1.6 | Provide weekly with the Contract Progress Report | |
| 80 | 01 33 00 | 01 | Preconstruction Submittals | Submittal Register | 1.8 | G | |
| 81 | 01 33 16.00 10 | 01 | Preconstruction Submittals | Design Quality Control Plan | 1.5.1 | G | |
| 82 | 01 33 16.00 10 | 01 | Preconstruction Submittals | Initial Design Conference | 1.5.2.2 | ||
| 83 | 01 33 16.00 10 | 01 | Preconstruction Submittals | Preconstruction Conference | 1.5.2.3 | ||
| 84 | 01 33 16.00 10 | 01 | Preconstruction Submittals | DCM Procedures | 3.5.1 | G | |
| 85 | 01 33 16.00 10 | 01 | Preconstruction Submittals | Submittal Register | 3.8.4 | G | |
| 86 | 01 33 16.00 10 | 05 | Design Data | Design and Code Checklists | 1.7.1 | C | |
| 87 | 01 33 16.00 10 | 05 | Design Data | Interim Design Submittals | 3.2.1 | R | |
| 88 | 01 33 16.00 10 | 05 | Design Data | Interior And Exterior Building Finishes Scheme | 3.6.5.1.1 | G | |
| 89 | 01 33 16.00 10 | 05 | Design Data | Conference Documentation | 3.7.3 | ||
| 90 | 01 33 16.00 10 | 05 | Design Data | Final Design Submittals | 3.8 | R | |
| 91 | 01 33 16.00 10 | 05 | Design Data | Design Complete Documents | 3.9 | C | |
| 92 | 01 33 16.00 10 | 11 | Closeout Submittals | DD Form 1354 | 3.8.5 | A | |
| 93 | 01 45 00.00 10 | 01 | Preconstruction Submittals | Quality Control (QC) Plan | 3.2 | G | |
| 94 | 01 45 00.00 10 | 01 | Preconstruction Submittals | Additional Requirements for Design Quality Control (DQC) Plan | 3.2.2 | G | |
| 95 | 01 45 00.00 10 | 05 | Design Data | Discipline-Specific Checklists | 3.2.2 | ||
| 96 | 01 45 00.00 10 | 05 | Design Data | Design Quality Control | 3.9.1 | ||
| 97 | 01 45 00.00 10 | 06 | Test Reports | QC Documentation | 3.9 | Provide weekly with the Contract Progress Report | |
| 98 | 01 50 00 | 01 | Preconstruction Submittals | Request for Contractor Staging Area | 1.1 | G | |
| 99 | 01 50 00 | 01 | Preconstruction Submittals | Photographic Record | 1.3 | ||
| 100 | 01 78 00 | 03 | Product Data | Warranty Letter | 1.7.1 | ||
| 101 | 01 78 00 | 03 | Product Data | Warranty Tags | 1.7.3 | ||
| 102 | 01 78 00 | 03 | Product Data | Spare Parts Data | 1.5 | ||
| 103 | 01 78 00 | 08 | Manufacturer's Instructions | Instructions | 1.7.1 | ||
| 104 | 01 78 00 | 10 | Operation and Maintenance Data | Operation and Maintenance Manuals | 3.4 | G | Provide (2) electronic sets (optical media) and (1) hard copy |
| 105 | 01 78 00 | 11 | Closeout Submittals | Working As-Built Drawings | 3.1 | G | Provide (2) electronic sets (optical media) and (2) hard copies |
| 106 | 01 78 00 | 11 | Closeout Submittals | Record Drawings | 3.3 | G | Provide (2) electronic sets (optical media) and (1) hard copy |
| 107 | 01 78 00 | 11 | Closeout Submittals | Certification of EPA Designated Items | 2.3 | G | |
| 108 | 01 78 00 | 11 | Closeout Submittals | Certification Of USDA Designated Items | 2.4 | G | |
| 109 | 01 78 00 | 11 | Closeout Submittals | DD FORM 1354 | 3.6 | G | |
| 110 | 01 78 00 | 11 | Closeout Submittals | Checklist for DD FORM 1354 | 3.6 | G | |
| 111 | 01 78 23 | 10 | Operation and Maintenance Data | Operation and Maintenance Data | 1.2 | G | Provide 30 days prior to scheduled Training |
| 112 | 01 78 23 | 10 | Operation and Maintenance Data | O&M Database | 1.3 | G | |
| 113 | 01 78 23 | 10 | Operation and Maintenance Data | Training Plan | 3.1.1 | G | Provide 30 days prior to scheduled Final Inspection |
| 114 | 01 78 23 | 10 | Operation and Maintenance Data | Training Content | 3.1.2 | G | Provide 14 days prior to scheduled Training |
| 115 | 01 78 23 | 10 | Operation and Maintenance Data | Training Outline | 3.1.3 | G | Provide 14 days prior to scheduled Training |
| 116 | 01 78 23 | 11 | Closeout Submittals | Training Video Recording | 3.1.4 | G | |
| 117 | 01 78 23 | 11 | Closeout Submittals | Validation of Training Completion | 3.1.6 | G | |
| 118 | SOW | 07 | Certificates | Contract Progress Report(s) | 2.4 | G | Provide weekly throughout life of contract. Utilize AF Form 3065, Contract Progress Report (or equal) |
| 119 | SOW | 01 | Preconstruction Submittals | B3001 Visitor Badge Issue Receipt | 1.3.7 | ||
| 120 | SOW | 11 | Closeout Submittals | B3001 Visitor Badge Return Receipt | 1.3.7 | ||
| 121 | 03 20 00.00 10 | 06 | Preconstruction Submittals | Test Reports | 2.8 | G | |
| 122 | 03 20 00.00 10 | 07 | Preconstruction Submittals | Steel Certificates | 1.4.2 | G | |
| 123 | 03 30 00 | 01 | Preconstruction Submittal | Quality Control Plan | G | ||
| 124 | 03 30 00 | 02 | Shop Drawings | Reinforcing Steel | 1.6.2.2 | G | |
| 125 | 03 30 00 | 03 | Product Data | Joint Sealants / Filler | G | ||
| 126 | 03 30 00 | 03 | Product Data | Concrete Curing | 2.4.1 | G | |
| 127 | 03 30 00 | 04 | Samples | Slab / Surface Samples (pictures) | 1.6.5.1 | G | |
| 128 | 03 30 00 | 05 | Design Data | Concrete Mix Design | 1.6.1.2 | G | |
| 129 | 03 30 00 | 06 | Test Reports | Compressive Strength Tests | 1.6.4 | G | |
| 130 | 03 30 00 | 06 | Field Test Reports | Slum / Air Content / water | 1.6.4 | G | |
| 132 | 03 30 00 | 07 | Mill Certificates | Reinforcing Steel | 2.6.1.d | G | |
| 133 | 03 30 00 | 03 | Product Data | Epoxy Anchorage System | G | ||
| 134 | 33 52 10 | 2 | Shop Drawings | Grounding and Bonding | 2.1.2 | ||
| 135 | 33 52 10 | 2 | Shop Drawings | Pipe Supports | 2.5.9 | ||
| 136 | 33 52 10 | 3 | Product Data | Insulating Flange Kits | 2.3.2 | G | |
| 137 | 33 52 10 | 3 | Product Data | Fuel Piping Flange Bolts, Nuts, and Washers | 2.3.4 | G | |
| 138 | 33 52 10 | 3 | Product Data | Stainless Steel Pipe | 2.4.2 | G | |
| 139 | 33 52 10 | 3 | Product Data | Flexible Connector | 2.5.5 | G | |
| 140 | 33 52 10 | 3 | Product Data | Pressure Gauge | 2.5.8 | G | |
| 141 | 33 52 10 | 3 | Product Data | Ball Valves | 2.6.1 | G | |
| 142 | 33 52 10 | 3 | Product Data | Swing Type Check Valves | 2.6.3 | G | |
| 143 | 33 52 10 | 3 | Product Data | Wafer Type Check Valve | 2.6.4 | G | |
| 144 | 33 52 10 | 3 | Product Data | Globe Valve | 2.6.5 | G | |
| 145 | 33 52 10 | 3 | Product Data | Thermal Relief Valve | 2.6.5 | G | |
| 146 | 33 52 10 | 3 | Product Data | Foot Valve | 2.6.8 | G | |
| 147 | 33 52 10 | 3 | Product Data | Tank Overfill Prevention Valve (Gravity Fill) | 2.6.9 | G | |
| 148 | 33 52 10 | 3 | Product Data | Tank Overfill Prevention Valve (Pumped Fuel Receipt) | 2.6.10 | G | |
| 149 | 33 52 10 | 3 | Product Data | Anti-Siphon Valves | 2.6.11 | G | |
| 150 | 33 52 10 | 6 | Test Reports | Preliminary Pneumatic Test | 3.3.2.2 | ||
| 151 | 33 52 10 | 6 | Test Reports | Final Pneumatic Test | 3.3.2.3 | ||
| 152 | 33 52 10 | 6 | Test Reports | Hydrostatic Test | 3.3.2.4 | ||
| 153 | 33 52 10 | 7 | Certificates | Contractor Qualifications | 1.4.1 | G | |
| 154 | 33 52 10 | 7 | Certificates | Licensed Personnel | 1.4.2.1 | ||
| 155 | 33 52 10 | 7 | Certificates | Demonstrations | 3.5 | ||
| 156 | 33 52 10 | 10 | Operation and Maintenance Data | Insulating Flange Kits | 2.3.2 | G | |
| 157 | 33 52 10 | 10 | Operation and Maintenance Data | Ball Valves | 2.6.1 | G | |
| 158 | 33 52 10 | 10 | Operation and Maintenance Data | Swing Type Check Valves | 2.6.3 | G | |
| 159 | 33 52 10 | 10 | Operation and Maintenance Data | Wafer Type Check Valve | 2.6.4 | G | |
| 160 | 33 52 10 | 10 | Operation and Maintenance Data | Thermal Relief Valve | 2.6.6 | G | |
| 161 | 33 52 10 | 10 | Operation and Maintenance Data | Foot Valve | 2.6.8 | G | |
| 162 | 33 52 10 | 10 | Operation and Maintenance Data | Tank Overfill Prevention Valve (Gravity Fill) | 2.6.9 | G | |
| 163 | 33 52 10 | 10 | Operation and Maintenance Data | Tank Overfill Prevention Valve (Pumped Fuel Receipt) | 2.6.10 | G | |
| 164 | 33 52 10 | 10 | Operation and Maintenance Data | Anti-Siphon Valves | 2.6.11 | G | |
| 165 | 33 52 23.15 | 1 | Preconstruction Submittals | Welding Procedure Specifications (WPS) | 1.6.2 | G | |
| 166 | 33 52 23.15 | 1 | Preconstruction Submittals | Welder Performance Qualification (WPQ) | 1.6.2 | G | |
| 167 | 33 52 23.15 | 1 | Preconstruction Submittals | Procedure Qualification Record (PQR) | 1.6.2 | G | |
| 168 | 33 52 23.15 | 1 | Preconstruction Submittals | Welding Operations | 1.6.1 | G | |
| 169 | 33 52 23.15 | 2 | Shop Drawings | POL Service Piping | 1.6.2 | G | |
| 170 | 33 52 23.15 | 6 | Test Reports | Examinations, Inspections and Tests | 3.2 | ||
| 171 | 33 52 23.15 | 7 | Certificates | Qualifications | 1.6 | G | |
| 172 | 33 56 10 | 2 | Shop Drawings | Grounding and Bonding | 2.1.1 | ||
| 173 | 33 56 10 | 3 | Product Data | Aboveground Storage Tank (Double Wall Steel) | 2.4.2 | G | |
| 174 | 33 56 10 | 3 | Product Data | Tank Protective Coatings | 2.6 | G | |
| 175 | 33 56 10 | 3 | Product Data | Atmospheric Vent | 2.7.6.1 | G | |
| 176 | 33 56 10 | 3 | Product Data | Emergency Vent | 2.7.6.3 | G | |
| 177 | 33 56 10 | 3 | Product Data | Independent Level Alarm System | 2.8 | G | |
| 178 | 33 56 10 | 3 | Product Data | Tank Gauges | 2.9 | G | |
| 179 | 33 56 10 | 3 | Product Data | Tank Mounted Fuel Dispensing Unit | 2.11 | G | |
| 180 | 33 56 10 | 6 | Test Reports | Aboveground Storage Tank Tightness Tests | 3.2.1 | G | |
| 181 | 33 56 10 | 6 | Test Reports | Tank Manufacturer's Tests | 3.2.3 | ||
| 182 | 33 56 10 | 6 | Test Reports | Tank Fill Tests | 3.4 | ||
| 183 | 33 56 10 | 6 | Test Reports | Tank Inspection Reports | 3.2.5 | G | |
| 184 | 33 56 10 | 7 | Certificates | Contractor Qualifications | 1.4.1 | G | |
| 185 | 33 56 10 | 7 | Certificates | Manufacturer | 1.4.1 | G | |
| 186 | 33 56 10 | 7 | Certificates | State | 1.4.1 | G | |
| 187 | 33 56 10 | 7 | Certificates | Pollution Liability Insurance | 1.4.1 | ||
| 188 | 33 56 10 | 7 | Certificates | Permitting | 1.4.2.1 | ||
| 189 | 33 56 10 | 7 | Certificates | Registration | 1.4.2.2 | ||
| 190 | 33 56 10 | 7 | Certificates | Licensed Personnel | 1.4.2.3 | ||
| 191 | 33 56 10 | 7 | Certificates | Demonstrations | 3.3 | ||
| 192 | 33 56 10 | 7 | Certificates | STI SP001 Inspector's Certification | 3.2.5 | G | |
| 193 | 33 56 10 | 8 | Manufacturer's Instructions | Aboveground Storage Tank | 2.4 | ||
| 194 | 33 56 10 | 8 | Manufacturer's Instructions | Independent Level Alarm System | 2.8 | ||
| 195 | 33 56 10 | 8 | Manufacturer's Instructions | Tank Gauges | 2.9 | ||
| 196 | 33 56 10 | 10 | Operation and Maintenance Data | Aboveground Storage Tank | 2.4 | G | |
| 197 | 33 56 10 | 10 | Operation and Maintenance Data | Independent Level Alarm System | 2.8 | G | |
| 198 | 33 56 10 | 10 | Operation and Maintenance Data | Tank Gauges | 2.9 | G |
&8Submittal Register_v3_03/07/22
File details come from the government source that posted it. Updated .