32 13 14.pdf

PDF 13 KB Posted

Attached to
Tinker AFB MAC BOA WWYK230052, Replace Vault and Fuel Tank, B1032
Solicitation number
FA813725R0033
Issued by

About this file

This technical specification document (Section 32 13 14) from Tinker Air Force Base details non-airfield pavement standards and specifications for April 2019, adopting the Oklahoma Department of Transportation (ODOT) Standard Specifications for Highway Construction. The document provides comprehensive guidelines for non-airfield paving projects, including roads, streets, parking facilities, storage areas, sidewalks, driveways, bridges, and associated infrastructure elements.

Key technical requirements include concrete strength specifications (minimum 650 psi flexural strength), mandatory drainage and separation layers for pavements over 8 inches thick, concrete curbs and gutters placed separately from pavement, and specific subgrade preparation protocols. The specifications mandate using materials from the ODOT Approved Material Suppliers List, with all materials requiring ODOT approval for their intended use. The document also provides definitional substitutions for various terms, replacing standard transportation department terminology with Tinker Air Force Base-specific references, while maintaining that all project correspondence must be channeled through the Contracting Officer.

View the file

Other files

File Type Posted
10 44 16.pdf PDF
33 08 55.pdf PDF
Att12_230052_Submittal Register_r2.pdf PDF
03 39 00.00 10.pdf PDF
03 30 00.pdf PDF
10_230052_SOW_BWR_Revision_r1.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
03 20 00.00 10.pdf PDF
31 23 16.pdf PDF
32 16 13.pdf PDF
07 92 00.pdf PDF
32 92 19.pdf PDF
33 52 40.pdf PDF
33 52 23.15.pdf PDF
32 31 13.pdf PDF
03 11 13.00 10.pdf PDF
32 11 23.pdf PDF
Att12_230052_Submittal Register_r2.xlsx XLSX spreadsheet
26 05 00.00 40.pdf PDF
32 12 10.1.pdf PDF
31 00 00.pdf PDF
31 23 06.pdf PDF
26 08 00.pdf PDF
26 00 00.00 20.pdf PDF
06 10 00.pdf PDF
33 56 10.pdf PDF
32 01 22.pdf PDF
31 23 15.pdf PDF
32 92 23.pdf PDF
02 41 00.pdf PDF
32 12 10.2.pdf PDF
WWYK230052 RFI responses COR Signed.pdf PDF
Sign-in Sheet WWYK230052 B1132.pdf PDF
Solicitation - FA813725R0033.pdf PDF
Wage Determination.pdf PDF
Att13_230052_Drawings.pdf PDF
Att12_230052_Submittal Register_r1.xlsx XLSX spreadsheet
ENG-34-066-58-75.pdf PDF
2 EAL List - BLANK to Contractors.xlsx XLSX spreadsheet
Att10_230052_SOW_BWR_Revision_24 April.pdf PDF
Fire Pump from WWYK180027.pdf PDF
B1032 from WWYK180027 IFC PLAN SET.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tinker AFB, OK TAFB Technical Specifications 2019

April 2019 Page 1 Section 32 13 14

SECTION 32 13 14

PAVEMENT; NON-AIRFIELD

Part 1 GENERAL

1.1 SCOPE

The Standard Specifications for Highway Construction, as published by the Oklahoma Department of Transportation (ODOT), are adopted as the Tinker Air Force Base Standard Specifications for all non-airfield paving. Non-airfield paving includes, but is not limited to, grading, drainage, drainage structures, roads, streets, parking facilities, storage areas, sidewalks, driveways, bridges and all associated signage, markings, lighting and signalization. The edition shall be the edition current on the date of the Notice to Proceed (NTP) with design.

1.2 DEFINITIONS

Certain terms included in the ODOT Standard Specifications shall incorporate the following substitutions in their use:

a. For Commission substitute Base Civil Engineer and Contracting

Officer

b. For Department substitute Tinker Air Force Base

c. For Director substitute Base Civil Engineer

d. For Resident Engineer substitute Contracting Officer

e. For Engineer substitute 72 ABW/CE

f. For Materials Division substitute 72 ABW/CE

These substitutions do not in any way alter the requirement that all project correspondence be channelled through the Contracting Officer.

1.3 REFERENCES

UNITED STATES DEPARTMENT OF DEFENSE; UNIFIED FACILITIES CRITERIA

UFC 1-200-01 General Building Requirements

UFC 3-201-01 Civil Engineering

OKLAHOMA DEPARTMENT OF TRANSPORTATION (ODOT)

ODOT SSHC Standard Specifications for Highway Construction

Tinker AFB, OK TAFB Technical Specifications 2019

April 2019 Page 2 Section 32 13 14

Part 2 PROCEDURE

2.1 REVISIONS, AMENDMENTS AND CLARIFICATIONS

2.1.1 Contract specific revisions, amendments and clarifications to the ODOT SSHC shall be included in the special conditions of the Contract.

2.1.2 General revisions, amendments and clarifications to the

ODOT SSHC are as follows:

2.1.2.1 Pay quantities and units shall be as specified in the line items of the IDIQ Contract. For non IDIQ contracts the pay quantities and units shall be as specified in the ODOT SSHC.

2.1.2.2 Concrete strength for roads, streets and parking areas shall be specified as flexural and shall have a minimum strength of 650 psi.

2.1.2.3 All pavements with a thickness (the cumulative total of all layers above the subgrade)of greater than 8 inches shall require a drainage layer and a separation layer. The separation layer may be fabric.

2.1.2.4 All curbs and gutters shall be concrete and monolithic. They shall be placed separate from pavement.

2.1.2.5 When preparing the subgrade, all plant materials and roots shall be removed and the excavation filled with select fill.

2.1.2.6 When working the subgrade, all soft, yielding or other unsuitable material shall be removed and replaced or modified in place until stable.

2.1.2.7 When preparing subgrades, the subgrade shall be proof rolled with a large roller or loaded scraper and visually checked for pumping even if it meets compaction requirements. Pumping subgrade material shall be removed or treated until it is stable.

2.2 MATERIALS

2.2.1 All materials shall be from a source listed on the ODOT

Approved Material Supppiers List.

2.2.2 All materials shall be ODOT approved for the use intended.

-- End of Section --