Revised_Bldg._____475_SOW_______01_Aug_14.docx

DOCX document 34 KB Posted

Attached to
MACC Solicitation # FA5685-14-R-0013 Federal contract opportunity
Solicitation number
FA5685-14-R-0013
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

About this file

See Attachement.

View the file

Other files for this federal contract opportunity

Other files attached to MACC Solicitation # FA5685-14-R-0013, newest first.
File Type Posted
FA5685-14-R-0013-0015.doc DOC document
FA5685-14-R-0013-0014.doc DOC document
Bldg._475_Drawings.pdf PDF
FA5685-14-R-0013-0012.doc DOC document
RESPONSE___8_MACC_Solicitation_FA5685-14-R-0013.docx DOCX document
Response___7-Solicitation___FA5685-14-R-0013.docx DOCX document
FA5685-14-R-0013-0011.doc DOC document
Attachment___31.docx DOCX document
Attachement___32.pdf PDF
RESPONSE___5_MACC_Solicitation_FA5685-14-R-0013.docx DOCX document
FA5685-14-R-0013-0010.doc DOC document
Questions___4_Response_to_MACC_Solicitation-FA5685-14-R-0013.docx DOCX document
Attachment___30_Gypsumboard_Wall_Detail.pdf PDF
Attachment___29_MACC_CIVIL-STRUCTURAL_DRAWINGS_____1.PDF PDF
Attachement___28_MACC_CIVIL-STRUCTURAL_DRAWINGS.PDF PDF
FA5685-14-R-0013-0009.doc DOC document
Response___3_to_MACC_Questions-FA5685-14-R-0013.docx DOCX document
Attachment___26_Section_H-4.docx DOCX document
FA5685-14-R-0013-0008.doc DOC document
Attachement___27_Supplement_to_2014_MACC_General_Specifications.docx DOCX document
FA5685-14-R-0013-0007.doc DOC document
INC-1104_Design_Review_Checklist.doc DOC document
PPL_Jun_2014.xls XLS spreadsheet
FA5685-14-R-0013-00005.doc DOC document
Past_Performance_Questionnarie__PPQ.docx DOCX document
Responses___2_to_Questions_for__MACC_Solicitation-5_July_14.docx DOCX document
RESPONSES_TO_QUESTIONS_FOR_MACC-SOLICITATION-FA5685-14-R-0013_-4_July_14.rtf RTF text file
FA5685-14-R-0013-0004.doc DOC document
Attachment___16_Asbestos_Register_List.pdf PDF
Attachment___12_LJYC_10-1081_INC-1101_-_Untabulated.xlsx XLSX spreadsheet
MACC_Solicitation___FA5685-14-R-0013-13_June_14.doc DOC document
Attachement___1_2014_MACC_General_Specifications_Guide.pdf PDF
Attachment___4_MACC_Schedule_of_Items_(Blank)__25_Feb_14-FINAL.xls XLS spreadsheet
Attachment___23_INC-1101_KTR_Cost_Estimate.xlsx XLSX spreadsheet
Attachment___11_SOW_LJYC_10-1081.pdf PDF
Attachment___8_LJYC_10-1052_INC_1106.xls XLS spreadsheet
Attachment___10_PPL_Feb_2012.xls XLS spreadsheet
Attachment___19_INC-1106_Schedule_of_Material_Submittals.xls XLS spreadsheet
Attachment___17_LJYC_11-1009_Repair_Roof_Bldg..pdf PDF
Attachment___21_LJYC___11-1009.xls XLS spreadsheet
Attachment___18_INC-1101_Cost_Price_Breakdown.xlsx XLSX spreadsheet
Attachment___20_Drawings_-_LJYC_11-1009_Repair_Roof_Bldg._475.pdf PDF
Attachment___7_INC-1101_Cost_Estimate.xlsx XLSX spreadsheet
Attachment___25_INC-1108_Design_Review_Checklist.xlsx XLSX spreadsheet
Attachment___5_Site_Visit_Reservation_Form3_FA5685-14-R-0013.docx DOCX document
Attachment___6_SOW_LJYC_10-1052.pdf PDF
Attachment___14_Drawings_LJYC_10-1081.pdf PDF
Attachment___15_LJYC___1081_PPL__Feb_2012.xls XLS spreadsheet
Attachment___24_INC-1106_Schedule_of_Material_Submittals.xls XLS spreadsheet
Attachment___22_SOS_for_MOCK_Project_Ren_B_444.doc DOC document
Show all 50

MACC Solicitation # FA5685-14-R-0013 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK FOR

LJYC 11-1009

— REPAIR REPLACE ROOF AT BUILDING 475— INCIRLIK AIR BASE

CONCEPT DRAWINGS

See attachment

RECOMMENDED FOR APPROVAL
NAME
SIGN
CHIEF OF ENGINEERING DESIGN
Kenneth Cox
CHIEF OF ENGINEERING
Paul Swinney
CHIEF OF OPERATIONS & MAINTENANCE
Joseph Smalls
DEPUTY DIRECTOR OF CIVIL ENGINEERING
Tom Carneal
DIRECTOR OF CIVIL ENGINEERING
James Brendlinger

BASE CIVIL ENGINEER

Matthew D. Welling, Maj USAF

WORK ELEMENTS

1.
Contractor shall provide all labor, materials, and equipment necessary to demolish, furnish, erect, and install all items listed below in accordance with all UBC, UBP, UBM, NFPA Codes, NEC, OSHA/ABA Regulations, CSI specifications, AFI’s and MIL. Std’s. The contractor is responsible for identifying unforeseen site conditions to the government in writing. Contractor shall adhere to all construction codes that are in standard use on Incirlik Air Base, and which govern work to be executed under this project. The contractor is also responsible for providing overall well working facilities and including items, which may not be specifically stated but are essential to the construction of such facilities. Any changes suggested by the contractor to the statement of work require approval from the contracting officer, civil engineering, before acceptance is given for a recommended change. In the event of conflict between statement of work, drawings and specifications, the specifications shall govern.
2.
The following general outline and list of Principle Features of Work in no way limits or reduces the responsibility of the contractor to perform all work necessary to provide a complete and usable system. The work includes but is not limited to the following:
3.
contractor shall provide safety equipment per OSHA
4.
Contractor shall design and provide new standing seam roofing system located at stair tower, and extend to existing roof (as shown on drawing). System shall including fasteners, gutters, downspouts, trim and all accessories. All fasteners to be hidden including, Valley, Ridges, Hips, Vents, Trim and all Accessories.
5.
Contractor shall provide computerized load calculations considering diversities for vertical loads, wind loads, seismic loads and vertical loads per Air Force Codes.
6.
Contractor shall design and provide Lightning Protection System
7.
1. Remove North roof to hip and tie new stair roof to existing roof structure. Design and provide galvanized steel framing, tie to existing roof framing. New framing for roof over existing stair shall span BUR which has ACM. Provide new standing seam roofing, RAL 1015 Yellow Beige. Provide access hatch into roof at north side. Align with new and existing roof. Existing downspout drop to remain as overflow provide screened outlet. Provide overflow drain at all scuppers. Provide and install 2mm new metal valley rain gutters. The valley rain gutters shall be manufactured with coil coated, factory painted metal sheet (color: RAL 8028, dark brown). All gutter connections shall be welded. Valley gutter flashings shall overlap with roof panels minimum 30cm. All gutters shall be supported every 100 cm. Provide and install new galvanized metal flashing for installation of the new roof. The metal flashing shall be factory painted (color: RAL 8028, dark brown). Minimum overlap of flashing with roof panels shall be 20cm. Provide and install new 0.7mm thick; factory painted metal downspouts (20cm) and gutters. (color: RAL 8028, dark brown) c/w connection to the storm sewer system and required accessories. Downspouts shall be supported every 100cm.

2. Provide and install anchors c/w steel safety rope.

3. Provide and install new metal ridges on the roof. Metal ridges shall be factory painted (color: RAL 1015, yellow beige).

4. Replace all existing roofing panels with standing seam roofing system

8
Details shall be constructed based on the NRCA Metal Panel and SPS Roofing System 2012 Edition (may be viewed in CES/CED offices. In general details of roof shall have no exposed fasteners. Joints shall be waterproof without reliance on sealant. (Sealant shall be considered only a secondary mean of water proofing whose primary purpose is to seal against air intrusion.) Supplied details shall be used for reference; details used shall be submitted for review and approval and shall have salient attributes.
9.
New roof over stair well to extend 1 meter past wall to cover windows. Install new roofing system over entry doors; two at North side first floor. New framing system shall be supported off the side of the building. Door at the second floor shall have hipped roof extension as shown on drawings. System shall be standing seam roofing system with hidden fasteners. New gutters, downspouts shall be connected to the exisiting storm drainage system. Provide trim and accessories.
10
Constructor shall not use for access, layout or disturb the BUR on the South side flat roof a it is ACM.
11
Definitions: Provide = furnish and install; BUR= Built Up Roof; ACM= Asbestos Containing Material
12
Contractor is to verify all dimensions prior to submittal of a proposal.
14
All field operations shall be performed according to the U.S. Army Corps of Engineers Manual EM385-1- 1, latest edition.
15
Contractor shall obtain approved AF Form 103 from the Construction Management office before starting any work and have a copy of the AF Form 103 and drawings on site at all times.
16
Contractor shall survey and submit shop drawings for approval prior to commencement of work.
17
Contractor shall restore site and portions of the roof not in this contract to its original condition and also verify proper drainage of all areas within the construction site.
18
Contractor shall be responsible for repairing any government property damaged during execution of work.
19
Contractor shall submit progress schedule to validate the estimated time required to complete the work including the following activities: 1) Time required for submitting fabrication shop drawings for approval. The milestone schedule should allow 10 days for review, approval and return of the shop drawings.

2) Time required to order and to receive the materials required for work after approval of shop drawings.

20
Once the project is accepted the contractor shall also update existing Government drawings to "as built” conditions using AutoCAD and provide soft copies that are prepared in accordance with SDSFIE Standards and compact disc of the as-built drawings and submit required documentation for close-out procedure.
21
Provide submittals of all Operation and Maintenance Data that is furnished by the manufacturer, or the system provider, required in the applicable technical sections. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item. Operation and Maintenance manuals must be submitted as four (4) original copies. Four (4) submittals of documents must be original and fully legible. Poor quality copies and material with hole punches obliterating the text or drawings will not be approved.
22
Contract close out responsibility will be limited to the submittal of ‘As built’ Shop Drawings, red line drawings, test data, material delivery list to TURAF, equipment warranty certificates and O&M manuals (4 original copies in English), to be given to the Contracting Officer.
23
All chemicals that are being used for this project shall be submitted for approval on AF Form 3952. Approval will be provided by Safety, Bioenvironmental Engineering, Environmental and Hazmat Pharmacy. MSDS in both Turkish and English shall be provided with the AF Form 3952 and they shall be available at the job site. Contractor shall submit hazardous material list for approval.
24
Contractor shall use a tracking system for tracking and reporting HAZMAT transactions and shall submit a letter of HAZMAT usage upon the completion of the project to Environmental (39 CES/CECV). The letter shall list the HAZMAT and quantities used during all phases of the project.
25
Asbestos containing materials, Class I and II ODC’s, lead based paints, PCBs/PCTs and materials containing any of the EPA 17 chemicals shall not be used during execution of the project.
26
If the Contractor encounters materials suspected of containing asbestos, they shall notify the Contracting Officer immediately, and shall wait for instruction before proceeding with work.
27
All construction debris shall be taken to an off base landfill daily and disposal at the closed landfill on the base and Roads & Grounds Area is not allowed.
28
Liquid HAZMAT items must be stored within a secondary containment. Incompatible materials must not be stored in the same secondary containment. Transfer of HAZMAT into unmarked containers is not allowed. The contractor shall maintain an inventory of the types and quantity of HAZMAT stored at the project site and must also have a binder with all of the MSDS in both Turkish and English available for use by employees and emergency responders.
29
Total design phase performance period is 80 days.

After the design is 100% complete and before issuance of CNTP, 30 calendar days for AF Form 103 and signature coordination to be added into the contract.

30
The construction performance period for this project is 80 days.