Attachment___25_INC-1108_Design_Review_Checklist.xlsx

XLSX spreadsheet 25 KB Posted

Attached to
MACC Solicitation # FA5685-14-R-0013 Federal contract opportunity
Solicitation number
FA5685-14-R-0013
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

About this file

Attachment 25

View the file

Other files for this federal contract opportunity

Other files attached to MACC Solicitation # FA5685-14-R-0013, newest first.
File Type Posted
FA5685-14-R-0013-0015.doc DOC document
FA5685-14-R-0013-0014.doc DOC document
Bldg._475_Drawings.pdf PDF
Revised_Bldg._____475_SOW_______01_Aug_14.docx DOCX document
RESPONSE___8_MACC_Solicitation_FA5685-14-R-0013.docx DOCX document
FA5685-14-R-0013-0012.doc DOC document
FA5685-14-R-0013-0011.doc DOC document
Attachment___31.docx DOCX document
Attachement___32.pdf PDF
RESPONSE___6_MACC_Solicitation_FA5685-14-R-0013.docx DOCX document
RESPONSE___5_MACC_Solicitation_FA5685-14-R-0013.docx DOCX document
FA5685-14-R-0013-0010.doc DOC document
Attachement___28_MACC_CIVIL-STRUCTURAL_DRAWINGS.PDF PDF
FA5685-14-R-0013-0009.doc DOC document
Attachment___30_Gypsumboard_Wall_Detail.pdf PDF
Attachment___29_MACC_CIVIL-STRUCTURAL_DRAWINGS_____1.PDF PDF
Response___3_to_MACC_Questions-FA5685-14-R-0013.docx DOCX document
Attachement___27_Supplement_to_2014_MACC_General_Specifications.docx DOCX document
FA5685-14-R-0013-0007.doc DOC document
Past_Performance_Questionnarie__PPQ.docx DOCX document
INC-1104_Design_Review_Checklist.doc DOC document
PPL_Jun_2014.xls XLS spreadsheet
Responses___2_to_Questions_for__MACC_Solicitation-5_July_14.docx DOCX document
RESPONSES_TO_QUESTIONS_FOR_MACC-SOLICITATION-FA5685-14-R-0013_-4_July_14.rtf RTF text file
FA5685-14-R-0013-0004.doc DOC document
FA5685-14-R-0013-0001.doc DOC document
Attachment___12_LJYC_10-1081_INC-1101_-_Untabulated.xlsx XLSX spreadsheet
MACC_Solicitation___FA5685-14-R-0013-13_June_14.doc DOC document
Attachement___1_2014_MACC_General_Specifications_Guide.pdf PDF
Attachment___4_MACC_Schedule_of_Items_(Blank)__25_Feb_14-FINAL.xls XLS spreadsheet
Attachment___23_INC-1101_KTR_Cost_Estimate.xlsx XLSX spreadsheet
Attachment___11_SOW_LJYC_10-1081.pdf PDF
Attachment___8_LJYC_10-1052_INC_1106.xls XLS spreadsheet
Attachment___10_PPL_Feb_2012.xls XLS spreadsheet
Attachment___19_INC-1106_Schedule_of_Material_Submittals.xls XLS spreadsheet
Attachment___17_LJYC_11-1009_Repair_Roof_Bldg..pdf PDF
Attachment___21_LJYC___11-1009.xls XLS spreadsheet
Attachment___18_INC-1101_Cost_Price_Breakdown.xlsx XLSX spreadsheet
Attachment___20_Drawings_-_LJYC_11-1009_Repair_Roof_Bldg._475.pdf PDF
Attachment___7_INC-1101_Cost_Estimate.xlsx XLSX spreadsheet
Attachment___5_Site_Visit_Reservation_Form3_FA5685-14-R-0013.docx DOCX document
Attachment___6_SOW_LJYC_10-1052.pdf PDF
Attachment___14_Drawings_LJYC_10-1081.pdf PDF
Attachment___15_LJYC___1081_PPL__Feb_2012.xls XLS spreadsheet
Attachment___24_INC-1106_Schedule_of_Material_Submittals.xls XLS spreadsheet
Attachment___22_SOS_for_MOCK_Project_Ren_B_444.doc DOC document
Attachement___2_MACC_Design_Guide_2014.docx DOCX document
Attachment___3__Past_Performance_Questionnaire.docx DOCX document
Attachment___13_LJYC_10-1081_INC-1101.xlsx XLSX spreadsheet
Attachment___9_Drawings_LJYC_10-1052.pdf PDF
Show all 50

MACC Solicitation # FA5685-14-R-0013 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Final Design Review Checklist Items

*The checklist must be filled out by hand
PROJECT NUMBER & TITLE:Date:
Type: 35%:_______, 65%:_______, 95%:_______
SECTION I: GENERAL
NO:ITEMYESNON/A
1Is there an impact on the user and/or facility occupier?
a. Will the facility be completely turned over to construction?
b. If answer to 1a is NO than is there a phasing plan?
c. If answer to 1b is NO than is the work safe to be conduceted while bldg occupied and in use?
d. Is the user notified of commencement of work?
e. To minimize impact to user(s); is the contract performance period broken down to material ordering and construction time?
2Does the project impact multiple facilities?
a. If YES is there an identified maximum number of facilities that can be worked on at one time?
b. Is it clear when the contractor will be allowed to additional facilities?
c. Is it possible for one inspector to work that many facilities, and maintain several other projects?
d. Is it clear who makes the choice on the order in which facilities are worked?
3Is the work itself or any part of the work in restricted area (loops & within AF red zones)?
a. If answer to above is YES, is this clearly identified in the project documents?
b. Will CE Military Escorts be required?
4Does the project require any full or partial road closures?
a. If answer to above is YES, has duration of road closure, parking, traffic signs & alternate traffic road been considered?
b. If YES, Is coordination time of up to 30 days considered in PoP?
5Does the project require any utility outages?
a. If answer is YES have the durations and number of occurances been identified?
b. If answer is YES, are all affected facilities by the outage identified?
c. If answer is YES is the user notified?
d. If YES, Is coordination time of up to 30 days considered in PoP?
6Are access and haul routes for the contractor considered?
7Does the project have any asbestos related work?
a. If YES, is it clear where it is located?
b. Is it clear how much must be removed?
c. Is the method of removing asbestos clear?
d. Is it indicated whether or not the facility will remain occupied?
e. Have all environmental permits been obtained?
f. Have all testing, certification, and disposal costs together w/ contractor's costs considered?
8Does the AF Form 66 accurately reflect the material submittals called for in the specifications?
9Is the contract construction performance time reasonable? Are the following considered:
a. Long-lead construction or equipment items?
b. Time b/w change of phasing?
c. Local site conditions and restrictions?
d. Utility marking & initial mobilization? (app 21 days)
e. Pre-Final & Final inspection period? (app 21 days)
10Does the project include government furnished equipment (GFE)?
a. If YES, is the equipment clearly identified in the project documents?
b. Is it identified when, and to what location the equipment will be delivered to the contractor?
c. Is there a memorandum for record filed to document GFE providing agencies agreement?
11Is the scope of work clear?
a. Are there any open questions?
12Has the project been reviewed by O&M representative(s)?
13Does the project require fire detectors & suppression system to be disabled (including ones in attic & mezzanine)
14Is the laydown area identified on the project drawings?
15Does the project request extended manufacturer warranties? If yes, is it requested in AF 66?
16Are there any maintenance of equipment requirements, i.e. chillers, generators etc?
a. If yes has it been incorporated and is the duration for maintanence identified?
SECTION II. CONSTRUCTION SITE
NO:ITEMYESNON/A
1Do the plans accurately depict obvious as-built conditions?
2Do the plans accurately depict the locations of utilities, i.e.:
a. Electrical power poles, underground electrical lines, and service to facility?
b. Telephone poles, underground communication lines, and service to facility?
c. Manholes?
d. Water lines and service to facility?
e. Gas lines and service to facility?
3Will temporary utilities be readily available if the project documents offer them?
4Spot check the elevations. Do the plans seem relatively accurate?
5Does the project require landscaping work?
a. If YES, do the plans indicate seeding, or some means for quick turf establishment in problem areas?
b. If YES, do the plans address turf placement?
6Are therey any abandoned underground utility lines to be left in place?
SECTION III. ARCHITECTURAL/STRUCTURAL
NO:ITEMYESNON/A
1Do the plans clearly distinguish the difference in existing and new work?
2Is the room finish schedule included into the drawings?
work?
3 Do the specifications call for all color selections to be submitted at one time?
4 Does the door finish schedule include information on all rooms indicated to receive
applicable work? Does it agree with the specifications?
5 Are all dimensions shown clearly? Do the dimensions shown agree with the indicated
3scale?
a. If YES, does it include all details of required items in all rooms?
b. If YES, does it include the door finish details as well?
c. If YES, are all items in agreement with the specification?
3Does the specification call for all color selections to be submitted at one time?
4Are all dimensions shown clearly?
a. Do the shown dimensions match with the scaling?
b. Do the structural, mechanical, and electrical floor plans agree with the architectural plans?
c. Do all concrete columns and walls on architectural plans agree with the structural plans?
5Do the plans allow adequate space in utility and mechanical rooms for proper installation and maintenance of equipment?
6Is there a complete legend for the project including architectural, structural, mechanical, and electrical symbols?
7If painting exterior, is building number painting included?
8Does the project call for floor leveling before installing carpeting or VCT?
9Is the new fence line interfeering with manholes, downspouts, yards & surrounding areas, is it blocking drainage?
SECTION IV. MECHANICAL/PLUMBING
NO:ITEMYESNON/A
1a.Does the project require temporary HVAC?
b. If yes has it been identified and requested?
2Do the plans show where all new gas, water, sewer lines, etc. connect to existing?
3Do the plumbing fixture locations agree with the architectural plans?
4Do the plumbing fixtures shown on the plans agree with the fixture schedule, and/or the specifications?
5Are all pipe concealment spaces, or chases shown on architectural plans?
6Do the plans allow for adequate ceiling height to install new ductwork at worst case intersection?
7Do the project documents call for structural support of piping, ductwork, plumbing fixtures and all mechanical equipment?
8Are all the sizes indicated for all ductwork and piping?
9a. Is all roof mounted, or externally mounted, mechanical equipment shown on architectural plans?
b. Does the roof mounted equipment require a maintenance catwalk?
10Does all mechanical equipment show connections for piping, power, controls, etc., as necessary?
11Place FCU in the proper locations, i.e. away from walkway path.
12Ensure that thermostats are shown on the drawings & installed inside of all buildings.
13If the drawings refer to a Government Furnished Computer for remote access, is computer availability checked?
14Is the route/path of new pipes clear of obstructions?
15Are pipe designators required?
SECTION V. ELECTRICAL
NO:ITEMYESNON/A
1a. Do the electrical plans indicate that all major pieces of equipment receive power?
b. Does all the scheduled mechanical equipment in the mechanical plans receive power?
c. Do the voltages, phases, and frequencies in the mechanical schedules agree with the electrical plans?
2Are the locations for all panel boards shown in the plans and on the electrical riser?
3Do the specifications require that all electrical work be in accordance with the latest edition of the NEC?
4a. If the plans call for removing existing panels and installing new, is temporary power provided for in the project documents?
b. If not, is this acceptable?
5Ensure that KTR use the proper sealant for exterior outdoor PVC high voltage lines.
6Does the facility(s) require a generator(s)?
SECTION VI. ENVIRONMENTAL
NO:ITEMYESNON/A
1Are there any environmental contaminants that may be present in existing equipment or on site? (i.e. - asbestos, lead paint, Hazardous Air Pollutants (HAPs), contaminated soil, Ozone Depleting Chemicals (ODC’s), etc.).
2Are there any environmental materials that can be recycled or recovered? (i.e. - Ozone Depleting Substances (ODS’s), Halon, lubes, etc.)
3Has the project been reviewed by a base environmental representative?
4Have MSDS and usage reports been requested for hazardeous materials for ENV review, and is a note inserted for KTR to keep them on site.
SECTION VII. FIRE ALARM SYSTEMS
NO:ITEMYESNON/A
1Are exit signs in the proper egress, access locations?
2Are notification appliances outside of buildings at the proper height?
3Are recessed fire extinguisher cabinets shown in the req'd locations inside of the building?
Design Engineer's Name & Signature:
Inspector's Name & Signature:

Form INC-1108, Constructability Review Checklist. (Rev 2, March 2012)